VALUE FOR MONEY AND POLICY REVIEW OF THE CLÁR AND RAPID LEVERAGED EXPENDITURE APPROACH © Department of the Environment, Community and Local Government, 2011. CONTENTS EXECUTIVE SUMMARY 1. Introduction 2. Efficiency 3. Effectiveness 4. Other observations 5. Performance measurement 6. Alternative approaches 7. Conclusion CHAPTER 1: TERMS OF REFERENCE, INTRODUCTION AND BACKGROUND 1. Background to the value for money and policy review initiative 2. Background to this VFM review 3. Terms of Reference 4. Brief introduction to the CLÁR and RAPID programmes 5. The rationale for the CLÁR and RAPID leveraged expenditure approach 6. Review steering group 4 4 5 6 7 8 8 8 9 9 9 9 10 13 14 CHAPTER 2: EVALUATE THE EXTENT TO WHICH THE KEY OBJECTIVE WAS ACHIEVED AND COMMENT ON THE EFFECTIVENESS OF THE LEVERAGED EXPENDITURE APPROACH 15 1. Introduction 15 2. CLÁR primary schools outdoor play facilities scheme 15 3. CLÁR group water scheme 19 4. CLÁR and RAPID sports capital top-up schemes 22 5. CLÁR class II and III roads and bridges scheme 25 6. RAPID playgrounds scheme 28 7. The compatibility of the leveraged expenditure approach objectives with the eligibility criteria for the leveraged schemes 38 8. Overlaps / complementarities between the CLÁR / RAPID leveraged schemes and selected relevant schemes / programmes operated by DCRGA 38 9. Conclusion 38 CHAPTER 3: EFFICIENCY 1. Introduction 2. CLÁR primary schools outdoor play facilities scheme 3. CLÁR group water schemes 4. CLÁR and RAPID sports capital top-up schemes 5. RAPID playgrounds scheme 39 39 39 43 45 45 2 CHAPTER 4: COSTS, COST EFFICIENCY AND PERFORMANCE MEASUREMENT 1. Introduction 2. CLÁR and RAPID sections’ total costs 3. Costs in relation to other selected State organisations 4. Outputs of the schemes examined by this review 5. Cost efficiency of the outputs produced for schemes analysed under this review 6. Performance measurement 7. Conclusion CHAPTER 5: CONTINUED ALLOCATION OF LEVERAGED FUNDING; ALTERNATIVE APPROACHES; AND MAIN CONCLUSIONS AND RECOMMENDATIONS 1. Continued allocation of leveraged funding 2. Alternative approaches 3. Main conclusions and recommendations 4. Recommendation 46 46 46 48 49 51 53 53 55 55 58 58 61 APPENDICES 62 APPENDIX I: A full list of the current RAPID areas APPENDIX II: RAPID leveraged schemes and details of the amounts paid from 2006 to 2009 inclusive APPENDIX III: A RAPID programme flowchart incorporating Pobal’s role APPENDIX IV: CLÁR leveraged schemes and details of the amounts paid from 2006 to 2009 inclusive APPENDIX V: Membership of the review’s steering committee APPENDIX VI: A brief description of CLÁR and RAPID schemes that have not been outlined in the report APPENDIX VII: Eligibility criteria of the schemes being examined in this review APPENDIX VIII: Extract from the revised RIA guidelines re: calculating public service implementation costs APPENDIX IX: Abbreviations 62 REFERENCES 81 63 65 66 70 71 75 77 80 3 EXECUTIVE SUMMARY 1. Introduction This is a review of the Ceantair Laga Árd Riachtanais (CLÁR) and Revitalising Areas by Planning, Investment and Development (RAPID) leveraged expenditure scheme which is in place to increase investment into those areas. The review’s objective is to analyse the leveraged schemes from 2006 to 2009 inclusive and to inform future policy-making regarding its future relevance and applicability. 1.1 Background to CLÁR and RAPID CLÁR Rural areas are included in the CLÁR programme as a result of substantial population decline. For CLÁR areas, the cost of providing such infrastructure into these disadvantaged areas could sometimes be prohibitive due to high unit costs and low population density issues. It leveraged funding from other public and private sources which enabled infrastructure to be provided that may not otherwise have been possible. RAPID RAPID areas are urban areas designated as disadvantaged by reference to a range of socioeconomic criteria including the levels of early school leaving; the proportion of one parent households; the unemployment rate; the proportion of social housing; and the age dependency rate. The RAPID programme was in existence a few years before the Department of Community, Rural and Gaeltacht Affairs (DCRGA)1 introduced the RAPID leveraged schemes. It was felt that other State bodies needed encouragement to entice them to invest in RAPID areas. CLÁR and RAPID were programmes targeted to accelerate investment to these areas. They aimed to create a more level playing field for the allocation of funds to these areas, as it was felt that the CLÁR and RAPID areas were not getting the same levels of investment, in comparison with nondesignated areas. Over the period, there were 21 such schemes in CLÁR areas and 7 in RAPID areas. In order to assess the efficiency and effectiveness of the leveraged approach, it was decided that the review would examine a subset of schemes. One of the main criteria used in selecting this subset was the relative volume of expenditure involved: CLÁR Primary Schools Play Facilities; CLÁR Group Water Scheme; CLÁR Class II and III Roads and Bridges; CLÁR and RAPID Sports Capital Top-Ups; and RAPID Playgrounds. 1 DCRGA was renamed DCEGA following a restructuring of Government Departments in March 2010. Subsequently, the Community function transferred to the DECLG in May 2011, following the disestablishment of DCEGA. DCRGA will be used in this document as this was the Department’s name for the review period being analysed. 4 2. Efficiency The Dept. of Finance Value For Money (VFM) Guidance Manual (2007) describes efficiency as the ratio of Outputs to Inputs, which can be viewed in two different ways: Whether the same level of Output can be achieved with fewer Inputs i.e. at a lower cost; or Whether a better quality or higher quantity of Outputs can be delivered from a fixed amount of Input. In normal evaluation circumstances, the total value of overall approvals into an area would be an Input and not an Output. However, the review found that given the nature of the leveraged approach, the overall approvals into an area should be regarded in these circumstances as an Output. Apart from the amounts of leveraged funding spent by DCRGA and its relevant co-funding partners, the main Input was the administration effort (in terms of staff and other resources) by CLÁR, RAPID and the co-funding partners. There were also additional costs associated with the leveraged approach. The review found that RAPID/Pobal costs taken as a percentage of the expenditure by RAPID section on the leveraged schemes were high when compared to the equivalent CLÁR costs. However this is also reflective of the different approach that was taken in relation to the RAPID leveraged schemes due to the role of the Area Implementation Teams (AIT) in signing off on all applications. In some instances, the relatively small grant amounts involved contributed to higher cost:approval ratios. The administration costs associated with the leveraged approach were found to be approximately 3%. Notwithstanding the fact that the figure is only 3%, the administrative costs associated with the approach raise a question about whether leveraged schemes can be efficient, compared to when funding is administered by one Government Department / Agency. 2.1 Multiple sources of funding Introducing a leveraged approach means introducing an additional statutory source of funding. In relation to the RAPID Playgrounds scheme, the review found that there were multiple sources of statutory funding available. The RAPID funding added to the other multiple sources of funding that were available. This leads to an overly complex funding mechanism which is wasteful on the administrative side, runs the risk of poor allocation, and lacks transparency. This particular point highlights one of the advantages associated with single point funding. In relation to the CLÁR Group Water Schemes, the Local Authorities received funding from both DEHLG and CLÁR section. The review found that the administration of this leveraged scheme was more difficult for the Local Authorities than if funding was being provided by a single body. In addition, certain administrative efficiencies would have resulted if the Department of Arts, Sport & Tourism (DAST) had handled all payment aspects of the Sports Capital Top-up schemes. There would have been one payment to successful applicants as opposed to one from DAST and one from either CLÁR or RAPID. 2.2 High costs for projects supported by leveraged funding The review found that some of the costs per house for Group Water Schemes supported by the leveraged approach, following the removal of the cap on the top-up, were very large. For example, 5 forty schemes had an average cost per house of more than €14,000, whereas the maximum payable in non-CLÁR areas by DEHLG was €6,475.66. Adequate structures were not put in place in order to assist CLÁR with the evaluation of each high cost project prior to approval taking place. Therefore, there is a danger with this approach that funding solutions which may not be the best value options may be chosen in order to utilise the incentive available. 2.3 Undefined responsibility One co-funding partner, DEHLG, outlined that it was only responsible and accountable for the fixed contribution funding of €6,475.66 per house that it was providing towards each Group Water Scheme. The presence of the CLÁR scheme meant that DEHLG was not responsible and accountable for any sums in excess of its own contribution. Although proposed projects were referred to them for comments/observations in accordance with good practice, they were adamant in stressing that no approval for the overall cost of individual projects was ever given. Approval of the CLÁR amounts rested solely with the section. In such circumstances, CLÁR had to be careful in relation to the overall amounts to be provided in relation to each project. CLÁR section could not be expected to have expertise in relation to each of the areas encompassed by each leveraged scheme. While CLÁR did not progress certain individual projects under the CLÁR Group Water Scheme without DEHLG expert advice, it was left to approve the CLÁR scale of funding for each project. The advice being provided by DEHLG was based on their responsibility and accountability for their fixed contribution funding only i.e. €6,475.66 per household. In a case where DEHLG is required to match on a € for € basis, all amounts per house over a certain amount, DEHLG would have been a full partner in the decision making process. However, this may have resulted in very few schemes actually proceeding, as DEHLG may not have been agreeable to these conditions. It must be remembered that projects funded under the leveraged approach would have been unlikely to have proceeded without the financial intervention from CLÁR and RAPID. 3. Effectiveness CLÁR and RAPID leveraged schemes offer a percentage of the total cost of specified investments in these areas. This is contingent on partner organisations providing matching funding. 3.1 How did partner organisations respond to the availability of leveraged funding? The review found that the approach increased investment into the disadvantaged areas over the period analysed and facilitated projects proceeding where it would be unlikely that they would have proceeded under normal circumstances. In other words, the co-funding partners would not have financed these projects without the financial intervention from CLÁR or RAPID. In relation to the CLÁR Group Water scheme, potential future infrastructure requirements may also have been catered for, as more houses in rural disadvantaged areas can be connected to it, as and when the need arises. Designated areas benefit when the leveraged funding is available. The review found that when it is no longer available, in the main, the allocation of funding between disadvantaged and nondisadvantaged areas reverts to its normal position (i.e. co-funding partners go back to their normal pattern in relation to the allocation of funding). Therefore, the leveraged approach did not cause a permanent shift in the way that funds are allocated by partner organisations between 6 disadvantaged and non-disadvantaged areas. The intervention of the leveraged expenditure approach was to facilitate projects proceeding in these disadvantaged areas, where it was unlikely that they would have proceeded under normal circumstances. One of the overall aims of this approach was that the co-funding partners would mainstream the treatment of such projects from these disadvantaged areas following the cessation of the leveraged funding approach. However, there was always a risk that co-funding partners could revert back to their normal funding patterns once an incentive such as this was removed. Analysis of the CLÁR and RAPID Sports Capital Top-up schemes and the RAPID Playgrounds scheme showed that the leveraged approach provided co-funding partners with the option to allocate their funding to other areas or programmes on the basis that the leveraged monies being provided by DCRGA would compensate for such a movement in funding. The co-funding partners use all funding sources in order to optimise their own expenditure allocation decisions. In some cases, this is not to the full benefit of the disadvantaged areas, as would have been the intention in initiating a leveraged approach. In other words, it can lead to there being extra investment into non-disadvantaged areas rather than disadvantaged areas. 4. Other Observations There was evidence that CLÁR and RAPID sections were not comprehensively evaluating the needs of their respective areas on an ongoing basis, in respect of whether the leveraged schemes in situ should remain or whether they should be replaced by new schemes to address any changing infrastructural needs of the areas. Inadequate levels of monitoring in relation to the RAPID Playgrounds scheme resulted in leveraged funding continuing to be made available to certain RAPID areas when it was no longer required following three cycles of the scheme having taken place. It was found that the leveraged approach was dependant on matching funds being provided by cofunding organisations. If the co-funding organisation does not have a sufficient budget available or is not encouraged to participate by the amount of leveraged funding available, the leveraged approach does not lead it to invest further in the designated areas. The CLÁR Primary Schools Play Facilities scheme was administered by CLÁR section, which was different to how the other schemes examined by this review were administered. The review found that Primary Schools were funded concurrently from both the CLÁR scheme and the Department of Education and Science (DES) Summer Works Scheme Play areas measure, even though both Departments were aware of this danger prior to the initiation of the CLÁR scheme and had a control mechanism in place to deal with it. It was never intended that this concurrent dual funding would occur. The maximum amount of funding that DES had to provide to each school under this scheme was low compared to what DES provides under its Summer Works Scheme. Consequently, this resulted in a larger number of much smaller grants under the CLÁR scheme. The review found that if the total amount of funding for Play Facilities had been available to DES to administer, then it would likely have continued to pay larger grants to a smaller number of Primary schools. 7 5. Performance Measurement There was no evidence of appropriate levels of Performance Indicators or a detailed Performance Measurement system being in place in relation to each of the schemes analysed as part of the review. No dedicated Performance Indicators were identified in relation to the leveraged approach itself. The leveraged schemes merited considerably greater monitoring, verification, performance and evaluation controls in place than was the case, in order to counteract to the greatest extent possible the weaknesses already outlined. For example, the CLÁR Class II and III roads and bridges scheme was difficult to analyse as the result of a lack of data being available. The provision of such data from co-funding partners should have been a prerequisite condition in order for partners to qualify for leveraged funding. 6. Alternative Approaches A number of alternative approaches were considered by the review, all of which had shortcomings. The main alternative approach analysed was in relation to adopting a ringfenced approach for funding relating to both areas. Following consideration, the steering committee decided that none of the alternative approaches considered could be proposed as an alternative to the leveraged approach. 7. Conclusion The leveraged approach did succeed in bringing extra investment into CLÁR and RAPID areas. However, the weaknesses observed in relation to that approach are of real concern. Therefore, it is the conclusion of the review that the leveraged schemes, in their current format, cannot be recommended to continue. If it was to fall for consideration in the future, it is acknowledged that it is very difficult to design an effective and efficient leveraged approach that would address the weaknesses outlined. At a minimum, the approach would have to be introduced in conjunction with appropriate monitoring, verification, performance and evaluation controls. There would be additional costs associated with these controls. Any new scheme would have to be scoped, researched, and planned, to include parameters and timeframes. 8 CHAPTER 1: TERMS OF REFERENCE, INTRODUCTION AND BACKGROUND At the outset, it should be explained that DCRGA was renamed the Department of Community, Equality & Gaeltacht Affairs (DCEGA) following a restructuring of Departments announced by the Taoiseach on the 23rd March 2010. In May 2011, the community function transferred to the Department of the Environment, Community & Local Government (DECLG), following the disestablishment of DCEGA. DCRGA will be used throughout this document as this was the name of the Department throughout the period being analysed. Furthermore, in order to avoid confusion, references to other Government Departments in this document will use one name with the caveat that the name chosen may have been subsequently changed in recent times. Please note that the Department of the Environment, Heritage & Local Government (DEHLG) became DECLG in May 2011. 1. Background to the value for money and policy review initiative The VFM and policy review initiative is part of a framework introduced to secure improved VFM from public expenditure. Its objectives are to analyse Exchequer spending in a systematic manner and to provide a basis on which more informed decisions can be made on priorities within and between programmes. It is one of a range of modernisation initiatives aimed at moving public sector management away from the traditional focus on inputs to concentrate on the achievement of results 2. Background to this VFM review This VFM and Policy Review is one of the reviews to be undertaken as part of the 2006-2008 round approved by Government. Each Department’s programme of reviews focuses on significant areas of expenditure and major policy issues and as a general rule, they have a minimum coverage of 10%-15% of each Department’s Budget. During that period, the CLÁR and RAPID leveraged expenditure schemes would have satisfied such criteria. 3. Terms of Reference 1. Identify the objectives of leveraged expenditure under the CLÁR and RAPID programmes; 2. Evaluate the extent to which these objectives have been achieved and comment on the effectiveness of the leveraged funding strategy in the achievement of these objectives; 3. Examine the compatibility of the objectives of leveraged expenditure under the CLÁR and RAPID programmes and the eligibility criteria for the leveraged schemes and confirm that these eligibility criteria were properly and consistently applied; 4. Identify the level and trend of costs, staffing, management and other resources, associated with leveraged expenditure under CLÁR and RAPID, input by the Dept. of Community, Equality & Gaeltacht Affairs and by other selected relevant State organisations. Identify the outputs and comment on the efficiency with which these outputs have been produced; 9 5. Examine and evaluate existing performance and impact indicators and specify potential future performance indicators that might be used to better monitor leveraged funding under the CLÁR and RAPID programmes; 6. Evaluate the degree to which the objectives warrant the continued allocation of leveraged funding and consider alternative approaches to achieving the same objectives; 7. Examine the overlaps and complementarities, if any, between the leveraged schemes and selected relevant schemes/programmes operated by the Department of Community, Equality & Gaeltacht Affairs; and 8. Make recommendations in relation to the continued relevance of the leveraged funding approach, the strategies employed and the efficiency of implementation. 4. Brief introduction to the CLÁR and RAPID programmes 4.1 Introduction to RAPID The RAPID Programme was launched in 2001. It is a focused Government initiative which targets 51 of the most disadvantaged urban areas in the Country. It was introduced on foot of commitments in the Programme and Prosperity and Fairness (PPF) (2000) for a targeted investment programme in urban disadvantaged areas. Fitzpatrick Associates (2006) in their evaluation of the RAPID programme noted that it is a reactive programme, operating in areas already exhibiting the results of decades of underinvestment. The RAPID Programme aims to ensure that priority attention is given to tackling the spatial concentration of poverty and social exclusion within these areas, through the targeting of State resources available under the National Development Plan (NDP). RAPID is built on the recognition of the existence of a range of planning, coordination and development structures in Ireland. It is designed to effectively work with and build on these existing structures. The programme requires Government Departments and State Agencies to bring about better coordination and closer integration in the delivery of services. Initially, the programme covered 25 of the most disadvantaged areas in Cities and other large urban areas. In 2002, the second strand of the programme extended its coverage to a further 20 provincial towns. In June 2006, RAPID status was extended to Ballyfermot in Dublin, bringing the total number of areas to 46. Since 2008, DCRGA focused on an analysis of 2006 Census data with a view to ensuring that the boundaries of existing RAPID areas were appropriate. A key concern was to ensure that the effectiveness of the programme was not diluted and that Government action continued to prioritise and target communities with the greatest needs. In May 2009, following an independent review of relevant 2006 Census data, the towns of Ballina, Dungarvan, Enniscorthy, Mullingar and Rathkeale were included in the RAPID programme bringing the number of areas to 51. A full list of the areas is in APPENDIX I. 10 The areas selected for inclusion in the programme have been identified by objective criteria as being the most deprived areas in the Country. The criteria include the levels of early school leaving; the proportion of one parent households; the unemployment rate; the proportion of social housing; and the age dependency rate. The RAPID leveraged schemes were introduced in 2004. They supported small scale local actions through co-funding with other Departments, State Agencies, and Local Authorities. All leveraged schemes related to capital projects2. All seven schemes under the programme were leveraged, acting as a lever to elicit money from other Government Departments, State Agencies and Local Authorities through co-funding arrangements. The RAPID leveraged schemes from 2006-2009 inclusive are outlined at APPENDIX II along with details of the amounts paid under each scheme over the same period. Responsibility for delivering the programme is with DCRGA, with Pobal3 coordinating its implementation on behalf of DCRGA. However, it is a matter for each individual Department to respond to issues of funding within its area of responsibility. Pobal also acts as a conduit between DCRGA and each RAPID AIT by means of a number of liaison officers based throughout the Country. These officers assist each area in the implementation of their projects. A multi-tiered implementation structure is in place to ensure that the RAPID programme progresses as originally envisaged and results in real benefits for local communities, consisting of a National Monitoring Committee (NMC); City / County Monitoring Group (CCMG); and AIT supported by a full time RAPID coordinator who is employed by the Local Authority. Each AIT prepares a plan identifying the needs of its area. A short description of the role of the NMC, CCMG and AIT is provided as part of a RAPID Programme Flowchart at APPENDIX III. 4.2 Pobal Pobal plays a coordination, support, administration and monitoring role in relation to the RAPID programme. Three levels of support are provided from within Pobal: Direct training is provided on a National basis on issues relevant to all local coordinators. As the programme develops, information exchange on successful approaches and best practice are also provided to all coordinators; Regional support clusters are organised. These look at issues of particular relevance to a region (e.g. the mechanisms of State service delivery within a region) and at particular strands of work taking place across a number of RAPID areas (e.g. community safety projects); and Contact is maintained on an individual basis with local coordinators to facilitate information exchange on operational matters and to identify the key issues of concern to them within their area. 2 Routine maintenance works were considered ineligible Pobal is a not for profit company with charitable status that manages programmes on behalf of the Irish Government and the EU. It is an intermediary that works on behalf of Government to support communities and local agencies toward achieving social inclusion, reconciliation and equality. 3 11 4.3 Overall objectives of the RAPID programme The RAPID programme’s primary objective was to address the infrastructural deficit that had developed in the poorest urban areas. Despite the Celtic Tiger many areas had not benefited and these areas in addition to having very old and outdated community infrastructure, also had many social problems such as drug abuse, vandalism and graffiti. These areas also had a much higher than average population on Social Welfare payments and very high unemployment rates. In addressing the infrastructural deficits that had developed, it was hoped that the social problems would be improved. For example, if teenagers had adequate recreational facilities then many will use these and spend less of their time engaging in anti-social practices. Schemes such as Closed Circuit Television (CCTV) and other schemes would obviously lead to a reduction in this kind of behaviour, however to succeed, the schemes also had to include progressive elements such as playgrounds and additional sports facilities. 4.4 Introduction to CLÁR The rural strand of the RAPID Programme, to be known as CLÁR, was launched in 2001. The CLÁR Programme was targeted at a number of rural areas where population decline had been the most significant over the 1926 to 1996 period, based on census of population data and was introduced to address depopulation and deficits in infrastructure and services in rural areas. It is a programme for revitalising rural areas. It provided co-funding together with other Government Departments, State Agencies, Local Authorities, and in some instances local communities, aimed at accelerating investment in selected priority developments under the NDP in order to tackle the decline in the regions identified. These investments supported physical, economic and social infrastructure across a variety of schemes. The schemes under the Programme covered a wide variety of developments such as Water & Sewerage Schemes, Sports capital projects, Health projects, School Outdoor Play facilities, Bilingual signage, and Coastal projects. The areas originally selected for inclusion in the CLÁR Programme were those which suffered the greatest population decline from 1926 to 1996, with the exception of the Cooley peninsula (which was included based on the serious difficulties caused there by Foot and Mouth disease). The average population loss in these regions was 50% and the total population benefiting was 284,000 across 17 counties. Following an analysis of the Preliminary 2002 Population Census data, the CLÁR areas were reviewed and extended in January 2003 arising from a commitment in the Agreed Programme for Government. The total population covered increased to 362,000 (from 284,000) across 18 counties with part of one other county added. The Programme was further extended in April 2006 to include areas with an average population loss of 35% per county between 1926 and 2002. Parts of five new counties were added, increasing the population benefiting from the Programme to nearly 727,000. The Programme covers parts of 22 counties and all of Co. Leitrim, with Counties Kildare, Wexford and Dublin being the only Counties without districts included in the Programme. 12 The CLÁR leveraged schemes from 2006-2009 inclusive are outlined at APPENDIX IV along with details of the amounts paid under each scheme over the same period. 4.5 Overall Objectives of the CLÁR programme 1. To target investment in rural areas. These areas would not normally attract investment due to depopulation, isolation and the expense involved in providing infrastructure and services. 2. To leverage other funding from lead departments and agencies that normally would not be provided due to the reasons outlined in point 1 above. 3. Balanced provision of infrastructure and services in rural areas. 5. The rationale for the CLÁR and RAPID leveraged expenditure approach 5.1 Rationale for the CLÁR leveraged expenditure approach 1. To provide infrastructure and services not normally provided. 2. To provide a financial incentive to other Departments and agencies to make funds available for the provision of infrastructure and services. 3. Equal access to infrastructure and services. The cost of providing the physical, economic and social infrastructure required in CLÁR areas could sometimes be prohibitive due to high unit costs and low population density issues. CLÁR funding (which leveraged funding from other sources i.e. public and private) enabled physical, economic and social infrastructure to be provided in CLÁR areas that may not otherwise have been possible. CLÁR was set up because of a need to influence policy regarding the provision of infrastructure and services in rural areas. DCRGA was not the lead department for the provision of certain services/infrastructural projects and was not in a position to provide funding alone but worked in partnership with the lead departments and agencies to create a wider provision of services to the benefit of a greater population in rural areas. 5.2 Rationale for the RAPID leveraged expenditure approach The RAPID Programme was in existence a few years before DCRGA introduced the leveraged schemes. It was felt that the other State Bodies needed encouragement to entice them to invest further in RAPID areas. The leveraged schemes were designed as a stimulus to encourage State Bodies to invest further in the designated areas. For example, if a Local Authority had €50,000 to invest in either a RAPID or non-RAPID area, but it was aware that if they spent the €50,000 on RAPID that an additional €25,000 would be made available to them, so that essentially they were getting €75,000 of facilities for only €50,000, then they would be more likely to spend the funds in RAPID areas. 13 5.3 The current status of leveraged schemes under both programmes At present, all leveraged schemes under both CLÁR and RAPID are closed to new applications, with the majority being closed since 2008. However, after the closure, there remained pre-existing funding commitments for DCRGA and the relevant co-funding partners in relation to projects that were approved prior to the closure. 6. Review Steering Group The review was overseen by a Steering Committee under the direction of an independent chairperson and comprising officials from DCRGA, Department of Finance (D/Fin) and Pobal. The composition of the Steering Committee is set out in APPENDIX V. The Steering Committee played an active role in the review process and met on a number of occasions to review progress on findings, conclusions and recommendations. 14 CHAPTER 2: EVALUATE THE EXTENT TO WHICH THE KEY OBJECTIVE WAS ACHIEVED AND COMMENT ON THE EFFECTIVENESS OF THE LEVERAGED EXPENDITURE APPROACH 1. Introduction The key objective of the leveraged expenditure approach under both programmes was to increase investment in the designated areas of each programme. This review attempts to evaluate the extent to which this objective was achieved over the 2006 to 2009 period inclusive, by examining how partner organisations responded to the availability of leveraged funding in the case of the following selected CLÁR and RAPID schemes: CLÁR Primary Schools Outdoor Play Facilities; CLÁR Group Water Scheme; CLÁR and RAPID Sports Capital Top-up; CLÁR Class II and III roads and bridges; and RAPID Playgrounds. One of the main criteria used in selecting this subset was the relative volume of expenditure involved. In relation to CLÁR, the selected schemes accounted for approximately 54%, 59%, 56%, and 57%, respectively, of total expenditure for each of the years in the 2006 to 2009 period. In relation to RAPID, the selected schemes accounted for approximately 61%, 65%, 27%, and 53%, respectively, of total expenditure over the same period. A brief description of other CLÁR and RAPID leveraged schemes in existence during the period is provided at APPENDIX VI. 2. CLÁR Primary Schools Outdoor Play Facilities Scheme 2.1 Introduction This scheme had been in operation prior to 2006. This review considers the scheme for the period from 2006 to 2009 inclusive. It aimed to improve outdoor play facilities in small rural primary schools in CLÁR areas. In 2006 and 2007, this scheme was co-funded by CLÁR section:DES:local sources on a 1.5:1.5:1 basis. DES withdrew as a co-funder from the beginning of 2008. In the main, from 2008, new approvals were funded by CLÁR and the local community on a 3:1 basis. There was evidence in some instances that the local contribution was coming from other State grants. Controls should have been put in place for this scheme to ensure that the local contribution was not provided from sources other than local ones. This scheme was closed to new applications in 2010. The type of projects funded cover the landscaping of play areas; the supply of goalposts, nets, basketball hoops etc.; and other recreational facilities for outdoor play areas. Since 2008, the maximum level of funding provided by CLÁR was €7,500 with a minimum matched funding of €2,500 from local sources. Prior to this funding of €3,750 was provided by both DCRGA 15 and DES. Applications for funding were made directly to CLÁR section. Each school could only avail of funding from this scheme on a single occasion. Before looking at the effect of the CLÁR scheme itself, it is necessary to look at other relevant schemes that support the development of play facilities / areas in primary schools. 2.2 Other DCRGA Schemes in relation to Play Facilities From the 1st January 2002, projects approved under the Gaeltacht Improvements Grants scheme, automatically attracted top-up funding of up to 20% from the CLÁR programme, where applicable. Some play facilities were sanctioned for funding. Updated lists of Gaeltacht sanctions were sent to CLÁR section on a regular basis. Details of all approvals under the CLÁR Play Facilities scheme over the 2006 to 2009 period inclusive were forwarded to the Gaeltacht section of DCRGA4 for crosschecking purposes in relation to any duplication that may have occurred. The Gaeltacht section informed the review that no duplication occurred. 2.3 Other DES Schemes that support Play Facilities/Areas These are the Minor Works Grant and the Summer Works Scheme. In addition, when DES is providing funding for new Primary Schools on ‘green field’ sites, some funding is also set aside for playground facilities/areas. Minor Works Grant Scheme The DES Minor Works Grant is intended to provide a school with the capacity to carry out day to day capital spending on the physical infrastructure of the school (e.g. items such as broken windows, broken doors etc.), without having to seek approval for each item from DES. Funding under this scheme also facilitates improvements to school grounds and the purchase of Physical Education equipment. The funding provided to each primary school under the Minor Works Grant scheme from 2006 to 2009 inclusive is calculated as follows: TABLE 1 Block allocation to each school €5,500 Additional allocation for each pupil €18.50 Additional allocation for each special needs pupil €74 Summer Works Scheme DES also operates the Summer Works Scheme. This scheme facilitates smaller works to be carried out by schools. Commensurate with the level of funding available, demonstrably necessary projects which command the highest priority rating are approved to proceed by DES. The ten priority ratings are as follows: 1. Gas Works; 2. Electrical Works; 3. Mechanical works; 4 The Gaeltacht functions were transferred to the Dept. of Arts, Heritage and the Gaeltacht with effect from May 2011, following the disestablishment of DCEGA. 16 4. Projects to facilitate inclusion and access for special needs pupils; 5. Toilet facilities; 6. Roof works; 7. Window projects; 8. Curricular requirement projects; 9. Other structural improvements; and 10. External environment projects. The provision or upgrade of a play area was under Priority 10. As DES is only in a position to fund all categories when sufficient funding is available, de facto funding for Priority Rating 10, external environment projects, is occasional. There was no Summer Works Scheme in 2008. Please see the TABLE below, which provides information specifically in relation to the Provision or Upgrade of a Play area under Priority 10 of the Summer Works Scheme. TABLE 2 Year 2006 2007 2009 Total Number of schools assisted in CLÁR areas Funding for CLÁR areas € 12 3 18 33 522,785 82,685 640,387 1,245,857 Number of schools assisted in non-CLÁR areas Funding for non-CLÁR areas € 37 8 48 93 2,251,908 360,125 2,566,057 5,178,090 Total number of schools assisted 49 11 66 126 Total funding provided € 2,774,693 442,810 3,206,444 6,423,947 2.4 Looking at the Summer Works Scheme on its own Analysing the Summer Works Scheme data on its own using the data provided in Table 2, approximately 24% of schools funded in 2006 were in CLÁR areas; approximately 27% in 2007, and approximately 27% in 2009 (giving an average of 26%). It was not possible to determine the spend per pupil across schools in CLÁR and non-CLÁR areas. Approximately 37% of Primary Schools in Ireland are located in CLÁR areas (1,207 out of 3,275). In all three years, the percentage of schools funded in CLÁR areas is below the percentage of schools that are located in CLÁR areas nationally. This shows a tendency for projects from disadvantaged areas to lose out when compared to nondisadvantaged areas, particularly as this scheme was not in receipt of any leveraged funding. The amount of funding provided to CLÁR areas in 2006 and 2007 was 19% of the total amount provided nationally. The figure was 20% in 2009. DES confirmed that the monies required for the CLÁR scheme came from the overall Primary Schools Capital allocation and did not specifically come from funding that was meant to be apportioned to the Summer Works Scheme Play Areas measure. Therefore, from the evidence gathered, DES continued to fund the same proportionate number of schools in CLÁR areas and continued to provide the same proportionate levels of funding to Primary Schools in CLÁR areas, while the CLÁR Play Facilities scheme was also in place. It was as if DES continued as it normally would have in its Summer Works Scheme Play Areas measure and was not influenced by any additional expenditure that it was paying towards the CLÁR scheme. In other 17 words, there was no policy shift from DES arising from the introduction of the CLÁR Play Facilities scheme. This was positive from a CLÁR area perspective. 2.5 Looking at the CLÁR scheme and the Summer Works Scheme measure together TABLE 3 Year 2006 2007 2009 Total Funding by DES to the CLÁR scheme Funding by DES to play areas in CLÁR € € 1,026,540* 593,554* 0 1,620,094 522,785 82,685 640,387 1,245,857 Total to CLÁR areas € Funding by DES to play areas in nonCLÁR € 1,549,325 676,239 640,387 2,865,951 2,251,908 360,125 2,566,057 5,178,090 Total to all areas € 3,801,233 1,036,364 3,206,444 8,044,041 * This amount was matched on a 1:1 basis as part of the CLÁR scheme It is interesting to provide a comparison of 2006 and 2007 (when the CLÁR incentive was availed of), with 2009 when the incentive of the CLÁR scheme was not availed of by DES. In overall terms, approximately 41% and 65%, respectively, of overall DES expenditure went to CLÁR areas in 2006 and 2007. In 2007, when DES had a much lower spend of just over €1m, the influence of the leveraged scheme was evident with CLÁR areas capturing 65% of the funding. When the leveraged scheme was no longer in place in 2009, approximately 20% of DES funding went to CLÁR areas. Across the period analysed, CLÁR schools got approximately 36% of the overall funding available from DES and CLÁR areas have 37% of the schools Nationally. However, had the CLÁR Play Facilities scheme not been in place, it is unlikely that Primary Schools in CLÁR areas would have achieved approximately 36% of overall funding. 2.6 Increased investment DCRGA succeeded in obtaining a leveraged funding amount of €1,620,094 from DES in the years 2006 and 2007, which DCRGA matched. On that basis, it can be said that the leveraged approach did increase investment in CLÁR areas in these years. There was a reduction in applications for this CLÁR scheme in 2008 and 2009. Therefore, it can be concluded that this scheme was effective in obtaining matching funding from DES to fund the majority of schools that wanted to avail of this scheme. Over the lifetime of the scheme, approximately 73% of primary schools in CLÁR areas were funded (DES provided information that there are 1,207 primary schools in CLÁR areas, which is approximately 37% of the total number in the whole Country). 2.7 Effectiveness No longer a priority for DES It appears that the provision of play facilities under the CLÁR scheme was not of sufficient priority to DES from 2008 onwards. It may have been a possibility that the overlap between the CLÁR scheme and the Summer Works Scheme play areas measure would have made it less of a priority. 18 Sole Statutory Funder When DCRGA became the sole statutory funder of this scheme, it could no longer be considered as a leveraged scheme. DCRGA did not get the same levels of matched extra investment in relation to the primary schools that it funded from 2008 onwards as it was now covering the funding that DES had been providing to the scheme. Leverage not matched Priorities can change very quickly for Departments and they must be adaptable in dealing with those changes from a financial perspective, by means of the yearly estimates allocations that are provided to them. Therefore, incentives of leveraged expenditure from other Departments could be matched in one year and not the next depending on priorities and circumstances. There is also the possibility that the overlap that existed between the CLÁR scheme and the Summer Works Scheme play areas measure may also have been a factor. There is always a level of uncertainty attached to a leveraged funding approach as it is dependant on the budget allocation of each of the co-funding partners. This uncertainty can be mitigated by advance agreement with co-funding partners on terms and funding. 3. CLÁR Group Water Scheme 3.1 Introduction This CLÁR scheme dealt with the construction of new group water schemes and the extension of existing schemes. Group Water Schemes consist of private entities involving two or more premises abstracting water from a common water source and sharing a pipe distribution system. Normally, these schemes are funded entirely through a DEHLG grant and a household contribution. However, in CLÁR areas, this funding would sometimes not cover the total cost of the schemes. In normal circumstances, Local Authorities do not consider the construction or extension of Group Water Schemes where the total cost of the schemes is not covered by this funding. If the total cost is greater than the DEHLG grant available and the household contribution, a shortfall arises. Whether individual Group Water Schemes go ahead or not once a shortfall develops, depends on how much funding a local community is prepared to put into a scheme. This scheme provided a top-up for group water schemes in CLÁR areas where the cost per house exceeded €7,618.42 (€6,475.66 DEHLG grant and €1,142.76 household contribution). The CLÁR funding was determined by taking the DEHLG grant and household contribution from the total cost of the scheme. This top-up facilitated the development of many more group water schemes in CLÁR areas which would not normally have proceeded due to high costs. CLÁR was attempting to contribute towards the provision of quality drinking water in these disadvantaged rural areas, as in the main, significant shortfalls would have arisen which would not have been funded by additional community contributions. Schemes were selected by the local authority on foot of applications received from groups. The applications in respect of this CLÁR scheme were submitted by the local authority to CLÁR section and the CLÁR funding was issued to the local authority. 19 Up until the end of 2006, the maximum CLÁR grant per house for each scheme was €8,382. From 2007 on, the cap on the grant was removed. The removal of the cap on the grant per house was to support the development of Group Water Schemes in CLÁR areas which would not normally go ahead due to high costs. If the cost per house was greater than €20,000, then the scheme was referred, in accordance with good practice, to DEHLG for comments/observations. DEHLG was also consulted by CLÁR section on all schemes costing more than €250,000 to CLÁR, or randomly on other schemes. 3.2 Other DEHLG Schemes that support the provision of water in Rural areas DEHLG Individual Water Supply Grant Scheme A grant of up to 75% of total cost, subject to a maximum grant of €2,031.58 is available for upgrading a private individual water supply. This grant is less than one third of the DEHLG grant towards the provision of a Group Water Scheme (i.e. €6,475.665 per household). Therefore, through these figures, DEHLG is highlighting the greater priority that it was affording to a Group Water Scheme when compared to a private individual water supply. DEHLG only fund private individual water supplies in instances where there is no alternative group or public supply available. 3.3 Other grants provided by DCRGA Supplementary Gaeltacht Grant Along with this CLÁR scheme, DCRGA also provided funding by means of a supplementary Gaeltacht grant for qualifying households with relevant proficiency in Irish of not more than €762 per house (i.e. two thirds of the household contribution) or 10% of the fixed cost per house, whichever was less. In weaker linguistic Gaeltacht areas, a reduced supplementary grant of generally 50% of the normal grant was permitted. 3.4 Schemes unlikely to have proceeded without CLÁR intervention All approvals under this CLÁR scheme from 2006 to 2008 inclusive have been examined and the following analysis has been produced in the TABLE below. TABLE 4 CLÁR Group Water Scheme Approvals Year Number where Number where Number where the shortfall was the shortfall was the shortfall was > €500 and > €1,000 and >€3,000 and <€1,000 per <€3,000 per <€5,000 per house* house* house* 2006 0 3 6 8 2007 3 1 10 16 2008 0 3 2 3 Total 3 7 18 27 * Schemes were chosen where all houses were located in CLÁR areas 5 Number where the shortfall was <€500 per house* Number where the shortfall was >€5,000 per house* 13 32 11 56 In February 2011, this was further increased by another €1,000 20 The information provided in TABLE 4 above leads to the following analysis. It is justifiable to say that it would have been unlikely for the 108 Group Water Schemes with a shortfall per house of >€500 to have proceeded, without the CLÁR scheme being in place. In such instances, each household is being asked to pay at least €500 more than the standard household contribution for a Group Water connection. One of the objectives of the CLÁR programme is to address deficits in infrastructure and services and this was done in this instance. There were a total of 3 schemes with a shortfall per house of less than €500 (the figures being €77, €120, and €160 per house in the respective schemes, with the number of houses being 16, 29 and 33 respectively). For example, Clare County Council returned the CLÁR grant in relation to one of these schemes, as it was not required. CLÁR section indicated that it was not uncommon for more houses to opt into schemes, after the initial application, resulting in a larger fund for a particular scheme, from an increased contribution from DEHLG and households. In some cases, this resulted in the CLÁR element being reduced or no longer being required. For the period 2006 to 2008 inclusive, approximately €42.2m was spent on this scheme in total with CLÁR section contributing approximately €15.9m and approximately €26.3m coming from the DEHLG grant and the household contribution. Therefore, investment in Group Water Schemes was increased as most schemes would probably not have proceeded without CLÁR intervention. A total of 122 schemes were supported in the period 2006 to 2008 inclusive. The average CLÁR funding approved per scheme between 2006, 2007 and 2008 was 36% of the total cost of the scheme. 3.5 DEHLG maintained its grant level at the same amount for CLÁR areas On an initial look at this scheme, one of the disappointments is that DEHLG kept its grant at the same level for both CLÁR and non-CLÁR areas at €6,475.66 per household throughout the period, despite approximately €15.9m being provided by CLÁR. However, it was never the intention of CLÁR section to cause an increase in this per household allocation by DEHLG. The funds that were provided by DEHLG for the Group Water schemes under this scheme could be said to have been leveraged as most of the schemes would not otherwise have proceeded. In 2002, Ireland was found by the European Court of Justice (ECJ) to be in breach of its obligations under the Drinking Water Directive by failing to ensure compliance with the quality standards and failing to reflect the binding nature of the Directive in relation to Group Water schemes. In response to the ECJ case, and in order to avoid imposition of financial penalties, a Rural Water Action Plan (An Action Plan for Rural Drinking Water Quality 2003-2006) was drawn up for the provision of treatment facilities for schemes identified as needing improvement. This represented a comprehensive and targeted response aimed at achieving compliance with the Directive within the shortest possible timeframe. The strategy being implemented to resolve deficiencies in these schemes was based on connecting poor quality schemes to a Local Authority public supply or, where this was not feasible, to provide standalone water treatment and disinfection equipment. DEHLG has outlined that it was still dealing with this priority over the 2006 to 2009 period, which is the period being considered by this review. 21 3.6 Increased Investment A total of 122 Group Water Schemes were approved for support in the 2006 to 2008 period inclusive, and it is unlikely that the vast majority of these schemes would have gone ahead without the CLÁR measure being in place. 4. CLÁR and RAPID Sports Capital Top-up schemes 4.1 Introduction DAST provided funding under the Sports Capital Programme. The Programme, which was managed by DAST, aimed to foster an integrated and planned approach to developing sports and physical recreation facilities throughout the Country. DAST has not run a Sports Capital Programme since 2008. The DAST Sports Capital Programme funding had been in place for some years prior to the introduction of the CLÁR and RAPID leveraged top-up funding mechanisms. This analysis considers the Sports Capital Programmes of 2006 to 2008 inclusive. The maximum CLÁR top-up was 20% of the DAST grant, with the RAPID figure being 30%. In 2006 and 2007, CLÁR section provided a top-up of the DAST sports capital grant to sports clubs in CLÁR areas that had been successful in securing this grant. The maximum top-up was 20% of the DAST grant, subject to overall CLÁR and DAST funding not exceeding 80% of the overall cost. The CLÁR Sports Capital top-up scheme did not have any new approvals from the end of 2007. From 2006 to 2008 inclusive, grant top-ups of 30% of the DAST approved grants, subject to overall funding not exceeding 80% of the total cost or the amount originally requested by the sporting body, were approved and paid by RAPID upon receipt of confirmation from DAST that its grants had been paid. In 2006 and 2007, the minimum level of ‘own funding’ to be provided by applicants was 20% of the total cost of the project for both CLÁR and RAPID areas. In 2008, the RAPID ‘own funding’ level was further reduced to 10%. The figure for all other areas was 30%. One of the criteria that DAST applied to applications was whether evidence had been provided that the project was located in a disadvantaged area. Applicants from CLÁR and RAPID areas were given additional points in the assessment process, with further additional points being available to RAPID applications if they had also been endorsed by an AIT. In order to provide full clarification, Sporting clubs in Gaeltacht areas did not apply to DAST for Sports Capital funding. Instead, they applied to the Gaeltacht section of DCRGA. This was a completely separate scheme to the one being provided by DAST. A further 10% top-up was provided to successful applicants who were located in CLÁR areas, giving an 80% total grant. The Gaeltacht section of DCRGA would pay the grant in full and reconcile with CLÁR section in relation to the 10% top-up. This top-up was paid from within the CLÁR subhead. 22 4.2 Amendments to scheme conditions in favour of CLÁR and RAPID areas The level of ‘own funding’ required from a non-disadvantaged area was 30%. In order to ‘level the playing field’ somewhat in relation to sporting bodies from CLÁR and RAPID to enable access to funds from the DAST Sports Capital Programme, the minimum level of ‘own funding’ required for local projects, when applying for funding from the programme, was reduced to 20% of the total cost of the project for CLÁR and RAPID areas in 2006 and 2007. In 2008, the RAPID ‘own funding’ level was reduced further to 10%. If a project had already been allocated a grant from another State funded source, it still had to provide at least 5% of the total cost of the project from its own funds. Although it was the case that the CLÁR and RAPID top-ups were paid after a project had successfully obtained a DAST Sports Capital Programme grant, DAST did acknowledge that it would have been aware of the CLÁR and RAPID top-ups when considering applications from CLÁR and RAPID areas. The National Institute for Regional Spatial Analysis (NIRSA) CLÁR statistics outline that approximately 18% of the population are located in CLÁR areas. Pobal population statistics outline that the population in RAPID areas is approximately 8% of the overall population. The adjustments made to the project selection process that were adopted by DAST following discussions with DCRGA appears to have worked in terms of the percentage of successful applicants who came from CLÁR and RAPID areas in 2006 to 2008 inclusive. The details in the tables below are based on information received from DAST. TABLE 5 % of Overall Successful Applications 2006 CLÁR RAPID ALL other areas Total 2007 16 13 71 100 2008 29 11 60 100 26 11 63 100 In 2006, CLÁR applications made up 16% of the total. At all other times over the three years, the percentage of applications from CLÁR and RAPID areas were in excess of the percentage of total population figures for these areas. Therefore, the stance adopted by DAST following negotiations with DCRGA can be said to have contributed to the position where the levels of successful applications from CLÁR and RAPID areas were in most cases, in excess of the population statistics for these areas. This is an example where changing the qualification rules for a particular grant can be used to favour disadvantaged areas. This was a very good result, but it cannot be attributed to the leveraged expenditure approach. 4.3 Increased Investment 398 sports clubs in CLÁR areas were provided with sports capital top-ups in 2006 and 2007 and 290 sports clubs in RAPID areas got sports capital top-ups under this RAPID scheme over the 2006 to 2008 period inclusive. 23 Overall levels of DAST Sports Capital Programme expenditure into CLÁR and RAPID areas Approximately 15% of overall Sports Capital Programme expenditure over the 2006 to 2008 period inclusive was approved for projects in CLÁR areas, with the corresponding figure for RAPID areas being 16%. This is a disappointing return for CLÁR areas considering that it has over double the population in its area compared to RAPID areas, along with the fact that there was a leveraged topup in place also. However, CLÁR section outlined that in CLÁR areas, it can be more challenging to develop the critical mass to pull together an infrastructural project proposal. Please see the table below. TABLE 6 OVERALL LEVELS OF DAST SPORTS CAPITAL PROGRAMME EXPENDITURE Year ALL other areas CLÁR € 2006 54,684,500 2007 55,878,700 2008 33,525,365 Total 144,088,565 RAPID € € 7,675,000 17,519,800 7,049,635 32,244,435 12,640,500 11,601,500 9,675,000 33,917,000 4.4 Effectiveness Comparing the levels of grants approved with the levels of grants that were sought This analysis is based on the levels of DAST Sports Capital grants approved as a percentage of the levels of grant sought. TABLE 7 Grant Approved as a % of Grant Sought Year CLÁR areas % 2006 2007 2008 RAPID areas % 55 47 39 All other areas % 37 41 37 59 48 45 For all three years, the percentages in ‘ALL OTHER AREAS’ are in excess of the CLÁR and RAPID figures, although there is only a single percentage point between CLÁR and ‘ALL OTHER AREAS’ in 2007. If the CLÁR and RAPID Top-ups were to be an added benefit for the designated areas, then the percentage figures outlined in Table 7 for CLÁR and RAPID areas should have been on a par with the percentage figures for ‘ALL OTHER AREAS’. If the CLÁR and RAPID top-ups are added to the information provided in the table above, the figures change as follows: TABLE 8 Grant Approved Plus Relevant Top-Up as a % of Grant Sought YEAR CLÁR areas % 2006 2007 2008 RAPID areas % 66 56 46 All other areas % 48 53 48 59 48 45 24 In all but one case, the CLÁR and RAPID percentage figures are now in excess of the ‘ALL OTHER AREAS’ percentage figures. Overall, it is striking that while the percentage figures for CLÁR and RAPID areas were below the percentage figures for ‘ALL OTHER AREAS’ prior to the leveraged topups being applied, post top-up they are not greatly in excess of the figures for ‘ALL OTHER AREAS’. In fact, in one case post top-up, the figure remains below the ‘ALL OTHER AREAS’ figure. Unintended incentive provided by the CLÁR and RAPID schemes The organisation deciding on the levels of grant aid can decide to allocate lower percentage levels of grant for areas that will be in receipt of a leveraged top-up. This allows the co-funding partner to fund more projects including projects that are in non-CLÁR or non-RAPID areas. In scenarios such as this, where the level of approvals are artificially low because relevant top-ups are due, then the top-up monies are effectively contributing to grants for non-designated areas, which is totally contrary to the objective of the scheme. 5. CLÁR Class II and III roads and bridges scheme 5.1 Introduction CLÁR co-funded Class II, Class III Local Roads and Bridges schemes on a 50:50 basis with the Department of Transport6, up to a maximum of €50,000 per project. The Local Authority selected the schemes and submitted applications to CLÁR. This additional funding under CLÁR was designed to upgrade or repair roads or parts of roads in isolated areas, which would not have been possible for Local authorities to do in normal circumstances. CLÁR approved funding and issued payments on receipt of claims and appropriate certification from the Local Authority. The rationale for CLÁR intervention in this scheme was to ensure that Class II and III roads and bridges in CLÁR areas were competing on a level playing pitch in relation to obtaining investment, when compared to the same roads and bridges in non-CLÁR areas. In this case the Local Authorities were already providing funding for Class II and III roads and bridges and CLÁR section was seeking to maximise investment into this area. The analysis produced in relation to this scheme is based on information received following the issuing of questionnaires to certain Local Authorities throughout the Country. Five Local Authorities were contacted in relation to providing information by means of questionnaire in relation to the analysis of the CLÁR Class II and III roads and bridges scheme. However, in three cases, either responses were not received or the information received was of insufficient quality in order to be used as part of the analysis. The main reason provided to us was there were hundreds of class II and III roads and bridges in the jurisdiction of the Local Authorities that had been approved for funding, particularly in the 2006 to 2008 period. The volume of data would have been large and would have been very time consuming to extract. The Gaeltacht section of DCRGA did confirm that they had a similar scheme in operation for Class II and III roads and bridges in Gaeltacht areas. Details were provided to the Gaeltacht section in 6 This Measure was funded on a 50:50 basis between DCRGA and DEHLG until there was a transfer of responsibility for roads to the Department of Transport. They continued with the 50:50 basis for funding with DCRGA. 25 relation to approvals over the period under the CLÁR scheme in order to crosscheck with the Gaeltacht scheme for duplication. The Gaeltacht section confirmed that no duplication occurred. 5.2 Increased Investment 712 Class II and III roads and bridges were approved for assistance over the 2006 to 2008 period inclusive. Analysis of County Sligo Sligo County Council’s response to the questionnaire is analysed below. TABLE 9 COUNTY SLIGO Year Total Cost € 2006 2007 2008 2009 3,519,814 4,661,222 4,527,125 2,050,040 Amount of CLÁR funding € Amount of CLÁR funding in % terms 387,784 223,967 221,375 N/A 11 5 5 N/A Amount of Local Authority funding to CLÁR areas exclusive of CLÁR funding € 2,559,030 3,688,755 3,573,450 1,472,665 Amount of Local Authority funding to CLÁR areas exclusive of CLÁR funding in % terms 73 79 79 72 Amount of Local Authority funding to non-CLÁR areas € 573,000 748,500 732,300 577,375 Amount of Local Authority funding to non-CLÁR areas in % terms 16 16 16 28 The level of funding, in each of the years that the CLÁR scheme was in place, was 84% in CLÁR areas. When the CLÁR scheme was no longer in place in 2009, the level of funding in CLÁR areas dropped to 72%. However, the first of these percentages includes CLÁR funding and the other does not. The table below outlines the percentage splits for Sligo County Council funding for CLÁR and nonCLÁR areas, when CLÁR funding was excluded in the years from 2006 to 2009 inclusive. TABLE 10 Year % funding in CLÁR areas 2006 2007 2008 2009 % funding in non-CLÁR areas 82 83 83 72 18 17 17 28 On the basis of the figures in this table, it is evident that the percentage levels of funding being provided by the Local Authority to CLÁR areas fell significantly in 2009 compared to the 2006 to 2008 period inclusive, when the CLÁR incentive was in place. This provides evidence that Sligo 26 County Council was incentivised by the CLÁR scheme to increase the levels of funding in CLÁR areas to match the leveraged funding that was being provided by DCRGA for this purpose. The drop from 82%-83% in the 2006 to 2008 period inclusive to 72% in 2009 is quite significant. There are factors that may have impinged on such a drop, aside from the removal of the CLÁR scheme. For example, once the CLÁR scheme was no longer in place, roads and bridges in nonCLÁR areas may have been in a worse state of repair than comparable ones in CLÁR areas and were therefore prioritised. Analysis of County Kerry The information provided by Kerry County Council is analysed below. TABLE 11 COUNTY KERRY Year Total Cost 2006 2007 2008 2009 7,020,009 5,894,645 5,713,521 3,911,634 Amount of CLÁR funding € Amount of CLÁR funding in % terms 248,496 299,209 295,745 N/A 4 5 5 N/A Amount of Local Authority funding to CLÁR areas exclusive of CLÁR funding € 6,063,857 5,111,836 4,736,609 3,302,279 Amount of Local Authority funding to CLÁR areas exclusive of CLÁR funding in % terms 86 87 83 84 Amount of Local Authority funding to non-CLÁR areas € 707,656 483,600 681,167 609,355 Amount of Local Authority funding to non-CLÁR areas in % terms 10 8 12 16 The level of funding, in the three years that the CLÁR scheme was in place, were 90%, 92% and 88%, respectively, in CLÁR areas. When the CLÁR scheme was no longer in place in 2009, the level of funding in CLÁR areas dropped to 84%. However, the latter percentage does not include CLÁR funding and the others do. The TABLE below outlines the percentage splits for Kerry County Council funding for CLÁR and nonCLÁR areas, when CLÁR funding was excluded in the years from 2006 to 2009 inclusive. TABLE 12 Year 2006 2007 2008 2009 % funding in CLÁR areas % funding in non-CLÁR areas 90 91 87 84 10 9 13 16 The percentage levels of funding being provided by Kerry County Council to CLÁR areas fell from an average of 89% in the 2006 to 2008 period to 84% in 2009. Although it is not a very significant shift in funding, it provides evidence that Kerry County Council was incentivised by the CLÁR scheme to 27 increase the level of funding in CLÁR areas to match the leveraged funding that was being provided by DCRGA for this purpose. 6. RAPID Playgrounds scheme 6.1 Introduction This scheme was co-funded with the Health Service Executive (HSE) on a 1:1 basis. Its aim was to increase the range of public play opportunities available to children and young people in designated RAPID areas. It provided funding for the provision of new playgrounds or the refurbishment of existing ones or the provision of Multi Use Games Areas (MUGA), in RAPID areas or areas that primarily served a RAPID area. The main objective of this scheme was the provision of community based play facilities in individual housing estates in RAPID areas. Attempting to achieve this concentration of playgrounds was always going to be perceived as being costly when compared to the normal number of playgrounds that are provided to communities in Ireland. In March 2004, the National Children’s Office published ‘READY, STEADY, PLAY!, A National Play Policy’. When the RAPID scheme was launched in 2004, co-funding was provided by the Dept. of Health and Children. The Dept. of Health and Children felt that this was a way of meeting their own strategic goals as well as those of DCRGA. Co-funding for this scheme was provided by the HSE from 2005 onwards. In 2006 to 2008 inclusive, each RAPID area could receive up to €66,000 in funding under this scheme, for each funding cycle that took place. For example, there was a funding cycle for this scheme in 2006/2007 and 2007/2008. Only capital projects were eligible for funding, with the site having to primarily serve a RAPID area and be in the ownership of the Local Authority. Universal design and safety standards were required to be adhered to. Appropriate recognition was to be given to the involvement of RAPID in the project. The relevant Local Authority in conjunction with the AIT for the appropriate RAPID area selected applications for approval. Pobal examined these applications on behalf of DCRGA and if they were in order, the applicants were invited to proceed with the projects. Monies were paid by the relevant Local Authorities, who then claimed from DCRGA in full. DCRGA recouped the relevant amounts from the HSE. Any amount over €66,000 had to be provided by either the relevant Local Authority or from other sources of funding. Given the disadvantaged nature of RAPID areas, such areas could not be expected to contribute any funding towards the provision of playgrounds in their areas. The analysis produced in relation to this scheme is based on information received following the issuing of questionnaires to certain Local Authorities throughout the Country. 6.2 Increased Investment 124 playgrounds were approved for support under the 2006/2007 and the 2007/2008 phases of the RAPID Playgrounds scheme. 28 The information provided by Sligo County Council and Sligo Borough Council is analysed below. Analysis of County Sligo TABLE 13 COUNTY SLIGO Year Number of playgrounds* How many playgrounds* approved for construction, refurbishment or expansion in RAPID areas How many playgrounds* approved for construction, refurbishment or expansion in non-RAPID areas 2006 2 1 1 2007 5 2** 3 2008 2 1** 1 2009 0 0 0 Total 9 4 5 * MUGA were not included in the return regarding County Sligo ** 9 playgrounds were included in the return with one playground in Doorly Park, Sligo Town being included only once even though it was funded in both 2007 and 2008 for different aspects of work to the playground itself. Using the Pobal estimated population figures for RAPID areas, it can be ascertained whether the development of playgrounds in RAPID and non-RAPID areas over the period was in proportion to the population of these areas. TABLE 14 COUNTY SLIGO Area Estimated population Playgrounds approved for construction, refurbishment or expansion from 2006 to 2009 inclusive Population per each playground approved for construction, refurbishment or expansion RAPID 4,645 4* NON56,249 5 RAPID * The Doorly Park playground has only been counted once for this analysis 1,161 11,250 The results of this table provide evidence that RAPID areas were favoured in terms of the work that took place over the period in comparison with the non-RAPID areas of the County. As the population of the RAPID area is only approximately 8% of the population of the whole County, a ratio of far less than 4:5 would have been expected in normal circumstances. It must be emphasised that the main objective was to provide community based play facilities in individual housing estates in RAPID areas. 29 The levels of funding provided by the Sligo Local Authorities to each of the playgrounds in the Sligo RAPID area is analysed below. TABLE 15 COUNTY SLIGO Year Total cost 2006 2007and 2008 2007 2008 Total Amount of Local Amount of local Amount of Amount of funding Authority funding community RAPID approved from any approved funding funding other sources € € € € € 175,508 72,908 0 66,000 36,600 373,000 116,000 0 36,000 221,000 40,000 60,000 648,508 10,000 0 198,908 0 0 0 30,000 60,000 192,000 0 0 257,600 In one instance, the total cost of the project was met by the RAPID scheme funding and there was no contribution made from Sligo Borough Council. For other playgrounds, RAPID provided three times as much, an equal amount, and one third of that provided by Sligo Borough Council. The pattern of RAPID contributions did not match what might be expected of a leveraged fund. However, this pattern of leveraged funding from RAPID/HSE gave flexibility to the relevant Local Authorities to find the appropriate solution for its RAPID areas. In overall terms, approximately 31% of the total cost of all RAPID projects was met by the Local Authority with 30% being provided by RAPID playgrounds scheme funding (i.e. RAPID/HSE). Given the overall levels of funding provided by the RAPID scheme, it is reasonable to say that it is unlikely that all 4 playgrounds in the Sligo RAPID area would have proceeded without the intervention being provided by the RAPID scheme, particularly the playground where all funding was met by the RAPID scheme, and the playground where 75% of the total cost was met by the RAPID scheme. Looking at the non-RAPID areas. TABLE 16 COUNTY SLIGO Year 2006 2007 2007 2007 2008 Total Total cost € 105,000 85,976 180,000 133,000 236,000 739,976 Amount of Local Authority funding approved € 44,523 0 67,500 0 0 112,023 Amount of local community funding € 477 6,878 45,000 0 0 52,355 Amount of funding approved from any other sources € 60,000 79,098 67,500 133,000 236,000 575,598 In three cases, no funding was provided by the Local Authority towards the overall cost of the project. The largest percentage amount of total cost that was met by a local community was 25%. 30 In overall terms, the Sligo Local Authorities provided approximately €199,000 to RAPID areas with a provision of approximately €112,000 to non-RAPID areas, over the period being analysed. The funding to RAPID areas equates to approximately 64% of the overall funding provided by the Sligo Local Authorities. This is an excellent return for the Sligo RAPID areas, considering that the RAPID areas represent approximately 8% of the County’s population. It outlines that the incentive being provided by the RAPID Playgrounds scheme worked in drawing expenditure to RAPID areas when compared to non-RAPID areas. Analysis of County Louth The next analysis is in relation to County Louth. The results of its questionnaire is analysed below. TABLE 17 COUNTY LOUTH Year 2006 2007 2008 2009 Total Number of playgrounds 3 1 2 4 10 How many playgrounds approved How many playgrounds approved for construction, refurbishment or for construction, refurbishment or expansion in RAPID areas expansion in non-RAPID areas 3 0 1 0 1 1 0 4 5 5 Using the Pobal estimated population figures for RAPID areas, it is possible to examine whether the development of playgrounds in RAPID and non-RAPID areas over the period was in proportion to the population of these areas. TABLE 18 COUNTY LOUTH Area RAPID NONRAPID Estimated population 7,996 103,271 Playgrounds approved for construction, refurbishment or expansion from 2006 to 2009 inclusive Population per each playground approved for construction, refurbishment or expansion 5 5 1,599 20,654 The results of this table provide evidence that RAPID areas were greatly favoured in terms of the work that took place over the period in comparison with the non-RAPID areas of the County. As the population of the RAPID area is only approximately 7% of the population of the whole County, a ratio of much less than 1:1 would have been expected in normal circumstances. It must be emphasised that the main objective was to provide community based play facilities in individual housing estates in RAPID areas. The next analysis will be in relation to the levels of funding provided by the Louth Local Authorities to each of the playgrounds in the Louth RAPID areas. 31 TABLE 19 COUNTY LOUTH Year 2006 2006 2006 2007 2008 Total Total cost € 177,648 105,726 179,053 111,937 213,865 788,229 Amount of Local Amount of local Authority funding community approved funding € € 105,648 39,726 13,053 0 60,806 219,233 Amount of RAPID funding € 0 0 0 0 0 0 0 66,000 66,000 66,000 66,000 264,000 Amount of funding approved from any other sources € 72,000 0 100,000 45,937 87,059 304,996 It is interesting to note the much higher level of funding provided by the relevant Local Authority to the single project that did not receive RAPID funding. In one instance, approximately 59% of the total cost of a project was met by RAPID funding and there was no contribution made from the relevant Local Authority. An additional €13,000 of funding for this project was provided by the RAPID Housing Estate Enhancement scheme. In overall terms, approximately 28% of the total cost of all RAPID projects was met by the Local Authority with 33% being provided by RAPID playgrounds scheme funding. Given the overall levels of funding provided by RAPID, it is reasonable to say that it is unlikely that all 5 playgrounds in the Louth RAPID areas would have proceeded without the intervention being provided by the RAPID scheme, particularly the playground where 59% of the total cost was met by the RAPID scheme. Looking at the non-RAPID areas. TABLE 20 COUNTY LOUTH Year 2008 2009 2009 2009 2009 Total Total cost € 100,891 16,003 22,951 135,003 135,003 409,851 Amount of Local Authority funding approved € 43,428 4,595 13,059 100,003 100,003 261,088 Amount of local community funding € 0 0 0 0 0 0 Amount of funding approved from any other sources € 57,463 11,408 9,892 35,000 35,000 148,763 No funding was provided by the local community in relation to any of these projects. In overall terms, the Louth Local Authorities provided €219,233 to RAPID areas with a provision of €261,088 to non-RAPID areas. The funding to RAPID areas equates to approximately 46% of the overall funding provided by the Louth Local Authorities. This is a very good return for the Louth 32 RAPID areas, considering that the RAPID areas represent approximately 7% of the County’s population. Another point emerges in relation to 2009 when the RAPID Playgrounds scheme was no longer in place. In the 2006 to 2008 period, 5 playgrounds were funded in the Louth RAPID areas versus 1 in non- Rapid areas. In 2009, no playground was funded in RAPID areas versus 4 in non-RAPID. Analysis of County Kilkenny The next analysis is in relation to County Kilkenny. TABLE 21 COUNTY KILKENNY Year Number of playgrounds 2006 2007 2008 2009 Total 1 2 3 3 9 How many playgrounds approved How many playgrounds approved for construction, refurbishment or for construction, refurbishment or expansion in RAPID areas expansion in non-RAPID areas 1 0 1 1 2 1 0 3 4 5 Using the Pobal estimated population figures for RAPID areas, it is possible to see whether the development of playgrounds in RAPID and non-RAPID areas over the period was in proportion to the population of these areas. TABLE 22 COUNTY KILKENNY Area RAPID NONRAPID Estimated population 3,259 84,299 Playgrounds approved for construction, refurbishment or expansion from 2006 to 2009 inclusive Population per each playground approved for construction, refurbishment or expansion 4 5 815 16,860 The results of this table provide evidence that RAPID areas were favoured in terms of the work that took place over the period in comparison with the non-RAPID areas of the County. As the population of the RAPID area is only approximately 4% of the population of the whole County, a ratio of substantially less than 4:5 would have been expected in normal circumstances. It must be emphasised that the main objective of this scheme was to provide community based play facilities in individual housing estates in RAPID areas. The next analysis will be in relation to the levels of funding provided by the Kilkenny Local Authorities to each of the playgrounds in the Kilkenny RAPID area. 33 TABLE 23 COUNTY KILKENNY Year 2006 2007 2008 2008 Total Total cost € 66,000 146,000 25,000 66,000 303,000 Amount of Local Authority funding approved € Amount of local community funding € 0 80,000 0 0 80,000 0 0 0 0 0 Amount of Amount of funding RAPID approved from any funding other sources € € 66,000 0 66,000 0 0 25,000 66,000 0 198,000 25,000 In two instances, the total cost was met in full by the RAPID scheme funding and in another case, the total cost was met by another source. The Local Authority only contributed to the funding of one playground. As outlined in the analysis of another County, the pattern of funding is not like that of a leveraged fund. However, this pattern of leveraged funding from RAPID/HSE gave flexibility to the relevant Local Authorities to find the appropriate solution for its RAPID areas. In overall terms, approximately 26% of the total cost of all RAPID projects was met by the Local Authority with 65% being provided by RAPID playgrounds scheme funding. In other words, RAPID provided 2.5 times more funding to the projects than the Local Authority. Given the overall levels of funding provided by RAPID, it is reasonable to say that it is unlikely that all 4 playgrounds in the Kilkenny RAPID area would have proceeded without the intervention being provided by the RAPID scheme, given that three of the four playgrounds had no funding from the Local Authority. Playgrounds were provided that would otherwise not have been provided, but there is little or no evidence of extra funding being provided to RAPID areas. We will next look at the non-RAPID areas. TABLE 24 COUNTY KILKENNY Year 2007 2008 2009 2009 2009 Total Total cost € 44,316 160,000 47,000 70,000 50,000 371,316 Amount of Local Authority funding approved € 3,546 80,000 47,000 35,000 0 165,546 Amount of local community funding € 0 0 0 35,000 0 35,000 Amount of funding approved from any other sources € 40,770 80,000 0 0 50,000 170,770 In one case, no funding was provided by the relevant Local Authority towards the overall cost of the project. In another instance, the percentage amount of total cost that was met by a local community was 50%. 34 In overall terms, the Kilkenny Local Authorities provided €80,000 to RAPID areas with a provision of €165,546 to non-RAPID areas. The funding to RAPID areas equates to approximately 33% of the overall funding provided by the Kilkenny Local Authorities. The €80,000 was provided for one playground, which was co-financed by RAPID. Of the remaining three playgrounds in RAPID areas, two were fully funded by RAPID and the other fully funded from another source. Another analysis can be made in relation to 2009 when the RAPID Playgrounds scheme was no longer in situ with the previous three years when it was. In the 2006 to 2008 period, 4 playgrounds were funded in the Kilkenny RAPID areas versus 2 in non- Rapid areas. In 2009, no playground was funded in RAPID areas versus 3 in non-RAPID. This would suggest that after the intervention of the RAPID scheme, the priority in Kilkenny was to provide playgrounds in non-RAPID areas, with the population statistics indicating that there is good reason for this. Kilkenny has a very small RAPID population (3,259 per the statistics) and four playgrounds were provided to serve this population. This meant that there was a playground for every 815 people which would roughly equate to a playground for every 100 children or so. In contrast, the non-RAPID areas have a playground for every 16,860 people. Analysis of Fingal The next analysis is in relation to Fingal County Council TABLE 25 FINGAL Year Number of playgrounds* How many playgrounds* approved for construction, refurbishment or expansion in RAPID areas How many playgrounds* approved for construction, refurbishment or expansion in non-RAPID areas 2006 6 0 6 2007 4 1** 3 2008 5 0 5 2009 0 0** 0 Total 15 1 14 * MUGA were not included in the return from Fingal County Council ** The Corduff playground in Blanchardstown has been counted only once even though funding was provided to it for construction and upgrading in both 2007 and 2009 respectively. Using the Pobal estimated population figures for RAPID areas, it is possible to examine whether the development of playgrounds in RAPID and non-RAPID areas over the period was in proportion to the population of these areas. 35 TABLE 26 FINGAL Area Estimated population RAPID NONRAPID Playgrounds approved for construction, refurbishment or expansion from 2006 to 2009 inclusive 11,867 227,525 Population per each playground approved for construction, refurbishment or expansion 1 14 11,867 16,252 The next analysis will be in relation to the level of funding provided by Fingal County Council to the playground in the Fingal RAPID area. TABLE 27 FINGAL Year 2007 and 2009 Total cost Amount of Local Amount of local Amount of Amount of funding Authority funding community RAPID approved from any approved funding funding other sources € € € € € 107,225 6,164 0 101,061 0 Looking at the non-RAPID areas. TABLE 28 FINGAL Year 2006 2006 2006 2006 2006 2006 2007 2007 2007 2008 2008 2008 2008 2008 Total Total cost Amount of Local Amount of local Authority funding community funding approved € € € 595,401 595,401 148,188 148,188 136,912 136,912 144,210 144,210 141,520 141,520 129,602 129,602 133,776 133,776 133,545 133,545 159,316 159,316 150,217 150,217 71,824 71,824 504,915 504,915 148,624 148,624 439,242 314,242 3,037,292 2,912,292 Amount of funding approved from any other sources € 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 125,000 125,000 36 The only instance in non-RAPID areas where ‘other sources’ funding was received was from Malahide Demense, where the €125,000 came from their income from concerts, for the refurbishment of the Demense’s playground. In overall terms, Fingal County Council provided €6,164 to RAPID areas with a provision of €2,912,292 to non-RAPID areas. The funding to RAPID areas equates to approximately 0.2% of the overall funding provided by the Council. This is a poor return in relation to the RAPID areas considering that they make up approximately 5% of the population of the Fingal County Council region, particularly when it is considered that the incentive of the RAPID playgrounds scheme was in place from 2006 to 2008 inclusive. In their Questionnaire return, Fingal County Council informed us of the following: ‘The scheme coincided with a large scale Playground Capital Investment Programme which was driven by the high levels of Development Levies available. On account of this, in the Fingal area at any rate, the RAPID scheme was less necessary than it is now……………….’ Enough information has been provided above regarding Fingal in order to be able to say that it appears that the RAPID funding was not required (it appears that all the funding available from RAPID/HSE under the various iterations of the RAPID scheme were not availed of). The Council had a large scale Playground Capital Investment Programme which coincided with the RAPID playgrounds scheme. Therefore, it appears that Fingal had enough capital resources at its disposal in order to fund the project in the RAPID area that did avail of RAPID funding. The RAPID scheme leveraged less than expected into the Fingal RAPID area and had no influence on how Fingal allocated its resources to playgrounds. 6.3 Effectiveness NPRRC data The National Play and Recreation Resource Centre (NPRRC) under the auspices of the Office of the Minister for Children and Youth Affairs was set up to provide information, support, and advice on a range of issues affecting the development of children's play in Ireland. It provides details on its website www.nprrc.ie of the number of playgrounds in each County in Ireland. It accepts that the list may not be up to date and naturally enough, there is no distinction between RAPID and nonRAPID areas. Using the details from the NPRRC website and the questionnaire returns, in relation to County Sligo, there are 6 playgrounds in Sligo Town (in both the RAPID and non-RAPID parts of the town), 4 of which received funding under the RAPID scheme over the 2006 to 2008 period. In Drogheda and Dundalk, the two RAPID areas in County Louth, there are 8 playgrounds (in both the RAPID and non-RAPID parts of the towns), 4 of which received funding under this Playgrounds scheme over the 2006 to 2008 period. These are very healthy returns for these towns, particularly for Sligo town, and it could be considered that perhaps there is now an overprovision of such facilities in Sligo Town given the overall population that it supports. Perhaps the funding that was provided over the 4 iterations of the RAPID Playgrounds scheme contributed to such a scenario arising. Because of this, it was always going to be likely that the provision of playground facilities in some RAPID areas would become very concentrated. 37 It is not necessary to look at the NPRRC data in order to see how well the Kilkenny RAPID area did as a result of this scheme. Kilkenny has a very small RAPID population (3,259 per the statistics) and four playgrounds were constructed, refurbished, or expanded over the 2006 to 2009 period inclusive, to serve this population. This meant that in this period alone, there was a playground constructed, refurbished, or expanded for every 815 people which would roughly equate to a playground for every 100 children or so. 7. The compatibility of the leveraged expenditure approach objectives with the eligibility criteria for the leveraged schemes The eligibility criteria for the leveraged schemes being analysed by this review are provided in APPENDIX VII. The key objective of the leveraged expenditure approach under both programmes was to increase investment in the designated areas of each programme. It was found that this objective was compatible with important eligibility criteria of each of the schemes being analysed as part of this review. 7.1 Confirmation that the eligibility criteria were properly and consistently applied The Internal Audit Unit of DCRGA advised that a random sample of 5% of approved applications should be checked for this purpose, provided that the overall levels of applications were not excessive. This is a ‘rule of thumb’ that is adopted by this Unit in similar circumstances. Both sections were visited where a random sample of 5% of approvals over the period (as outlined in the Outputs section of Chapter 4) were chosen in relation to each selected scheme. On the basis of this analysis, it can be confirmed that the eligibility criteria for the selected schemes were properly and consistently applied. 8. Overlaps / complementarities between the CLÁR / RAPID leveraged schemes and selected relevant schemes / programmes operated by DCRGA The Rural Development Programme (RDP) 2007-2013 was examined in connection with the CLÁR leveraged schemes and the new Local and Community Development Programme (LCDP) with the RAPID leveraged schemes. In overall terms, it was found that there was no overlap and that there was a complementary relationship between the CLÁR leveraged schemes and the current RDP. In essence, a complementary relationship exists between the new LCDP and the RAPID leveraged schemes. 9. Conclusion This review has found that the leveraged expenditure approach did succeed in bringing increased investment into CLÁR and RAPID areas in the years in which the leveraged schemes were active. The costs of bringing this extra investment and other weaknesses found with the approach are discussed in the following Chapters. 38 CHAPTER 3: EFFICIENCY 1. Introduction The Dept. of Finance VFM Guidance Manual (2007) describes efficiency as the ratio of Outputs to Inputs, which can be viewed in two different ways: Whether the same level of Output can be achieved with fewer Inputs i.e. at a lower cost; or Whether a better quality or higher quantity of Outputs can be delivered from a fixed amount of Input. In normal evaluation circumstances, the total value of overall approvals into an area would be an Input and not an Output. However, the review found that given the nature of the leveraged approach, the overall approvals into an area should be regarded in these circumstances as an Output. Apart from the amounts of leveraged funding spent by DCRGA and its relevant co-funding partners, the main Input was the administration effort (in terms of staff and other resources) by CLÁR, RAPID and the co-funding partners. Arising from the explanation above, the following efficiency issues arose. 2. CLÁR Primary Schools Outdoor Play Facilities Scheme 2.1 Overlaps with the DES Minor Works Grant Scheme and with DES Summer Works Scheme for Play Areas Minor Works Grant Scheme Schools could use the funding they received under the Minor Works Grant scheme for play facilities/areas, although it was not specifically for this purpose. Therefore, there was potential for an overlap between the CLÁR scheme and this scheme, but it was at the discretion of each individual school as to what to spend their Minor Works Grant monies on. Therefore, any overlap was dependant on the decisions made by each individual school in a CLÁR area. On that basis, indirect duplication could arise between the funding being provided by the DES Minor Works Grant Scheme and the CLÁR Play Facilities scheme. Once the CLÁR scheme was introduced, primary schools in CLÁR areas that may have been considering using part of their Minor Works Grant for playground facilities at that particular time, could now utilise this funding for other needs of the school. DES outlined that in 2010, it issued €8m under its Minor Works Grant scheme to all Primary Schools to address their playground and PE equipment requirements. In its opinion, such devolved funding allocations would render unnecessary further investment into this CLÁR scheme. The Minor Works Grant scheme could have been used to administer the CLÁR Primary Schools scheme on the basis of one off payments to all Primary Schools in CLÁR areas. However, over use of such a method of allocation is very crude and it does not result in the optimum allocation of resources to those who require them most. 39 Priority 10 Summer Works Scheme for Play Areas Prior to the initiation of the CLÁR scheme, both Departments acknowledged that there was a danger of an overlap between the proposed activities under the CLÁR scheme and activities under the Summer Works Scheme. In order to protect against this danger, DES was agreeable to the operation of the CLÁR scheme on the basis that lists of schools approved would be cross checked between both Departments to avoid dual funding occurring. However, funding in respect of playground development should only have been available from one source as opposed to the two outlined above. Rather than providing co-funding in relation to this particular CLÁR scheme, DES could have used its Summer Works Scheme funding to meet a range of priority needs, whereas the CLÁR section focus in this area was solely in relation to play facilities. The activities funded under each were as follows: TABLE 29 CLÁR scheme DES summer works scheme play areas measure Provision of a play area* Upgrade of a play area* Landscaping of play areas Provision of soft/safety play surfaces Marking out of surface yard games Construction of basketball/soccer/tennis courts Supply of goalposts, basketball hoops and nets Swings/Slides/Climbing Frames Supply of nets and posts for tennis, netball, volleyball and badminton Provision of storage sheds for play equipment Fencing * This includes the landscaping of play areas; the provision of play surfaces; and fencing. As outlined in TABLE 2, 126 schools nationally were assisted under the Summer Works Scheme for the provision or upgrade of a play area, with 327 of these being in CLÁR areas. From these 32, 20 received funding from both the Summer Works Scheme and the CLÁR primary schools outdoor play facilities scheme. Therefore, approximately 63% of the schools funded over the period from CLÁR areas under the DES Summer Works Scheme play areas measure, also received funding from the CLÁR scheme. The details are as follows: 7 One school received funding in both 2006 and 2007 from the Summer Works Scheme for the upgrading of a play area 40 TABLE 30 Year of approval for the summer works scheme County in which each school is located 2006 Westmeath 1 Cavan 1 Mayo 1 Monaghan 1 Mayo 2 Galway 1 Westmeath 2* Donegal 1 Sligo 1 Leitrim 1 Westmeath 2* Cork 1 Limerick 1 Cork 2 Donegal 2 Mayo 3 Roscommon 1 Monaghan 2 Laois 1 Clare 1 Limerick 2 Amount approved by DES for the CLÁR primary schools scheme € 3,059 2,048 3,546 3,750 2,062 3,750 3,063 1,056 912 3,750 Amount approved by CLÁR section for the CLÁR primary schools scheme € 3,750 3,000 3,750 3,750 3,750 3,750 3,299 3,750 3,729 3,750 3,750 3,000 3,750 3,750 3,750 3,750 3,299 3,750 3,729 3,750 Total 20 779,103 63,274 * Received funding in 2006 and 2007 from the Summer Works Scheme 63,274 2007 2009 Amount approved from the summer works scheme play areas measure € 4,309 30,229 47,700 30,624 31,572 36,694 63,000 44,555 38,692 17,775 12,373 85,653 67,925 19,000 33,250 48,450 61,384 14,395 29,840 16,720 44,963 3,059 2,048 3,546 3,750 2,062 3,750 3,063 1,056 912 3,750 On examination, some funding from both DES and CLÁR for the same item occurred in relation to 9 of the schools outlined above. The crosschecking control that was introduced to avoid this happening was insufficient and there is no evidence that dual funding implications were examined. 2.2 Scheme could have been administered by DES CLÁR section sought and received sanction (2003) from DES to operate and administer the scheme. However, it would appear that this CLÁR scheme could have easily slotted in as a top-up to the funding being provided under the DES Summer Works Scheme Play Areas measure to Primary Schools in CLÁR areas. Had the scheme been administered in this way, there may have been a more focused allocation of resources to those schools that had been awarded funding by DES. Primary Schools in CLÁR areas applied to CLÁR section in DCRGA. Payments were made by CLÁR section, who reconciled with DES in relation to the DES co-funding element. On that basis, it was 41 not incorporated into existing DES primary school schemes structures (e.g. DES Summer Works Scheme Play Areas measure). This is different to the administrative arrangements for the other schemes being analysed by this review. The danger of any dual funding arising may have been lower had the CLÁR Play Facilities scheme been administered by DES. Had the scheme been administered by DES, there would have been a risk that Priority 10 of the Summer Works Scheme would not be reached and therefore leveraged funding would not be released. However, on balance, it may have been better to take this risk in order to avoid any form of dual funding occurring. 2.3 Low maximum level of grant The table below outlines the average payment made by DES to primary schools in CLÁR areas assisted over the period. TABLE 31 Year 2006 2007 2008 2009 Average payment made by DES Average payment made by DES to primary schools to the CLÁR primary schools assisted in CLÁR areas under priority 10 of the summer scheme works scheme € € 3,388 43,565 3,279 27,562 N/A8 N/A N/A 35,577 The CLÁR Primary Schools Outdoor Play Facilities scheme was administered by DCRGA with funding being matched on a 1:1 basis between DCRGA and DES, subject to there being a maximum payment of €3,750 from each Department. Each school could only avail of CLÁR funding on one occasion. Because of this, schools would have had to prioritise what they required in terms of outdoor play facilities when making their application for funding. As the CLÁR scheme was subject to a maximum payment, the previous table outlines the vast difference that there was between the average payments made by DES to the CLÁR scheme and to its Summer Works (play areas) measure. This is heightened by the number of Primary Schools supported under each scheme in CLÁR areas. In 2006 and 2007, the CLÁR scheme supported 484 schools with the Summer Works play areas measure supporting only 15. The CLÁR scheme may well have received greater DES funding had the maximum payments been set at much higher levels. In the years that it participated in the leverage scheme, DES had to spread its resources widely and thinly in CLÁR areas which is contrary to the way that it spends Play Areas resources when it has full control over allocation. A leverage scheme with a low maximum amount per school resulted in resources being allocated in a manner where a large number of schools got some benefit. 8 DES did not fund all 49 schools under the CLÁR measure in this year. On that basis, any average figure calculated would not statistically be in line with the 2006 and 2007 figures and therefore cannot be used for analysis. 42 3. CLÁR Group Water Scheme 3.1 Cost per house in relation to each Group Water Scheme analysed TABLE 32 Year Number of schemes* with a cost per house < €10,000 Number of Number of Number of Number of schemes* schemes* schemes* schemes* with a cost with a cost with a cost with a cost per house per house per house per house between between between between €10,000 €12,000 €14,000 €16,000 and and and and €12,000 €14,000 €16,000 €18,000 2006 5 11 5 8 0 2007 13 18 7 11 6 2008 6 3 3 4 2 Total 24 32 15 23 8 * Schemes were chosen where all houses were located in CLÁR areas Number of schemes* with a cost per house between €18,000 and €20,000 0 6 0 6 Number of schemes* with a cost per house > €20,000 1 1 1 3 From the table above the following is evident: 3 schemes had a cost per house greater than €20,000; 9 had a cost per house greater than €18,000; 17 had a cost per house greater than €16,000; 40 had a cost per house greater than €14,000; 55 had a cost per house greater than €12,000; 87 had a cost per house greater than €10,000. CLÁR section outlined that all schemes with a cost per house in excess of €20,000, and some other schemes, were referred, in accordance with good practice, to DEHLG for comments/observations prior to a decision being made in relation to funding such schemes as part of the CLÁR scheme. DEHLG outlined that it was not providing approval for any of the CLÁR Group Water Schemes to go ahead. DEHLG was only responsible and accountable for the fixed contribution funding of €6,475.66 per house that it was providing towards each Group Water Scheme. The presence of the CLÁR scheme meant that DEHLG was not responsible and accountable for any sums in excess of its own contribution. On that basis, the funding being provided by the CLÁR scheme made it easier for DEHLG to give the go ahead for certain schemes when it was not paying in excess of €6,475.66 per house. Therefore, despite the caution exercised by CLÁR in contacting DEHLG for its advice in relation to certain schemes, the amounts paid out by CLÁR in some instances were very high. In order to protect itself in relation to the overall cost of certain projects, CLÁR section should have had adequate structures in place in order to evaluate each high cost project prior to approval being made in relation to the CLÁR element of funding. Such structures could have involved the relevant co-funding partner, among others, under an ethos of shared responsibility for decision making and on the basis of those from Government Departments/Agencies using their professional objectivity 43 in seeking to balance VFM with the provision of certain services for disadvantaged areas. However, the decision on approving CLÁR funding rested with CLÁR section. Up until the end of 2006, the CLÁR top-up was capped at €8,382 per house. The removal of the maximum grant per house was to support the development of Group Water Schemes in CLÁR areas which would not normally go ahead due to high costs. When the grant cap was removed, it gave Group Water Schemes the latitude to introduce more isolated houses into the scheme, resulting in an increased average cost per house. It may be that an analysis after a number of years would reveal lower costs per house than those initially outlaid, arising from new connections. It could be argued that CLÁR section should have compared the cost of providing funding for private individual water supplies and Group Water Schemes, and chosen the most efficient option. However, the comparison of both is not on a like for like basis, particularly given the prioritisation afforded to Group Water Schemes by DEHLG. Group Water Schemes are the preferred solution, but there must be a point where the benefit of a water supply from a Group Scheme to a disadvantaged rural community is outweighed by the cost of that Group Scheme. At that point, an alternative solution is preferable. In a case where DEHLG is required to match on a € for € basis, all amounts per house over a certain amount, DEHLG would have been a full partner in the decision making process. However, this may have resulted in very few schemes actually proceeding, as DEHLG may not have been agreeable to these conditions. It must be remembered that projects funded under the leveraged approach would have been unlikely to have proceeded without the financial intervention from CLÁR and RAPID. 3.2 Dual funding Details of the Group Water Schemes that were funded under this CLÁR scheme and the DCRGA supplementary Gaeltacht grant during the period of this review are in the TABLE below. This funding was paid to the Local Authorities who reduced the overall household contribution required from the Group Water scheme by this amount. TABLE 33 County Name of scheme Amount allocated under the supplementary Gaeltacht grant € Donegal Meenmore West GWS (2006)* Ardcrone Craugheyboyle GWS (2006)* Shallogans (2006)* Galway Cammus (2006)* Cloughbrack (2006)* Dooras (2006)* * Year of approval in the CLÁR Group Water Schemes 19,812 16,764 6,858 110,490 67,056 39,624 Further funding of not more than a maximum of €762 per house was provided by the DCRGA Gaeltacht section to reduce a household contribution amount of €1,142.76. 44 3.3 Local Authorities Local Authorities outlined that administration of the funding element of the CLÁR Group Water Schemes was more difficult than if it was being provided by a single body. 4. CLÁR and RAPID Sports Capital Top-up schemes Subject to suitable monitoring and control mechanisms being in place, certain administrative efficiencies would have resulted if DAST had handled all aspects of Sports Capital Grants. For example, there would have been one payment to successful applicants rather than two payments (one from DAST and one from DCRGA) on each occasion that a payment was due to them. 5. RAPID Playgrounds scheme 5.1 Multiple sources of statutory funding In some instances, there were multiple sources of statutory funding available for playgrounds in both RAPID and non-RAPID areas. The RAPID funding added to the multiple sources of statutory funding available. This leads to an overly complex funding mechanism which is wasteful on the administrative side, runs the risk of poor allocation, and lacks transparency. This particular point highlights one of the advantages associated with single point funding. 45 CHAPTER 4: COSTS, COST EFFICIENCY AND PERFORMANCE MEASUREMENT 1. Introduction Staffing/management costs, and other resources costs have been calculated in accordance with the method of calculating Public Service Implementation costs outlined at APPENDIX VIII. This Chapter looks at the costs associated with the administration of the leveraged schemes and compares that to the amounts approved or spent under the leveraged schemes. For example, expenditure figures rather than approval figures, are being used to obtain trends data because approvals under the majority of leveraged expenditure schemes ceased in 2008. However, approval figures are used for the cost: approval ratios. This Chapter also looks at Performance Measurement. 2. CLÁR and RAPID sections’ Total Costs 2.1 CLÁR Staffing/Management costs and CLÁR other resources costs associated with leveraged expenditure TABLE 34 Year 2006 2007 2008 2009 Expenditure by CLÁR section on the CLÁR leveraged schemes € 10,144,312 13,888,014 19,008,879 13,563,664 Estimated CLÁR section staffing/management costs associated with leveraged expenditure € 349,315 371,001 400,628 334,270 Estimated CLÁR section other resource costs9 associated with leveraged expenditure € 109,231 116,840 126,173 104,874 Estimated total CLÁR section costs associated with leveraged expenditure € 458,546 487,841 526,801 439,144 The trend of the estimated total CLÁR section costs, taken as a percentage of the expenditure by CLÁR section on the leveraged schemes over the period were as follows: A reduction from 4.5% to 3.5% from 2006 to 2007; A reduction from 3.5% to 2.8 % from 2007 to 2008; An increase from 2.8% to 3.3% from 2008 to 2009. 2.2 RAPID Staffing/Management costs, other resources costs and Pobal costs associated with leveraged expenditure In addition to DCRGA, Pobal are contracted to provide services including administration in relation to RAPID. Pobal outlined that the overall RAPID administration grant reflected in its Annual Accounts related to the overall management of the RAPID programme which included an apportionment directly relating to the RAPID leveraged schemes. This grant was paid to Pobal by DCRGA. Management of the RAPID programme would also have involved the following functions: 9 These costs encompass accommodation, utilities, support and back office staff, training, travel, and so on. 46 To work with and support the DCRGA in the delivery of the RAPID Programme; Training and Support for all RAPID Co-ordinators; Training and Support for RAPID AIT and other beneficiaries; Management of the RAPID Community Support Budget; Liaising with and supporting Government Departments and National Monitoring Committee on Programme Policy Development and Implementation; Publishing of Programme Reports such as Case Studies and relevant Programme Guidance; Co-ordination and implementation of systems to ensure information dissemination and communication within the Programme; Collection and dissemination of monitoring information; Submission of quarterly progress reports to the NMC; and Organisation/support of NMC meetings. The steering committee agreed that 15% of the overall administration paid to Pobal for administering the RAPID programme related to the RAPID leveraged schemes. In relation to this 15%, Pobal had a direct working relationship with RAPID Areas and AIT. They took on a specific role on behalf of DCRGA to ensure that all leveraged scheme applications went through the AIT process. This process ensured that all leveraged scheme applications were needs based and was an additional step in the application process, which differed from the CLÁR process. In relation to the overall management of the RAPID programme, one of the functions provided by Pobal was in relation to training and support for all RAPID AIT. This function differed from the functions that Pobal provided under the RAPID leveraged schemes as this support role with AIT was primarily about bringing Agency and Community Representatives together on specific thematic issues, to support them in taking on their roles on AIT, and to enhance their engagement in the wider programme. For example, community representatives on AIT were brought together at a National level, AIT were brought together at regional seminars, and specific Agency representatives (e.g. HSE, Garda Síochána) personnel were brought together at a National level. Please see the table below outlining the costs to be attributed in relation to the RAPID leveraged schemes. TABLE 35 Year 2006 2007 2008 2009 Expenditure by RAPID section on the RAPID leveraged schemes € 4,544,554 5,315,989 8,174,277 9,064,602 RAPID section staffing/management costs € 220,453 241,723 205,903 223,050 RAPID section other resources costs € 66,783 75,044 64,133 67,860 15% of the amounts paid to Pobal for RAPID grants administration € 109,800 122,039 110,936 140,082 Total costs € 397,036 438,806 380,972 430,992 47 The trend of the total RAPID/Pobal costs, taken as a percentage of RAPID expenditure on the leveraged schemes over the period were as follows: A reduction from 8.7% to 8.3% from 2006 to 2007; A reduction from 8.3% to 4.7% from 2007 to 2008; An increase from 4.7% to 4.8% from 2008 to 2009. 3. Costs in relation to other selected State organisations The focus is on the five schemes that were selected for analysis in this review. 3.1 CLÁR Primary Schools Outdoor Play Facilities scheme DES outlined that the work undertaken by its staff in relation to this scheme involved seeking Ministerial sanction for funding and processing payment requests from DCRGA. This work would in total amount to at most one or two days annually and cannot therefore be registered meaningfully. On that basis, it can be taken that the DES costs in relation to this scheme were negligible. 3.2 CLÁR and RAPID Sports Capital Top-up schemes DAST outlined that the management of CLÁR and RAPID top-ups involved a very small amount of extra work for officials who were already managing the allocations under the DAST Sports Capital Programme. On that basis, the costs of DAST can be taken as being negligible. 3.3 CLÁR Group Water Schemes 17 Local Authorities were involved with this scheme over the period in question. Of these, four had only one Group Water scheme and a further four had only two Group Water schemes. On that basis, the costs of the Local Authorities will be calculated in relation to the remaining nine. Information was sought from relevant Local Authorities in this regard. TABLE 36 Year Estimated staffing/management costs of Local Authorities associated with this scheme € 2006 2007 2008 2009 Total 220,473 260,481 380,975 327,808 1,189,737 Estimated other resources costs of Local Authorities associated with this scheme € 69,435 82,035 119,983 103,238 374,691 Total estimated Local Authority costs associated with this scheme € 289,908 342,516 500,958 431,046 1,564,428 3.4 CLÁR Class II and III roads and bridges scheme 24 Local Authorities were involved with this scheme over the period in question. Of these, three had less than nine schemes. On that basis, the costs of the Local Authorities will be calculated in relation to the remaining 21. Information was sought from relevant Local Authorities in this regard. 48 TABLE 37 Year Estimated staffing/management costs of Local Authorities associated with this scheme Estimated other resources Total estimated Local costs of Local Authorities Authority costs associated with this associated with this scheme scheme € € € 2006 217,995 68,654 286,649 2007 286,330 90,176 376,506 2008 265,565 83,636 349,201 2009* Negligible Negligible Negligible Total 769,890 242,466 1,012,356 *As this scheme ceased in 2008, costs in relation to 2009 were predominately recorded as NIL by relevant Local Authorities and can be taken to be negligible in an overall context. 3.5 RAPID Playgrounds scheme During the period under scrutiny in this review, there was a RAPID Playgrounds scheme in 2006/2007 and 2007/2008. The HSE informed us that they had minimal involvement in the Playgrounds scheme and no staff were assigned to work on it. On that basis, they returned a costs figure of NIL. 25 Local Authorities were entitled to avail of the scheme over the period covering this review. Information was sought from relevant Local Authorities in this regard. TABLE 38 Year 2006 2007 2008 2009 Total Estimated staffing/management Estimated other resources costs of Local Authorities associated costs of Local Authorities with this scheme associated with this scheme € € 264,935 83,216 184,253 58,028 239,487 75,423 112,810 35,528 801,485 252,195 Total estimated Local Authority costs associated with this scheme € 348,151 242,281 314,910 148,338 1,053,680 4. Outputs of the schemes examined by this review The steering committee agreed that the Outputs associated with the leveraged expenditure approach were the total value of the overall approvals into CLÁR and RAPID areas and the number of projects successfully supported. In normal evaluation circumstances, the total value of overall approvals into an area would be an Input and not an Output. However, given the nature of the leveraged expenditure approach and the fact that this review is specifically focused on the leveraged expenditure approach, then resources committed to a designated area become an Output. 49 The Outputs associated with each scheme being examined by this review are outlined below. TABLE 39 CLÁR Primary Schools Outdoor Play Facilities Scheme Year 2006 2007 2008 2009 Total Total amount of Amount of funding Amount of Total number of approvals from CLÁR approved by CLÁR funding schools approved section and DES section approved by DES for funding € € € 2,053,080 1,026,540 1,026,540 303 1,187,108 593,554 593,554 181 344,055 323,577 20,478 49 59,241 59,241 0 10 3,643,484 2,002,912 1,640,572 543 TABLE 40 CLÁR Sports Capital Top-Up Scheme Year Amount of sports capital Amount of top-up Total funding Number of sports grants approved by DAST approved by CLÁR approved for clubs grant aided in for CLÁR areas section CLÁR areas CLÁR areas € € € 2006 7,675,500 1,535,100 9,210,600 127 2007 17,519,800 3,503,960 21,023,760 271 Total 25,195,300 5,039,060 30,234,360 398 TABLE 41 RAPID Sports Capital Top-Up Scheme Year 2006 2007 2008 Total Amount of sports capital Amount of top-up Total funding Number of sports grants approved by DAST approved by RAPID approved for clubs grant aided for RAPID areas section RAPID areas in RAPID areas € € € 12,640,500 3,791,650 16,432,150 107 11,601,500 3,480,450 15,081,950 106 9,675,000 2,884,426 12,559,426 77 33,917,000 10,156,526 44,073,526 290 50 TABLE 42 CLÁR Group Water Schemes Year Number of schemes approved for funding Total Total amount of Amount of Amount of the number of approvals from CLÁR CLÁR funding DEHLG grant plus houses* section, DEHLG, plus approved the household the household contribution contribution € € € 2006 30 982 11,602,677 4,121,389 7,481,288 2007 62 1,439 16,799,703 6,027,652 10,772,051 2008 30 1,246 13,819,502 5,779,560 8,039,942 Total 122 3,667 42,221,882 15,928,601 26,293,281 * The majority of houses would be in a CLÁR area, but for some schemes, there would be a minority of houses in non-CLÁR areas also. TABLE 43 CLÁR Class II and III Roads and Bridges Scheme Year 2006 2007 2008 Total Total funding approved € 5,999,913 5,989,569 5,999,369 17,988,851 Amount of funding Amount of funding Number of roads and approved by CLÁR approved by DEHLG/Dept. bridges approved for section of Transport funding € € 2,999,957 2,999,956 224 2,994,785 2,994,784 244 2,999,684 2,999,685 244 8,994,426 8,994,425 712 TABLE 44 RAPID Playgrounds Scheme Year Total funding approved € 2006/2007 3,000,000 2007/2008 3,000,000 Amount of DCRGA funding approved € 1,500,000 1,500,000 Amount of HSE funding approved € 1,500,000 1,500,000 Number of playgrounds approved for funding Total 3,000,000 3,000,000 124 6,000000 61 63 5. Cost Efficiency of the Outputs produced for schemes analysed under this review Costs per scheme are made up the CLÁR and RAPID/Pobal section costs. These are looked at in the next Section. The costs of the co-funding partners are added in Section 5.2, thereby allowing for the calculation of cost:approval ratios. 51 5.1 CLÁR and RAPID/Pobal sections’ cost per scheme For these purposes, it will be necessary to estimate a cost per scheme in relation to both CLÁR and RAPID/Pobal sections. Expenditure arose on 18 CLÁR leveraged Expenditure schemes in 2006, on 19 in 2007, on 18 in 2008 and on 15 in 2009. On that basis, the cost per scheme on each CLÁR leveraged scheme is as follows: TABLE 45 Year 2006 2007 2008 2009 Total Estimated total CLÁR section costs associated with Estimated CLÁR section cost leveraged expenditure per scheme € € 458,546 25,475 487,841 25,676 526,801 29,267 439,144 29,276 1,912,332 109,694 Expenditure arose on each of the 7 RAPID leveraged schemes in each of the years being examined by this review. On that basis, the cost per scheme on each RAPID leveraged scheme is as follows: TABLE 46 YEAR Total RAPID section plus Pobal costs associated with Total RAPID section plus Pobal leveraged expenditure cost per scheme € € 2006 397,036 56,719 2007 438,806 62,687 2008 380,972 54,425 2009 430,992 61,570 Total 1,647,806 235,401 5.2 Cost efficiency of the outputs produced for schemes analysed under this review The cost per scheme is added to any cost identified in relation to the co-funding partners. CLÁR Primary Schools Outdoor Play Facilities Scheme The overall cost of providing approvals of €3,643,484 over the period of the review was approximately €109,694. That is a ratio of cost:approval of 1:33. CLÁR Sports Capital Top-up Scheme The overall cost of providing approvals of €25,195,300 over the period was approximately €109,694. That is a ratio of cost:approval of 1:230. RAPID Sports Capital Top-up Scheme The overall cost of providing approvals of €33,917,000 over the period was €235,401. That is a ratio of cost:approval of 1:144. 52 CLÁR Group Water Schemes The overall cost of providing approvals of €42,221,882 over the period was approximately €1,674,122. That is a ratio of cost:approval of 1:25. CLÁR Class II and III roads and bridges scheme The overall cost of providing approvals of €17,988,851 over the period was approximately €1,122,050. That is a ratio of cost:approval of 1:16. 6. Performance measurement The review found that there were no dedicated Performance Indicators in place in relation to the leveraged expenditure approach. There was no evidence of appropriate levels of Performance Indicators or a detailed Performance Measurement system being in place in relation to each of the schemes analysed as part of the review. Difficulties in obtaining the required data for analysis Five Local Authorities were contacted in relation to providing information by means of questionnaire in relation to the analysis of the CLÁR Class II and III roads and bridges scheme. However, in three cases, either responses were not received or the information received was of insufficient quality in order to be used as part of the analysis. The main reason provided to us was the hundreds of class II and III roads and bridges in the jurisdiction of the Local Authorities that had been approved for funding, particularly in the 2006 to 2008 period. The volume of data would have been large and would have been very time consuming to extract. Monitoring and Evaluation Notwithstanding the bottom-up nature of project selection (e.g. community participation in decision making etc.) following each yearly cycle of the RAPID Playgrounds scheme, there should have been monitoring and evaluation in place in order to consider the current levels of playgrounds in each RAPID area. This would have led to the drafting of a priority list of required playgrounds in RAPID areas throughout the Country. On this basis, there should not have been a blanket allocation of €66,000 for each RAPID area. Greater levels of funding could have been provided on a case by case basis to address the next priorities for playground development throughout the RAPID areas of the Country. A system such as this would also have helped in determining whether this scheme had now served its purpose or not. 7. Conclusion In overall terms, the costs associated with the RAPID schemes are high in comparison with the costs associated with the CLÁR schemes. This particularly comes to light when looking at the cost: approval ratios for both the CLÁR and RAPID Sports Capital schemes. However, there are costs associated with Pobal administering the leveraged expenditure approach in relation to RAPID. There was also the different approach that was taken in relation to the RAPID leveraged schemes due to the role of the AIT in signing off on all applications. Given that the maximum level of approval for the CLÁR Primary Schools scheme was €7,500, this would have had a negative bearing on the cost:approval ratio for this scheme and would go some way to explaining why its ratio is well below that of the CLÁR and RAPID Sports Capital schemes. 53 These schemes are being compared with each other as the co-funding partner in each case was another Government Department. The costs associated with the involvement of the Local Authorities in the CLÁR Group water scheme and the CLÁR roads scheme provides some explanation towards the cost:approval ratios that arise in these instances. In some instances, the relatively small grant amounts involved contributed to higher administration cost:approval ratios. This Chapter shows that the administration costs associated with the leveraged approach were found to be approximately 3%. Notwithstanding the fact that the figure is only 3%, the administrative costs associated with the approach raise a question about whether leveraged schemes can be efficient, compared to when funding is administered by one Government Department / Agency. The Report of the Special Group on Public Service Numbers and Expenditure Programmes, Volume 1, (2009) outlined the following in relation to DCRGA: ‘Programme savings Irrespective of Departmental changes, the Group sees significant scope for reductions in expenditure allocations in this area. The Group recommends the discontinuation, on a phased basis, of a number of programmes within the Department which can be better accommodated under existing schemes in other Departments. ……………………………, RAPID and CLÁR fall into this category.’ In relation to performance measurement, there was no evidence of appropriate levels of Performance Indicators or a detailed Performance Measurement system being in place in relation to each of the schemes analysed as part of the review. 54 CHAPTER 5: CONTINUED ALLOCATION OF LEVERAGED FUNDING; ALTERNATIVE APPROACHES; AND MAIN CONCLUSIONS AND RECOMMENDATIONS 1. Continued allocation of leveraged funding Chapter 2 of this review examined how partner organisations responded to the availability of leveraged funding in the case of selected CLÁR and RAPID measures and Chapter 3 looked at efficiency issues. The analysis from these Chapters will form the basis of the consideration regarding continued allocation. The fundamental question to address is whether we are better off to retain or to dispense with the leveraged expenditure approach and why. This review has found that the leveraged expenditure approach increased investment into CLÁR and RAPID areas in the years in which the leveraged schemes were active. On the other hand, the leveraged expenditure approach provided co-funding partners with the option to allocate their funding to other areas or programmes on the basis that the leveraged monies being provided by DCRGA could compensate for such a movement in funding. The leveraged funds become another source of funding for the co-funding partners and they may in some instances, seek to use all funding sources in order to optimise their own expenditure allocation decisions. In some instances, this is not to the full benefit of CLÁR and RAPID areas, as would have been the intention of CLÁR and RAPID sections in initiating a leveraged expenditure approach. This response was observed in particular, in relation to the Sports Capital Top-up schemes and to a lesser extent in the Playgrounds scheme. Other unintended consequences of the leveraged approach is that as the leveraged funding is available, there is a danger that funding solutions that might not be the best value options may be chosen, or there is a danger that inferior or lower priority projects may be chosen, in order to avail of the leveraged amounts available, unless a comprehensive oversight and quality control arrangement is in place. In relation to funding solutions, there were high costs associated with certain Group Water schemes that were funded under the CLÁR scheme, although the only real alternative to these schemes was for such communities to rely on their current sources (i.e. communal village well etc.) or to have their own private water provision. However, there must be a point where the benefit of a Group Water scheme supply to a CLÁR area is outweighed by the total costs associated with the scheme. In order to protect itself in relation to the overall cost of certain projects under the Group Water Schemes, CLÁR section should have had adequate structures in place in order to evaluate each high cost project before approval was made in relation to the CLÁR element of funding. Such structures could have involved the relevant co-funding partner, among others, under an ethos of shared responsibility for decision making and on the basis of those from Government Departments/Agencies using their professional objectivity in seeking to balance VFM with the provision of certain services for disadvantaged areas. However, the decision on approving CLÁR funding rested with CLÁR section. 55 CLÁR and RAPID sections did not, nor cannot be expected to have expertise in relation to each of the areas encompassed by each leveraged scheme. This means that both sections required expert advice from their co-funding partners (e.g. in terms of projects being selected for funding). Such co-funders only become full partners in the decision making process when they are providing substantial levels of their own funding to particular projects. There is a dependence on matching funds being provided by co-funding organisations. If the cofunding organisation does not have a sufficient budget available or is not encouraged to participate by the amount of leveraged funding available, the leveraged funds are not leading it to invest further in the designated areas. After the incentive of leveraged funding is removed or after a co-funding partner withdraws its funding, the allocation of funding by co-funding partners has been observed, in some instances, to favour non-disadvantaged areas, resulting in a rebalancing of funding (i.e. designated areas benefit when the leveraged funding is available. When it is no longer available, the allocation of funding between disadvantaged and non-disadvantaged areas reverts to its normal position. Therefore, lesser amounts are provided to the disadvantaged areas. With no incentive such as the leveraged funding approach available, co-funding partners go back to their normal pattern in relation to the allocation of funding). One of the overall aims of this approach was that the co-funding partners would mainstream the treatment of such projects from these disadvantaged areas following the cessation of the leveraged funding approach. However, there was always a risk that co-funding partners could revert back to their normal funding patterns once an incentive such as this was removed. Evidence has been provided that projects have proceeded through the assistance of the leveraged approach that would not have proceeded in normal circumstances. In other words, the co-funding partners would not have financed these projects without the financial intervention from CLÁR or RAPID. However, introducing a leveraged funding approach means introducing an additional statutory source of funding. One of the problems associated with this is that each partner only feels responsible and accountable in relation to the amounts that they are putting forward towards the projects. Given that this is the case, CLÁR and RAPID had to be very careful that the levels of funding being provided by them for various projects could not be deemed to be very large or excessive, notwithstanding the benefits being provided to the disadvantaged areas. This points to the importance of having a comprehensive oversight and quality control arrangement in place encompassing the expertise of all funders. This may include a maximum top-up level of funding and relevant matched funding from co-funding partners, where possible. For example, the evidence provided in relation to the Group Water Schemes was that DEHLG was only responsible and accountable for the fixed contribution funding of €6,475.66 per house that it was providing towards each Group Water Scheme. The presence of the CLÁR scheme meant that DEHLG was not responsible and accountable for any sums in excess of its own contribution. On that basis, the funding being provided by the CLÁR scheme made it easier for DEHLG to give the go ahead for certain schemes when it was not paying in excess of €6,475.66 per house. In relation to funding limits, the following was found: In the case of the CLÁR Outdoor Play Facilities scheme, the maximum amount of funding to be provided to each school appeared low, when compared to the level of funding that DES 56 provided under its Summer Works Scheme Play Areas measure. As a consequence, this resulted in a larger number of much smaller grants under the CLÁR scheme. Contrast this with the removal of the cap on the grant under the CLÁR Group Water Schemes, which led to some very large grants per household. If the maximum grant is too low, the danger is that a cofunding partner is forced to spread its resources very thinly, and if it is too high, the amounts being paid by CLÁR and RAPID may be excessive. 1.1 Department of Finance review of Capital Expenditure The Department of Finance document Infrastructure Investment Priorities (2010) outlined the following in relation to the focus of future medium term policy for DCRGA on Infrastructure Investment Priorities: “A number of investment programmes under the aegis of DCEGA fund investment which is analogous to mainstream investment programmes in larger Departments. For instance, CLÁR funds the same type of infrastructure as the Dept. of the Environment, Heritage and Local Government;………………………………………………………………………………. In future, any residual or ongoing investment needs should be funded by the Government Department with primary sectoral responsibility, in consultation with DCEGA where appropriate.” The report outlined the following in relation to CLÁR: “Clár is designed to target investment in rural areas of greatest population decline. It provides ‘leverage funding’ for small-scale infrastructure in depopulated areas for which there is not deemed to be a compelling economic justification or business case by funding agencies. ……………………………………………. It is imperative that all capital investment yields maximum value for money and has the widest possible impact in terms of expansion of infrastructure. For this reason, there is only marginal justification for continued spending under the Clár programme as resources can be expected to have greater impact if invested through other programmes. For this reason continued high levels of investment are not sustainable or appropriate in the current economic context.” In relation to RAPID, the report says: “RAPID provides investment for small scale projects aimed at improving quality of life in areas of high urban poverty and social disadvantage. The programme seeks to ensure that priority attention is given to the 51 designated areas by focusing State resources available to best effect. ………………………………………. These programmes, ………………………, have the important objective of reducing anti-social behaviour, crime and improving public health outcomes. ………………………………. Continued investment in this programme will be required into the medium-term.” 1.2 Conclusion in relation to continued allocation The weaknesses described earlier in this Chapter are a concern when gauged against the positive outputs produced. While the leveraged schemes did undoubtedly produce positive results, the range of weaknesses leads to the conclusion that the leveraged schemes in their current format should not be continued. At present, no new applications are being considered for any of the leveraged schemes. 57 2. Alternative approaches The introduction of the leveraged expenditure approach was a recognition that projects in depopulated or disadvantaged areas may have tended to lose out. DCRGA would be of the opinion that a return to the pre-leverage situation that does not have incentives for designated areas will not result in the prioritisation of funding to CLÁR or RAPID areas. At present, all of the CLÁR and RAPID leveraged schemes are closed to new applications. A number of alternative approaches were put forward by the Evaluation Unit, all of which had shortcomings. The main alternative approach analysed was in relation to adopting a ringfenced approach for funding relating to both areas. Following consideration, the steering committee decided that none of these alternatives could be considered to be a viable alternative to the leveraged expenditure approach. 2.1 Conclusion in relation to alternative approaches No viable alternative was found to the leveraged approach. Therefore, if the leveraged approach was to fall for consideration in the future, it is acknowledged that it is very difficult to design an effective and efficient leveraged approach that would address the weaknesses outlined. At a minimum, the approach would have to be introduced in conjunction with appropriate monitoring, verification, performance and evaluation controls. There would be additional costs associated with these controls. Any new scheme would have to scoped, researched, and planned, to include parameters and timeframes. 3. Main conclusions and recommendations Effectiveness The leveraged expenditure approach increased investment into CLÁR and RAPID areas in the years in which the leveraged expenditure schemes were active, and resulted in projects proceeding that would have been unlikely to have proceeded under normal circumstances without an incentive being provided by the leveraged approach; Following the withdrawal of DES from the CLÁR Primary Schools leveraged scheme, DCRGA then became the sole Statutory funder and this scheme could no longer be considered to be leveraged; In order for the leveraged expenditure approach to work, funding has to be provided by a statutory co-funding partner. There is always a level of uncertainty attached to a leveraged funding approach as it is dependant on the budget allocation of each co-funding partner. This uncertainty can be mitigated by advance agreement taking place with co-funding partners in relation to terms and funding; In relation to the Group Water Schemes funded under the CLÁR scheme, as this infrastructure is now in place, more houses in rural disadvantaged areas can be connected to it as and when the need arises; In the Sports Capital Top-up schemes, DAST had the authority to decide on the levels of grant aid to all successful applicants, while knowing the levels of leveraged top-ups that would be available to successful applicants from CLÁR and RAPID areas. This provided an unintended incentive to move funding away from CLÁR and RAPID areas, as the top-ups would compensate in some way for such movement, thus allowing more funding to be spent on areas outside of CLÁR and RAPID. The leveraged funds become another source of funding for the co-funding partners and they may in some instances, seek to use all funding 58 sources in order to optimise their own expenditure allocation decisions. In some instances, this is not to the full benefit of CLÁR and RAPID areas. This response was observed to a lesser extent in the RAPID Playgrounds scheme; For the CLÁR and RAPID Sports Capital Top-up schemes, the percentage figures for CLÁR and RAPID areas on grants approved versus grants sought were below the percentage figures for ALL OTHER AREAS prior to the leveraged top-ups being applied; In some instances, when the RAPID Playgrounds scheme funding ceased, proportionally more funding went to the non-RAPID areas. The same result was observed in relation to the CLÁR Class III Roads and Bridges scheme. In contrast, DES continued to fund the same proportionate number of schools and provide the same proportionate level of funding to schools in CLÁR areas under its Summer Works Scheme Play Areas measure. In other words, there was no policy shift from DES arising from the introduction of the CLÁR Play Facilities scheme. One of the overall aims of the leveraged approach was that the cofunding partners would mainstream the treatment of such projects from disadvantaged areas, despite the costs involved, following the cessation of the leveraged funding approach. However, in the main, the evidence is that co-funding partners reverted to their normal funding patterns once the leveraged expenditure incentive was removed. Efficiency Concurrent dual funding arose in the CLÁR Primary Schools Play Facilities scheme with funding being provided under the DES Summer Works Scheme Play Areas measure. From an administration perspective, funding should only have been available from one of these. Although both Departments were aware of possible dual funding and had a control mechanism in place to deal with it, dual funding occurred; Local Authorities outlined that administration of the funding element of the CLÁR Group Water Schemes was more difficult than if it was being provided by a single body; In relation to the CLÁR Group Water Schemes, CLÁR section outlined that all schemes with a cost per house in excess of €20,000, and some other schemes, were referred, in accordance with good practice, to DEHLG for comments/observations prior to a decision being made in relation to funding such schemes as part of the CLÁR measure. DEHLG outlined that it was not providing approval for any of the CLÁR Group Water Schemes to go ahead; DEHLG was only responsible and accountable for the fixed contribution funding of €6,475.66 per house that it was providing towards each Group Water Scheme. The presence of the CLÁR scheme meant that DEHLG was not responsible and accountable for any sums in excess of its own contribution; Removal of the cap on the top-up in the CLÁR Group Water Schemes gave latitude for the introduction of more isolated houses to schemes, resulting in some very high average costs per house. For example, forty schemes had an average cost per house of more than €14,000, whereas the maximum payable in non-CLÁR areas by DEHLG was €6,475.66; CLÁR and RAPID sections did not, nor cannot be expected to have expertise in relation to each of the areas encompassed by each leveraged scheme. This means that both sections required expert advice from their co-funding partners. Such co-funders only become full partners in the decision making process when they are providing substantial levels of their own funding to particular projects. It is concluded that a lack of expertise on the CLÁR side combined with a capped grant from DEHLG led to some very high CLÁR grant amounts per house on some Group Water Schemes; 59 Subject to suitable monitoring and control mechanisms being in place, certain administrative efficiencies would have resulted if DAST had handled all aspects of Sports Capital Grants. For example, there would have been one payment to successful applicants rather than two payments (one from DAST and one from DCRGA) on each occasion that a payment was due to them; In some instances, there were multiple sources of statutory funding available for playgrounds in both RAPID and non-RAPID areas. The RAPID funding added to the multiple sources of statutory funding available. This leads to an overly complex funding mechanism which is wasteful on the administrative side, runs the risk of poor allocation, and lacks transparency. This particular point highlights one of the advantages associated with single point funding; In overall terms, the costs associated with the RAPID schemes were high when compared with the costs associated with the CLÁR schemes. The costs Chapter showed that the additional amount added to administration costs associated with the leveraged approach was approximately 3%. This raises a question about the efficiency of the leveraged approach compared to when funding is administered by one Government Department/Agency. In some instances, the relatively small grant amounts involved contributed to high cost:approval ratios; As the leveraged funding is available, there is a danger that funding solutions that might not be the best value options may be chosen, in order to avail of the leveraged amounts available, unless a comprehensive oversight and quality control arrangement is in place. For example, there must be a point where the benefit of a Group Water Scheme supply to a CLÁR area is outweighed by the total costs associated with the scheme. However, it was difficult for CLÁR and RAPID to set their maximum level of funding figure for each scheme. In the case of the CLÁR Play Facilities scheme, the maximum amount of funding to be provided to each school appeared low, when compared to the level of funding that DES provided under its Summer Works Scheme Play Areas measure. As a consequence, this resulted in a larger number of much smaller grants under the CLÁR scheme. Contrast this with the removal of the cap on the top-up level under the CLÁR Group Water Schemes, which led to some very large grants per household. If the maximum grant is too low, the danger is that a co-funding partner is forced to spread its resources very thinly, and if it is too high, the amounts being paid by CLÁR and RAPID may be excessive. Other Observations If the total amount of funding for Play Facilities had been available to DES to administer as it saw fit, then it would likely have continued to pay larger grants, as it does under the Summer Works Scheme Play Areas measure when compared to the CLÁR scheme. More Primary schools would have got a larger grant but equally, other schools would have got nothing. It could be argued that this approach would have seen a more optimal use of resources; Approximately 26% of Primary schools funded under the DES Summer Works Scheme Play Areas measure over the three years 2006, 2007 and 2009, were from CLÁR areas, while approximately 37% of Primary schools are located in CLÁR areas. This shows a tendency in normal circumstances for projects from disadvantaged areas to lose out when compared to non-disadvantaged areas, as this scheme did not have a leveraged expenditure incentive attached to it; 60 Perhaps there is now an overprovision of playground facilities in some RAPID AREAS. The number of playgrounds per head of population in the Sligo and Kilkenny RAPID areas is very high. Perhaps the funding that was provided over the 4 phases of the RAPID Playgrounds scheme contributed to such a scenario arising. It appears that this scheme was no longer required while it was still in existence and points to the need for continued prioritisation of funding to the real needs of RAPID areas from one year to another. However, it should be noted that this scheme sought to secure playground facilities for individual estates in RAPID areas; There was evidence that CLÁR and RAPID sections were not comprehensively evaluating the needs of their respective areas on an ongoing basis, in relation to whether the leveraged schemes in situ should remain or whether they should be replaced by new schemes to address any changing infrastructural needs of the areas. On this basis, perhaps the number of leveraged schemes should have been limited to between 4 and 8 in order to provide the greatest levels of targeted investment to these disadvantaged areas; DCRGA’s opinion is that a return to any form of a pre-leverage situation that does not have incentives for designated areas would result in CLÁR and RAPID areas losing out. Performance Measurement In relation to the CLÁR Roads and Bridges scheme, there was a lack of data available in relation to expenditure levels in CLÁR versus non-CLÁR areas. The lack of such available data made the analysis of this scheme difficult. Such information should have been available to CLÁR section on a regular basis over the course of this CLÁR scheme as a control mechanism. The provision of such information from the Local Authorities should have been one of the conditions for availing of CLÁR funding; Notwithstanding the bottom-up nature of project selection (e.g. community participation in decision making etc.) following each yearly cycle of the RAPID Playgrounds scheme, there should have been monitoring and evaluation in place in order to consider the current levels of playgrounds in each RAPID area. This would have led to the drafting of a priority list of required playgrounds in RAPID areas throughout the Country. On this basis, there should not have been a blanket allocation of €66,000 for each RAPID area. Greater levels of funding could have been provided on a case by case basis to address the next priorities for playground development throughout the RAPID areas of the Country. A system such as this would also have helped in determining whether this scheme had now served its purpose or not; The review found that there were no dedicated Performance Indicators in place in relation to the leveraged expenditure approach. There was no evidence of appropriate levels of Performance Indicators or a detailed Performance Measurement system being in place in relation to each of the schemes analysed as part of the review. 4. Recommendation From the analysis of the leveraged schemes in their current format, the leveraged approach cannot be recommended to continue. If it was to fall for consideration in the future, it is acknowledged that it is very difficult to design an effective and efficient leveraged approach that would address the difficulties and challenges outlined. At a minimum, the approach would have to be introduced in conjunction with appropriate monitoring, verification, performance and evaluation controls. There would be additional costs associated with these controls. Any new scheme would have to be scoped, researched, and planned, to include parameters and timeframes. 61 APPENDIX I A FULL LIST OF THE CURRENT RAPID AREAS A. Urban areas B. Provincial areas 1. Bray; Cork: 2. Blackpool, The Glen, Mayfield; 3. Fairhill, Gurraneabraher, Faranree; 4. Knocknaheeny, Churchfield 5. Togher, Mahon; 6. Drogheda; Dublin: 7. Ballyfermot; 8. Ballymun; 9. Blanchardstown; 10. Clondalkin; 11. Dún Laoghaire Rathdown 12. Fettercairn; 13. Finglas; 14. Jobstown; 15. Killinarden; 16. North East Inner City; 17. Northside; 18. North West Inner City; 19. South East Inner City; 20. South Inner City; 21. South West Inner City; 22. Dundalk; Limerick: 23. Ballynanty, Kileely; 24. King’s Island, Bishops Palace; 25. South Limerick City; B.1 Larger Towns 27. Athlone 28. Carlow 29. Clonmel 30. Ennis 31. Galway 32. Kilkenny 33. Navan 34. Sligo 35. Tralee 36. Wexford B.2 Smaller Towns 37. Athy 38. Ballina 39. Ballinasloe 40. Carrick on Suir 41. Cavan 42. Dungarvan 43. Enniscorthy 44. Longford 45. Mallow 46. Mullingar 47. New Ross 48. Rathkeale 49. Tipperary 50. Tuam 51. Youghal 26. Waterford. 62 APPENDIX II RAPID LEVERAGED SCHEMES FROM 2006 TO 2009 INCLUSIVE Leveraged schemes 20062009 1. Housing estate enhancement 2. Playground grants 3. Traffic easing schemes 4. CCTV and similar schemes 5. Small scale capital grants scheme for schools 6. Sports capital top-up Co-funding partner(s) Funding split % RAPID:DEHLG and Local Authorities RAPID:HSE RAPID:DEHLG and Local Authorities RAPID: Department of Justice, Equality & Law Reform (DJELR) RAPID:DES and the Dormant Accounts Fund RAPID:DAST* 45:55 50:50 50:50 50:50 33:67 A top-up of the DAST grant by RAPID. The topup was 30% of the total funding figure. 7. Health schemes RAPID:HSE 50:50 * DAST utilises monies granted by the Oireachtas that have been part-funded by the National Lottery. DETAILS OF THE AMOUNTS PAID FROM 2006 TO 2009 INCLUSIVE 2006 Leveraged scheme 1. Playground grants 2. Sports capital top-up 3. Health schemes 4.Housing estate enhancement 5. Traffic easing schemes 6. CCTV 7.Other schemes with DJELR Total Amounts paid by RAPID section € 1,269,219 1,220,238 1,157,630 446,829 385,666 40,000 24,972 4,544,554 Amounts paid by co-funding partners € 1,269,219 2,847,222 1,157,630 546,125 385,666 40,000 24,972 6,270,834 2007 Leveraged scheme Amounts paid by RAPID section € 1. Sports capital top-up 1,674,523 2. Playground grants 1,479,561 3. Housing estate enhancement 602,036 4. CCTV 510,301 5. Health schemes 485,744 6. Traffic easing schemes 388,493 7. Small scale capital grants for schools* 175,331 Total 5,315,989 * This leveraged measure was introduced in 2007 Amounts paid by co-funding partners € 3,907,220 1,479,561 735,822 510,301 485,744 388,493 355,975 7,863,116 63 2008 Leveraged scheme Amounts paid by RAPID Section* Amounts paid by co-funding partners* € € 1. Small scale capital grants for schools 3,967,712 8,055,657 2. Sports capital top-up 1,209,032 2,821,075 3. Playground grants 1,013,758 1,013,758 4. CCTV 989,047 989,047 5. Housing estate enhancement 425,027 519,780 6. Traffic easing schemes 302,278 302,278 7. Health schemes 267,423 267,423 Total 8,174,277 13,969,018 * A further €58,080 was spent on signage, which was introduced in 2008. This cost was split on a 1:1 basis by DCRGA and its co-funding partners 2009 Leveraged scheme Amounts paid by RAPID section* Amounts paid by co-funding partners* € € 1. Sports capital top-up 2,672,549 6,235,945 2. Playground grants 1,699,985 1,699,985 3. Small scale capital grants for schools 1,388,703 2,819,488 4. Housing estate enhancement 1,296,816 1,584,997 5. CCTV 1,055,265 1,055,265 6. Traffic easing schemes 911,284 911,284 7. Health schemes 40,000 40,000 Total 9,064,602 14,346,964 * A further €3,888 was spent on signage. This cost was split on the same basis as in 2008 above. 64 APPENDIX III A RAPID PROGRAMME FLOWCHART INCORPORATING POBAL’S ROLE 65 APPENDIX IV CLÁR LEVERAGED SCHEMES FROM 2006 TO 2009 INCLUSIVE Leveraged schemes 2006-2009 1. Forestry access roads 2. Class II & III roads and bridges 3. Small public water and sewerage schemes 4. Group water schemes** Co-funding partner(s) CLÁR:Coillte CLÁR:Department Transport CLÁR:DEHLG: Local Authority CLÁR/DEHLG/local contribution of 5. Group sewerage schemes CLÁR/DEHLG/local contribution 6. Water & sewerage – Shannon tax incentive areas 7. Design, Build, Operate (DBO) water conservation scheme CLÁR:DEHLG:local contribution CLÁR/DEHLG/local contribution 8. CLÁR/ Liaison Entre Actions pour le Développement de L’Economie Rurale (LEADER)*** village and countryside enhancement scheme 9. Local Authority housing estate enhancement scheme 10. Bi-lingual signage scheme CLÁR: Local Action Groups (LAG):Local Authority:local contribution Funding split % 50:50 50:50 with each road project to be capped at €50,000 50:25:25* Top-up of the DEHLG grant and household contribution on a scheme by scheme basis. The average CLÁR funding provided was 37.5% of the total scheme costs. Top-up of the DEHLG grant and household contribution on a scheme by scheme basis. The average CLÁR funding provided was 44.7% of the total scheme costs. 50:25:25 Top-up of the DEHLG grant and household contribution on a scheme by scheme basis, to a maximum CLÁR payment of €200 per connection. The average CLÁR funding provided was 35% of the metering costs. 33.3:16.7:33.3:16.7 The maximum project cost funded under this scheme was €100,000 CLÁR:Local Authority:local contribution (1) CLÁR:local community sources**** 47.5:47.5:5 (2) CLÁR:local private sources***** (1) CLÁR:DES:local sources in 2006 and 2007 (2) 50:50, the maximum CLÁR payment was €1,000 (1) 37.5:37.5:25 (2) CLÁR: local sources (2) 75:25. 12. Sports capital grants 13. Gaeltacht sports and community grants 14. CLÁR/LEADER community initiatives 15. Coastal Scheme (1) Marine development for piers and harbours up to €200,000 CLÁR/DAST CLÁR/Gaeltacht Division of DCRGA CLÁR:local sources The maximum CLÁR payment was €7,500 CLÁR provide a 20% top-up of the DAST grant. The CLÁR top-up was 20% of the total funding figure. 50:50 (2) Marine Development for piers and harbours over €200,000 16. Ambulance scheme CLÁR:DAFF:Local Authority 11.Primary school outdoor play facilities enhancement scheme CLÁR:Department of Agriculture, Fisheries & Food (DAFF):Local Authority (1) 50:50, the maximum CLÁR payment was €2,000 37.5:37.5:25 12.5:75:12.5 CLÁR:Irish Red Cross and Order of Malta 80:20 66 17. Health Scheme (1) Minor health projects CLÁR:HSE 33.3:66.7 (2) Major health projects 18. Regional Airports scheme CLÁR:HSE 50:50 (1) CLÁR:local 90:10 contribution****** (2) CLÁR:local 75:25 contribution******* 19. Broadband scheme CLÁR: local contribution 80:20 20. Courthouses CLÁR:Courts service 33.3:66.7 21. Fibre Optic scheme CLÁR:Údarás na Gaeltachta 50:50 * The CLÁR funding split changed from 37.5% to 50% from 2007; ** The average CLÁR funding approved per scheme between 2006 to 2008 inclusive was 36% of the total cost. 2009 was not used for these purposes as only 1 scheme was approved. *** LEADER companies are also known as LAG; **** For village/townland signage; ***** For private individuals signage; ****** For a fire tender; ******* For a car park. DETAILS OF THE AMOUNTS PAID FROM 2006 TO 2009 INCLUSIVE 2006 Leveraged scheme 1. Class II, Class III local roads 2. Public water schemes 3. Sports capital grants 4. Minor health 5. Group water schemes 6. CLÁR / LEADER community initiatives 7. Local Authority housing estate enhancement 8. Airports 9. Major health 10. Primary school outdoor play facilities enhancement 11.Forestry access roads 12. Leitrim water & sewerage – Shannon tax incentive areas 13. Marine development for piers and harbours 14. Group sewerage schemes 15. Gaeltacht sports and community grants 16. Bridges 17. Broadband 18. Bi-lingual signage scheme Total Amounts paid by CLÁR section € 2,772,506 1,300,227 1,053,600 800,611 759,888 736,635 516,262 509,894 300,000 Amounts paid by co-funding partners € 2,772,506 2,167,045 5,268,000 1,601,223 1,436,319 736,635 570,605 56,655 300,000 260,790 258,618 434,650 258,618 254,732 153,750 150,522 140,261 134,620 32,169 9,227 10,144,312 254,732 256,250 186,216 561,043 134,620 8,042 9,227 17,012,386 67 2007 Leveraged scheme Amounts paid by CLÁR section € 1. Class II, Class III local roads 2. Public water schemes 3. Sports capital grants 4. Group water schemes 5. Primary school outdoor play facilities enhancement 6. CLÁR / LEADER community initiatives 7. Village and countryside enhancement 8. Sewerage – Shannon tax incentive areas 9. Forestry access roads 10. Gaeltacht sports and community grants 11. Ambulance measure 12. Local Authority housing estate enhancement 13. Minor health 14. Bridges 15. Marine development for piers and harbours 16. Courthouses 17. Bi-lingual signage scheme 18. Broadband 19. Fibre optic Total 2,826,863 2,782,488 1,754,642 1,426,854 1,020,156 876,876 807,258 594,374 491,066 423,784 241,590 233,548 117,197 116,616 82,500 50,000 20,796 16,064 5,342 13,888,014 Amounts paid by cofunding partners € 2,826,863 2,782,488 8,773,210 2,279,260 1,700,260 876,876 1,614,517 594,374 491,066 1,695,136 60,397 258,132 234,393 116,616 137,500 100,000 20,796 4,016 5,342 24,571,242 2008 Leveraged scheme Amounts paid by CLÁR section € 5,332,499 3,620,102 2,870,435 1,672,300 774,683 697,190 619,394 542,260 Amounts paid by co-funding partners € 8,518,148 3,620,102 2,870,435 8,361,500 1,291,138 4,880,329 619,394 2,169,041 1. Group water schemes 2. Public water schemes 3. Class II, Class III local roads 4. Sports capital grants 5. Marine development for piers and harbours up to €200,000 6. Marine development for piers and harbours over €200,000 7. CLÁR / LEADER community initiatives 8. Gaeltacht sports and community grants 9. Primary school outdoor play facilities enhancement for CLÁR : local sources 161,868 53,956 9. Primary school outdoor play facilities enhancement for CLÁR : DES: local 376,219 627,031 sources* 10. Ambulance scheme 535,526 133,882 11. Village and countryside enhancement 465,611 931,222 12. Forestry access roads 456,619 456,619 13. Local Authority housing estate enhancement 365,150 403,587 14. DBO water conservation scheme 245,533 455,990 15. Group sewerage schemes 131,937 163,224 16. Bridges 94,255 94,255 17. Bi-lingual signage scheme 38,003 38,003 18. Broadband 9,295 2,324 Total 19,008,879 35,690,180 * Although new approvals were no longer co-funded by DES from the end of 2007, there were still pre-existing funding commitments in relation to projects that were approved prior to this date 68 2009 Leveraged scheme Amounts paid by CLÁR section € 5,122,492 3,386,028 1,389,164 1,319,000 828,326 505,035 373,196 Amounts paid by co-funding partners € 8,182,682 3,386,028 2,315,273 6,595,000 1,656,651 624,797 1,492,784 1. Group water schemes 2. Public water schemes 3. Marine development for piers and harbours 4. Sports capital grants 5. Minor health 6. Group sewerage schemes 7. Gaeltacht sports and community grants 8. Primary school outdoor play facilities enhancement CLÁR: local sources 145,820 48,607 8. Primary school outdoor play facilities enhancement CLÁR : DES : local sources* 161,841 269,735 9. CLÁR / LEADER community initiatives 100,000 100,000 10. Bi-lingual signage scheme 84,411 84,411 11. Local Authority housing estate enhancement 61,354 67,813 12. Forestry access roads 44,606 44,606 13. DBO water conservation scheme 31,416 58,344 14. Broadband 8,201 2,050 15. Ambulance measure 2,774 694 Total 13,563,664 24,929,475 * Although new approvals were no longer co-funded by DES from the end of 2007, there were still pre-existing funding commitments in relation to projects that were approved prior to this date 69 APPENDIX V MEMBERSHIP OF THE REVIEW’S STEERING COMMITTEE Ms. Dympna Butler (Chairperson); Mr. Pat Boyle, DCRGA; Ms. Caroline Carey, DCRGA; *transferred to the Department of Social Protection in August 2010 Ms. Caroline Clarke, DCRGA; Ms. Eileen Cunnane, DCRGA; * retired in October 2009 Mr. Trevor Donnelly, DCRGA; *transferred to the Department of Arts, Heritage and the Gaeltacht in May 2011 Mr. Kevin Fadden, DCRGA; Mr. Steven Fadian, DCRGA; Ms. Catherine Fahy, DCRGA; Ms. Karen Flynn, DCRGA; Mr. Seamus Jackson, DCRGA; *retired in June 2010 Mr. Paul Kelly, DCRGA; *transferred to the Department of Social Protection in May 2011 Ms. Caitriona King, DCRGA; Mr. Paddy Langan, DCRGA; *transferred to the Department of Justice and Equality in May 2011 Mr. Aidan O’Reilly, DCRGA; Mr. Don Sexton, DCRGA; Mr. Larry Dunne, D/Fin; Mr. Pat Kiernan, D/Fin; Mr. Nelius Lynch, D/Fin; Ms. Maria Farry, Pobal. * For various reasons, there were some changes in the membership of the committee over the lifetime of the review process. 70 APPENDIX VI A BRIEF DESCRIPTION OF CLÁR AND RAPID SCHEMES THAT HAVE NOT BEEN OUTLINED IN THE REPORT CLÁR SCHEMES 1. Forestry Access Roads Projects are selected by Coillte following consultations with the Local Authorities. Coillte submit to CLÁR section a list and maps of roads that have been agreed with Local Authorities and Local Authority engineers. This scheme is now closed. 2. Small Public Water and Sewerage schemes The Local Authority selects the schemes and submits applications to CLÁR section. CLÁR section processes the applications, approves funding and issues payments on receipt of claims and appropriate certification from the Local Authority. This scheme has been closed to new applications since August 2008, but there are still a number of projects underway. 3. Group sewerage schemes CLÁR provides top-up funding for the DEHLG grant of €2,031.58 per house and the household contribution of €1,000 per house in respect of group sewerage schemes. This top-up grant facilitates the development of many more schemes in CLÁR areas which would not normally go ahead due to high costs. The schemes are selected by the Local Authority on foot of applications received from groups and the applications are submitted to CLÁR by the Local Authority. CLÁR section processes the applications, approves funding and issues payments on receipt of claims from the Local Authority. This scheme has been closed to new applications since August 2008, but there are still a number of projects underway. 4. Water & sewerage - Shannon tax incentive areas Leitrim County Council selects the schemes and submits applications to CLÁR section. CLÁR section processes the applications, approves funding and issues payments on receipt of claims and appropriate certification from the Local Authority. This scheme is now closed. 5. DBO Water conservation scheme A top-up is provided under the CLÁR programme where necessary and on a case by case basis, in instances where the funding available from the DEHLG for water conservation and demand management measures is not sufficient to cover the cost. The total grant available, including CLÁR top-up is €553 per domestic and €494 per non-domestic connection. The maximum CLÁR top-up is €200 per connection. This scheme has been closed to new applications since August 2008. 6. CLÁR / LEADER village and countryside enhancement scheme This scheme covers small scale infrastructural projects (e.g. environmental works, walks, playgrounds, car parks, monastic settlements. The maximum project cost funded under this scheme is €100,000. Under the new RDP 2007-2013, co-funding with CLÁR was not permitted and on that basis, this scheme is now closed. 71 7. Local Authority housing estate enhancement scheme The works covered under this scheme include landscaping, paving, play / amenity areas, development of open spaces, seating areas, lighting, boundary walls etc. This scheme is now closed. 8. CLÁR / LEADER community initiatives These are community based projects of an infrastructural nature. Projects attracting less than 50% public funding under LEADER qualified for CLÁR funds subject to certain conditions. This made it possible for the local LEADER companies to undertake more projects in CLÁR areas as their funding provision reduced from 50% to 25% for CLÁR / LEADER co-funded projects. The maximum amount of CLÁR and LEADER funding is €65,000 each (€130,000 in total). In exceptional circumstances, aid up to €100,000 from each could be approved as long as the project did not involve economic activity. 9. Coastal scheme This scheme facilitates minor repair and safety works on small piers and slipways, along with coastal erosion works in CLÁR areas (including Gaeltacht areas and the Islands). Projects are selected for funding by DAFF. CLÁR has no input into the selection or monitoring of projects. CLÁR payments are made on notification of the completion of works by DAFF. This scheme is now closed to new applications, but there are still a number of projects underway. 10.Ambulance scheme The scheme provides funding for the purchase of fully fitted ambulances and the provision of garages for the vehicles, where required. The vehicles are to be of a standard specification, and to be agreed by the Voluntary Ambulance Service and the National Hospitals Office. The vehicles must be housed within a CLÁR area. This scheme is now closed. 11. Health schemes Minor and major health projects under this scheme are recommended by the HSE. The types of projects funded are the development, refurbishment and improvement of health centres and facilities (including ambulance services, the provision of people carriers, and upgrades to social centres, day care centres etc.). CLÁR payments under this scheme are made on a phased basis on vouched expenditure and certification by the HSE. This scheme is now closed to new applications, but there are a number of projects still underway. 12. Regional airports scheme CLÁR funding of €353,400 (75% of the cost) was provided in 2003 to upgrade the car park facilities at Ireland West Airport Knock, Charlestown, Co. Mayo. In 2005, CLÁR funding of €1,006,500 (90% of the cost) was provided for the purchase of two fire tenders at the Airport. This scheme is now closed. 13. Broadband scheme This scheme is a pilot trial project of broadband technology in selected industrial estates, business and educational / training centres in CLÁR areas to promote the rollout of broadband infrastructure to facilitate the development of the Information Society. This scheme is now closed. 72 14. Courthouses This scheme is in relation to the cost of refurbishment / enhancement works to courthouses in CLÁR areas selected by the Courts Service. This scheme is now closed. 15. Fibre optic scheme Following the announcement by the Department of Public Enterprise of a major programme to bring high speed Internet access to 67 towns around the country, CLÁR funding was announced in 2002 for the delivery of fibre optic networks to Industrial Parks in Belmullet, Co Mayo and Dungloe, Co Donegal. This scheme is now closed. 16. Bi-lingual signage scheme The aim of the scheme is to provide funds for the erection of village / townland, and private bilingual signs in CLÁR areas. Applications are made to the LAG / County Development Board (CDB) who act as a coordinator for this scheme. For the village / townland signage, funding is provided by CLÁR section, with a contribution from the local community on a 1:1 basis. The maximum level of CLÁR funding is €2,000. For the private individual’s signage, funding is provided by CLÁR section, with a matching private contribution on a 1:1 basis. The maximum level of CLÁR funding is €1,000. 17. Gaeltacht sports and community grants The aim of the scheme is to tackle critical infrastructural deficiencies in the Gaeltacht and to enhance the social, cultural and economic fabric of the region. Infrastructure projects within Gaeltacht areas, which are also CLÁR areas, and which qualify for a grant under the terms of the DCRGA’s Gaeltacht Sports and Recreation Grant scheme qualify for this grant. It is paid at a rate of 20% of the amount of the Gaeltacht grant approved, up to a maximum total grant of 80% of the cost of the project. 73 RAPID SCHEMES 1. Housing estate enhancement The aim of this scheme is to support small scale capital works to enhance the physical environment within Local Authority housing estates and flat complexes. Eligible works will include landscaping, paving, improvement of open spaces, seating areas, lighting, boundary walls and works to make open spaces in flat complexes amenable to recreational use. This scheme is funded by the DCRGA and Local Authority Internal Capital Receipts and Local Authority Internal Revenues. Monies are paid by the Local Authorities and then claimed from DCRGA. 2. Traffic easing schemes The aim of the scheme is to support small scale capital works to improve road safety in RAPID areas. Eligible works include speed ramps, pedestrian lights, dishing and improvement of footpaths and road improvement works. Monies are paid by the Local Authorities and then claimed from DCRGA. The relevant Local Authorities deal with ongoing running costs. 3. CCTV and similar schemes In relation to these schemes, monies are paid in advance to Pobal by DCRGA and DJELR. Pobal pay grantees on the completion of works. CCTV The aim of the scheme is to support local communities in the provision of CCTV systems. It is administered by Pobal on behalf of DJELR. Justice, Equality and Law Reform Scheme The aim of the scheme is to provide funding for community safety, youth and probation related projects and initiatives in RAPID areas. DJELR administers the scheme. Graffiti The aim of this scheme is to address the problem of graffiti in RAPID areas through abatement, enforcement and education. It is administered by Pobal on behalf of DJELR. 4. Small scale capital grants scheme for schools This scheme provides small scale capital grants for both the enhancement of existing and the provision of new outdoor play areas, school libraries, dining areas and parent rooms. Monies are paid by DES / Dormant Accounts Fund and then claimed from DCRGA. 5. Health schemes The aim of the scheme is to fund projects providing community health facilities. Eligible projects include the purchase of a van for meals on wheels, a play area for a special needs playgroup, premises for youth facilities, improvement of a women’s refuge and facilities for the elderly. Monies are paid by the HSE and then claimed from DCRGA. 74 APPENDIX VII ELIGIBILITY CRITERIA OF THE SCHEMES BEING EXAMINED IN THIS REVIEW 2.1. CLÁR Primary Schools Outdoor Play Facilities - The school had to be a Primary School located in a CLÁR area; - The school could not have been funded previously under this Scheme; - The facilities were to be outdoors and for the purposes of play; - The maximum contribution from the Scheme would be 75% of the total cost subject to a maximum payment of €7,500; The facilities that could be grant aided were: Landscaping of play areas; Construction of basketball / soccer / tennis courts; Supply of goal posts and nets; Basketball hoops and nets; Supply of nets and posts for tennis, netball, volleyball and badminton; Play equipment – swings / slides / climbing frames; Netting around an area to keep the ball in play; An amount of the funding approved could be used for the purchase of a storage shed to store play equipment (maximum amount of €2,000); Fencing; and Soft / safety play surfaces. 2.2 CLÁR class II and III roads and bridges Scheme - The roads / bridges had to be located in a CLÁR area; - DEHLG had to clear the list of selected projects that were sent from each Local Authority to CLÁR section. When this clearance was received, CLÁR section notified the Local Authorities of the approved projects. 2.3 CLÁR Group Water Scheme - The schemes were selected by the Local Authority on foot of applications received from groups; - Only houses located in CLÁR areas qualified for CLÁR funding. Where only some of the houses in a scheme were located in a CLÁR area, the CLÁR funding was approved on a pro-rata basis; - Contingency costs were not to be included in the scheme costs on the CLÁR funding application; - Ancillary costs over the tender price must be kept to a minimum. Such costs would be examined critically and had to be less than 25% of the contractor’s tender price; - The Local Authority was required to certify on the application form that the scheme met the following: A minimum of 90% of eligible houses must join the scheme; Only schemes with minimum Dept. of the Environment specifications would be funded with no upsizing above these specifications allowed; the DEHLG grant had been approved; Tenders had been received for the scheme; 75 The contractor had been selected; and The scheme represented good value for money in terms of the prices tendered and the standard costing for such schemes. 2.4 CLÁR Sports capital top-up scheme The facility had to be located in a CLÁR area; The sporting body had been successful in being approved for a Sports Capital Programme grant from the Dept. of Sport; 2.5 RAPID Sports capital top-up scheme The facility is located in or serves the community in a RAPID area; The sporting body had been successful in being approved for a Sports Capital Programme grant from the Dept. of Sport; 2.6 RAPID Playgrounds Scheme The Playground must be in a RAPID area Projects are selected by the Local Authority in conjunction with the RAPID AIT. The Local Authority in conjunction with the AIT for the RAPID area will be required to submit an application for each project selected for their area The site must already be in the ownership of the local authority. In line with the National Children’s Strategy and the National Play Policy, children should be consulted in relation to the design and development of the play facility. The principles of Universal Design (as outlined in Ready, Steady, Play: A National Play Policy) should be incorporated in all projects to ensure that the facilities are as accessible as possible to all children. The local authorities must agree to carry out the on-going maintenance. Each RAPID area can claim up to €66,000. This can be used to support one or more projects, selected by the Local Authority in conjunction with the RAPID AIT All applications had to have the signature of the AIT chair and the relevant Director of Services with the Local Authority before they would be considered. 76 APPENDIX VIII EXTRACT FROM THE REVISED REGULATORY IMPACT ANALYSIS (RIA) GUIDELINES RE: CALCULATING PUBLIC SERVICE IMPLEMENTATION COSTS Regulations and their implementation often result in considerable costs to the public service and it is important that these costs are taken into account in the context of RIA. This appendix has been prepared to assist officials in identifying the type of public service implementation costs which may need to be assessed as part of the consideration of different options. Such options may, for example, involve the establishment of a new Agency or the creation of new functions for a Department or Agency which may, in turn, result in a need for additional staff. Staffing Costs The following issues are intended to be indicative only and where you are attempting to assess public service implementation costs it is important that you discuss any issues arising with the Department of Finance at an early stage. In line with Government policy on the modernisation of the public service, opportunities for efficiencies such as those associated with the use of shared services should be identified in the context of your analysis of public service implementation costs. The figures used in this exercise are an important part of insuring an informed RIA is carried out, however these figures do not in any way prejudice any subsequent Government Decisions in relation to the allocation of resources for any services subsequently approved for implementation. Direct Salary Cost Direct salary cost is defined as the gross wage or salary paid to an individual at the relevant grade plus the associated employers’ Pay Related Social Insurance (PRSI) payment. An average salary cost should be worked out for each grade based on the current salaries Circular issued by the Department of Finance by taking a cash value mid way between the scale minimum and the highest point, or Long Service Increment (LSI), as appropriate. The appropriate PRSI charge should be added to this figure. Total Salary Cost Total salary cost is defined as direct salary cost plus an imputed pension contribution. Employing civil/public servants normally results in the creation of entitlements to pensions which are payable in the future. In estimating the total cost of employing a civil servant, allowance must be made for this deferred cost. The pension contribution is based on gross salary, and not direct salary cost, because employers’ PRSI is not reckonable for pension purposes. For further details on how to calculate pension contributions please contact your Departmental Vote section in the Department of Finance. In general a further cost of the order of 25% will be recommended as an appropriate additional charge. This figure may need to be varied, particularly if any staff involved would have enhanced pension accrual rates. Total Staff Cost Total staff cost is defined as total salary cost plus an allowance for overheads. Each officer requires office space, materials, use of telephones, fax, postage service, etc. In addition, security services have to be provided, recruitment and training expenses are incurred, personnel services are provided, and so on. It is usually easiest to include provision for these by applying a proportionate increase in salary costs. It is estimated that an addition of 40% to direct salary cost is required to recover overheads. This is a composite figure applicable to the generality of civil service situations and encompasses costs for accommodation, utilities, 77 support and back-office staff, training, travel, and so on. It is important to note that these are average costs and are applicable only on a general basis. When preparing estimates of staff costs, sections will be required to consult with their departmental corporate services in the first instance. Where more specific information is available, it should be used, particularly if there are additional costs in respect of specialist equipment or accommodation, or higher levels of travel and subsistence, for example. However, care should be taken that appropriate allowances are made for cost elements like pension rights and direct and indirect overheads. This is set out in summary form in the table below: A B C D Pay Direct salary cost Total salary cost Total staff cost Mid point of pay range using formula above Pay + Employers PRSI B + Imputed pensions cost (typically 25% of A) C + 40% of A in respect of ‘overheads’ Daily and Hourly Rates Daily and hourly staff costs in respect of any grade conditioned to a 41 hour week (gross) can be calculated by using the following general formulae: Daily rate for a grade Annual cost for grade _______________________ (249 - annual leave entitlement) Hourly rate for a grade Annual cost for grade ________________________________ (249 - annual leave entitlement) x 6.95) (April 2008) The figures above relate to situations where new services, programmes or agencies requiring new staff are envisaged. Where proposals involve the abolition of services, programmes or agencies, it will be necessary to consult the relevant Vote Section of the Department of Finance in order to derive costings based on the time scales involved. Accommodation Costs Where dedicated new office accommodation may be required, for example where a new Agency is being established, it is important that consideration is given to the actual costs involved in the context of the costing of total cost staff time. The factors to be taken into account will include the number of staff to be accommodated, the proposed space allocation per head, the ancillary functions proposed such as public spaces and meeting rooms, the location considered appropriate, the availability of suitable accommodation and the balance between supply and demand in the office accommodation market which will affect the cost per square metre which can be agreed. If you are unsure as to the level of accommodation 78 costs which may be involved, or if specialist accommodation is required, you should seek the advice of the OPW. Contact details are as follows: Property Management Services Office of Public Works 51 St. Stephen’s Green Dublin 2 Tel: 6476000 79 APPENDIX IX ABBREVIATIONS AIT: CCMG: CCTV: CDB: CLÁR: DAFF: DAST: DBO: DCEGA: DCRGA: DECLG: DEHLG: DES: D/Fin: DJELR: ECJ: HSE: LAG: LCDP: LEADER: LSI: MUGA: NDP: NIRSA: NMC: NPRRC: PPF: PRSI: RAPID: RDP: RIA: VFM: Area Implementation Team City/County Monitoring Group Closed Circuit Television County Development Board Ceantair Laga Árd-Riachtanais Department of Agriculture, Fisheries & Food Department of Arts, Sport & Tourism Design, Build, Operate Department of Community, Equality & Gaeltacht Affairs Department of Community, Rural & Gaeltacht Affairs Department of the Environment, Community & Local Government Department of the Environment, Heritage & Local Government Department of Education and Science Department of Finance Department of Justice, Equality & Law Reform European Court of Justice Health Service Executive Local Action Groups Local and Community Development Programme Liaison Entre Actions pour le Développement de L'Economie Rurale Long Service Increment Multi Use Games Areas National Development Plan National Institute for Regional Spatial Analysis National Monitoring Committee National Play and Recreation Resource Centre Programme for Prosperity and Fairness Pay Related Social Insurance Revitalising Areas by Planning Investment and Development Rural Development Programme Regulatory Impact Analysis Value for money 80 References Department of Finance, Value for Money and Policy Review Initiative Guidance Manual, (2007) Department of Finance, Infrastructure Investment Priorities 2010-2016, A Financial Framework, (2010) Department of Finance, The Report of the Special Group on Public Service Numbers and Expenditure Programmes, Volume 1, (2009) Fitzpatrick Associates, Economic Consultants, Evaluation of the RAPID programme- Final report, (2006) Government of Ireland, Programme for Prosperity and Fairness (PPF), (2000) 81