ENVIRONMENTAL “GREEN FLAG” CHECKLIST FOR PRE-CONSTRUCTION This Environmental Checklist is designed to assist project managers in identifying potential environmental requirements early in the planning process. This will enable the project manager to determine and meet environmental requirements for all project specific construction activities. 22 CES/CEAN stands ready to help provide you with more detailed guidance on environmental requirements, and address any questions/concerns you may have. Also, 22 CES/CEAN can assist with obtaining permits or answer questions on environmental requirements for any project. Remember that this is only a simple checklist - there are a myriad of environmental requirements, and those requirements can easily become overwhelming, so if you have a question, please call! General Information Project Number: Official Project Name: Project Manager: Phones: Points of Contact: Description of Project and Requirements: (Street Address, Intersections, GIS Coordinates; Attach SOW, Site Location; Total Acreage Disturbed; Construction Start Date:) 22 CES/CEAN – Environmental Green Flag Checklist – Rev 4, as of 2/9/2016 - Page 1 of 7 ENVIRONMENTAL “GREEN FLAG” CHECKLIST Environmental Points of Contacts Program Air Cultural/ Natural Resources/ Water / Waste Water EMS/ P2/ Recycling/ Solid Waste ESOHCAMP/ HAZMAT/ HAZWASTE NEPA/ Storage Tanks/ Toxics Restoration Government Personnel Mike Mackay (759-3927) Dave Pettus (759-4446) Kristi Draney Pat O’Brien Jim Correia Cole Knight Dennis Heyer Booz Allen Support (759-3884) (759-5345) (759-3345) (759-3887) (759-5733) 22 CES/CEAN – Environmental Green Flag Checklist – Rev 4, as of 2/9/2016 - Page 2 of 7 ENVIRONMENTAL “GREEN FLAG” CHECKLIST WATER DISCHARGE REQUIREMENTS YES 1. Are you doing construction dewatering? 1a What are you going to do with the water? 1b How many gallons of water will be discharged? Note: Best Management Practices (BMPs) must be followed and reporting to 22 CES/CEAN must be done on the construction water discharges. In addition, pre-discharge notification and sampling may be required for those discharges >75,000 gallons that are covered by this permit. Discharging any water that may have contaminants such as soap, dirt, or oil into any waterway, concrete channel, ditch, street, or onto the ground must have prior written approval from 22 CES/CEAN. 2. Are you going to disturb more than 1 acre of land? (Note: “Disturb” is defined as any land used for staging, storage, parking, and any temporary access roads (unpaved) in addition to any actual construction “footprint”. If so, you will need a construction Stormwater permit from the U.S. EPA. This normally takes about 10 days.) 2a. You must also prepare, and submit for written approval to 22 CES/CEAN, a Stormwater Pollution Prevention Plan (SWPPP) for the construction activity prior to submitting the NOI. 2b. In order to obtain the permit you are required to prepare and submit a signed Notice of Intent (NOI) to 22 CES/CEAN at least 10 days prior to the start of any land disturbance. The NOI must be submitted to KDHE 60 days prior to start of any land disturbance and that the NOI and SWPPP should be submitted to 22 CES/CEAN prior to submitting it to KDHE. 2c. You must comply with the plan you have written once work commences (Including: conducting biweekly inspections and assuring permit conditions are being met together with written documentation of the inspections are required by the SWPP plan). 2d. For projects covering over 5000 square feet, the project must maintain predevelopment hydrology to the maximum extent technically feasible. Follow all Air Force guidance for implementation of the Energy Independence and Security Act. 2e. Within 30 days of completion of construction, you must submit a signed Notice of Termination (EPA Form 3510-13) to 22 CES/CEAN. 3. Are you going to install or close a well monitoring portal and/or observation hole? If so, written approval from 22 CES/CEAN is required to ensure the State Engineer’s regulations are complied with prior to installation or closing. 22 CES/CEAN – Environmental Green Flag Checklist – Rev 4, as of 2/9/2016 - Page 3 of 7 NO N/A REMARKS ENVIRONMENTAL “GREEN FLAG” CHECKLIST AIR EMISSIONS REQUIREMENTS YES NO N/A REMARKS YES NO N/A REMARKS 1. Are you going to install an emergency generator(s)? If so, what is the capacity of the generator(s)? Note: all generators must be reported to 22 CES/CEOFP (CE Power Production) so they can be added to the air emission inventory regardless of size or use. ENVIRONMENTAL IMPACT ANALYSIS PROCESS (EIAP) The Environmental Impact Analysis Process, driven by the National Environmental Policy Act (NEPA), will require one or more of the following: Categorical Exclusion (CATEX), Environmental Assessment (EA), Environmental Impact Statement (EIS). NEPA coordination duration, from submittal of report(s) to receipt of clearance(s), may take 6 months to 2 years. Funding for this analysis is the responsibility of the project proponent. 1. Complete AF Form 332 (Base Civil Engineer Work Request) and submit to 22 CES Customer Service. 22 CES/CEAN reviews the AF Form 332 at Work Request Review Board (WRRB). If required, submit AF Form 813 (Request for Environmental Impact Analysis) to 22 CES/CEAN. 2. If a CATEX applies (determined by EIAP manager), 22 CES/CEAN will annotate specific CATEX code on AF Form 332, which will normally complete the EIAP milestone. NOTE: Some CATEXes require documentation on AF Form 813 (ref 32 CFR 989, Appendix B). In such cases, submit AF Form 813 to 22 CES/CEAN. 3. If no CATEX applies, complete AF Form 813 and submit to 22 CES/CEAN. 22 CES/CEAN will determine the EIAP milestone schedule and request additional input for the AF Form 813. 4. Define all proposed actions and list all reasonable alternatives and unknowns. 5. Provide documentation of approved site location (and alternative sites, if any). Example: site plan, drawing, etc. 6. Major projects now require 36 months advance notice to complete an EA, per HQ AFSPC/MSEVP. EAs normally take 6 to 12 months to complete. (NOTE: If EIS is required, the EIS can take 2 years to complete and get approval from Secretary of the Air Force.) 7. Minor fix or repair jobs may not require EIAP or coordination with 22 CES/CEAN prior to start. However, see Item 8 below. 8. Coordination through 22 CES/CEAN is required on all AF Form 103 (Base Civil Engineering Work Clearance Request) A properly executed AF 332 or AF 813 is required before 22 CES/CEAN will sign an AF 103. 9. For SABER projects, verify that EIAP was completed prior to SABER contract award. Also identify applicable city, county, state, or federal air, water, or waste permits required prior to contract award. 22 CES/CEAN – Environmental Green Flag Checklist – Rev 4, as of 2/9/2016 - Page 4 of 7 ENVIRONMENTAL “GREEN FLAG” CHECKLIST ENVIRONMENTAL BASELINE SURVEY (EBS) YES NO N/A NO N/A REMARKS 1. The Base Real Property Office (22 CES/CEAO) normally determines whether or not a project requires an EBS or an EBS waiver. Contact 22 CES/CEAO, 759-4457, to verify EBS requirement. 2. If EBS is required, complete AF Form 813 and submit to 22 CES/CEAN to initiate both EIAP and EBS processes. CEAN will determine milestone schedule and request additional input, as needed. 3. An EBS can take from 6 to 12 months to complete, coordinate, and get approval. If applicable, an EBS waiver may take less time. 4. Verify that EIAP and EBS were completed prior to contract award. FUEL/OIL STORAGE & EQUIPMENT MAINTENANCE YES 1. Are you going to refuel equipment at the work site? 1a. If equipment is going to be refueled with tankers, how and where will that be done? (Note: DOT requirements for fuel transfers must be followed, and the contractor must coordinate with Security Forces personnel to bring tankers into the restricted area [if applicable].) 2. Will fuel be stored on-site? If so, the fuel storage area must have spill containment controls (i.e., tanks must be double-walled). Notify McConnell AFB Fire Department prior to storing fuel on-site. 3. How much petroleum, oil or lubricants (POL) are going to be stored (gallons)? 3a. If 55 gallons or greater total are to be stored, long term, on site above ground, prepare and implement a contractor Spill Prevention Control and Countermeasure (SPCC) Plan, or incorporate the fuel storage into the base’s SPCC plan (or provide funding to update the base SPCC). Any container that is in the SPCC Plan will require monthly inspection and personnel that own, operate or handle these containers will require annual training per the SPCC Plan. 3b. Secondary containment or control measures as listed in 40 CFR 112.7(5)c(1), shall be included in the SOW, design, and specifications to the project. The secondary containment or the controls must prevent POL from entering storm drains, drainage ditches, soil, streambeds or any path that will allow the POL to reach the navigable waters of the United States. 3c. Ensure the re-occurring work program (RWP) is updated to ensure all the maintenance and inspections are done oil filled equipment or storage tanks according to 40 CFR 112 and/or the SPCC. (Note: Any corrective action to a project that requires an update to the SPCC Plan must be incorporated, no later than 6 months after submittal and reply, into the SPCC Plan, per 40 CFR 112.5(1). A Professional Engineer must certify any technical amendment to the SPCC Plan in accordance with 40 CFR 112.3(3).) 4. Storage Tanks? Prior written approval from 22 CES/CEAN is required for the placement of any storage tank on McConnell AFB property. 5. Are you going to repair or maintain equipment at the work site? If so, what kind of solvents will be used for parts washing? How will waste solvent and/or used oil be managed/ disposed? (Note: Contact Hazardous Material/ Waste office at 759-5345/ 5346 for storage and disposal information). 6. What provisions are you making to ensure that oil or other chemicals will not be released to the ground? 22 CES/CEAN – Environmental Green Flag Checklist – Rev 4, as of 2/9/2016 - Page 5 of 7 REMARKS ENVIRONMENTAL “GREEN FLAG” CHECKLIST ASBESTOS REQUIREMENTS YES NO N/A REMARKS YES NO N/A REMARKS 1. Are you going to remodel or disturb any material that may contain asbestos, such as pipe insulation, roofing material, wallboard, underground electrical conduit, asbestos-cement pipe (transite), stucco, or floor or ceiling tiles? If so, an inspection of these materials must be performed by a certified inspector. (Note: Asbestos waste must be disposed of a facility permitted to accept asbestos waste. All copies of testing, abatement and manifests must be provided to 22 CES/CEAN). WASTE GENERATION/DISPOSAL REQUIREMENTS 1. Are you going to remove any construction debris such as liquid wastes, pipe, soil, rock, asphalt, or concrete? 1a. Debris must be disposed of at an approved site. 1b. Only approved HAZMAT intended for use with this contract will be stored on MAFB. 2. Are you going to dig a trench or excavate in an area that may have petroleum or other contamination (e.g. from nearby activities such as service stations or old landfills)? (Note: Contaminated material cannot be used for backfill; it must be properly disposed. Contact 22 CES/CEAN) 3. Are you going to generate any special wastes such as asbestos, sandblasting debris, soils, solvents, flammable liquids, chemical wastes, paint wastes, fluorescent light tubes or ballasts, or wastes that may contain metals such as lead, chromium, or mercury (e.g. lead paint)? (Note: Wastes must be sampled to determine the appropriate disposal method.) 4. If your project involves waste generation/disposal, what are your plans to meet the environmental requirements for waste disposal? (Note: Non-Hazardous Wastes (Solid Wastes) that are recyclable are tracked and must be recycled and weights must be reported to the 22 CES/CEAN.) 4a. All contractor personnel involved in waste handling must be properly trained for the handling, collection, and storage of that waste IAW 40 CFR 264.16. 4b. All RCRA and Special waste manifest must be signed by 22 CES/CEAN. Signed facility copies of the manifest will be returned to 22 CES/CEAN for record keeping. 5. All contractors are required to enroll in Enterprise, Environmental Safety & Occupation Health Management Information System (EESOH-MIS), and all hazardous materials introduced onto MAFB must be and approved through EESOH-MIS. (Note: All materials not used in the construction process are the responsibility of the contractor and are to be removed from MAFB upon completion of contract. All hazardous waste generated or abandoned by the contractor will be the contractor’s responsibility. Should MAFB need to dispose of contractor Hazardous Waste the cost will be billed to the contractor.) 22 CES/CEAN – Environmental Green Flag Checklist – Rev 4, as of 2/9/2016 - Page 6 of 7 ENVIRONMENTAL “GREEN FLAG” CHECKLIST WILDLIFE YES NO N/A REMARKS YES NO N/A REMARKS YES NO N/A REMARKS There are currently no species federally or state-listed as endangered, threatened, or species of special concern on MAFB. Migratory Birds: All migratory birds are protected under the Migratory Bird Treaty Act. Any activity that may impact migratory birds must be coordinated through the US Fish and Wildlife Service. This will take 30 to 90 days. CULTURAL & PROPERTY ACQUISITIONS 1. Will the project consist of digging or trenching? Although McConnell AFB has been surveyed for archeological sites, there is always the potential for unknown, and unanticipated sites to be discovered during any project involving excavation. Such sites can be badly damaged or destroyed by excavation. If previously undetected archeological resources are discovered during project activities work must be stopped immediately, and the individual responsible for implementing the work or job foreman will immediately notify the 22 CES/CEAN. The site must be protected from further disturbance until 22 CES/CEAN has cleared the project to proceed! ENVIRONMENTAL REGULATIONS ADDED TO ALL PROJECTS 52.223-3, Hazardous Material Identification and Material Safety Data. 52.223-4, Recovered Material Certification. 52.223-5, Pollution Prevention and Right-to-Know Information. 52.223-6, Drug-Free Workplace. 52.223-7, Notice of Radioactive Materials. 52.223-8, [Reserved] 52.223-9, Estimate of Percentage of Recovered Material Content for EPA-Designated Products. 52.223-10, Waste Reduction Program. 52.223-11, Ozone-Depleting Substances. 52.223-12, Refrigeration Equipment and Air Conditioners. 52.223-13, Certification of Toxic Chemical Release Reporting. 52.223-14, Toxic Chemical Release Reporting. In addition to the above clauses, all contracts shall include the following clause that is published on the MAFB LAN : AFI 32-7086/50SUP1, Hazardous Materials Management, 03 Jan 00 22 CES/CEAN – Environmental Green Flag Checklist – Rev 4, as of 2/9/2016 - Page 7 of 7