Contract No. OSM 26(7605)102.1 SUMMARY TABLE OF CONTENTS Each Technical Specification listed below includes sections providing the Scope, Procedure, Measurement, and Payment. For clarification, many Technical Specifications have sections providing information regarding Staging, Materials, Maintenance, and Removal. The following is a general summary of the work effort for each Technical Specification. For more detailed descriptions including additional work effort, refer to individual Technical Specifications and Drawings. Technical Specifications (Tech. Spec.) # Title Scope of Work Brief overview of selected work to extinguish fire in abandoned Phillips Mine Page # TS-1 – TS-2 Blasting Plan and Safety Program 1 Identifying and notifying residents or owners of dwellings or other structures within ½ mile of proposed blasting area; conducting pre-blast surveys upon property owner request; acquiring blasting activity permit; signage; safety training and program development including mine fire-related issues TS-2 – TS-3 Mobilization and Demobilization 2 3 Notifying PA One-Call; delivering and assembling all necessary equipment preparatory to construction with removal upon project completion; signage Gate Fabricating and installing a gate at the construction entrance prior to excavation activities TS-3 – TS-4 TS-4 – TS-5 Office Facility and Staging Area 4 Establishing onsite office trailer with internet and phone service throughout project activities with removal and land reclamation upon project completion; firefighting foam storage with freezing protection; limited E&S Control installation TS-5 – TS-6 Erosion and Sediment Pollution Controls (E&S Controls) 5 Completing and filing NPDES co-permittee application and agreement and Notice of Termination upon project completion; installing, stabilizing, maintaining, and removing (if not a permanent facility) a rock construction entrance, temporary and permanent diversion ditches, compost filter sock barriers, and Temporary Sediment Basin with Temporary Collection Ditch; (note that clay material excavated from Borrow Area 2 to be used to fill vents and prepare area for placement of excess cut from Temporary Sediment Basin construction) TS-6 – TS-14 Clearing and Grubbing 6 Removing and handling of trees, brush, and solid waste including monitoring well casings and includes recycling or onsite or offsite disposal; (note that existing monitoring well casings are not to be disturbed until necessary for excavation operations) TS-14 – TS-16 Water Source, Delivery, Storage 7 Contracting with North Fayette Municipal Authority to install tap on existing waterline or developing other water source; developing delivery system with pipe, hoses, pumps, etc. to excavation areas; constructing holding pond or other storage facility(ies); removal with land reclamation of water source, delivery system, and holding pond TS-16 – TS-18 Firefighting Foam 8 Providing and maintaining all necessary supplies and equipment to dispense foam on “hot” or burning materials; removal of supplies and equipment and firefighting foam restocking upon project completion TS-18 – TS-19 Contract No. OSM 26(7605)102.1 # Title Page # Temporary Surface Seal 9 Excavating clay material from Borrow Area 2; filling vents and installing continuous temporary seal using clay borrow; installing Temporary Collection Channel, as part of E&S Controls, with quenching pools concurrent with Temporary Surface Seal installation TS-19 – TS-22 Northern Air Barrier 10 Excavating and segregating weathered and unweathered overburden materials; coal removal and sale; installing air barrier along final highwall with compacted weathered material; initial backfilling with unweathered material and final backfilling with compacted weathered material; includes reclamation of abandoned surface coal mine TS-22 – TS-26 Eastern Air Barrier/Seal 11 Excavating and segregating weathered and unweathered overburden materials; coal removal and sale; measuring temperatures of final highwall; installing air barrier/seal with clay material, excavated from Borrow Area 1, spread and compacted along final highwall; potentially excavating, handling, and cooling of heated materials; initial backfilling with unweathered material and final backfilling with compacted weathered material TS-26 – TS-29 Southern Fire Barrier 12 Excavating and segregating weathered and unweathered overburden materials; blasting; coal removal and sale; measuring temperatures of final highwall with possible relocation of highwall to higher cover; installing fire barrier with clay material excavated from Borrow Area 1; excavating area for installation of future installation of infiltration manifold; excavating, handling, and cooling of heated materials; initial backfilling with unweathered material and final backfilling with compacted weathered material (note that final backfill may be completed in conjunction with Extinguishment Operations) TS-30 – TS-35 Extinguishment Operations 13 Removing Temporary Infiltration Structure, Temporary Sediment Basin, and Temporary Collection Channel; excavating and segregating weathered and unweathered overburden materials including sandstone and heated materials; coal removal and sale; installing quenching pools within the excavation area using clay material recovered from Temporary Surface Seal removal; using firefighting foam or water spray to cool working faces and excavated material, as needed; cooling “warm” (>90°F to <150°F) overburden materials by spreading or diluting; cooling “hot” (>150°F) overburden materials by immersing in quenching pools; installing fire barrier with clay material excavated from Borrow Area 1 along eastern sidewall; installing Sidewall Interceptor Drain using sandstone rubble; initial backfilling with unweathered material and sandstone rubble; final backfilling with weathered material TS-35 – TS-42 Permanent Infiltration System 14 Installing permanent facilities to re-establish surface and subsurface water drainage to the existing abandoned underground mine; including installation of a rock-lined collection channel, wet meadow, and rock drain; riprap to be durable sandstone for corrosive environment (acidic water) TS-42 – TS-44 Seeding 15 Establishing vegetative cover, temporary and permanent, using grasses and legumes including soil amendments and fertilizer TS-44 – TS-48 Tree Planting 16 Planting about 13,000 tree seedlings on about 19 acres for permanent revegetation in previously forested areas on the Robert T. & Mary Ann Verney property Appendix – Generalized Columnar Section; Borehole Logs 10 – 56C1 TS-48 – TS-50