STATEMENT OF WORK DATE: PROJECT TITLE: PROJECT NUMBER: PROJECT LOCATION: I. July 15, 2015 Paint Flooring, Ceiling, & Roads 648-15-111 Portland VA Medical Center PROJECT DESCRIPTION This project requires the following: Demo and disposal of existing VCT and cove base in rooms 5C 146,147,148B, and 151A. Provide and install new Armstrong Medintec or equivalent flooring and coving up walls with welded seams in the areas 5C 146,147,148B, and 151A. The contractor is responsible for moving all items in order to accomplish the project. Replace all floor mounted door stops and replace with new. See drawing A-1 and specifications. Demolish and dispose of existing asphalt in areas shown on drawing S-3. Provide and install new asphalt according to the drawings and specs. Repaint road lines that have been removed in the process. Replace road markers that have been removed in the process. Contractor is to provide flaggers, signage, and approved methods to minimize traffic related delays and to keep busy traffic moving while work is ongoing. Contractor will not block off any road ways while performing work. Contractor will be in constant contact TriMet and C-Tran to Co-ordinate these road repairs and to make sure that the bus stops are not obstructed. All work shall be completed in accordance with the drawings and specifications. This is a summarized description of work; refer to the drawings and specifications for additional detail. II. PERIOD OF PERFORMANCE The period of performance for this effort is 120 calendar days from notice to proceed. This is considered to be a practicable schedule length. Schedules submitted for less than 120 calendar days will not be accepted. III. OPTIONS The following options shall be priced separately as identified in the bid schedule, see applicable drawings and specifications for additional detail: Option 1, CLIN 0002: Install plank flooring and cove base in the PT/OT area of building 11 in Vancouver as shown on the drawing A-2 and specifications. Remove and dispose of existing flooring materials. Prep floor according to manufactures specs. Work to occur after normal working hours and/or on the weekend. The period of performance of Option 1, CLIN 0002 is 60 calendar days. Option 2, CLIN 0003: Page 1 of 4 Patch and Paint Building 20 Dental as shown on drawing A-3 and specifications. Work to occur after normal working hours and/or on the weekend. This suite includes wall hung items. It will be the contractor’s responsibility to move these items in order to paint the suite and replace them. The period of performance of Option 2, CLIN 0003 is 60 calendar days. Option 3, CLIN 0004: Remove and dispose of ceiling tiles shown on drawing A-4 and specifications. Install new ATC ceiling at the same elevation as existing ceiling. Remove, replace and/or relocate any existing ceiling mounted devices as needed for this installation. Patient care in this area requires installation to be completed without blocking access to any part of the corridor or patient rooms. Work must be performed in a clean and safe manner and may require phasing. The period of performance of Option3, CLIN 0004 is 60 calendar days. IV. GENERAL REQUIREMENTS The Contractor shall keep the COR and the Contracting Officer informed at all times of the status and progress of the project. The contractor may be required to go thru General Hospital Environment Awareness information and/or training. These requirements will be informed in the pre-construction meeting. This information or training is typically short in duration and may consist of videos, special instructions, or seminars. The period of performance for this effort is 120 calendar days from notice to proceed. This is considered to be a practicable schedule length. Schedules submitted for less than 120 calendar days will not be accepted. 1. ACCESS TO WORK SITE: The contractor will contact the COR for access requirements and hours. A majority of work under this project is required to be performed outside of normal, including weekends. 2. CONTRACTOR FURNISHED MATERIEL: Contractor shall provide all materials, equipment, supplies, and service tools necessary to complete the work identified under this project. 3. EXECUTION: All work is to be completed within 120 calendar days of notice to proceed. All work will be in accordance with applicable VA design guides, specifications, directives, standards and requirements, energy conservation methods, local and federal codes including but not limited to the following: NEC NFPA Life Safety Code ASHRAE OSHA Standards JCAHO Standards EPA regulations ASME ASPE National and Local Building Codes TCEQ Others as applicable Page 2 of 4 4. Submittals: All documents will be submitted through the contracting office to the CO and COR. The contractor shall provide all required submittals prior to the start of any work on the project. A schedule for the work will be provided at a pre-construction meeting. Submittals to be provided are but are not limited to: Work schedule Employee listing Project Schedule Schedule of Values Environmental Protection Plan as required in the specifications. Working Drawings and/or Shop drawings Safety plan Bond Requirements SF1413 Statement and Acknowledgment 5. Scheduling: The contractor shall provide the work schedule for the work to be performed. The schedule will be part of the proposal package. One section of the schedule should include a breakdown of personnel required to perform the service. Since parking is limited at the VA Medical Center scheduling is very important for the completion of this project and some work may need to be done in evenings or on weekends. In the event climate or weather conditions become unsuitable for work or may provoke an environmental hazard, the entire work shall be re-scheduled and be approved by COR. Postponement will not reflect any penalties assessed to the Contractor, nor should there be any additional cost to the Government. 6. Interference with Hospital Functions: Contractor personnel are required to interrupt their work at any time so as not to interfere with hospital functions. This includes but not limited to, utility service, fire protection systems, and the passage of facility patients, personnel, equipment and carts. 7. Utility Shutdown: The contractor will coordinate with owner before disconnecting any circuit or conducting any utilities modification or stoppage. Any shutdown shall be coordinated with a minimum of two weeks notification and shall be submitted with the appropriate action plan. 8. Status and Schedule of Work Reports: The contractor will complete and submit on a weekly basis, daily logs to the COR and the CO. 9. Identification of Workers: Uniforms or work attire are to be cleaned and maintained in good condition, and will be worn as designated by the manufacturer. On the absent of the CFS a temporally acting supervisor will be identified and he/she will assume full responsibility for the work site till relieved from his/her responsibilities. 10. Documentation of Products to Be Used: The Contractor will be required to submit a material approval submittal of all supplies and material to be used in the project, as required in the submittal section of this scope. Any material safety data sheet, company specification and brochure will be attached to the form. The form must be returned to the CFS approved prior of using the material or supplies. The CFS must comply with all comments, remarks and instructions attached to the form. A separate sequential logged must be maintained by the Contractor and CO to keep track of all submittals processed. Page 3 of 4 11. Damages: Any damage by contractor personnel during the performance of this project shall be corrected/repaired to the previous existing condition or better. 12. Disposal of Waste: The Contractor will not dispose of any excess materials at any location on the Medical facility premises unless approved by the COR. All waste and rubbish materials are to be disposed off the Medical Facility premises by the Contractor, and disposal shall be in accordance with Federal and local regulatory guidance and laws. At completion of work, all areas of construction and surrounding areas will be thoroughly cleaned of any debris. 13. Safety: While in the performance of the work, the Contractors personnel shall abide by the safety requirements of the Medical Center. The Contractor shall exercise extreme care in making the work area safe at all times. The number one priority is to protect patients and hospital staff from any possible injury resulting from the equipment or materials. The Contractor is responsible for security of equipment each day. There is no storage area available on site. The hallways nor corridors shall not be used to store, pile or place construction materials or supplies. In the event of a situation requiring use of the corridor for such purposes, approval of the VA Medical Center Safety Manager/Officer shall be obtained previously. No painting material or supplies shall be placed where patients may recover them. Any safety violation or emergency situation should be reported to a hospital official immediately. The Contractor shall conform to all Federal, State and local regulations governing painting chemicals and equipment, which may be in effect. All equipment used to perform the work will conform to OSHA regulations. Work site safety will be governed by the Medical Center. 14. Phasing: Required phasing coordination. The work needs to be closely coordinated with the COR to minimize disruption of the normal facility function. 15. Inspections: The daily work will be inspected by Contractor Field Supervisor (CFS) to be provided by contractor. This CFS will ensure that all the work is being performed according to the specifications and regulations involved in this contract. The COR and VA Facility Management Service personnel may regularly inspect the work and accept if satisfactory. COR will schedule the inspections and provide a copy of it to the CFS and CO. The CFS or representative will be present during the inspection. The COR must inform the CFS of any hospital staff taking part on the inspection. The result of the inspection must be presented, in writing, to the CO. The Contractor must request the project final inspection in writing through the contracting office to the CO. 16. Final Inspection: The contractor shall schedule a final inspection with the Project Engineer to ensure the evaluation meets or exceeds requirements in this SOW. Contracting Officer’s Representative (COR) Michael Major Engineering Technician Portland VA Medical Center 3710 SW US Veterans Hospital Road Portland, OR 97239 Office phone: 503-572-0908 Email: michael.major@va.gov Page 4 of 4