OWML Board Paper 16-03(a) 15 April 2015 Planning Update Executive Summary The purpose of this paper is update the OWML Board on progress against the baseline plan. Progress is reported against the programme plan, in terms of progress against deliverables and milestones; planned activities over the next month; issues log and risk register. There is an agreed Level 1 Integrated Plan, subject to change control, and published on the Ofwat website. The baseline plan was published on 18 February 2015. Open Water maintains a detailed Level 2 Plan, which informs the integrated plan. The Open Water programme is progressing according to schedule and in line with the baseline plan. Close monitoring through fortnightly internal progress meetings and fortnightly PM Group meetings with Defra and Ofwat ensure that any delays or changes are captured and addressed in a timely manner. 1 OWML Board Paper 16-03(a) 15 April 2015 Progress - Reporting Period 13 March 2015 to 10 April 2015 Level 1 Integrated Plan – Milestones There are no milestones in the Level 1 Integrated Plan for the defined period. Progress The table below details the key activities completed during the period. Status and Achievements against Plan Activity On Schedule Company workshops held on MAP2 feedback and MAP3 content. Yes Development of Business Requirements ongoing and on schedule. Yes Procurement process - PQQ issued for IT System through MOSL. Yes Procurement process - Completed PQQs received and assessed. Yes Assurance RFP issued, tender received and Deloitte appointed to prepare the Assurance Framework. Yes Transition Plan - Oxera appointed. Yes First draft of the key messages for Boards in MAP3 is complete. Drafting of MAP3 main document has commenced. Yes Requirements for initial data uploads issued to companies (02/04/15) Yes Twice monthly update calls with stakeholders established. Yes 2 OWML Board Paper 16-03(a) 15 April 2015 Plan Delays The table below details the activities delayed during the period. Delays to scheduled activities Activity Scheduled Date Revised Date Reason Action to remedy Impact on other programme activities Data Pilot 05/03/15 TBA Issue delayed due to insufficient detail provided in draft report Additional resource employed to progress. In discussion with industry. None Planned - Reporting Period 13 April 2015 to 15 May 2105 Level 1 Integrated Plan - Milestones There are the following milestones in the Level 1 Integrated Plan for the defined period. Milestones in the period Owner Date On Schedule Transition Plan and Data Guidance Open Water 30/04/15 Yes Issue MAP3 Open Water 11/05/15 Yes Milestones in the period Owner Date On Schedule Appoint Chair of MOSL MOSL 28/04/15 No 3 OWML Board Paper 16-03(a) 15 April 2015 Planned The table below lists the planned activities for the period to 15 May 2015. The activities have a RAG status in the schedule box, indicating the risk to delivering on time. The activities are reported separately by owner. The status of the activities for MOSL is based on our best understanding as there is currently no reporting line from MOSL into Open Water for workplan reporting purposes. Activities for the period – Open Water Owner Date On Schedule Draft MAP3 document Open Water 24/04/15 Yes Ongoing development of MAP3 codes and processes Open Water 20/04/15 Yes Workplan Review Group meeting Open Water 22/04/15 Yes Develop Transition Plan Strategy Open Water 30/04/15 Yes Prepare and issue data guidance Open Water 30/04/15 Yes Ongoing development of Business Requirements for IT System procurement, in conjunction Open Water with preparation of MAP3 15/05/15 Yes Activities for the period - MOSL Owner Date On Schedule Procurement process - issue of Request For Outline Design Solution to shortlist applicants MOSL 17/04/15 Yes Establish MOSL Board and Membership MOSL 30/04/15 No Procurement process – receipt of submissions for Outline Design Solutions MOSL 05/05/15 Yes Procurement process - Preparation of Request for Detailed Solution documentation MOSL 05/06/15 Yes 4 OWML Board Paper 16-03(a) 15 April 2015 Risk Management Open Water maintains a detailed risk and issues log, reviewed regularly with each of the workstream leads and reported at the Audit and Risk Committee meetings. The following tables detail the highest rated programme risks and associated mitigation measures by programme owner and the risks closed in the period. Risk Register R-029 remains as the highest risk, based on the uncertainty around the timescale for the design and build of the Central IT System. Ownership of this risk has been transferred to MOSL (Table 1). The risk score for Risk R-022 has increased from 15 to 25, due to the uncertainty surrounding the transition of Open Water at the end of May. R-027 and R-028 show the risk associated with programme co-ordination between the Codes workstream and the Procurement of the IT System by MOSL. Risks R-007 and R-026 have been closed in the reporting period (Table 3). The risks are listed in order of risk score severity, with impact as the primary factor. Table 1 Mitigated Risk status change MOSL Risks ID. R-029 Risk Description Delay in design and build of IT systems against baseline plan. Consequence Key milestones may be missed. Delays in design and build impact testing & commissioning and GoActive/Go-Live dates. Increased cost of system. Possible reduction in functionality of system, to reduce time and cost. Date of impact Prob (1-5) Impact (1-5) 03 September 2015 5 5 5 Risk Score 25 Agreed Management Action for mitigation Early dialogue with vendors during procurement process, regarding programme, cost and functionality. Outline plan to be submitted with RfDS. Detailed plan required post tender award. Due Date for mitigation Owner Post Mitigation Risk Score Comments End July 2015 MOSL 20 No visibility of a design/build plan or the cost until RfDS in July, the risk remains high. OWML Board Paper 16-03(a) 15 April 2015 Table 2 Mitigated Risk status change Open Water Risks ID. Risk Description Consequence Date of impact Prob (1-5) Impact (1-5) R-022 Lack of clarity/decisions surrounding transition of OW Programme to new delivery partner. R-019 R-028 Change in direction may cause instability and lack of confidence amongst stakeholders. Transition activities not successfully completed. Potential loss of momentum and adverse impact on activities post May 2015. Impact on longer term financial reports of OWML. 31 May 2015 5 5 Programme governance arrangements restrict the recruitment or retention of resources. Programme milestones may not be achieved, due to loss of experienced resources. 31 May 2015 5 MAP (PreVendor) not available until 14 July 2015. MAP (Post-Vendor) scheduled for publication 03 September 2015. Limited time for vendors to review MAP (Pre-Vendor). Insufficient time for vendor input and codes team to incorporate before issue in September and formal consultation by Ofwat. 03 September 2015 5 6 Agreed Management Action for mitigation Due Date for mitigation Owner Post Mitigation Risk Score Comments 25 OWML and Ofwat working closely to ensure a smooth transition. Transition plan required to provide timeline and clarity of roles and responsibilities. Transition group to be established. RACI matrix to be prepared and issued. 31 May 2015 JR 25 Mitigation updated. Mitigated risk score remains the same until transition plan agreed. 4 20 Ensure clear programme governance arrangements are in place to support delivery. 31 May 2015 AS 20 4 20 Move publication date for MAP (Post-Vendor) to 30 September 2015 and liaise with vendors during review process. Incorporate requirements for vendors to mobilise so that Codes development timetable can be met 18 September 2015 MA 12 Probability increased due to loss of key resources. Date of impact changed to reflect revised transition date of 31 May 2015. Mitigation to reduce probability Risk Score OWML Board Paper 16-03(a) 15 April 2015 Mitigated Risk status change ID. Risk Description Consequence Date of impact Prob (1-5) Impact (1-5) Risk Score R-027 Demand on resources in both Codes and Procurement teams during MAP3 development and dispersed nature of teams Difficult to co-ordinate teams and results in insufficient time to review Outline Design and RFx documents. May impact quality of Outline Design and RFx documents and may not accurately reflect details of market codes. 17 April 2015 (Outline Design) & 05 June 2015 (RFx) 4 5 20 R-021 Companies unable to adequately demonstrate market readiness and technical capability- cross reference MO_R-013 Fail to build awareness with business customers and new entrants (cross reference Comms_R-001) Companies unable to access the market. Delay to shadow operation and go live. Secretary of State does not sign off. 01 October 2016 4 5 20 30 June 2015 3 5 15 R-008 Lack of competition in the market. Companies fail to respond to a competitive market. 7 Agreed Management Action for mitigation Due Date for mitigation Owner Post Mitigation Risk Score Comments Codes team are working closely with Requirements team to ensure requirements reflect MAP3. Clear communication and integrated planning between Codes Team and Procurement Team to ensure adequate time for review is factored in to the plans. Programme interdependencies to be identified and reflected in plans. MAP3 to include initial transition guidance. Engagement with companies to ensure timelines are clear through the Workplan Review Group. 05 June 2015 MA 12 Mitigation to reduce impact. Probability remains the same. Impact reduced to 3 to reflect that the work that the requirements team are doing to analyse and understand the codes and their impact on the system requirement 30 September 2016 AS 12 Mitigation to reduce probability and impact. Review risk mitigation post MAP3. 31 December 2015 AC 12 Need to define measures of success for engagement. Stakeholder plan developed to engage with stakeholders outside of current Water Industry. Business events across the regions started in Jan 2015. OWML Board Paper 16-03(a) 15 April 2015 Mitigated Risk status change ID. Risk Description Consequence R-010 Incumbent companies not aware of the activities they are required to do in preparation of market opening (cross reference MO_R-007) R-020 Stakeholders fail to understand that the Open Water engagement plan is to support retail market opening, not to inform market participants of the approach they should take (cross reference Comms_R-006) Delays in appointment of Market Operator R-024 Date of impact Prob (1-5) Impact (1-5) Market opening is delayed. 01 October 2016 3 5 15 Lack of understanding will result in uncertainty and the programme is unable to provide assurance that the new retail market will be ready April 2017. 30 June 2014 3 5 15 No entity in place to manage the market. Delays in recruiting and training staff. Delays in awarding contracts. Risk to market opening. 01 April 2015 Ongoing 4 5 20 8 Risk Score Agreed Management Action for mitigation Due Date for mitigation Owner Post Mitigation Risk Score MAP3 to include initial transition guidance. Companies (Wholesalers and Retailers) are on the Open Water high level plan. Workplan Review Group (WRG) established to ensure companies aware of Open Water activities and to engage in planning. Stakeholder plan being developed to ensure all stakeholders understand the role of Open Water and their activities. Business events to be held across the regions starting in Jan 2015. Workplan Review Group set up to engage with stakeholders on deliverables and key milestones. 31 December 2016 MA 12 31 December 2015 AC 12 Discussions with HMT. 30 May 2015 JR 10 Comments Risk re-opened. More dialogue required, particularly in relation to transition. Risk mitigation to be reviewed post MAP3. Mitigation to reduce probability of risk OWML Board Paper 16-03(a) 15 April 2015 Mitigated Risk status change Table 3 Mitigated Risk status change ID. Risk Description Consequence Date of impact Prob (1-5) Impact (1-5) Risk Score R-025 General Election (07.05.15) - no party secures majority. Delays in issuing MAP3, until new government is formed. 11 May 2015 5 3 15 R-023 DEFRA/Ofwat do not meet key regulatory dates. Secretary of State sign-off delayed. Market Opening delayed. Critical path activities delayed. 31 December 2015 2 5 10 Date of impact Prob (1-5) Impact (1-5) 31 March 2015 5 3 Agreed Management Action for mitigation Due Date for mitigation Owner Post Mitigation Risk Score Comments Workshops set up before the issue of MAP3 to communicate codes. Document scheduled for publication 11.05.15. Alignment of DEFRA/Ofwat/OW programmes. HLG meetings. Regular reviews of progress set up. 11 May 2015 AS 9 13 February 2015 MA 5 Mitigated risk score improved through PM Group discussions and Integrated level 1 Plan. Due Date for mitigation Owner Post Mitigation Risk Score Comments 31 March 2015 JR 0 Closed Risks ID. R-026 Risk Description Consequence Planned budget may not be spent before 01 April 2015. Potential complications of an underspend that needs to be managed with Ofwat. Reputational impact from not spending planned budget. 9 Risk Score 15 Agreed Management Action for mitigation Credit note action agreed with Ofwat to credit any unspent monies to incumbent companies. RISK CLOSED OWML Board Paper 16-03(a) 15 April 2015 Mitigated Risk status change ID. R-007 Risk Description Delay in procurement of IT systems Consequence Key milestones may be missed (cross reference MO_R-004). Delays in procurement impact testing & commissioning and GoActove/Go-Live dates. Date of impact Prob (1-5) Impact (1-5) 03 August 2015 3 5 Risk Score 15 Agreed Management Action for mitigation Due Date for mitigation Owner Post Mitigation Risk Score Procurement plan in place. Additional risk raised for the design and build of the IT System (R-029). Ownership of R-029 with MOSL. 15 August 2015 MS 0 Comments RISK CLOSED Issues Register Ref. Issue description Consequence Impact (H/M/L) Management Action Issue Management Status I-003 We do not have clarity of the Go / No Go criteria or process to support market opening . Lack of clarity surrounding governance and decision makers to support programme. The required processes to enable market opening are not followed with the consequence that market opening is delayed. High Need to develop Go / No Go criteria in conjunction with Defra / Ofwat (High Level Group). Development of Assurance Framework is in progress. Red No understanding of the programme governance and sign off process. High RACI in development to support sign off process. Red Relationship between Open Water and MOSL Lack of communication regarding MOSL activities on procurement adversely impact the Open Water planning process High Collaboration between OWML and MOSL individuals undertaking requirements and procurement activities. Ensure transparency of plans, risks and issues. Clarity of roles and responsibilities. Red I-008 I-010 10