RTWG Action Items - February, 2015

advertisement
Southwest Power Pool, Inc.
REGIONAL TARIFF WORKING GROUP
Pending Action Items Status Report
February 26, 2015
Action Item
Date
Originated
Priority
Status
Comments
Dennis Reed asked Charles Hendrix and SPP Staff to bring a
recommendation to the RTWG regarding how to deal with these
generators. Charles Hendrix to provide an update at the May 26, 2011
RTWG meeting.
51
What to do about
generators that have
only built out a
portion of the
generation facility as
specified in the IA?
February 3,
2011
In Progress
The Business Practices Working Group will be addressing this issue as
part of their current Generation Interconnection improvement initiative.
BPWG is currently discussing.
Status remains unchanged
4-16-2014 - Staff and BPWG addressed in the GI Improvements Tariff
Policy and Tariff. Language addressing this is included in the GI
Improvements filing in ER14-781. The filing is pending.
Filing was partially accepted pending a compliance filing in Docket
ER14-781-003.
Action Item
Date
Originated
Priority
Status
Comments
Dennis Reed requested that the reference in Attachment AI Section II
Criteria for Inclusion of Facilities, 1. be updated to correctly reflect the
Base Plan Upgrade Definition. Currently, it references Section 1.3(h) of
the Tariff, which no longer exists.
Assigned to Matt Harward
65
Update reference in
Attachment AI ,
Section II. 1. to
correctly reflect the
Base Plan Upgrade
Definition
March 22,
2012
In Progress
2/12/2014 -Correction is reflected in TRR 120 – Attachment AI to be
presented at the RTWG Meeting – September, 2014 – RTWG Approved
TRR 119 – September 24, 2014 and MOPC approved on October 14,
2014.
10/28/14 – BOD approved TRRs 119 and 120
01/15/2015 – TRRs 119 and 120 scheduled to be filed at FERC.
01/15/2015 – Revisions filed at FERC – Docket ER15-859-000
Chair to designate Task Force to begin process.
October, 2012 – Task Force Members have been assigned
67
Develop "Hub and
Spoke" language in
accordance with the
AGCTF whitepaper.
May 3, 2012
In Progress
71
SPP Legal to
research how other
RTOs and WECC
have addressed DC
tie interconnections
July 26, 2012
In Progress
2/26/2015 – Tom Hestermann (Sunflower) was appointed Chair of the
Hub and Spoke Task Force
Assigned to Staff – Tessie Kentner
Action Item
Date
Originated
Priority
Status
Comments
Assigned to BPWG
Include language in a Business Practice that was deleted in TRR 110 –
Order 1000 Compliance, Attachment Y.III.2(d)(vii)(a)
77
Develop Business
Practice - IEP
process
If the Board of Directors accepts the IEP’s recommendation, pursuant to
Section III.2(f)(i) of this Attachment Y, resulting in all RFP proposals
being eliminated from consideration due to a low score in any evaluation
category, the DTO for the Competitive Upgrade will be identified as
follows:
09/24/2013
In Progress
4-16-2014 - Regulatory Processes is developing Business Practices on
the IEP process to be presented in the fourth quarter of 2014.
8-15-2014 – Staff is developing a straw proposal for the SPCTF Order
1000 to further define what is included in the RFP, what is expected from
the respondents, and more clarification on how the IEP should score
certain items. The reference to the Minimum Design Standards being
developed by the PCWG will also be included.
2-26-2015 – Staff presented BPR 059 – Competitive Upgrade Request
for Proposal Issuance
Roll-In methodology Tariff revisions to be reviewed and filed at FERC.
78
Z2, Attachment J,
Section III – Future
Roll-In
June 26, 2014
Open
Assigned to the CPTF
1-22-2015 – On hold pending FERC’s acceptance of the LTCR Filings –
ER14-2553
Action Item
Date
Originated
Priority
Status
Comments
Describe if the Balancing Transfers are completely offset between Base
Plan Zonal reductions and Base Plan Regional increases in the OATT
Schedule 11 rates.
79
Ten Year Forecast
July 24, 2014
Open
Assigned to Staff
1-22-2015 – Ten Year Forecast will be presented at the RTWG February
26, 2015 meeting.
Provide all future 10 Year Forecasts of Allocated Transmission Costs to
include integrated Systems (IS) parties: WAPA, Basin Electric and
Heartland Electric.
Assigned to Staff
80
Ten Year Forecast
July 24, 2014
Open
1-22-2015 – Ten Year Forecast that include IS parties will be presented
at the RTWG February 26, 2015 meeting.
2-26-2015 – Ten Year Forecast that include IS parties has been
rescheduled for the RTWG March 25 – 26, 2015 Meeting.
Download