Notice of Completion – Municipal

advertisement
April 29th 2015
The Honourable Glen Murray
Ministry of the Environment and Climate Change
77 Wellesley Street West
11th Floor, Ferguson Block
Toronto, Ontario
M7A 2T5
Attention: Kathleen Hedley
Re: Notice of Completion – Municipal Class Environmental Assessment – Second Avenue (MR72)
Infrastructure Improvements. Notice issued April 1, 2015.
Requester Details: The following letter of concern is presented by the Ramsey Lake Stewardship
Committee, a grassroots organization focused on improving the health and water quality of Ramsey Lake.
Ramsey Lake covers 8 km2 and is a small urban lake in the centre of Greater Sudbury. It is a municipal
drinking water source for over 60,000 Sudburians.
Proponent Details: Reference is made to Notice of Completion issued April 1st, 2015 regarding
Municipal Class Environmental Assessment 2nd Avenue (MR72) Infrastructure Improvements by the City
of Greater Sudbury.
Project Details: It was recommended that Second Avenue (a two lane secondary arterial) be widened to
five lanes from Donna Drive to Scarlett Road, widened three lanes from Scarlett Road to Kenwood Street
and the storm ditches removed.
Concerns: We have a number of concerns related to this project.
Project File was not completed in 2014
As noted by the MOECC Environmental Approvals Branch letter, dated Feb. 4, 2015, a project file was not
completed for this roadwork in 2014. We, like the MOECC, are concerned that the project was not
planned in accordance with the requirement of the Class EA. We have concerns that a Class B EA was
chosen for the current assessment instead of a Class C. As well, because of this oversight construction has
been delayed and 2nd Ave has been allowed to further deteriorate.
No current Transportation Master Plan, piecemealing of costs
Since a new Transportation Master Plan (available for initial public consultation May 2015) may speak to
how the city will address the transportation of people instead of just cars, we feel it prudent for any new
road designs to reflect a more broad approach to transportation and to consider more than the
movement of a single passenger vehicle. Had a more up-to-date TMP been available, perhaps building
sidewalks to move people on foot, bike lanes to move people on bikes, a pedestrian crossing, and adding
bus bays would have not been considered ‘add-ons’ by the proponent. In 2014, they were not considered
part of the initial cost of this roadwork (under $1M). (Page 10 of the Project File) Had these non-car
related features been initially considered, a Class C EA would have been required due to the elevated cost
of over $2.7M. This piece-mealing of costs, to avoid a Class C EA, is unacceptable to the community, as it
does not allow for meaningful consultation in a cost-effective and community-minded way. “Projects
must not be piece-mealed with component parts or phases being addressed separately” as stated in the
Municipal Class Environmental Assessment rulebook for municipal roads, water and sewers. Without a
Class C EA, citizens were not provided with other options like building a three-lane road for the entire
stretch of 2nd Ave, improving stormwater ditches and using the saving in asphalt for better overall
stormwater management.
Induced Demand or Congestion?
While looking at updating the 2005 Transportation Study, the Infrastructure Services Department
identified “the need for widening Second Avenue (MR 72), due to existing and future congestion.”
However, the proponent also state that “traffic volumes forecast for the year 2031 Preferred Alternative
are expected to remain close to existing 2011 traffic volumes.” We would like all models of congestion to
take into account “induced demand”, whereby building a bigger road encourages more people to use the
road. “By exaggerating the economic benefits of road capacity increase and underestimating its negative
effects, omission of induced traffic can result in over-allocation of public money on road construction and
correspondingly less focus on other ways of dealing with congestion and environmental problems in
urban areas.”
http://vbn.aau.dk/ws/files/67056413/N_ss_Nicolaisen_Strand_2012_Traffic_Forecasts_Ignoring_Indu
ced_Demand._A_Shaky_Fundament_for_Cost_Benefit_Analyses.pdf
A wider road will contribute more to current sodium and phosphorus drinking water issues
We are not just concerned with the process that led to the decision to widen 2nd Ave but also that the
widening of 2nd Ave and the removal of storm ditches will increase the amount of impervious surface area
in the Ramsey Lake watershed. This is important because 2nd Ave is in a drinking water Issue
Contributing Area
http://sourcewatersudbury.ca/images/uploaded_files/ARSPP2013/ARMaps2013/3.11_Ramsey_Contrib
utingIssues_Aug2011_web.pdf according the Greater Sudbury Source Protection Plan, which came into
effect April 1, 2015. We expected this to be mentioned in the environmental sections of the project file.
Technically, there are two drinking water issues for this area. See threats in Appendix A. For both sodium
and phosphorus, a threat is:
 The establishment, operation or maintenance of a system that collects, stores, transmits, treats or
disposes of sewage, which includes stormwater.
 The application of road salt.
http://sourcewatersudbury.ca/images/uploaded_files/ApprovedSPP_Sept2014/Greater_Sudbury_Sourc
e_Protection_Area_Approved_SPP_Sept_19.pdf (pg. 12 SPP)
Although the additional 7,500 square metres of road (according to the project file) may not seem like a
lot, it does mean an additional 300 kg of salt per snowfall. (using 40g salt/m2 road.) Since the City of
Greater Sudbury, on average, experiences 23 days a year of 5-20cm snowfalls
(http://www.currentresults.com/Weather/Canada/Ontario/Places/sudbury-snowfall-totals-snowaccumulation-averages.php), the city will use 23 x 300 kg = 6,900 kg of extra salt for the expanded
roadway per year. This salt will go into the groundwater or will directly wash into Ramsey Lake.
The city has a salt management plan but with more roads expected to be built in the watershed (Silver
Hills Road), the salt use will continue to go up and so will salt levels in Ramsey Lake. The sodium level in
Ramsey Lake was measured by the city as 55 mg/L in 2010, and already over the 20mg/L reportable
level. We expected some mention of this in the project file.
We are also concerned about the stormwater coming from this area. Much of the stormwater will flow to
Frobisher Creek, which originally was a natural creek but is now a stormwater management area. Of
particular concern are the phosphorus levels measured from outflows from Frobisher Creek to Ramsey
Lake. In the last year tested (2010), phosphorus was measured at 110.5 μg/L, (Bradley, J. MSc. Urban and
industrial drivers of phytoplankton communities in Sudbury, Ontario, urban lakes. Laurentian University,
Sudbury, ON. Dr. Ramcharan) significantly over the Ontario Provincial Water Quality Objective guidelines
of 30 μg/L for protection of streams. https://www.ontario.ca/document/water-management-policiesguidelines-provincial-water-quality-objectives
We have some concerns that this stormwater management area is showing signs it may not be able to
perform to an ‘enhanced level’ especially when more stormwater is expected to flow through it.
The environmental impact of choosing to widen the road to 5 lanes in one area and three lanes in the
other will increase impermeable land, increase stormwater run-off, and phosphorus & salt inputs to
Ramsey Lake. As a community stewardship group we would have liked to have options presented to us
which would have allowed for better flow of traffic on 2nd Ave, (three lane option) while still considering
the environmental effects on Ramsey Lake.
Sincerely,
Lilly Noble
Co-Chair
Ramsey Lake Stewardship Committee
Cc: Clerk, City of Greater Sudbury
Director, Environmental Approvals Branch, MOECC
Rosanna White, Environmental Planner/Environmental Assessment Coordinator
Appendix A
Greater Sudbury Source Protection Plan Policies
http://sourcewatersudbury.ca/images/uploaded_files/ApprovedSPP_Sept2014/Greater_Sudbury_Sourc
e_Protection_Area_Approved_SPP_Sept_19.pdf
Policy S4EF-PI
Where S3F-PI does not apply and where a sewage system (existing and/or future) is in an area where
this activity could be a significant drinking water threat, the Ministry of the Environment shall ensure
that the Environmental Compliance Approval that governs the sewage system includes appropriate terms
and conditions to ensure that:
a. The sewage system (existing) ceases to be a significant drinking water threat; or
b. The sewage system (future) never becomes a significant drinking water threat.
This policy applies to all sewage threats, including stormwater infrastructure.
Policy S7F-LUP
The City of Greater Sudbury shall incorporate into its official plan policies related to reducing stormwater
runoff volume and pollutant loadings from developments in the vulnerable areas where stormwater
management facilities could be a significant threat. These policies shall:
a. Encourage implementation of a hierarchy of source, lot-level, conveyance and end-of-pipe controls;
b. Encourage the implementation of innovative stormwater management measures;
c. Consider flexibility in development standards to incorporate alternative community design and
stormwater techniques, such as those related to site plan design, lot grading, ditches and curbing, drive
way surfaces, and the use of open space as temporary detention ponds; and
d. Support implementation of source control programs, which are targeted to existing areas that lack
adequate stormwater controls.