Board Meeting: May 2015 Agenda Number: 12 (ii) File Ref: EL0034 LORD HOWE ISLAND BOARD Business Paper ITEM Renewable Energy Program BACKGROUND In December 2011 the Lord Howe Island Board approved the LHIB Energy Supply Road Map (the Road Map) which outlined a plan to provide more than 80% of the Island’s electricity needs through renewable energy, thus reducing the reliance on diesel fuel. The Road Map identified the commercially proven technologies of wind and solar PV which can be safely integrated into the existing generation and distribution system. The Board CEO signed a Funding Agreement with ARENA on 17 July 2014 for a $4.5M grant, which includes $0.5M of contingency. Since submitting the Business Case to the NSW Government, the major change has been the adoption of a loan arrangement with TCorp (NSW Government's bank) for the funding, and repayment of the loan using savings in diesel consumption. The loan arrangement was adopted to maximise the funding available from ARENA. CURRENT POSITION ARENA Funding The 3rd and 4th milestone reports were submitted before 30 March 2015 as required, and all milestone requirements were achieved by the Board. ARENA has yet to make payment of $220,000 on the 2nd milestone from 31 December 2014. State Government Activities Negotiations between TCorp and the Board regarding the terms of the loan, have not commenced yet. Electric Vehicles In late April, the Board’s Manager Infrastructure and Engineering Services (MIES) met in Sydney with representatives of RMS and Transport for NSW regarding the statewide review of conditional registration. It is clear that Lord Howe Island is a consideration in the review and the Board will be invited to make a submission when a Discussion Paper is released within the next month. The Board will ensure that the Discussion Paper is made available to Island residents for individual comment directly to Transport. The MIES invited the RMS and Transport representatives to visit the Island. Owner's Engineer Jacobs has continued to provide excellent service in carrying out the Owner’s Engineer role. Recently, the major task was the finalisation of the Technical Feasibility Study for the project, included as Attachment A. In addition, Risk Management and Contracting Strategy workshops were held in Sydney in late April, in conjunction with ARENA. Contracting Strategy The procurement / contract options examined for this project fall into the following categories: Design & Construct (D&C) – including Engineering Procurement Construction (EPC) Project Management / Construction Management – including Engineering Procurement Construction Management (EPCM) Construct only A combination of the above The recommended procurement method is for an overarching Project Manager and Owner’s Engineer (PMOE) to assist the Board with the management of packages of work delivered either as D&C, supply only or construct only. Interestingly, this is similar to the recommendation from ABB in their 2013 work. The following figure shows the recommended arrangement. For this recommended model, the advantages and disadvantages are listed below. Advantages Lower overall capital cost compared to D&C/EPC Lower incidence of variations due to scope, performance or quality requirements Changes and innovation can be introduced during the project’s delivery and managed Can accommodate owner’s team undertaking some work Warranties are direct with the owner Owner’s team has greater control over equipment/vendor/subcontractor selection Allows relationship to develop between vendor/contractor and the owner Owner’s staff are involved and develop a sense of ownership Focus tends to be on Life Cycle Cost rather than solely on minimum upfront cost Disadvantages Cost and time risk stays with the owner Contingency is managed by the owner Constructability risk remains with the owner eg. should ground conditions not be as expected, the owner is responsible for cost and time variations Larger owner’s team required or the owner needs to engage the required skills Program and cost can escalate if owner’s team or OE ‘enhance’ too much Final cost is not known till project completion. This applies to EPC also where variations occur or delay costs are granted to the contractor. The project would be divided into five or six packages as follows: Package Procurement by Fee Type Battery and control system Solar PV plant D&C D&C Lump sum Lump sum Wind turbine plant Supply only Lump sum Infrastructure – for third party construction Construct only Lump sum Infrastructure for owner’s team construction Construct only Owner’s cost Environmental Assessment and Development Approvals Jacobs are close to finalising the specific environmental assessment work for the solar PV, battery and access road construction. The noise assessment work was finalised in late April and made available to the public. Attachment B is the Noise Fact Sheet distributed in late April 2015. Attachment C is the photo-montage of the solar panels on the site. Community Consultation Jacobs are planning a 2nd visit to the Island 8-11 May to coincide with the release of the Noise Assessment and the Community Markets on 10 May. During that visit, there will also be a meeting with SEWG. Jacobs have been engaged to carry out further community consultation work over the next 6 months to ensure that the valued work of the SEWG and the high level of community support is not lost. The next phases of work will include: Community stakeholder meetings in September Information on a Community Owned Solar Scheme as part of the project Wind and Avifauna Monitoring Mast The wind and avifauna monitoring mast was installed and erected on 13th November 2014. Data is collected on a fortnightly basis and sent to Jacobs for analysis. Highlights include: Average wind speeds for the top of the mast are 7m/s, slightly less than the last Board report A maximum wind gust of 100km\hr was recorded in April. Solar irradiation levels continue to be lower than expected. A 2nd instrument will be installed in early May to rule out any instrumentation issues. RECOMMENDATION It is recommended that the Board: 1. Note the above information 2. Approve the contracting strategy Prepared __________________ Andrew Logan Manager, Infrastructure & Engineering Services Endorsed __________________ Penny Holloway Chief Executive Officer