STANDARD SPECIAL PROVISION SUPERPAVE ASPHALT MIXTURE DESIGN, STANDARD AND RPS CONSTRUCTION OF PLANT-MIXED ASPHALT PAVEMENT COURSES WITH DEPARTMENT LOCAL ACCEPTANCE, AND PAYMENT BY PERCENT WITHIN TOLERANCE (PWT) I. DESCRIPTION- This work is the Standard and RPS construction of plant-mixed asphalt mixtures on a prepared surface using a volumetric mixture design developed with the Superpave Gyratory Compactor (SGC). Acceptance of the work is based on test results using Local Acceptance (LA), Independent Assurance (IA) Testing and statistical evaluation of test results by PWT procedures. Acceptance testing is performed locally at the Contractor’s designated laboratory by the Department’s Representative. This special provision applies to all bituminous paving items of Sections 309, 311, 316, 409, 410, and 411. II. MATERIALS – Section 409.2 with additions and modifications as follows: (e) Mixture Composition for Standard and RPS Construction. 1. Virgin Material Mixtures. Section 409.2(e)1. Replace the first three paragraphs with the following: Size, uniformly grade, and combine aggregate fractions in proportions to produce a Job Mix Formula (JMF) that conforms to the material, gradation, and volumetric Superpave Asphalt Mixture Design requirements as specified in Bulletin 27, Chapter 2A, for the specified Nominal Maximum Aggregate Size (NMAS) and design Equivalent Single Axle Loads (ESALs). Submit a copy of each completed JMF, signed by a certified Bituminous Level 2 Plant Technician, to the District Materials Engineer/District Materials Manager (DME/DMM) at least three weeks before the planned start of mixture production. Include a list of all material sources and the asphalt mixture producer in the JMF. For each JMF to be tested according to PTM No. 757, submit the calibration factors (Cƒ and200 Cƒ) for the JMF which are specific to each ignition furnace to be used for the testing. Provide calibration factors that were determined within the preceding twelve month period. Do not start mixture production until after the DME/DMM reviews and signsoff on the JMF. Submit a new JMF with a change in material sources or if a new JMF is necessary to produce a mixture conforming to this specification. 1.b Plant Technicians. Section 409.2(e) 1.b. Replace paragraph with the following: Page 1 of 13 1. b Plant Technicians. During mixture production, provide a certified Bituminous Level 1 Plant Technician at the plant and an on-call certified Bituminous Level 2 Plant Technician, both meeting the requirements outlined in Publication 351. Instruct and train the certified technicians to perform all tests and to control plant operations. All technicians must carry a valid certification card during mixture production. The Department’s certified Bituminous Level 1 or Level 2 Plant Technician will be properly trained and will meet the requirements outlined in Publication 351. III. CONSTRUCTION–Section 409.3 with additions and modifications as follows: (a) Preplacement Requirements. Section 409.3(a). Add the following subsection: 3. Local Acceptance Quality Control (LA QC) Plan. Submit a LA QC Plan that is separate from all other QC Plans to the Representative for review and sign-off. Ensure that the LA QC Plan details the methods and procedures to be used by the Contractor for sampling, packaging, transporting, handling, and securing the mixture and density samples used for acceptance. Include the location of the designated Contractor or Producer laboratory testing facility in the LA QC Plan. Submit the QC plan at least three weeks before the planned start of paving. Do not start work until the Representative has reviewed and signed-off on the LA QC Plan. Should the Representative determine that the LA QC Plan is not being followed; the Representative will direct the stoppage of paving operations and LA sample testing. Stop all paving operations and LA sample testing immediately when directed. Under the direction of the Representative, investigate the cause of the LA QC Plan not being followed. Perform corrective actions to the satisfaction of the Representative. Revise the LA QC Plan if necessary or as directed by the Representative. If the Representative is not satisfied, the Department may discontinue testing of LA samples and begin Department testing and lot acceptance as specified in Section 409.3(h)2. and Section 409.3(j)4. When the Representative is satisfied with the corrective actions, resume testing of LA samples. (c) Bituminous Mixing Plant. Section 409.3(c). Add the following subsection: 3. Laboratory Testing Facility. For testing of LA samples by the Department, identify a laboratory testing facility where the local testing is to be performed. Identify either the laboratory located at the asphalt mixture production plant, or identify a laboratory located where the traveling time between the laboratory location and project location is less than or equal to the traveling time between the laboratory located at the production plant and the project location. Identify a laboratory testing facility which has demonstrated testing proficiency through an AASHTO Materials Reference Laboratory’s (AMRL’s) On-Site Laboratory Assessment performed within the last two years prior to the start of LA sample testing. The AMRL On-Site Laboratory Assessment must have been completed on the equipment proposed for utilization by the Department. The Department may consider other testing proficiency qualification processes, but only under extreme circumstances and only when an AMRL On-Site Laboratory Assessment cannot be performed. At the project preconstruction meeting, submit the identified laboratory testing facility location and AMRL Laboratory Assessment report and any necessary corrective action documentation to correct any deficiencies on the Laboratory Assessment report for review by the Representative. The Representative will review the laboratory testing facility location and AMRL assessment documentation and, if acceptable, designate the laboratory testing facility for the project. Use the designated laboratory for testing all LA samples. If a change in the designated laboratory testing facility is necessary, submit the new laboratory testing facility location at least two weeks in advance of the proposed change. Include the AMRL Laboratory Assessment report for the new laboratory testing facility and any necessary corrective action documentation for any deficiencies noted by the AMRL Laboratory Assessment report. The Representative will review the new laboratory testing facility and AMRL assessment documentation and, if acceptable, designate the new laboratory testing facility for the project. The Representative will specifically review the testing facility equipment to ensure it meets the required test method requirements, manufacturer installation requirements, standardization or calibration requirements and frequency, manufacturer maintenance requirements and frequency, maintenance log records, and the facility plan for removing equipment from service should it fail to meet any requirements, requires standardization or calibration, or becomes inoperable or requires repair/maintenance. Provide laboratory testing equipment at the designated laboratory testing facility as required in the specified test methods and as modified in Bulletin 27 for properly testing mixture and density LA samples. Provide test equipment to the Department to test LA samples. Page 2 of 13 (h) Spreading and Finishing. 2. a Lots and Sublots. Material will be accepted in the field on a lot by lot basis. Lots will be established cumulatively and will be specific for each JMF. Each lot consists of five equal sublots (n=5). A completed sublot has a mixture acceptance box sample as specified in Section III. (h)2. b and either a core collected according to PTM No. 1 or other density acceptance as specified in Section III. (j). A normal lot size is 2,500 tons with five, 500 ton sublots (n=5), unless operational conditions or project size dictate otherwise. If operational conditions or project size dictate, readjustment of the lot will be made as specified in Table D. Breakdowns or stoppages of short periods due to such causes as weather or equipment failure will not be considered as reason to adjust the lot size. The original lot will be continued when work resumes after short stoppages of less than 5 days. If a lot is terminated due to a stoppage of 5 days or more, adjust the lot size and number of sublots as specified in Table D. If work stoppages exceed 5 days, a new lot will be established. To terminate a lot without a work stoppage of 5 days or more, stop paving operations and notify the Inspectorin-Charge in writing of the lot termination and include the reason for termination. Do not begin paving again until the Inspector-in-Charge authorizes paving activities to resume. If a lot is terminated when quantities exceed a normal size lot of 2,500 tons, the work will be considered two separate lots, a normal size lot and a terminated lot. The terminated lot will be only that portion of the work which exceeds the 2,500 ton normal sized lot up to the point the paving operations were stopped. A terminated lot will be evaluated based on the samples obtained before the lot was terminated. For terminated lots with three or more sublots, acceptance will be determined using PWT pay factor adjustments. Terminated lots with two or fewer sublots will be evaluated according to Section 409.3(h) 2.a.1. For terminated lots where density acceptance is by pavement cores, if the first randomly selected coring location was not yet reached at the time the lot was terminated, the Inspector will recalculate one new sample location according to PTM No. 1, PTM No. 729, and PTM No. 746 from the pavement placed. The payment for any terminated lot the Contractor elects to terminate will be 90% of the contract unit price or the payment value determined by evaluating the samples tested, whichever is less. Remove and replace terminated lot pavements when test results indicate defective work. The District Executive will not consider requests for reduced payment on terminated lots when test results indicate defective work. 2.b Mixture Acceptance Samples. Section 409.3(h)2.b. Replace completely by adding the following three subsections: 2.b.1 Mixture Samples for Local Acceptance (LA). The Inspector will select different sample locations in each sublot according to PTM No. 1 and PTM No. 746. In the presence of the Inspector, obtain one loose mixture sample according to PTM No. 746 for each sublot directly from the uncompacted mixture placed by the paving equipment specified in Section 409.3(e) and immediately package. For 19 mm and smaller NMAS mixtures, package individual samples in cardboard boxes dimensioned approximately 3 3/4 inches x 4 3/4 inches x 9 1/2 inches. For 25 mm and larger NMAS mixtures, package individual samples in cardboard boxes dimensioned approximately 5 inches x 5 1/2 inches x 9 inches. Do not package samples in cardboard boxes with any one dimension greater than 10 1/4 inches or any one dimension smaller than 3 1/2 inches. Immediately after packaging, the Inspector will take possession of the sample and will identify the sample by ECMS project number, lot and sublot number, location (station and offset), date of placement, mixture type, and as LA samples (Sample Class AS). Provide a sufficient number of containers of adequate size to contain at least five mixture LA samples from the mixture acceptance lot. Containers may be sized large enough to also contain any pavement core density acceptance samples. If multiple containers are needed, the Inspector will identify containers as being from the same lot and containing LA samples. Do not package LA samples from more than one lot in the same container. The Inspector will inspect the containers. Repair, modify or replace any containers determined to be inadequate or that are not able to be sufficiently secured. Provide newly purchased and unopened padlocks to the Inspector for securing the containers. If the containers cannot be secured with keyed padlocks, the Department will provide individually Page 3 of 13 numbered security ties, security tape or other security devices for securing the containers. The Inspector will properly secure the containers with a security device before the containers are turned over to the Contractor for immediate transport to the designated testing laboratory. If the container or samples show any evidence of their security being compromised, the Department may reject them for testing, suspend paving operations, and require additional samples to be taken for acceptance. For QC purposes, a maximum of one loose mixture sample per sublot may be obtained. No loose mixture or core samples may be taken by the Contractor for mixture composition testing after the mixture acceptance samples are obtained. Do not obtain any other pavement samples, except those which are directed by and surrendered to the Department, unless allowed in writing from the District Executive (DE). If other loose mixture samples are taken by the Contractor for QC testing purposes, keep these samples completely separated from the mixture samples for LA. Do not combine, replace or otherwise intermingle QC samples with LA samples. 2.b.2 Mixture Samples for Independent Assurance (IA). For IA, the Department will select the initial lot and a minimum of one out of every ten lots thereafter for IA. For each lot selected by the Inspector and with the Inspector present, obtain mixture samples for IA by splitting the mixture sample obtained for LA for each sublot. Obtain mixture samples in each sublot of the selected lot in sufficient quantity to split the mixture sample into two portions, a LA sublot sample and an IA sublot sample. For 19 mm and smaller NMAS mixtures, package individual samples in cardboard boxes dimensioned approximately 3 3/4 inches x 4 3/4 inches x 9 1/2 inches. For 25 mm and larger NMAS mixtures, package individual samples in cardboard boxes dimensioned approximately 5 inches x 5 1/2 inches x 9 inches. Do not package samples in cardboard boxes with any one dimension greater than 10 1/4 inches or any one dimension smaller than 3 1/2 inches. Immediately after packaging, the Inspector will take possession of the IA samples and will identify the samples by ECMS project number, lot and sublot number, location (station and offset), date of placement, mixture type, and as IA samples (Sample Class IA). Leave at least one side of the cardboard sample box free of any writing or marking for LTS use in testing the samples. The Inspector will submit the IA samples to LTS for testing by delivering them to the shipping point in a timely manner. 2.b.3 Theoretical Maximum Specific Gravity (Gmm) Verification Samples. For lots where density acceptance is by pavement cores, the Inspector will select the same sample locations chosen for LA in each sublot. In the presence of the Inspector, obtain one loose mixture sample for each sublot at each sample location directly from the uncompacted mixture placed by the paving equipment specified and immediately package. The loose mixture sample at each location will be used to determine the Gmm and corresponding theoretical maximum density (lbs/ft 3) values. For 19 mm and smaller NMAS mixtures, package individual samples in cardboard boxes dimensioned approximately 3 3/4 inches x 4 3/4 inches x 9 1/2 inches. For 25 mm and larger NMAS mixtures, package individual samples in cardboard boxes dimensioned approximately 5 inches x 5 1/2 inches x 9 inches. Do not package samples in cardboard boxes with any one dimension greater than 10 1/4 inches or any one dimension smaller than 3 1/2 inches. Immediately after packaging, the Inspector will take possession of the samples and will identify the samples by ECMS project number, lot and sublot number, location (station and offset), date of placement, mixture type, and as Gmm verification samples (Sample Class FV). For QC purposes, a maximum of one loose sample per sublot may be obtained. No loose mixture or core samples may be taken by the Contractor for mixture composition testing after the Gmm verification samples are obtained. Do not obtain any other pavement samples, except those which are directed by and surrendered to the Department, unless allowed in writing from the DE. 2.c Mixture Acceptance Sample Testing. Section 409.3(h)2.c. Replace with the following: LA testing by the Department’s certified LA Representative will be utilized for acceptance purposes unless otherwise directed. 2.c.1 LTS Testing. Section 409.3(h)2.c. Replace subsection title, replace all paragraphs, and add two subsections as follows: 2.c.1 Testing of Local Acceptance (LA) Mixture Samples. Prior to any testing, the Department LA Page 4 of 13 Inspector will examine the containers and samples for any evidence of their security being compromised. No testing will be performed on any samples if the Inspector determines that the security of the LA samples have been compromised. Testing of LA samples will not begin prior to completion of the Lot and will begin immediately after the Inspector arrives at the testing location and determines the samples to be secure. LA samples are the top priority for testing over all other testing upon the Department Representative arriving at the designated testing laboratory to test the LA samples. Do not discard any LA samples used for lot acceptance until directed by the Representative. The Department will retain all paperwork used in the LA sample testing for a period of not less than three years from the date of testing. 2.c.1.a Department Testing. At the designated LA laboratory testing facility, the Department’s certified LA Inspector will test each sublot mixture LA sample according to PTM No. 757 or PTM No. 702, Modified Method D, if previously identified problematic aggregates are used in the mixture to determine Asphalt Content (AC), percent passing the 75 µm (No. 200) sieve, and the percent passing the Primary Control Sieve (PCS). The Contractor’s technician may be present to witness the testing performed by the Local Acceptance Inspector. The technician must bring to the immediate attention of the Inspector any deviation in performing the test according to the specified test method. If deviations are not noted at the time they occur, the test results will be considered accurate. The Department will analyze the test results for extreme values according to PTM No. 4 at the 5% significance level. If the discarding of an extreme value reduces a lot to less than three remaining test results, the Department will accept the lot as specified in Section 409.3(h)2.a.1. The Department will determine mixture acceptance, as specified in Section IV. (a).4.a.3. If acceptance test results indicate a defective lot (remove and replace) or a lot with an OLPF < 90, the Contractor may request in writing that the Department retest the lot in accordance with Section IV. (a)4. b. If the Asphalt Content, the percent passing the 75 µm (No. 200) sieve, or percent passing the PCS does not achieve an OLPF ≥ 100 for two consecutive lots or a total of three lots, stop all production of the JMF. Determine the cause of the problem and provide a proposed solution to the Department. Do not resume production of the JMF until the representative reviews the proposed solution and authorizes production to continue. 2.c.2 LTS Testing of Independent Assurance (IA) Mixture Samples. The LTS will test the mixture samples for IA according to PTM No. 757 or PTM No. 702, Modified Method D, if previously identified Problematic aggregates are used in the mixture, to determine asphalt content and the percent passing the 75 µm (No. 200) sieve. The LTS will use the calibration factors (Cƒ and 200 Cƒ) provided with the JMF for PTM No. 757. The Department reserves the right to verify Contractor provided calibration factors (Cƒ and 200 Cƒ) provided when deemed necessary. 2.c.2.a Mixture IA Sample Test Result Analysis. LTS IA split sample test results will be compared to the LA split Acceptance Sample test results on the same lot. If the difference in the average LA and IA test results meet the Independent Assurance tolerances in Table E-1, the Department will continue with IA testing at a minimum of one out of every ten lots thereafter for each JMF. Table E-1 Independent Assurance Tolerances on Lot Averages Testing Criteria Max. Difference Between Average Test Results (n≥3) Asphalt Content for 9.5 mm and 12.5 mm NMAS Mixtures Asphalt Content for 19 mm, 25 mm and 37.5 mm NMAS mixtures Percent Passing the No. 8 sieve for 9.5 mm and 12.5 mm NMAS mixtures Percent Passing the No. 4 sieve for 19 mm, 25 mm And 37.5 mm NMAS mixtures Percent Passing the No. 200 sieve for all mixtures Page 5 of 13 ±0.3% ±0.4% ±4% ±5% ±1.2% If the difference between the lot averages of IA sample test results and LA sample test results exceeds the maximum Independent Assurance tolerances in Table E-1, specific calibration factors (Cf and 200 Cf) will be determined for each ignition furnace used for testing the IA samples and LA samples according to PTM No. 757 (LTS and Contractor or Producer ignition furnaces) and additional IA samples will be collected in accordance with Section III.(h)2.b.2 from the project for IA comparison. If the IA tolerances in Table E-1 are still exceeded, the Representative will perform an investigation as to the cause for the non-comparison of the test results. Provide information to the Representative, as requested, on the integrity of samples and on the testing equipment used in the sample testing. The Representative will also review personnel and test methods used in the LA testing. Implement corrective measures for any noted deficiencies to ensure the tests are performed according to the prescribed procedures. The Representative will record the LA sample test results, the IA sample test results and any applicable corrective measures in the Field Inspector’s Diary. The Representative will select the next lot on the project for IA and will submit the IA split samples to LTS for testing. If the difference between subsequent IA split sample test results and LA split sample test results exceeds the IA tolerances in Table E-1, the Department may discontinue testing of LA samples and begin LTS testing of the mixture acceptance samples for the remainder of the project and revert to Section IV for measurement and payment. If the difference between subsequent IA split sample test results and LA split sample test results meets the IA tolerances in Table E-1, the Department may continue testing of LA samples with IA testing at a minimum of one out of every ten lots. (j) Mat Density Acceptance. 4.c Density Acceptance Samples. Section 409.3(j) 4.c. Replace the three paragraphs completely by adding the following two sub sections: 4. c.1 Density Samples for Local Acceptance (LA). The Inspector will select different sample locations in each sublot according to PTM No. 1, PTM No. 729, and PTM No. 746. With the Inspector present, drill 6inch diameter cores as soon as possible but no later than the day following placement. The core at each location will be used to determine the bulk specific gravity (Gmb) and density (lb/ft 3) of the compacted mix. Do not compress, bend, or distort samples during cutting, handling, transporting, and storing. If samples are damaged, immediately obtain replacement samples, as directed by the Inspector, from within 12 inches of the original sample location. Within 24 hours after coring, backfill the hole with mixture of the same JMF or with mixture used for subsequent courses and compact and seal the mixture. The Inspector will identify the samples by ECMS project number, lot and sublot number, location (station and offset), date of placement, mixture type, and as LA samples (Sample Class AS). Provide the daily theoretical maximum specific gravity value from Section 409.2(e) 1.d.4 for the density calculation of the lot. If density samples from the lot are taken from more than one day’s placement, the average of the daily theoretical maximum specific gravity values from each production day will be used to calculate the percent of theoretical density for each individual density acceptance core placed for the individual and corresponding sublot increments on that production day upon Gmm verification as described in Section III. (j)4. d.1.b. Provide sample containers of sufficient strength to prevent samples from being damaged during transport. The Representative will submit samples for one lot in one container. The inspector will properly secure the containers with a security device before being immediately transported to the designated testing laboratory. If the container or samples show any evidence of their security being compromised, the Department may reject them for testing, suspend paving operations and require additional samples to be taken for acceptance. Provide adequate facilities at all times to maintain the samples in a proper environment to prevent degradation. For QC purposes, a maximum of one pavement core per sublot beyond the pavement cores obtained for LA may be obtained unless the Representative allows additional cores. The test results from the density LA samples can be used for QC purposes. No pavement cores may be taken by the Contractor after the pavement core LA and IA samples are obtained. Do not obtain any other pavement cores, except those which are directed by and surrendered to the Department, unless allowed in writing by the District Executive. If other pavement core samples are taken by the Contractor for QC testing purposes, keep these samples completely separated from the pavement core samples for LA and IA. Do not combine, replace or otherwise intermingle QC samples with LA and IA samples. 4. c. 2 Density Samples for Independent Assurance (IA). For IA, the Department will select the initial lot and a minimum of one out of every ten lots thereafter for IA. For each lot selected by the Inspector and with the inspector present, drill 6-inch diameter cores according to PTM No. 729 at the same time that the density samples for LA are Page 6 of 13 drilled. Drill samples as companion samples of the density samples for LA and within 12 inches of the sample location for the density sample for LA. Do not compress, bend, or distort samples during cutting, handling, transporting, and storing. If samples are damaged, immediately obtain replacement samples, as directed by the Inspector, from within 12 inches of the location of the density sample for LA. Within 24 hours after coring, backfill the hole with mixture of the same JMF or with mixture used for subsequent courses and compact and seal the mixture. With the Inspector present, identify the samples by ECMS project number, lot and sublot number, location (station and offset), date of placement, mixture type, and as IA samples (Sample Class IA). Provide the daily theoretical maximum specific gravity value from Section 409.2(e)1.d.4 for the density calculation of the lot. Immediately after identifying, submit the density IA samples to the Inspector. Provide sample containers of sufficient size to package density IA samples for one lot in one container. Provide sample containers of sufficient strength to prevent samples from being damaged during transport. The Inspector will package the density IA samples in the containers and submit the companion core IA samples to LTS for testing by delivering them to the shipping point in a timely manner. For QC purposes, a maximum of one pavement core per sublot beyond the pavement cores obtained for IA may be obtained unless the Representative allows additional cores. No pavement cores may be taken by the Contractor after the pavement core LA and IA samples are obtained. Do not obtain any other pavement cores, except those which are directed by and surrendered to the Department, unless allowed in writing by the District Executive. If other pavement core samples are taken by the Contractor for QC testing purposes, keep these samples completely separated from the pavement core samples for LA and IA. Do not combine, replace or otherwise intermingle QC samples with LA and IA samples. 4.d Acceptance Sample Testing. Section 409.3(j)4.d. 4.d.1 LTS Acceptance Testing. Section 409.3(j)4.d.1. Replace subsection title and the two paragraphs with the following two subsections: 4.d.1 Testing of Local Acceptance (LA) Density Samples. Prior to any testing, the Department’s certified LA Inspector will examine the containers and samples for any evidence of their security being compromised. No testing will be performed on any samples until the Inspector has determined the samples to be secure. Testing of samples will not begin prior to completion of the lot and will begin immediately after the Inspector arrives at the testing location. LA samples are the top priority for testing over all other testing upon the Department Representative arriving at the designated testing laboratory to test the LA density samples. Do not discard any LA samples used for lot acceptance until directed by the Representative. The Contractor’s technician will package the tested samples for dispute resolution and submit to the inspector to properly secure the containers with a security device before transport to an adequate facility to maintain the samples in a proper environment to prevent degradation. The Department will retain all paperwork used in the LA sample testing for a period of not less than three years from the date of testing. 4.d.1.a Department Testing. At the designated LA laboratory testing facility, the Department’s certified LA Inspector will test each density acceptance sample according to PTM No. 715, and if necessary PTM No. 716, to determine the bulk specific gravity (Gmb) and bulk density (lbs/ft 3) of the compacted mixture. The Contractor’s technician may be present to witness the testing performed by the LA Inspector. The technician must bring to the immediate attention of the Inspector any deviation in performing the test according to the specified test method. If deviations are not noted at the time they occur, the test results will be considered accurate. The Department will analyze the bulk density test results for extreme values according to PTM No. 4 at the 5% significance level. If discarding an extreme value reduces a lot to less than three remaining test results, the Department will accept the lot as specified in Section 409.3(h) 2.a.1. Individual sublot density values will be calculated and rounded to the nearest tenth of a percent of theoretical maximum density according to ASTM E 29. Lot average density will subsequently be calculated from the individual sublot values and rounded to the nearest tenth according to ASTM E29. The Department will accept lots with three or more test results as specified in Section Page 7 of 13 IV. (a)4. a.3. If acceptance test results indicate a defective lot (remove and replace) or a lot with an OLPF < 90, the Contractor may request in writing that the Department retest the lot in accordance with Section IV. (a)4. b. If cores are not taken within one day after placing the mixture, or if the density for two consecutive lots or for a total of three lots does not result in a payment factor for in-place density of ≥100, stop paving operations for the project as directed. Review and evaluate the operation and determine the cause of the problem. Do not resume paving until after the Representative reviews the proposed solution and authorizes paving to continue. 4. d.1.b Gmm Verification Testing. The Department’s certified LA Inspector will then randomly select one of the Gmm verification loose mixture samples obtained as specified in Section III. (h) 2. b.3 from the lot. The Department will test the randomly selected Gmm verification loose mixture sample to determine the Gmm of the compacted mixture according to AASHTO T 209 as modified in Bulletin 27, with the following exception: • the samples will be obtained as specified in Section III. (h) 2. b.3 The Department’s certified LA Inspector will compare the randomly selected Gmm verification sample test result with the Contractor’s daily Gmm value for that same production or placement date. If the Department and Contractor Gmm values do not differ by more than ±0.030, the Contractor’s daily Gmm values in the whole lot will be considered verified and the Contractor’s daily Gmm values will be used to determine the percent of theoretical maximum density for each density acceptance sample placed on that date. If the initial randomly selected Department Gmm verification sample test result differs from the Contractor’s daily Gmm value for that same production or placement date by more than ±0.030, the Department’s Gmm test result value will be used as the acceptance Gmm value to determine the percent of theoretical maximum density for the individual density acceptance cores produced or placed on that same date. The Department reserves the right to select more than one Gmm verification sample from the lot representing the same production or placement date and to select other Gmm verification samples from the lot representing different production or placement dates to verify the Contractor’s daily Gmm values. When more than one Gmm verification sample is selected from the lot representing the same production or placement date, the Department Gmm test results will be averaged and the averaged used to verify to the Contractor’s daily Gmm value for that same production and placement date. The Department will determine acceptance, with respect to density, as specified in Section IV.4 (a) 4.a or Section IV.4 (a) 4.b. 4. d.2 LTS Testing of Independent Assurance (IA) Density Samples. The LTS will test the density samples for IA according to PTM No. 715, and if necessary PTM No. 716, to determine the percent compaction. 4.d.2.a Density IA Sample Test Result Analysis. LTS IA density sample test results will be compared to the LA density sample test results on the same lot. If the difference in the average test results of the LA and IA meet the IA tolerances in Table E-2, the Department will continue with IA testing at a minimum of one out of every ten lots thereafter for each JMF. TableE-2 Independent Assurance Tolerances on Lot Averages Testing Criteria PTM No. 715 or PTM No. 716, Gmb Max. Difference Between Test Results (n≥3) 0.030 000 If the difference between the lot averages of IA sample test results and LA sample test results exceeds the maximum IA tolerances in Table E-2, the Representative will perform an investigation as to the cause for the non-comparison of the test results. Provide information to the Representative, as requested, on the integrity of samples and on the testing equipment used in the sample testing. The Representative will also review personnel and test methods used in the LA testing. Implement corrective measures for any noted deficiencies to ensure the tests are performed according to the prescribed procedures. The Representative will record the LA Sample test results, the IA sample test results and any applicable corrective measures in the Field Inspector’s Diary. The Representative will select the next lot on the project for IA and will submit the IA companion density samples to LTS for testing. If the difference between subsequent IA sample test results and LA sample test results exceeds the IA tolerances in Table E-2, the Department may discontinue testing of LA samples and begin LTS testing of the acceptance samples for the remainder of the project and revert to Section IV for measurement and payment. If the difference between Page 8 of 13 subsequent IA sample test results and LA sample test results meets the IA tolerances in Table E-2, the Department may continue testing of LA samples with IA testing at a minimum of one out of every ten lots. IV. MEASUREMENT AND PAYMENT – Sections 409.4 and 411.4 with modifications and additions as follows: (a) Standard Construction 3. Mixture Acceptance by Certification and Density Acceptance by Non-Movement and OptimumRolling Pattern. Section 409.4(a)3. Replace Table H with the following: TABLE H Contract Unit Price Adjustments - Mixture Acceptance by Certification Mixture NMAS All sizes Test Criteria Printed Tickets Test Value Asphalt Content At least 90% of Daily Printed Tickets Within 0.2% of JMF Less than 90% of Daily Printed Tickets Within 0.2% of JMF 19.0 mm and smaller Pay Factor 100 85 QC Sample Testing** Single Sample Multiple Samples (n=1) (n≥2) ±0.7% ±0.5% 100 ±0.8% to 1.0% ±0.6% 85 > ±1.0% ≥ ±0.7% * 25.0 mm and larger QC Sample Testing** ±0.8% ±0.6% 100 ±0.9% to ±1.2% ±0.7% 85 > ±1.2% ≥ ±0.8% * Gradation Single Sample Multiple Samples (n=1) (n≥2) All sizes QC Sample Testing for % ±3.0% ±2.1% 100 Passing 75 μm (No. 200) ±3.1% to ±4.0% ±2.2% to ±2.7% 85 Sieve** > ±4.0% ≥ ±2.8% * All sizes QC Sample Testing for % ±6% ±4% 100 Passing 2.36 mm (No. 8) ±7% to ±8% ±5% 85 Sieve** > ±8% ≥ ±6% * In-Place Density All sizes Non-Movement Section 409.3(j)2. 100 Optimum-Rolling Pattern Section 409.3(j)3. 100 Sizes from Table I Acceptance Sample Testing As outlined in Table I Section of Pavement Cores 409.4(a)4.a.1 * Defective pavement. Remove and replace or, when permitted by the District Executive in writing, leave in place and the Department will pay 70% of the contract unit price. ** For these test criterion, the daily Pay Factor will be determined by the single sample test result from the daily QC sample. If more than one QC sample test result is available for a day, the Pay Factor will be determined based on the average of the results using multiple sample tolerances. If corrective action is taken, Pay Factors will be independently determined for material placed before and after the corrective action. 4. Mixture Acceptance by Lot and Density Acceptance by Non-Movement, Optimum Rolling Page 9 of 13 Pattern, or Pavement Cores. Section 409.4(a)4. Replace completely with the following: The Department will pay on a lot-by-lot basis at the contract unit price, adjusted for Pay Factors (PF) as specified. For the PF based on percent within tolerance (PWT), the Department will determine the individual PWT values for in-place density (PWTD), asphalt content (PWTAC), percent passing the 0.75µm (No. 200) sieve (PWT200), and for percent passing the primary control sieve (PWTPCS) according to Section 106.03(a)3, using the upper and lower specification limits in Table I. The Department will determine each PF for in-place density, asphalt content, percent passing the 0.75µm (No. 200) sieve, and for percent passing the primary control sieve according to Section IV. (a) 4. a. The Department will determine the Overall Lot Pay Factor (OLPF) according to Section IV. (a) 4. a.2. 4.a Pay Factors 4.a.1 Pay Factors for In-Place Density (PFD), Asphalt Content (PFAC), and Percent Passing 75 µm (No.200) Sieve (PF200) and Primary Control Sieve (PFPCS). For lots with density acceptance by nonmovement or optimum-rolling pattern, PF = 100.00. The Department will determine PFD for lots with density acceptance by pavement cores and PFAC, PF200, and PFPCS, for all lots according to the following: 4.a.1.a All PWT Parameters Greater Than or Equal to 50. When PWT , PWT , PWT , and D AC 200 PWTPCS are each greater than or equal to 50, the Department will determine the pay factor for each PWT according to one of the following equations as appropriate. When PWT is ≥ 90, determine the pay factor for the specific pay parameter according to the following equation: PFX = 100+ 0.4(PWTX-90) Where, (1) PFX = Pay Factor of the individual pay parameter (PFD, PFAC, PF200 or PF PCS) PWTX = Percent within Tolerance of the individual pay parameter (PWTD, PWTAC, PWT 200 or PWTPCS) * For 9.5 mm and 12.5 mm courses with average density < 93.0, the maximum PF D = 100 Where, T = Theoretical Maximum Density, lbs/ ft3. When PWT is <90 and ≥50, determine the pay factor for the specific pay parameter according to the following equation: PFX = 70 + 0.75(PWTX-50) Where, (2) PFX = Pay Factor of the individual pay parameter (PFD, PFAC, PF200 or PF PCS) PWTX = Percent within Tolerance of the individual pay parameter (PWTD, PWTAC, PWT200 or PWTPCS) 4.a.1.b One PWT Parameter Less Than 50. When either PWTD or PWTAC is less than 50, the lot is defective. When PWT200 is less than 50, the lot is defective when the average percent passing the 0.75 μm (No. 200) sieve is greater than ± 2.0% from the JMF. When PWT PCS is less than 50, the PFPCS = 60.00. For defective lots, the DE will recommend and submit for review and concurrence one of the following bulleted options to the Director of the Bureau of Project Delivery (BOPD). Upon receiving concurrence, the District will direct one of the following: Page 10 of 13 Leave the lot in place. The District Executive will apply an OLPF of 70. Remove and replace the entire lot. The District Executive will direct removal and replacement of the entire lot at no additional cost to the Department with new lot acceptance sampling and testing. 4.a.1c Two PWT Parameters Less Than 50. When two or more of PWTD, PWTAC, or PWT200 are less than 50 with the mean percent passing the 0.75μm (No.200) sieve greater than ± 2.0% from the JMF, the lot will be considered defective and the DE will direct removal and replacement of the entire lot with new acceptance sampling and testing. 4.a.2 Overall Lot Pay Factor (OLPF). The Department will determine the OLPF according to the following equation and will round the resulting OLPF to the nearest whole number: OLPF = (0.50 x PF ) + (0.30 x PF ) + (0.10 x PF ) + (0.10 x PF D AC 200 ) PCS Where, PF D = Pay Factor for In-Place Density PF = Pay Factor for Asphalt Content AC PF = Pay Factor for Percent Passing the 75 μm (No. 200) Sieve 200 PF = Pay Factor for Percent Passing the Primary Control Sieve (PCS) PCS TABLE I Upper and Lower Specification Limits for Calculating Percent Within Tolerance Mixture Nominal Maximum Aggregate Size 9.5 mm, 12.5 mm 19 mm 25 mm and 37.5 mm All sizes 9.5 mm (PCS = 2.36 mm (No. 8) sieve) 12.5 mm (PCS = 2.36 mm (No. 8) sieve) 19 mm (PCS = 4.75 mm (No. 4) sieve) 25 mm (PCS = 4.75 mm (No. 4) sieve) 37.5 mm (PCS = 4.75 mm (No. 4) sieve) RPS 9.5 mm, 12.5 mm Standard 9.5 mm, 12.5 mm Testing Criteria Lower Specification Upper Specification Limit (L) Limit (U) Asphalt Content from JMF Value, % -0.4 +0.4 -0.5 +0.5 -0.6 +0.6 Percent Passing the 75 µm (No. 200) sieve from JMF Value, % -1.5 +1.5 Percent Passing the Primary Control Sieve from JMF Value, % -5 +5 -5 +5 -8 +8 -9 +9 -9 +9 Mat Density* 92.0 91.5 98.0 98.0 Page 11 of 13 (3) All 19 mm courses, 25 mm binder 91.0 98.0 courses 25 mm and 37.5 mm base courses 90.0 no upper limit * Where Limits = The Percent of Theoretical Maximum Density 4.a.3 Payment. The Representative will compute the percent of the contract unit price paid as follows: Lot Payment= CP(OLPF)/100 Where, CP = OLPF= (4) Contract unit price per lot (unit price times lot quantity) Overall Lot Pay Factor 4.b Retesting. Section 409.4(a)4.b. Replace subsection reference, title, and all language completely with the following: 4.b Dispute Resolution. For mixture acceptance testing or density acceptance testing, the Contractor may request in writing that the Department retest a lot if the initial test results indicated a defective lot (remove and replace) or a lot with an OLPF < 90, except for density when one or more density acceptance cores in the lot were coated with paraffin wax as a result of PTM No. 716 during the original density acceptance testing. Provide written retest requests to the District Executive within 3 weeks of the date the test results are released. Retests will not be allowed if a written retest request is not received within 3 weeks of the date the test results are released. Provide quality control test results and control charts, companion sample test results (if available), test data trend evaluation, and any other pertinent information to justify the retest request. The Department will evaluate the information and may allow retesting if the information submitted provides a reasonable basis to conclude that the failing test results may not represent the in-place material. The retest will be performed by the LTS. For retesting of materials failing for asphalt content or percent passing 75 µm (No. 200) sieve, the Inspector will identify the locations where the original box samples were collected. The Inspector will select retest sample locations 24 inches from the original sample locations longitudinally in the direction of traffic. If the 24 inch offset causes the retest sample location to fall outside of the sublot, the Inspector will select the retest sample location 24 inches from the original sample locations longitudinally in the opposite direction from traffic. With the Inspector present, provide appropriate traffic control and drill 6-inch diameter cores for retesting purposes according to the procedure for drilling in PTM No. 729. Ensure drilling procedures include washing off and towel drying the core samples immediately after drilling. Within 24 hours after coring, backfill the hole with mixture of the same JMF or with mixture used for subsequent courses and compact and seal the mixture. Provide traffic control, core, and backfill the core holes at no cost to the Department. The test method used for asphalt determination during the original acceptance testing (PTM No. 757 or PTM No. 702) will be used by the LTS for the retest, unless the (DME/DMM) grants written approval for a change in test method. The results determined by LTS of the retest cores will be used to calculate payment for asphalt content, primary control sieve, and percent passing the 75 µm (No. 200) sieve for the lot. For retesting of density acceptance, the Inspector will forward the original density acceptance cores to the LTS to be utilized. The LTS will retest each original density acceptance core according to PTM No. 715 and PTM No. 716, as necessary, to determine the Gmb and bulk density values. The LTS will not perform Gmm testing for lots where the Contractor’s Gmm value was previously considered verified according to Section III. (j)4. d.1.b. After Gmb testing is completed, for lots where the Contractor’s Gmm value was not verified, the LTS will select one original density acceptance pavement core from each production or placement date represented by the density acceptance cores in the lot. Each core selected will be the core with the highest bulk density for that production or placement date from the retest results (e.g., if a lot was placed over three production days, and the lot density acceptance cores include at least one core from each production or placement day, the original density cores selected during a density retest to perform Gmm testing will be three; one from each production or placement date). The LTS will perform Gmm testing on the selected cores according to AASHTO T 209 as modified in Bulletin 27, with the following exceptions: • the samples will be obtained as specified in Section 409.3(j)4.c.1, Page 12 of 13 • • • no conditioning, only drying, will be performed on the sample, the minimum sample size will be waived, as necessary, to use the 6-inch diameter pavement core sample, and the supplemental procedure for mixtures containing porous aggregate will only be performed when either the coarse aggregate or fine aggregate in the mixture has a water absorption value ≥ 1.5% as indicated on the JMF and then only when the calculated percent of theoretical maximum density indicates any one individual failing sublot which results in a density pay factor less than 100.00. The LTS Gmm value(s) determined will be the Gmm values used to determine the percent of theoretical maximum density for the cores represented by the applicable production or placement dates in the lot. Either the previously verified Contractor’s Gmm value(s) or the newly tested LTS Gmm value(s) will be used for acceptance to determine the percent theoretical maximum density for each sublot core in the lot. Upon completing the retesting of the original density acceptance cores, the retest values determined by LTS will be used to determine the final payment factor percentage for density. The Department will deduct from the overall lot payment the cost per lot associated with conducting a retest as follows: Test Method PTM No. 702/739 PTM No. 757 Mixture Acceptance Retest Cost if Retest Results Indicate Mixture Acceptance Retest Cost if Retest Results Indicate ≥100% Pay Factor(s)* $900 $500 <100% Pay Factor(s)* $3,500 $2,000 Density Acceptance Retest Cost if Density Acceptance Retest Retest Results Indicate Cost if Retest Results Indicate<100% Pay Factor ≥100% Pay Factor PTM No. 715, or PTM $200 $750 No. 716 only PTM No. 715, or $1,100 $4,000 PTM No. 716, and AASHTO T 209 as specified in Section 409.3(j)4.d.1.b * For lots where the original test results indicated a defective lot, only the pay factor(s) where original test results indicated a PWT < 50 for asphalt content, percent passing the 75 μm (No. 200) sieve, or density will be utilized to determine the retest cost. If no original test results indicated PWT < 50 for lots where OLPF < 90, then all pay factors will be utilized to determine the retest cost. Page 13 of 13