7- MINISTRY OF PUBLIC INFRASTRUCTURE, NATIONAL DEVELOPMENT UNIT, LAND TRANSPORT AND SHIPPING National Development Unit General The National Development Unit (NDU) operates to contribute towards the enhancement of the quality of life through three main activities: Provision of community-based infrastructure and amenities. Implementation of land drainage programme. Provision of information, advice and related services to empower citizens. The above activities are financed under the Programme “Community Based Infrastructure and Public Empowerment” which has, as priority objectives, to improve the safety of inhabitants in flood prone areas and enhance community welfare. One of the major services is to provide an effective drainage system in flood prone areas, through the Land Drainage and Watershed Management Programme. To achieve its objectives, the NDU has divided the island in four zones. Rate contracts for the construction and upgrading of roads and drains were awarded on a zonewise basis through Open Advertising Bidding (OAB). As regards emergency projects, they were awarded to the existing Zonal Contractors and other Contractors through the emergency procurement method. A time frame of about six months was set for the implementation of the emergency projects. 7.1 Planning and Managing of Projects For the year 2013, NDU has incurred total expenditure of some Rs 1.71 billion out of the revised budget of Rs 1.74 billion. A sum of some Rs 1.16 billion was incurred for the Land Drainage Watershed Management Programme out of the above total expenditure of Rs 1.71 billion. The expenditure exceeded the approved budget of Rs 225 million under this Programme by more than 400 per cent. Part of the additional provision of Rs 951.5 million obtained through Virement and under the Supplementary Estimates was for implementation of emergency projects under the Emergency Rehabilitation Programme (ERP) following the torrential rain of 13 February and flash floods of 30 March 2013. 107 Observations Over the past years, NDU has undertaken more projects that were initially planned in the budget but the financing requirements were not duly assessed. Following award of rate contracts and emergency projects, Works Orders were issued as and when projects were approved. The following were observed: Rs 1.16 billion comprised payments, among others, of Rs 586.7 million for emergency projects awarded under the ERP and by the Road Development Authority (RDA) and Rs 250 million for on-going projects awarded prior to 2013. As of 31 December 2013, there were still commitments totalling some Rs 1.165 billion outstanding under these projects as shown in Table 7-1. Table 7-1 Payments and Outstanding Commitments as of 31 December 2013 Projects Commitments at 31.12.12 Rs million Awarded in 2013 Rs million Paid in 2013 Rs million Emergency Projects under ERP 1,313.5 563.6 749.9 RDA Projects 62.9 23.1 39.8 250.0 375.6 836.7 1,165.3 On-going projects prior to 2013 625.6 Total 625.6 1,376.4 Commitments at 31.12.13 Rs million As regards emergency projects under ERP, this situation should not have arisen in view of the fact that all emergency projects awarded from February to May 2013 should have been completed within the time frame of six months. A prioritised list of projects, targeted for 2013 comprising on-going and new projects together with the estimated costs and implementing dates, had not been worked out. It was also noted that: When preparing the budget for 2013, NDU did not take into account the previous years’ outstanding commitments of Rs 625.6 million. Of 166 drain projects proposed for 2013, only 15 projects for an estimated cost of Rs 75.2 million were awarded during the year 2013, out of which six were completed and nine were still outstanding as of 31 December 2013. 108 MINISTRY OF PUBLIC INFRASTRUCTURE, NATIONAL DEVELOPMENT UNIT, LAND TRANSPORT AND SHIPPING Recommendations A realistic budget should be prepared, based on proper planning of projects which should take into consideration all outstanding commitments from previous projects. Given that NDU spent significant funds in projects, it should urgently put into operation the Project Management System that has already been developed to exercise proper control and effective monitoring of projects and ensure their timely completion. NDU should monitor closely the issue of Works Orders under rate contracts so that the financial resources allocated are sufficient to meet all commitments. This would help NDU to minimize risks of not meeting its contractual obligations. NDU’s Reply NDU has taken note of the need for proper planning for drain projects. With the assistance of the World Bank, a comprehensive study is being undertaken in flood prone areas to come up with an Integrated Drain Plan to prevent flooding. 7.2 Zonal Contracts A rate contract is awarded following an OAB and approval of the Central Procurement Board (CPB) on the basis of approved rates to execute works as and when required. The quantities in the scope of works are estimates and of indicative nature. Payments are based on actual quantities of works measured jointly on site upon completion of works. Four rate contracts for the construction and upgrading of roads and drains were awarded on a zonewise basis (Zonal Contractors) by the CPB through OAB for a period of 18 months in March 2012 and February 2013. Two of the four rate contracts, which expired in September and October 2013 respectively, were extended up to May 2014. A total of 143 Works Orders for a total amount of some Rs 504.2 million under the existing and extended contracts were issued for the four zones in 2013. The four rate contracts for a total value of Rs 713.6 million awarded to three Contractors A, B and C are as shown in the Table 7-2. 109 MINISTRY OF PUBLIC INFRASTRUCTURE, NATIONAL DEVELOPMENT UNIT, LAND TRANSPORT AND SHIPPING Table 7-2 Zonal Contracts Awarded Zone Date of Award Contract Period Contractors Amount Rs million 1 6 Mar 12 Mar 12 to Sep 13 A 180.8 2 4 Feb 13 Feb 13 to Aug 14 B 172.8 3 4 Feb 13 Mar 13 to Sep 14 C 203.8 4 6 Mar 12 Mar 12 to Oct 13 C 156.2 Total 713.6 Source: Project Files and NDU Database Observations Procurement proceedings for award of new contracts for Zones 1 and 4, which expired in September and October 2013 respectively, were initiated by NDU through CPB in July 2013. The estimated costs for Zones 1 and 4 were Rs 229 million and Rs 238.5 million respectively. The procurement exercise was subsequently cancelled on the ground that international bids had to be invited since the estimated contract cost per zone was more than Rs 200 million. It was only on 22 April 2014 that a fresh tender exercise was launched. Pending the award of new contracts, the existing contracts were extended on three occasions to December 2013, March 2014 and May 2014. The amounts allocated to the two Contractors A and C under the extended contracts for Zones 1 and 4 were however not specified. As of 28 February 2014, Works Orders amounting to Rs 99.2 million and Rs 102.1 million respectively were already issued. These represented 55 and 65 per cent of the respective existing contracts awarded in March 2012. This is not in line with Section 25 (2) (d) of the Public Procurement Act (PPA) and Regulation 44(3) of the Public Procurement Regulations (PPR) which stipulate that “the limit where additional works, which were not included in the initial contract have, through unforeseeable circumstances, become necessary, shall be 30 per cent of the initial contract value”. Recommendations Bidding procedures should be properly planned so that new contracts are awarded before the expiry of existing contracts. The estimated costs of the works, time required for bid preparation and bid exercise should be carefully analysed before choosing the procurement method and launching of bids. NDU should comply with the provisions of the PPA and PPR in particular, the prescribed limit for any additional works entrusted to existing Contractors. 110 MINISTRY OF PUBLIC INFRASTRUCTURE, NATIONAL DEVELOPMENT UNIT, LAND TRANSPORT AND SHIPPING 7.3 Emergency Rehabilitation Programme and RDA Projects Following the torrential rain of 13 February 2013, the approval of Government was obtained on 15 February 2013 for the urgent implementation of a number of projects in various localities in Port Louis and neighbouring regions and other places such as Baie du Tombeau, Bois Rouge, Pamplemousses, Fond du Sac, Cottage, l’Amitie and Gokhoola for dredging of canals, repair of bridges, embankments and putting up of drain systems under ERP. NDU awarded 47 projects for the sum of Rs 853 million from February to May 2013 under ERP I. After the flash floods of 30 March 2013, giving rise to unprecedented flooding in Port Louis and neighbouring regions, NDU undertook urgent maintenance and rehabilitation of drain systems. NDU funded 19 projects of Rs 62.9 million, which were executed by the RDA. Further, in order to prevent recurrence of flooding, 17 projects were awarded under ERP II for Rs 460.5 million during the period March to May 2013. As of 31 December 2013, a sum of Rs 586.7 million was incurred on 83 emergency projects for a total contract value of some Rs 1.376 billion as shown in the Table 7-3. Table 7-3 ERP and RDA Projects Type of Projects Projects Awarded Contract Value Rs million Actual Expenditure Rs million Number Period ERP I 47 Feb - May 13 853.0 377.7 ERP II 17 Mar - May 13 460.5 185.9 RDA 19 Feb - May 13 62.9 23.1 Total 83 1,376.4 586.7 Source: Project files 7.3.1 Financing and Approval of Emergency Projects Government’s approval was needed for emergency projects as they were not budgeted. Further, prior financial clearance has to be obtained from Ministry of Finance and Economic Development (MOFED) on all requests made that would entail additional provision or commitment of funds. Observations 11 projects under ERP I for a total value of some Rs 42 million were not found in the list of emergency projects approved by Government on 15 February 2013. On 5 April 2013, Government took note of progress in rehabilitation works following the flash floods of 30 March 2013. However, there was no approval of Government for the implementation of ERP II projects and those executed by RDA estimated at Rs 523.4 million. 111 MINISTRY OF PUBLIC INFRASTRUCTURE, NATIONAL DEVELOPMENT UNIT, LAND TRANSPORT AND SHIPPING On 10 and 30 April 2013, MOFED approved additional provision of funds amounting to Rs 472 million for the implementation of emergency projects following floods in February and March 2013. The funds were used not only for emergency projects related to 2013 but also to finance similar projects awarded in 2011 and 2012. There were six cases where Works Orders totalling some Rs 70.9 million were issued before financial clearance was obtained from MOFED. Further, in seven projects, Works Orders for some Rs 194.4 million issued from February to May 2013 exceeded the approved sum of Rs 69.8 million by Rs 124.6 million. 7.3.2 Allocation of Emergency Projects Sections 21(1) and 21(2) of the PPA provide that “a public body may purchase goods, other services or works from a single supplier without competition in cases of extreme urgency” and that “the scope of the emergency procurement shall as far as possible be limited to the period of the emergency so that appropriate competitive procurement methods may be utilised at the conclusion of the emergency period” respectively. At NDU, a time frame of about six months was set for the implementation of the emergency projects. Following advice on emergency procurement sought by NDU in June 2013, the Attorney General’s Office (AGO) stated that: with a view to ensuring transparency and in line with good practices although NDU may resort to emergency procurement, nothing prevents an informal bidding exercise to be carried out from amongst Contractors who have proven experience in carrying out such works. most of the proposed emergency projects were within a specific zone and awarding the projects to zonal contractors might raise concerns as to their capacity to carry out such works within a short time frame. Observations All the contracts under ERP I and II for 2013 were awarded under Emergency Procurement. In 2011, emergency contracts were awarded through restricted bidding as provided in Section 19.1 of the PPA. For Zone 2, projects of total contract value of Rs 742.5 million were awarded to Contractor B as of 31 December 2013. This figure comprised projects of Rs 172.8 million awarded under the zonal contract in February 2013 and 17 emergency projects totalling some Rs 569.7 million were awarded without competition during the period February to May 2013. The latter amount represented about 41 per cent of total contracts of Rs 1.376 billion under ERP. Neither restricted bidding was resorted to nor were informal quotations sought from other Contractors to ensure reasonableness of prices quoted by Contractor B before allocating emergency projects. Moreover, projects awarded to Contractor B were not completed within the contract period as detailed below: 112 MINISTRY OF PUBLIC INFRASTRUCTURE, NATIONAL DEVELOPMENT UNIT, LAND TRANSPORT AND SHIPPING Of the above mentioned 17 emergency projects awarded in 2013, eight of them amounting to Rs 307 million were still not completed as of 31 December 2013. The emergency period ranged from four to six months and was therefore exceeded by one to four months. Six emergency projects of total contract value of Rs 48.3 million due for completion during the period July 2011 to March 2013 were still not yet completed as of 31 December 2013. Delay in completion of works ranged from nine to 29 months. Recommendations Financial clearance and Government’s approval should be sought before embarking into emergency projects. Moreover, the value of Works Orders should not exceed the limits approved by MOFED. NDU should ensure that projects awarded as emergency ones strictly fulfill the requirements of the PPA. As such, the performance of Contractors should be monitored closely so that all emergency projects are executed within the agreed emergency period. To ensure transparency in the process and in line with good procurement practices, NDU should consider resorting to informal bidding exercises for emergency contracts as advised by the AGO. A cost comparison exercise should be done taking into consideration the reasonableness of prices quoted before award of contracts. NDU’s Reply On 9 September 2013, clearance of MOFED was obtained for an additional amount of Rs 87 million and on 13 December 2013, approval was obtained to provide additional funds of the order of Rs 1,315 million. In view of the Government decision to give priority to projects under the ERP, it was decided to implement drains projects under the normal programme at a later stage. Setbacks were experienced for the implementation of emergency projects in terms of difficulties to obtain wayleave, need for acquisition of land, relocation of services; consequently, there was revision in the completion of projects. 7.4 Non Compliance with Conditions of Contract Out of 49 projects, a sample of 17 of a total contract value of Rs 284.8 million was examined. Instances of non compliance with conditions of the contract are shown below: Performance Security According to General Conditions of Contract (GCC), the Contractor is required to provide a performance security of 10 to 15 per cent of the Contract Price, which shall be from a local 113 MINISTRY OF PUBLIC INFRASTRUCTURE, NATIONAL DEVELOPMENT UNIT, LAND TRANSPORT AND SHIPPING commercial bank approved by the public body and shall be valid up to the issue of the Defects Liability Certificate for the works. The performance securities for two projects were not adjusted to reflect increase in contract value due to additional works entrusted to the Contractors. In three cases, the performance securities were not extended to cover the Defects Liability Period in respect of works, which were not completed within the contractual period. For six projects, the NDU accepted performance securities issued from an insurance company instead of a local commercial bank. Programme of Works According to GCC, the Contractor shall submit for approval a Programme of Works within seven days from the date of the Works Order. For four projects, the Programme of Works was submitted from four to 11 months after the issue of the Works Order; and in four cases, these were not submitted at all. Extension of Time According to GCC, the Contractor shall at latest, within a period of seven days after completion of works request the Project Manager to extend the Intended Completion Date. If the Contractor fails to give early warning of a delay, same shall not be considered in assessing the new Intended Completion Date. In three projects, no early warning was given by the Contractor. Nevertheless, extension of time was approved by the Project Manager. Further, the additional time granted was not supported by documentary evidence, such as weather report. Practical Completion According to GCC, the Contractor shall request the Project Manager to issue a Certificate of Completion of works, within 28 days from the date on which the works were actually completed on site. Certificates of completion of works were issued four and six months after the completion of two projects instead of 28 days. For another six projects that were completed, no practical completion certificates were issued. Liquidated Damages According to the Particular Conditions of Contract, the Contractor shall pay liquidated damages to the Employer at the rate of Rs 5,000 per calendar day for each day that the completion date is later than the Intended Completion Date. Liquidated damages were not claimed for three projects although there were delays in the completion of works. 114 MINISTRY OF PUBLIC INFRASTRUCTURE, NATIONAL DEVELOPMENT UNIT, LAND TRANSPORT AND SHIPPING Test Results According to the internal circulars of NDU issued in February 2013, all test results should be submitted by the Contractor at the appropriate time period when the item of work is being performed. Further, as per Contract for road works, standard tests shall be carried out by the Contractor. For one project, the sample sizes for “in-situ density tests for areas under vehicular traffic loading and asphalt wearing course” and for “the diameter and thickness of coring of asphaltic wearing course” should have been 25 instead of 17, and 17 instead of eight respectively. No instruction was seen for a lesser sample. Further, no test reports were attached to the payment certificates for two other projects. Recommendations All terms and conditions of the contracts and internal circulars should be strictly complied with. NDU should ensure that liquidated damages should be claimed where there are delays in completion of contracts and that test results reports are submitted prior to payments. NDU’s Reply It will be ensured that no contracts or work order would be issued without submission of performance security. In case of non submission of performance security, it is contemplated to withhold a specific amount of money from subsequent payment to constitute the amount required for performance security. Necessary measures will be taken to ensure that Contractors comply with the conditions of contract. 115 MINISTRY OF PUBLIC INFRASTRUCTURE, NATIONAL DEVELOPMENT UNIT, LAND TRANSPORT AND SHIPPING 116 MINISTRY OF PUBLIC INFRASTRUCTURE, NATIONAL DEVELOPMENT UNIT, LAND TRANSPORT AND SHIPPING