IEReport/UTILITY SHIFTING Feb

advertisement
The work for shifting of Electrical Line/Poles, towers, Water pipelines, Canal etc
Gujarat Energy Transmission Corporation Ltd (GETCO)
S.No
.
Chainage
Status
IE Remarks
1 84+115 (1no Tower)
Final estimate has been submitted to
NHAI by GETCO for shifting work but
due to higher cost of revenue impact
loss, PD NHAI requested to IE to give
their
recommendation
for
any
Not required to
alternate arrangement. Re-alignment
Shift
Proposal at this stretch is under
process (which accomodates tower in
an island). P&P drawing submitted to
IE for review and IE has reviewed the
same.
Km 124+886,
Km 124+232,
2
Km 125+566,
Km 125+943, (4 no’s Tower)
Alignment has
been
shifted
GETCO has submitted estimate to and
hence
NHAI Surat on 16.01.2012.
these
Towers
are not to be
shifted.
POWER GRID
S.No
.
Chainage
Status
Proposal has been submitted to
NHAI by Power Grid Crop. Amount
of proposed Survey estimate has
been deposited by EPC of
Package –A on dated: 18th Feb
2011. Resurvey was done by
PGCIL.
101+769, 119+682,
1 119+742, 119+792,
119+895
IE Remarks
Vehicle
clearance
was found proper
and hence it is not
necessary to raise
the HT line (Refer
Para No 29 of SPV
Letter
No-11265
dated: 18/09/2014
Dakshin Gujarat Viz Company Ltd.
LT Line
S.No
.
Chainage
1 75+930 to 90+000 (Palsana)
2
111+000 to 132+000
(Rander)
Status
Estimate resubmitted by DGVCL to
NHAI on 04.11.10. EPC of PackageA has started shifting works on the
basis of earlier estimates served to
NHAI by DGVCL. Estimate (Revised)
has been approved by NHAI HO &
15% supervision charges have been
paid by NHAI to DGVCL on 27th May
2011.
Shifting work completed from km.
111+00 to 115+00 and remaining
stretch is also waiting for land
acquisition to start shifting work. A
IE Remarks
Some
poles/electrical
line near village
Dhamdod poles
is yet to shift
Electrical lines
at
following
locations
are
yet not shifted.
total of 60%
completed.
been Km 114+000 to
Km
115+000
(Near Getco),
km 119+000 to
Km
120+000
(Kribhco
to
Mora junction),
Km 121+000 to
Km
122+000
(NTPC to RIL)
& Km 122+000
to Km 124+000
(Mora to L&T)
Sewer pipeline –Surat Municipal Corporation (SMC)
S.No
.
1
S.No
.
1
Chainage
103+290 to 106+570
Chainage
95+400 to 115+600
work
has
Status
IE Remarks
Sewer Pipe Line located from Ch. Km
103+290 to Km 106+570. The
estimate of Rs. 4, 46, 54,320/- for
shifting 2.3 km sewer line has been
submitted by SMC to PD NHAI. PD
has sent to NHAI HQ.NHAI HQ has
raised few queries. SMC has given its
reply. After discussions between
SMC, SPV, EPC & IE in meetings,
At present this
SMC has submitted their Revised
sewer line is not
estimate of RS 5,07,87,000 and
required to shift
salvage value of Rs. 9,33,000 to
NHAI. NHAI asked for comments on
the matter from IE. IE raised few
queries which were answered by
Concessionaire on 17.05.2012. Now,
IE has advised to use the existing
PSC pipes for shifting in utility
corridor of project highway on
29.05.2012.
Gujarat Water Supply Board
Status
Shifting of water pipeline has been
started at various Locations. S97+400
to 98.520, 101+900 to 102+360,
104+800 to 105+120, 105+950 to
106+170,109+250 to 109+690 on
LHS and 114+400 to 115+500 RHS
work in progress. Revised Estimate of
5.167 Cr was submitted in March
2011. Revised estimate are yet to be
approved
IE Remarks
IE had
repeatedly
requested
concessionaire
to complete the
work of shifting
of water supply
pipe line but
work is not
completed by
concessionaire
Suwali Irrigation Minor Canal
S.No
.
1
Chainage
Status
IE Remarks
Km 117+150 to Km 121+550
Affecting Km 117+150 to Km
121+550 andKribhco ROB.
Estimate of Rs. 14.59 Cr was
submitted by Irrigation Deptt to NHAI
in Feb 2011 (based on old SOR) and
in-principle approval was received.
Recently, Revised Estimate of Rs
27.78 Crores prepared by EPC was
submitted to NHAI in Feb 2012.EPC
has taken up the work for 1.9m.
Concessionaire
had been
requested by IE
complete
shifting work of
Suwali canal
but balance
work is not yet
started which is
stalled since
long by
concessionaire
LT Line- Dakshin Gujarat Viz Company Ltd.
S.No
.
Chainage
Status
IE Remarks
Shifting work is in progress.
Yet not
completed
0+000 to 17+000 (Ucchal)
1
17+000 to 28+000 (Songarh)
Yet not
completed
2
28+000 to 32+000 (Vyara)
3
Shifting work is in progress.
Revised Estimate approved for
Songadh S/D.
43+000 to 48+000 (Vyara)
Yet not
completed
32+000 to 43+000 (Vyara BP)
Yet not
completed
4
5
50+00 to 53+200 (Valod )
6
Estimate has been approved by
NHAI. Revised Estimate approved.
53+200 to 59+25 (madhi)
7
Revised Estimate approved.
59+725 to 69+700 (Bardoli)
8
Yet not
completed
69+700 to 75+930 Bardoli
BP)
Yet not
completed
Yet not
completed
Yet not
completed
Estimate has been approved by
NHAI. Revised Estimate approved
Yet not
completed
GAS Pipe Line
S.No
.
1
Chainage
Status
GAIL Ltd.
Gas agencies are in-principle agreed to
the construction of Road over their
pipelines
with
proper
protection
arrangements.
2
GSPC Gas
3
4
They have agreed to take up the
relocation of their gas pipe lines and
necessary actions have been initiated
from their end.
Work is affected due to land acquisition
issues. (HAEP and Plot N. 538/2, 539
and 708/A
GGCL
GGCL has completed the shifting work
at Sachin GIDC. In other reaches they
have
in
principle
agreed
for
construction of road over their Pipelines
At Isolux Toll Plaza, GGCL pipe
line was crossing through the tunnel
which was shifted on 30th July 2014.
GSPL
Frequent coordination meetings are
being held with GSPL representatives
for their updations and so as to avoid
confusions.
Verbally they have
communicated their acceptances for
the works.
Crossings have to be
protected by GSPL.
IE Remarks
Concessionaire has to start
construction of road work.
Hazira
Area
Industries
Association had offered
their
falls
cooperation
/coordination during the
construction of service road
over their gas pipe line
passing through Hazira
Industrial area along the
Project Highway of NH-6
(Please refer NHAI letter
No-4136 dated: 18/09/2014)
Concessionaire has not
provided the details of Land
Acquisition for shifting of
Gas Pipe Line.
Hazira
Area
Industries
Association had offered
their
falls
cooperation
/coordination during the
construction of service road
over their gas pipe line
passing through Hazira
Industrial area along the
Project Highway of NH-6
(Please refer NHAI letter
No-4136 dated: 18/09/2014)
Concessionaire has to start
the construction work for
administrative building at
Toll Plaza at Km 89+950.
Hazira
Area
Industries
Association had offered
their
falls
cooperation
/coordination during the
construction of service road
over their gas pipe line
passing through Hazira
Industrial area along the
Project Highway of NH-6
(Please refer NHAI letter
No-4136 dated: 18/09/2014)
Concessionaire
has
to
following
GSPL
and
completes the construction
of road work.
Hazira
Area
Industries
Association had offered
their
falls
cooperation
5
BPCL & IOCL
Both the organizations are yet to give
their go ahead for road works over their
pipelines. This is affecting stretches
after Tapi. IOCL compound wall which
is a part of Land Acquisition too is
affecting road works beyond Tapi.
Shifting BPCL retail outlet at Sachin is
pending.
/coordination during the
construction of service road
over their gas pipe line
passing through Hazira
Industrial area along the
Project Highway of NH-6
(Please refer NHAI letter
No-4136 dated: 18/09/2014)
Compound wall of IOCL has
been
already
shifted.
Concessionaire
had
to
follow-up the issue and
completes the construction
of service road work at
earliest.
Hazira
Area
Industries
Association had offered
their
falls
cooperation
/coordination during the
construction of service road
over their gas pipe line
passing through Hazira
Industrial area along the
Project Highway of NH-6
(Please refer NHAI letter
No-4136 dated: 18/09/2014)
Download