Multipurpose Port Development in Zanzibar Preliminary Assessment of PPP Options August, 2014 Contents Purpose & Scope 1 Background 1 Current Situation 1 Existing Port at Malindi 1 Proposed New Port at Maruhubi 4 Projections Projected Traffic Growth Projected Revenue Growth 8 8 12 Options Under Consideration 16 Preliminary Conclusions 17 1. Phased Development of Multi-Purpose Port at Maruhubi Only 18 2. Development of Maruhubi Port and Separate OSB Port 19 3. Development of Combined Multi-Purpose Commercial & OSB Port at Deepwater Location Recommended PPP Structure Annex 1 – Maruhubi Port Development 20 20 22 ILLUSTRATIONS Figures Figure 1 Current Conditions at the Port of Malindi 2 Figure 2 Proposed Layout of Phase 1 Multi-purpose Port Development at Maruhubi 6 Figure 3 Proposed Maruhubi Port Area & Phase 1 Development 6 Figure 4 High-Growth 15-Year Traffic Projections for Zanzibar 9 Figure 5 High-Growth 25-Year Traffic Projections for Zanzibar 9 Figure 6 Medium-Growth 15-Year Traffic Projections for Zanzibar 10 Figure 7 Medium-Growth 25-Year Traffic Projections for Zanzibar 10 Figure 8 Low-Growth 15-Year Traffic Projections for Zanzibar 11 II CONTENTS Figure 9 Low-Growth 25-Year Traffic Projections for Zanzibar 11 Figure 10 Combined High, Medium & Low-Growth Scenarios, Total Throughput (Tons), 2012-204012 Figure 11 Projected Operating Revenues, Costs & EBITDA 2015-2030, High Growth Scenario 13 Figure 12 Projected Operating Revenues, Costs & EBITDA 2015-2030, Medium Growth Scenario 14 Figure 13 Projected Operating Revenues, Costs & EBITDA 2015-2030, Low Growth Scenario 15 Figure 14 Future Port Development Sites Under Consideration 16 Figure 15 Full Rendering of Maruhubi Port Development – All Phases 22 Figure 16 Phase 1 Development – Detailed Rendering 23 Tables Table 1 Value of Total Trade 2009-2013 3 Table 2 Maruhubi Port Phase 1 Investment Plan 4 Table 3 Comparison of Port Characteristics – Malindi & Maruhubi 5 Table 4 Present Value of Projected Revenues, Expenses & EBITDA, 15 and 25yrs – High Growth Scenario 14 Table 5 Present Value of Projected Revenues, Expenses & EBITDA, 15 & 25yrs, Medium, LowGrowth 15 Purpose & Scope This Preliminary Assessment of PPP Options has been developed as part of the activities under a World Bank contract for development of a PPP Policy and Guidelines and preliminary assessment of potential PPP projects for the Government of Zanzibar. Below we provide details on the current state of Zanzibar’s main port, the Government of Zanzibar’s plans for port sector development, and recommendations for PPP structures to promote those developments. Background Current Situation Due to congestion at the Port of Malindi, the Government of Zanzibar has determined that development of a new port will be necessary in order to accommodate future growth of cargo and passenger traffic arriving to Zanzibar. Current plans envision construction of a new multipurpose port on Unguja Island constructed in a phased approach. The government’s vision also includes potential construction of a separate port to service oil and gas exploration activities in Zanzibar, as well as upgrading and/or construction of new port facilities on Pemba Island, and re-development of the current port/harbour area to service ferries, cruise liners and other passenger traffic. Development of the harbor area presents significant real estate potential that, if well-developed, can bring significant value to the Government. EXISTING PORT AT MALINDI Located in the heart of Stone Town, the current Malindi Port is highly congested, operating at and sometimes above capacity and is confined to a small area on the outskirts of the city, limiting its potential to expand and creating congestion around the port area. Stone Town has been declared a UN World Heritage site, further hindering potential development and expansion of the existing port. Current traffic volumes at the Port of Malindi in terms of cargo and passengers are fairly significant considering the population it serves. In 2013, the port handled approximately 70,000 twenty foot equivalent units (TEUs) and 260,000 tons of 2 general cargo, and processed a total of 1.5 million passengers from ferries offering service from Dar es Salaam to Stone Town.1 The figure below illustrates the congestion surrounding the port, including the city of Stone Town as well as vessel traffic anchored at sea waiting to offload cargo. The port at Pemba is significantly smaller, handling less than 100,000 tons of general cargo per year. Figure 1 Current Conditions at the Port of Malindi Yard – Container Storage Breakwater Passenger Terminal Area Office/Admin Buildings Warehouses Congestion – Ships waiting to call at port Congestion (Dhow Harbour) Berth 2 Berth 1 Downtown Stone Town CURRENT CONDITIONS AT MALINDI PORT Source: Consultant, Based on Image from Google Earth Approximately 90% of total cargo shipped in containers is offloaded within the port, further congesting the port area and reducing the speed at which cargo can be offloaded and moved in and out.2 Due to congestion, ships must currently anchor at sea and wait for the main berth to vacate, sometimes 4-5 days, before being able to offload cargo. Since there are no shore cranes at Malindi port, the port relies solely on ship-to-shore cranes to offload containers which are then transported by reach stackers. Container ships calling at the port can take up to 2 days to offload (average of between 250-400 containers per ship). The majority of 1 Information received during interviews with MoIC & ZPC - March & May, 2014 2 Interview with Zanzibar Ports Corporation 3 PRELIMINARY ASSESSMENT OF PPP OPTIONS: PORT DEVELOPMENT IN ZANZIBAR containers leaving Zanzibar are empty, given the significant difference between import and export volumes. Currently Malindi port accommodates 1 larger CMA-CGM vessel from the Middle East and 6 feeder vessels per week from smaller shipping lines. In terms of volume, the majority of the goods processed through the port are imports (approximately 90%); however export cargo has experienced steady growth over the last several years which is expected to continue.3 The table below provides import and export value statistics for the 2009-2013 period. Table 1 Value of Total Trade 2009-2013 ('000 Tzs) 2009 % of Total 2010 % of Total 2011 % of Total 2012 % of Total 2013 % of Total Imports 120,882 80% 129,137 88% 164,187 73% 271,273 80% 208,052 70% Exports 29,745 20% 17,907 12% 61,261 27% 67,391 20% 87,800 30% Total 150,627 100% 147,044 100% 225,449 100% 338,664 100% 295,852 100% Source: Zanzibar 2013 Economic Survey Malindi Port Characteristics: Over the last several years, Malindi Port has operated at or above capacity and remains continuously congested. Water depth limits the size of vessels that can call at the port, and limited equipment, including the absence of shore cranes, makes offloading cargo slow, adding further congestion. The port’s key characteristics are listed below: 4 Built: 1920’s, Refurbished 2008 Managed by: Zanzibar Ports Corporation (100% publicly owned) Located: 60km North of Dar es Salaam Average depth surrounding port: 10m (range of 8-13 m) Two approach channels: English Pass - max depth 12m & South Pass – max depth 13m+ 2 Berths: 240m (depth of 7-13m) & 130m (depth of 5m) Maximum Vessel Size: 13,000 DWT, 200m in length Yard Space: 75,000 sq meters (1.75 ha) Storage: 2 storage warehouses, each 4,200 m2; Empty Container Storage: Bwawani – 1.75 ha Designed Handling Capacity: 160,000 tons general cargo, 25,000 tons liquid bulk cargo Shore cranes: None 3 Interview with Zanzibar Ports Corporation 4 Feasibility Study for New Zanzibar Port Project Phase 1 4 Other Equipment: Reach stackers Dredging Requirements: Heavy siltation, continuous dredging required Several sites have been identified as potential locations for construction of a new port to replace Malindi, including the Maruhubi Port site, for which several feasibility studies have been undertaken (most recently in September, 2013). Three additional natural deep water sites on Unguja Island have been evaluated as part of a pre-feasibility study effort by Royal Haskoning which assessed potential port sites at Maruhubi, as well as deep water sites at Fumba, Mangapwani, and Bumbwini. The Government of Zanzibar’s vision is to serve as a regional transshipment hub, cater to the needs of the oil and gas sector as it pursues exploration off the coast of Pemba, and to act as a processing hub for the deep sea fishing industry. Part of this vision includes the need to relocate domestic port facilities further from Stone Town to reduce congestion and provide space for development of commercial activities linked to the port. This requires any future port to consider not only growth in cargo volumes for Zanzibar, but also potential growth of transit cargo, and the needs of the oil and gas and deep sea fishing industries (accommodation of large vessels, space for handling of project cargo and special equipment, space to build fish processing facility, etc.). The site for the new Zanzibar port will need to meet all of these requirements. PROPOSED NEW PORT AT MARUHUBI Discussions are underway and an MOU has been signed with the Chinese Harbour Engineering Company (CHEC) for design and construction of the Maruhubi Multipurpose Port located approximately 2km north of the existing Port of Malindi. The new port would be developed in 2-3 phases, the first phase including development of a multi-purpose terminal capable of handling containers, general cargo, and some bulk cargo as well as liquid bulk (oil) imports. Under the current plans, investment for Phase I of the port development will total approximately $230 million including a $200 million loan from China Ex-Im Bank, as well as close to $30 million in equity provided by CHEC. It is unknown whether the contract would be a turnkey design and construction contract or a concession contract for design, construction, operation and maintenance of the port. The proposed investment plan and financing terms for the port, as outlined in the Feasibility Study for Phase 1 of the Maruhubi Port Project carried out by CHEC, are outlined in more detail in the table below: Table 2 Maruhubi Port Phase 1 Investment Plan Description Amount ($US) Construction Investment $225.2 million Financing Costs $2.5 million Working Capital .74 million 5 PRELIMINARY ASSESSMENT OF PPP OPTIONS: PORT DEVELOPMENT IN ZANZIBAR Total Investment $228.4 million Repayment Period: 5 + 20 = First 5 years, payments on interest only, then annual installments on principal & interest over 20 years Annual Interest Rate: 1% Hurdle Rate: 8% Guarantee Provided by Government of Zanzibar (Ministry of Finance) Source: Feasibility Study of New Zanzibar Port Project Phase 1 Phase 1 would include construction of one larger berth 300 meters in length at a maximum depth of 13.5 meters to accommodate vessels of up to 50,000 dwt, as well as a smaller berth of 65m and maximum depth of 5 meters able to accommodate tugboats and other small vessels. Phase 1 would also include container and general cargo yards of 54,000 sqm and 18,000 sqm respectively. There is a natural approach channel leading directly to the proposed site of the Phase 1 development, however dredging and land reclamation are needed to meet the required depths, estimated at approximately 1.54 million cubic meters (at a cost of $24 million or $15.56 per cubic meter, considered very high compared to costs). The project period is estimated at 25 years, with construction making up 2.5 years and operations making up 22.5 years (from 2016-2030). Phase 1 would accommodate cargo traffic through the year 2030, and would be built with a capacity to handle up to 200,000 TEU and 250,000 tons of cargo per year (total of approximately 2.25 million tons p.a.). Although a concrete proposal has not been reviewed, this analysis assumes that in the year 2030 construction of Phase 2 would be complete and would begin operations. The table below provides a comparison between the current Malindi port and the planned port at Maruhubi: Table 3 Comparison of Port Characteristics – Malindi & Maruhubi Characteristic Malindi Port Proposed Maruhubi Terminal Phase 1 Average Depth 10m (range of 8-13 m) 13.5m Berths 2 berths, 240m (depth of 7-13m) & 130m (depth of 5m) 2 berths, 300m (depth of 13.5m) & 65m (depth of 5m) Vessel Size 13,000 dwt 50,000 dwt Yard Space 75,000 sq meters 72,000 sqm Handling Capacity (Tons) 160,000 tons general cargo, 25,000 tons liquid bulk cargo 200,000 TEU, 250,000 tons general cargo Source: Feasibility Study for New Zanzibar Port Project Phase 1 6 Below is a rendering of the Phase 1 development to be constructed by CHEC, as well as a map showing the location of the new port area and proposed Phase 1 development in relation to Malindi Port. Figure 2 Proposed Layout of Phase 1 Multi-purpose Port Development at Maruhubi Source: Feasibility Study of New Zanzibar Port Project Phase 1 Figure 3 Proposed Maruhubi Port Area & Phase 1 Development Proposed Phase 1 Development Proposed Maruhubi Port Area Existing Malindi Port 7 PRELIMINARY ASSESSMENT OF PPP OPTIONS: PORT DEVELOPMENT IN ZANZIBAR Source: Consultant using Image from Google Earth As can be seen above, the proposed new port at Maruhubi would include construction of an access road connecting with the main road leading into and out of Stone Town (Malawi Rd.). While the proposed new terminal is further from the city than the existing port, the access road connects with a main artery immediately surrounded by commercial and residential buildings, meaning port traffic would compete with commuters going into and out of the city to other parts of the island. While congestion in the downtown area would be reduced with relocation of the port, a new center of congestion would be created at the new Maruhubi port entrance, particularly during the construction phase with transport of construction materials, and would move congestion from the center of Stone Town to the outskirts potentially causing a domino effect as traffic shifts to new roads to avoid port congestion. Equally, the terminal would be located in a highly developed area, making the acquisition of additional land for development of a terminal to accommodate oil and gas requirements unlikely. In addition, the Maruhubi site does not meet the depth requirements for an oil and gas port, under the current proposal, meaning construction of a second port facility in a natural deep water location would be required to service the oil and gas industry. Such duplication is unlikely to be cost-effective. The CHEC Phase 1 port development plan differs from the Government of Zanzibar’s original plans for the phased development of the new commercial port at Maruhubi. According to the 2007 Zanzibar Transport Master Plan, the Maruhubi port development total investment cost was projected at a total of US $200 million, $80-90 million of which would be set aside for development of Phase 1 (approximately $102.5 million in 2014 dollars). The Phase 1 development at Maruhubi envisioned in the Transport Master Plan included a 420m berth with a depth of 12-14m with a preference for handling vessels of up to 60,000dwt and a capacity to handle 50,000 TEU and 150,000 tons of general cargo. The plan also included 65,000 m2 for a container yard and storage. The general size and depth of the port in the current CHEC plans are more or less consistent with the port envisioned as part of the 2007 Transport Master Plan. 8 Projections From the data above and interviews with various stakeholders, it is clear that Malindi Port is no longer able to accommodate the levels of both passenger and cargo traffic currently arriving to Zanzibar, considering projected future growth rates of containerized cargo and the port’s designed handling capacity. Congestion surrounding the port and inadequate storage space within the port causes continuous delays and a new multipurpose port is needed to replace the existing cargo port facilities. To address this need, the government is considering phased construction of a new multi-purpose commercial port at Maruhubi which would accommodate ships up to 50,000 dwt, with a total capacity of 250,000 tons of general cargo and 200,000 TEU through 2030.5 In order to provide a better understanding of the size and type of facilities needed to accommodate future growth in cargo traffic in Zanzibar, a highlevel analysis of historical traffic at Malindi port was undertaken, and projections for future traffic and revenues were developed based on historical growth trends. These results are presented below. PROJECTED TRAFFIC GROWTH Taking into consideration historic cargo throughput at Malindi from 2000 – 2012 (taken from the Feasibility Study for New Zanzibar Port Project Phase 1), 15-year and 25-year traffic projections were developed based on high, medium, and low-growth scenarios, as shown in Figures 4-9 below. General assumptions for traffic growth calculations include the following: High, medium and low-growth scenarios were based on projected GDP growth for Zanzibar following trends in GDP, tourism, and population growth respectively;6 Conversion from TEUs to tons is assumed at 10 tons/TEU (TEUx10=tonnage) Under the high-growth scenario based on projected GDP growth, total throughput by the year 2030 is estimated at approximately 2.6 million tons ( approximately 580,000 tons general cargo, and 197,000 TEU) and by 2040 reaches close to 4.3 million tons (approximately 955,000 tons general cargo and 321,000 TEU). Planned capacity for the Phase 1 development project totals approximately 2.25 million tons, meaning within the high-growth scenario the maximum capacity of the Phase 1 development would be reached prior to the end of the project period in 2030 (capacity would instead be reached in 2028). Figures 4 and 5 below illustrate these high-growth scenarios: 5 Feasibility Study for New Zanzibar Port Project Phase 1 6 Taking into account historical GDP growth for Zanzibar from 2000-2013 and projected growth based on IMF GDP growth projections for Tanzania 9 PRELIMINARY ASSESSMENT OF PPP OPTIONS: PORT DEVELOPMENT IN ZANZIBAR Figure 4 High-Growth 15-Year Traffic Projections for Zanzibar 3,000,000 Phase I Full Capacity (2028) 2,500,000 Tons 2,000,000 1,500,000 1,000,000 500,000 2012 2015 2018 Liquid Bulk (Petroleum - Tons) 2021 2024 General Cargo (Tons) 2027 2030 Containers (Tons) Source: Statistics from Feasibility Study of New Zanzibar Port Project Phase 1 Figure 5 High-Growth 25-Year Traffic Projections for Zanzibar 4,500,000 4,000,000 3,500,000 Phase I Full Capacity (2028) Tons 3,000,000 2,500,000 2,000,000 1,500,000 1,000,000 Phase I Project Period 500,000 2015 2020 Liquid Bulk (Petroleum - Tons) 2025 2030 General Cargo (Tons) 2035 2040 Containers (Tons) Source: Statistics from Feasibility Study of New Zanzibar Port Project Phase 1 In the medium-growth scenario, based on projected GDP growth from international tourism growth, total throughput by the year 2030 is estimated at approximately 2.09 million tons (approximately 468,000 tons general cargo, and 158,000 TEU) and by 2040 reaches close to 3.4 million tons (approximately 757,000 tons general cargo and 254,000 TEU). These figures are illustrated in Figures 6 and 7 below. Under the medium-growth scenario, total Phase 1 capacity is reached in the year 2032 when total throughput reaches 2.3 million tons, shown in Figure 7 below. 10 Figure 6 Medium-Growth 15-Year Traffic Projections for Zanzibar Source: Statistics from Feasibility Study of New Zanzibar Port Project Phase 1 Figure 7 Medium-Growth 25-Year Traffic Projections for Zanzibar Source: Statistics from Feasibility Study of New Zanzibar Port Project Phase 1 In the low-growth scenario, based on projected GDP growth from population growth, total throughput by the year 2030 is estimated at approximately 1.47 million tons (approximately 328,000 tons general cargo, and 110,000 TEU) and by 2040 reaches close to 1.97 million tons (approximately 441,000 tons general cargo and 149,000 TEU). These figures are illustrated in Figures 8 and 9 below. Under the low-growth scenario, total Phase 1 capacity is not reached within the projected period (2015-2040). 11 PRELIMINARY ASSESSMENT OF PPP OPTIONS: PORT DEVELOPMENT IN ZANZIBAR Figure 8 Low-Growth 15-Year Traffic Projections for Zanzibar 1,600,000 1,400,000 1,200,000 Tons 1,000,000 800,000 600,000 400,000 200,000 2012 2015 Liquid Bulk (Petroleum - Tons) 2018 2021 2024 General Cargo (Tons) 2027 2030 Containers (Tons) Source: Statistics from Feasibility Study of New Zanzibar Port Project Phase 1 Figure 9 Low-Growth 25-Year Traffic Projections for Zanzibar 2,500,000 2,000,000 Tons 1,500,000 1,000,000 Phase I Project Period 500,000 2015 2020 Liquid Bulk (Petroleum - Tons) 2025 2030 General Cargo (Tons) 2035 2040 Containers (Tons) Source: Statistics from Feasibility Study of New Zanzibar Port Project Phase 1 Based on the above projections, traffic is projected to surpass planned capacity of the Phase 1 port development at Maruhubi in two of the three scenarios, meaning construction of Phase 2 would need to begin between 2025 and 2030 in order to meet expected demand, depending on actual growth during the Phase 1 project period. 12 Figure 10 Combined High, Medium & Low-Growth Scenarios, Total Throughput (Tons), 2012-2040 Source: Consultant analysis based on projections using Statistics from Feasibility Study of New Zanzibar Port Project Phase 1 PROJECTED REVENUE GROWTH While the Zanzibar Port Corporation’s full financial statements were not analyzed for this briefing note, a simplified analysis and projection of revenues and costs was undertaken to determine potential port revenue for the Phase 1 project period (2030) and potential revenue for the life of the port asset (Phase 1) through 2040. Revenues and costs were projected based on the total operating revenue and operating costs for 2013 provided during interviews with officials at the ZPC from which the cost per unit was calculated for general cargo, twenty foot equivalent units (TEUs), and liquid bulk. General assumptions taken into consideration for the revenue and cost projections include: Beginning operating costs equal to 70%7 of operating revenues from 2012-2018 (through 1st year of Phase 1 port operations), decreasing by 5% every 3 years starting in 2019 based on assumption of more efficient, modern facilities and increased operating efficiency under management of a private operator. Operating costs reduce to 50% of operating revenues by the end of the project period in 2030; Estimated per unit tariffs were calculated by multiplying total share of cargo type as a percent of total throughput for 2012 by total revenue (2012) and dividing by cargo type (example: [TEU (expressed as tons)/Total Tonnage x Revenue]/# of TEU). The estimated per-unit tariffs were calculated at US $11.57 per ton for general cargo and liquid bulk, and $115.75 per TEU; 7 Assumption based on information provided during interviews with Zanzibar Ports Corporation 13 PRELIMINARY ASSESSMENT OF PPP OPTIONS: PORT DEVELOPMENT IN ZANZIBAR Revenue and Prices were assumed to grow at the rate of U.S. inflation, based on IMF projections through 2019; Present value of revenues, costs and EBITDA calculated for both the project period (2016-2030 assuming construction begins 2016 and operations begin 2018) and for the projected asset life (25 years, through 2040) at discount rates of 12% (Tanzania), 6% (China) and 3% (low-rate comparison); IRR was calculated based on investment costs for Phase 1 of US $230 million and project period of 25 years (2016-2030); Revenues and costs were projected based on high, medium and low-growth scenarios using projected GDP growth based on projected GDP, number of international tourists, and population, as described in the section on traffic analysis above. Under the high-growth scenario based on projected GDP growth through 2030, operating revenues and costs are estimated to reach US $31 million (Tzs 49.6 billion) and US $15.5 million (Tzs 24.8 billion) respectively, leaving an EBITDA of US $15.5 million, as shown in Figure 11 below. Figure 11 Projected Operating Revenues, Costs & EBITDA 2015-2030, High Growth Scenario 35,000 30,000 '000 $USD 25,000 20,000 15,000 10,000 5,000 2012 2015 Projected Revenue ($000) 2018 2021 2024 2027 2030 Projected Operating Expenses ($000) Projected EBITDA ($000) Source: Consultant Analysis Based on Data from Stakeholder Interviews March, 2014 Based on the high-growth scenario presented above and using the results for operating revenues, operating expenses and EBITDA from 2015-2040, the 15 and 25-year present values were calculated based on the three benchmark discount rates presented above to provide an idea of the Zanzibar Port Corporation’s (or future port operator’s) capacity to generate operating cash flow and to finance future port development. The table below provides the projected present values based on the high-growth scenario. 14 Table 4 Present Value of Projected Revenues, Expenses & EBITDA, 15 and 25yrs – High Growth Scenario SUM SUM 15 yr. PV PV PV 25 yr. PV PV PV $US ('000) (2030) 12% 6% 3% (2040) 12% 6% 3% Operating Revenue $321,455 $129,147 $195,269 $247,695 $731,242 $169,583 $318,209 $469,413 Operating Expenses $187,265 $79,552 $117,107 $146,432 $392,159 $99,770 $178,577 $257,291 EBITDA $134,189 $49,595 $78,162 $101,263 $339,083 $69,813 $139,632 $212,122 Source: Consultant Analysis Based on Data Received During Stakeholder Interviews, March 2014 The table above shows a 15-year present value of EBITDA of approximately US $49.6 million at the 12% Tanzanian benchmark discount rate, and approximately US $78.2 million at the 6% Chinese benchmark discount rate, while 25-year present value of EBITDA reaches US $69.8 million at 12% and US $139.6 million at the 6% discount rate. With a present value of EBITDA of less than $230 million under the high-growth scenario, covering financing costs for the Phase 1 port development project will not be possible without significant government subvention or grant funding, even at the proposed 1% interest rate through a China Ex-Im Bank 25-year loan. IRR was also estimated under the high-growth scenario for the 2016-2030 project period taking into consideration the estimated required investment of $230 million, resulting in a -5.15% IRR for the Phase 1 project period. The figures below present the projected operating revenues, operating expenses and EBITDA for the Phase 1 Project Period under the medium and low-growth scenarios, while Table 4 below summarizes the present value of revenues, expenses and EBITDA under the same scenarios. Figure 12 Projected Operating Revenues, Costs & EBITDA 2015-2030, Medium Growth Scenario Source: Consultant Analysis Based on Data from Stakeholder Interviews March, 2014 15 PRELIMINARY ASSESSMENT OF PPP OPTIONS: PORT DEVELOPMENT IN ZANZIBAR Figure 13 Projected Operating Revenues, Costs & EBITDA 2015-2030, Low Growth Scenario 20,000 '000 $USD 15,000 10,000 5,000 2012 2015 2018 2021 2024 2027 2030 Projected Revenue Projected Operating Expenses ($000) Projected EBITDA ($000) Source: Consultant Analysis Based on Data from Stakeholder Interviews March, 2014 Under the medium growth scenario, total revenues reach approximately US $24.7 million in 2030, while operating expenses and EBITDA reach US $12.35 million, and under the lowgrowth scenario revenues reach US $17.3 million while operating expenses and EBITDA reach US $8.6 million. As the table below demonstrates, under both the medium and low-growth scenarios, present value of total EBITDA at the three benchmark rates reach a maximum of US $85.1 million under the medium-growth scenario by the year 2030 and only US $66.7 million under the low-growth scenario. By extending the project period through 2040, these numbers rise to US $172.9 million and US $122.3 million under the medium and low-growth scenarios respectively, falling short of the required US $230 million investment required under the proposed Maruhubi Phase 1 development. Table 5 Present Value of Projected Revenues, Expenses & EBITDA, 15 & 25yrs, Medium, Low-Growth SUM $US ('000) SUM 15 yr. PV PV PV 25 yr. PV PV PV (2030) 12% 6% 3% (2040) 12% 6% 3% M E D I U M G R O W T H S C E N A R I O Operating Revenue $270,559 $111,264 $166,315 $209,719 $595,277 $143,329 $263,771 $385,445 Operating Expenses $158,473 $68,902 $100,300 $124,671 $320,832 $84,935 $149,028 $212,534 EBITDA $112,087 $42,362 $66,015 $85,048 $274,445 $58,395 $114,743 $172,910 L O W G R O W T H S C E N A R I O Operating Revenue $213,016 $91,023 $133,579 $166,788 $417,620 $111,576 $195,531 $278,009 Operating Expenses $125,924 $56,839 $81,292 $100,070 $228,226 $67,116 $112,268 $155,681 EBITDA $96,016 $34,184 $52,287 $66,718 $189,394 $44,460 $83,263 $122,329 Source: Consultant Analysis Based on Data Received During Stakeholder Interviews, March 2014 16 Options Under Consideration Figure 14 Future Port Development Sites Under Consideration Bumbwini Mangapani Maruhubi Fumba a Source: Consultant using map image from: http://mapsof.net/map/topographic-map-of-zanzibar The 2007 Transport Master Plan and current CHEC proposal envision development of a multipurpose commercial port at Maruhubi to potentially serve as a regional transshipment hub to compete with the ports at Dar es Salaam, Mombasa and Djibouti for cargo destined for East Africa. While several feasibility studies have shown the Maruhubi port site area to be 17 PRELIMINARY ASSESSMENT OF PPP OPTIONS: PORT DEVELOPMENT IN ZANZIBAR suitable for a larger commercial port, other sites may provide more preferable locations for port development, particularly if the new port is to serve the oil and gas industry. The map above illustrates the various port sites considered in this briefing based on sites identified in previous port development feasibility studies for Zanzibar. While some sites were explored in Pemba, none have been determined as suitable for positioning of a large commercial and/or OSB port, and are not included in this report. As mentioned previously, the four sites under consideration include Maruhubi, Bumbwini, Mangapani, and Fumba. Based on our investigation, developing a regional transshipment hub in Zanzibar is unlikely. Generally, regional transshipment hubs must be anchored on domestic cargo, and currently the majority of Tanzania’s domestic cargo is handled at the Port of Dar es Salaam. Furthermore, current and projected traffic volumes do not indicate the increase in cargo necessary for Zanzibar to become a regional transshipment hub, particularly taking into consideration the current role of larger transshipment hubs in the Middle East, port expansion and modernization projects taking place at the ports of Djibouti and Mombasa, as well as the potential development of the port at Bagomoyo on Mainland Tanzania. Preliminary Conclusions Developing a new commercial greenfield port in Zanzibar is compatible with the Government’s PPP strategy; Developing one multi-purpose port for cargo and oil and gas industry requirements would be more efficient than developing two separate port facilities, as currently contemplated. While development of a larger multi-purpose port to accommodate both general cargo and oil and gas exploration could be more complicated, it would most likely result in greater cost savings and economies of scale than development of two separate ports; Locating the new port in one of Unguja’s natural deep water locations will allow larger vessels and would most likely significantly reduce the cost of capital and maintenance dredging. The current Maruhubi proposal is not a deep water location; The PPP formula would be financed primarily using private finance, but will require some government funds to finance the development of basic infrastructure. This is the case for the majorly of the greenfield port projects around the world; Once the new port is complete, the existing port facilities at Malindi could be developed using PPP into a harbor and fully-dedicated passenger facility; The current Maruhubi proposal of a large commercial port facility in close proximity to Stone Town and existing tourist attractions will create additional congestion, reduce opportunities to develop industry and other associated commercial activities that might leverage off of the port, and discourage future tourist growth; The current Maruhubi proposal is located in a heavily developed area without much opportunity for land-side expansion. Developing a green field port at a site without 18 land limitations for future expansion is an important condition for attracting quality port operators and industrial real estate developers; More important than the cost to construct the new port facilities is the 40-year present value of operating a port at a suboptimal location. Building a suboptimal facility would not only reduce potential revenue generation, but would also generate additional congestion, environmental and social costs, and higher operating and logistics costs. Based on the above conclusions, below we provide a brief analysis of the three main options under consideration by the Government of Zanzibar for port development, based on current plans and previous feasibility studies undertaken. 1. Phased Development of Multi-Purpose Port at Maruhubi Only In previous sections we described the proposed plan for the phased development of a large commercial port at Maruhubi. While the land has been allocated and several feasibility studies conducted to determine the suitability of the Maruhubi site, we believe the Maruhubi location is not the most ideal for port development in Zanzibar based on several factors, as follows: The day-to day activity of a large scale commercial port on the outskirts of Stone Town is not compatible with the development of a high-end tourism industry; At a maximum 13.5 meter depth, the Maruhubi port site still limits the size of vessels that can call at the port to smaller feeder vessels (Handymax and Supramax being the largest – up to 50,000 dwt) and does not provide the minimum depth required to attract large Panamax and Post-Panamax ships used to transport large quantities of containers (i.e. transshipment vessels); Fairly significant land reclamation and dredging will be required to develop the site; With the recent oil and gas discoveries near Pemba Island, catering to the offshore exploration and construction industry will be critical, however the minimum depth required for Offshore Supply Base (OSB) ports is 20 meters, while the maximum depth at Maruhubi will be only 13.5 meters, meaning the Maruhubi port development plan could not be expanded to cater to the oil and gas industry. Also, the land surrounding the Maruhubi site is insufficient for the demands of the oil and gas industry for storage and lay-down areas; Based on the investment plan for the Phase 1 development at Maruhubi and the projected traffic and revenues under the highest-growth scenario presented above, the Phase 1 project is not feasible without significant government subsidization or grant funding, greatly diminishing the possibility of attracting a world-renowned private port operator to manage the new port; 19 PRELIMINARY ASSESSMENT OF PPP OPTIONS: PORT DEVELOPMENT IN ZANZIBAR The Maruhubi port site is only slightly removed from the current Malindi port and still surrounded by commercial and residential areas close to the city center meaning congestion surrounding the new port would continue to be a problem. Expansion beyond the port area would also be difficult and costly given the proximity to Stone Town. The new port should have significant expansion capacity to promote the development of related industries with very low land prices; Although a natural entrance channel exists at the Maruhubi port site, the surrounding areas are shallow and changes in currents could bring increased siltation and mean higher maintenance dredging costs in the future. 2. Development of Maruhubi Port and Separate OSB Port While development of the Maruhubi Port site has received much attention of late, it has become clear the Government of Zanzibar is keen to develop a port capable of servicing the offshore oil and gas industry to support exploration and future production activities. One option under consideration is to develop a commercial port at Maruhubi and develop a separate OSB port at one of the natural deep-water sites recently identified by Royal Haskoning. Development of an OSB port in Zanzibar will of course depend on proven reserves and the potential for growth in the oil and gas sector, which will dictate the characteristics of the port including the land required for development, total capacity, required depth and related dredging, and potential construction of a breakwater, among others. Based on the traffic and revenue analysis above as well as our experience in the port sector, we believe development of a separate OSB port has the potential to be less complicated than combining with a multipurpose port, however we believe development of two separate ports would be a suboptimal course of action for the Government of Zanzibar for the following reasons, in addition to those mentioned under Scenario 1 above: Based on even the highest-growth scenario for projected traffic and revenues as well as planned investment, the Phase 1 development at Maruhubi would not be feasible without significant government subsidization or grant funding, as mentioned above, meaning development of two ports to handle commercial cargo and OSB separately would be even less financially feasible, and would significantly reduce the possibility of attracting a private port operator to manage either port; A separate OSB port would support oil and gas exploration and production activities over a specified period of time, with cargo volumes tapering off as oil and gas field development advances. After a certain time the amount of cargo moving through the OSB port would greatly diminish, leaving a port operating far below capacity and receiving very little cargo. Repurposing the port would be difficult as commercial activities would already be centered at Maruhubi and, as shown above, projected traffic levels would not be enough to support two ports. 20 3. Development of Combined Multi-Purpose Commercial & OSB Port at Deepwater Location A third option would include development of one, multi-purpose combined commercial and OSB port at one of the three natural deep-water sites previously identified. This option would, of course, require further analysis of the various deep-water sites proposed under previous studies to determine the optimal location for such a port, as well as the total required investment based on estimated demand for port services. Based on the analysis presented above, our experience in port development in Africa and worldwide, and based on feasibility studies undertaken for port development in Zanzibar, we believe this option presents the best potential outcome for the Government of Zanzibar for the following reasons: Although total capital investment for this larger port would most likely be higher than required investment for Phase 1 at Maruhubi, total investment for a combined commercial/OSB port would be far less than the combined investment for two separate ports, meaning significant cost savings and economies of scale can be achieved by combining the two ports; Choosing a site further from Stone Town (Bumbwini, Mangapani, Fumba) would provide more space for expansion, critical for meeting future traffic needs over the next 100 years; The sites at Bumbwini, Mangapani and Fumba offer natural deep water ports which would not only accommodate larger container ships and vessels carrying project cargo, but would also likely require less capital and maintenance dredging to maintain the entrance channel and turning basin at the required depth, lowering overall maintenance costs; Development of a combined port would create a more attractive and profitable business that would attract top port operators, particularly under a design, build, operate and maintain concession contract; A combined port in a larger area would allow for phased development of multipurpose cargo terminals to accommodate containers and general cargo as well as large fishing vessels on one side with an OSB terminal on the other side, and would allow for development of free zones and processing zones around the port area, increasing opportunities for industrial development and job creation linked to the port. Recommended PPP Structure It is essential to note that port developments are important long-term investments which must consider 30-40 year operating periods and enough space to accommodate 100 years’ worth of growth. Careful consideration must be given to the timing and location of new port 21 PRELIMINARY ASSESSMENT OF PPP OPTIONS: PORT DEVELOPMENT IN ZANZIBAR developments with a longer-term view that will support national development well into the future. The Government of Zanzibar finds itself at a critical juncture where current decisions will affect future growth and development of the island, and choosing the least-best option could pose a serious threat to the government’s economic growth and development objectives. Location of a port is one of the most critical elements for ensuring the port will have the throughput and revenue-generating capacity to accommodate growth in a highly competitive global economy. Selection of a suboptimal location would serve as a disincentive for private operators who would be less likely to invest in a port development in Zanzibar. Taking into consideration the traffic and revenue projections and analysis presented above, this paper recommends consideration for development of a combined commercial and OSB port at one of the three natural deep water locations identified above under a 30-year DesignBuild-Operate-Maintain concession contract. This option would allow the Government of Zanzibar to attract a top quality port construction and operations company with significant worldwide experience in both commercial and OSB port site development, and would allow for the possibility of developing a world-class multi-purpose port that could serve as a model for the region. This option would require significant investment on the part of the government in basic port infrastructure; however the potential for value generation would be greatly enhanced under such an arrangement. 22 Annex 1 – Maruhubi Port Development The figure below shows the full Maruhubi Port Development Plan proposed by CHEC based on the phased approach, with Phase 1 highlighted in orange. Figure 15 Full Rendering of Maruhubi Port Development – All Phases Source: Feasibility Study of New Zanzibar Port Project Phase 1 Figure 16 below provides a more detailed rendering of the proposed Phase 1 port development identifying various characteristics of the Phase 1 project including berth, container yard, storage area, office buildings, customs inspection, and lorry parking areas, among others. 23 PRELIMINARY ASSESSMENT OF PPP OPTIONS: PORT DEVELOPMENT IN ZANZIBAR Figure 16 Phase 1 Development – Detailed Rendering Source: Feasibility Study of New Zanzibar Port Project Phase 1