BUILDINGS & GROUNDS COMMITTEE MEETING Summary January 27, 2015 PRESENT: Trustee Bob Wunderlich, Trustee Barbara Adams, Dr. Debra Daniels, Dr. Judy Mitchell, Wayne King, Dan Lantz, Rick Lyman, Janice Reedus, Kelly Rohder, Pat Van Duyne, DKA representatives: Dominick Demonica and Greg Spitzer 1. Approval of summary After reviewing the summary of the meeting held on December 2, 2014, no additions or comments were recommended. 2. Upcoming bid status RFP: Commissioning Agent Services 465 vendors were notified and 10 of them submitted a reply. Affiliated Engineers, Inc from Madison, WI was chosen. Other submissions were either over budget or did not have prior experience J. Reedus 3. R. Lyman Project Status Report Multipurpose Center/Romeoville Expansion Update Schematic design phase is being wrapped up City Center Campus CDB held pre-bid meeting last week. Mechanical, Electrical, and Plumbing bids will be opened on Thursday, January 29th General Trades bids will be opened on Thursday, February 5th Capital Improvement Updates Painting, Replace Carpet/Tile, Lighting These updates are for C-Building offices and are expected to take place in the summer Phase VI keyless entry Progress continues to be made and the C-Building classrooms are currently in process. Upgrade DDC Romeoville Campus is complete Obtaining pricing for the Greenhouse and Weitendorf facility Replace Roof S-Building Bid will be released in February Parking Lot Improvements & Fire Lane at K-Building Projects are being combined into one bid Bid is expected to be out in February Repairs to D2001 and D2002 Construction documents are in progress Construction to start in May Buildings & Grounds Summary – January 27, 2015 Smart Classroom Renovation Bid documents are in process. A demonstration has been set up for Thursday, January 29th for the high tech furniture. Cover/Repair Exterior Stairs H-Bridge Rick Lyman proposed replacing the current stairwell with a galvanized stairwell with open tread. The committee viewed renderings of the project and agreed to move forward with the project. 4. Other Schematic Design Proposal for Multipurpose Facility and Romeoville Expansion Mr. Dominick Demonica and Greg Spitzer from Demonica Kemper Architects (DKA) presented the proposed schematic design for the Multipurpose Center and the Romeoville Expansion. DKA demonstrated that the feedback received from the steering and programming committee meetings was taken into account in the final renderings. IGEN/StraightUp Solar Panel Installment at Weitendorf Pat Van Duyne informed the committee that JJC will be partnering with IGEN, along with six other participating colleges, for a bulk purchase of solar panels. Installation of the solar panel for JJC will take place at the Weitendorf campus. The total cost is expected not to exceed $83,000. DCEO will refund 50% of those expenses. Next meeting – February 24 – 5:00 p.m. – Multipurpose room A-1002 Buildings & Grounds Summary – January 27, 2015