The work for shifting of Electrical Line/Poles, towers, Water pipelines, Canal etc Gujarat Energy Transmission Corporation Ltd (GETCO) S.No . Chainage Status IE Remarks 1 84+115 (1no Tower) Final estimate has been submitted to NHAI by GETCO for shifting work but due to higher cost of revenue impact loss, PD NHAI requested to IE to give their recommendation for any Not required to alternate arrangement. Re-alignment Shift Proposal at this stretch is under process (which accomodates tower in an island). P&P drawing submitted to IE for review and IE has reviewed the same. Km 124+886, Km 124+232, 2 Km 125+566, Km 125+943, (4 no’s Tower) Alignment has been shifted GETCO has submitted estimate to and hence NHAI Surat on 16.01.2012. these Towers are not to be shifted. POWER GRID S.No . Chainage Status Proposal has been submitted to NHAI by Power Grid Crop. Amount of proposed Survey estimate has been deposited by EPC of Package –A on dated: 18th Feb 2011. Resurvey was done by PGCIL. 101+769, 119+682, 1 119+742, 119+792, 119+895 IE Remarks Vehicle clearance was found proper and hence it is not necessary to raise the HT line (Refer Para No 29 of SPV Letter No-11265 dated: 18/09/2014 Dakshin Gujarat Viz Company Ltd. LT Line S.No . Chainage 1 75+930 to 90+000 (Palsana) 2 111+000 to 132+000 (Rander) Status Estimate resubmitted by DGVCL to NHAI on 04.11.10. EPC of PackageA has started shifting works on the basis of earlier estimates served to NHAI by DGVCL. Estimate (Revised) has been approved by NHAI HO & 15% supervision charges have been paid by NHAI to DGVCL on 27th May 2011. Shifting work completed from km. 111+00 to 115+00 and remaining stretch is also waiting for land acquisition to start shifting work. A IE Remarks Some poles/electrical line near village Dhamdod poles is yet to shift Electrical lines at following locations are yet not shifted. total of 60% completed. been Km 114+000 to Km 115+000 (Near Getco), km 119+000 to Km 120+000 (Kribhco to Mora junction), Km 121+000 to Km 122+000 (NTPC to RIL) & Km 122+000 to Km 124+000 (Mora to L&T) Sewer pipeline –Surat Municipal Corporation (SMC) S.No . 1 S.No . 1 Chainage 103+290 to 106+570 Chainage 95+400 to 115+600 work has Status IE Remarks Sewer Pipe Line located from Ch. Km 103+290 to Km 106+570. The estimate of Rs. 4, 46, 54,320/- for shifting 2.3 km sewer line has been submitted by SMC to PD NHAI. PD has sent to NHAI HQ.NHAI HQ has raised few queries. SMC has given its reply. After discussions between SMC, SPV, EPC & IE in meetings, At present this SMC has submitted their Revised sewer line is not estimate of RS 5,07,87,000 and required to shift salvage value of Rs. 9,33,000 to NHAI. NHAI asked for comments on the matter from IE. IE raised few queries which were answered by Concessionaire on 17.05.2012. Now, IE has advised to use the existing PSC pipes for shifting in utility corridor of project highway on 29.05.2012. Gujarat Water Supply Board Status Shifting of water pipeline has been started at various Locations. S97+400 to 98.520, 101+900 to 102+360, 104+800 to 105+120, 105+950 to 106+170,109+250 to 109+690 on LHS and 114+400 to 115+500 RHS work in progress. Revised Estimate of 5.167 Cr was submitted in March 2011. Revised estimate are yet to be approved IE Remarks IE had repeatedly requested concessionaire to complete the work of shifting of water supply pipe line but work is not completed by concessionaire Suwali Irrigation Minor Canal S.No . 1 Chainage Status IE Remarks Km 117+150 to Km 121+550 Affecting Km 117+150 to Km 121+550 andKribhco ROB. Estimate of Rs. 14.59 Cr was submitted by Irrigation Deptt to NHAI in Feb 2011 (based on old SOR) and in-principle approval was received. Recently, Revised Estimate of Rs 27.78 Crores prepared by EPC was submitted to NHAI in Feb 2012.EPC has taken up the work for 1.9m. Concessionaire had been requested by IE complete shifting work of Suwali canal but balance work is not yet started which is stalled since long by concessionaire LT Line- Dakshin Gujarat Viz Company Ltd. S.No . Chainage Status IE Remarks Shifting work is in progress. Yet not completed 0+000 to 17+000 (Ucchal) 1 17+000 to 28+000 (Songarh) Yet not completed 2 28+000 to 32+000 (Vyara) 3 Shifting work is in progress. Revised Estimate approved for Songadh S/D. 43+000 to 48+000 (Vyara) Yet not completed 32+000 to 43+000 (Vyara BP) Yet not completed 4 5 50+00 to 53+200 (Valod ) 6 Estimate has been approved by NHAI. Revised Estimate approved. 53+200 to 59+25 (madhi) 7 Revised Estimate approved. 59+725 to 69+700 (Bardoli) 8 Yet not completed 69+700 to 75+930 Bardoli BP) Yet not completed Yet not completed Yet not completed Estimate has been approved by NHAI. Revised Estimate approved Yet not completed GAS Pipe Line S.No . 1 Chainage Status GAIL Ltd. Gas agencies are in-principle agreed to the construction of Road over their pipelines with proper protection arrangements. 2 GSPC Gas 3 4 They have agreed to take up the relocation of their gas pipe lines and necessary actions have been initiated from their end. Work is affected due to land acquisition issues. (HAEP and Plot N. 538/2, 539 and 708/A GGCL GGCL has completed the shifting work at Sachin GIDC. In other reaches they have in principle agreed for construction of road over their Pipelines At Isolux Toll Plaza, GGCL pipe line was crossing through the tunnel which was shifted on 30th July 2014. GSPL Frequent coordination meetings are being held with GSPL representatives for their updations and so as to avoid confusions. Verbally they have communicated their acceptances for the works. Crossings have to be protected by GSPL. IE Remarks Concessionaire has to start construction of road work. Hazira Area Industries Association had offered their falls cooperation /coordination during the construction of service road over their gas pipe line passing through Hazira Industrial area along the Project Highway of NH-6 (Please refer NHAI letter No-4136 dated: 18/09/2014) Concessionaire has not provided the details of Land Acquisition for shifting of Gas Pipe Line. Hazira Area Industries Association had offered their falls cooperation /coordination during the construction of service road over their gas pipe line passing through Hazira Industrial area along the Project Highway of NH-6 (Please refer NHAI letter No-4136 dated: 18/09/2014) Concessionaire has to start the construction work for administrative building at Toll Plaza at Km 89+950. Hazira Area Industries Association had offered their falls cooperation /coordination during the construction of service road over their gas pipe line passing through Hazira Industrial area along the Project Highway of NH-6 (Please refer NHAI letter No-4136 dated: 18/09/2014) Concessionaire has to following GSPL and completes the construction of road work. Hazira Area Industries Association had offered their falls cooperation 5 BPCL & IOCL Both the organizations are yet to give their go ahead for road works over their pipelines. This is affecting stretches after Tapi. IOCL compound wall which is a part of Land Acquisition too is affecting road works beyond Tapi. Shifting BPCL retail outlet at Sachin is pending. /coordination during the construction of service road over their gas pipe line passing through Hazira Industrial area along the Project Highway of NH-6 (Please refer NHAI letter No-4136 dated: 18/09/2014) Compound wall of IOCL has been already shifted. Concessionaire had to follow-up the issue and completes the construction of service road work at earliest. Hazira Area Industries Association had offered their falls cooperation /coordination during the construction of service road over their gas pipe line passing through Hazira Industrial area along the Project Highway of NH-6 (Please refer NHAI letter No-4136 dated: 18/09/2014)