OWML Board Paper no 16-03c - 15th April 15 CONFIDENTIAL Programme Lead update Programme governance and leadership There remains substantial uncertainty about the future management of the Open Water programme. While, it is possible for OWML to be ready to meet the transition target date of 31 May 2015, it is not clear that others could be ready by this date. The main obstacle to OWML being ready would be the requirement for a Members’ meeting to be held and for a 75% majority of those participating to vote in favour of the winding up of OWML. Cathryn Ross’s letter to licensed companies (of 13 February 2015) did not actually specify a transition date. It preferred a looser formulation that OWML had been asked to continue to the end of May and to complete several tasks. That letter also announced the appointment of Adam Cooper, who has experience in Ofgem and considerable experience in public affairs and energy commodities, to lead the Open Water programme from an Ofwat perspective. In February, OWML agreed to continue until the end of May subject to: - appropriate resources being made available from Ofwat for the remainder of the current financial year and for the first two months of the 2015-16 financial year; the current team being ready, able and willing to continue to work on this basis; and there being clarity about to whom the OWML activities would be transferred and the existence of a clearly defined and implementable transition plan. The first two of these conditions have now been met. There remains, however, some uncertainty on the third of these. Peter Bucks has initiated a transition working group that should meet in the next week or so. The principal obstacles to a successful transition at the end of May relate to: Ofwat being resources to take on its responsibilities; and MOSL having an elected Board with appropriate independent non-Executive members. 1 OWML Board Paper no 16-03c - 15th April 15 CONFIDENTIAL Ofwat has recently issued a tender for support services relating to the opening of the non-household retail market. The potential scope of this tender is quite wide but there still appears to be an intention to pursue a ‘Thick MOSL’ option. There is a draft of Ofwat’s RACI analysis of the activities required for market opening and this appears to confirm a ‘Thick MOSL’. Time has, however, been lost in the setup of MOSL. The original timeline had a fully constituted Board in place by the middle of May. This was timetabled in order to allow the new Board to take a key procurement decision relating to the central systems. MOSL has currently had confirmation from around a quarter of incumbent companies that they intend to join MOSL. MOSL is currently planning to appoint the non-Executive team in advance of the membership applications being closed and the election of an incumbent and a new entrant director. The intention is to form a nominations committee from the existing Board and two invited new entrants. This option has the advantage of speed, but could be seen to lack legitimacy. The nominations committee under this option is not representative. The approach is also not consistent with the articles and could, unless the articles were to be changed, leave the company open to challenge. Even under this revised approach, it is highly unlikely that MOSL could be properly constituted before the middle/ end of June 2015. Defra continues to emphasise the need for a robust, independent and high quality Board to be appointed. It is important that the independent non- executive roles are properly described. OWML has edited an initial role description, which focused on the longer term potential MO role. As noted previously, we all need to be quite careful about taking the views of HM Treasury for granted when it comes to the organization and classification of the MO. There is currently insufficiently close working between the procurement work of MOSL, the design activities and the codes and processes work stream. My view remains that the procurement activities should be managed within OWML and that all activities should be transitioned in a single step to MOSL, should this be the result of Ofwat’s RACI analysis. The original plan for a transition to MOSL was envisioned on this basis and Board has previously been alerted to the risks in both cost and time of an insufficiently coordinated approach. There remains uncertainty as to what happens to the team currently working on MAP 3. This is far from optimal. It is a substantially demotivating factor at a time when we require maximum commitment from the relatively small team that we have at our disposal. Claire 2 OWML Board Paper no 16-03c - 15th April 15 CONFIDENTIAL Nichols has resigned from the programme. Harriet Towler will return to Severn Trent after MAP 3 and will not extend (as I had always hoped) her secondment. On a much brighter note, James Rickleton, formerly a senior official at the NAO, has commenced work as the COO of OWML. He is already proving to be a most valuable addition to the core team. Notwithstanding this uncertainty, the programme team is progressing ‘full steam ahead’ on MAP 3. As Board members will see there is still a substantial number of areas where we will need clarity from Ofwat on policy matters. There have also been further conversations between the Scottish Government and Defra (particularly around commencement in both Scots and English law of the joint licensing provisions included in the 2014 Act. High-level Programme Plan Despite the distractions of when any transition may take place, the work of OWML is on track. There are separate papers on the MAP front end, its structure and the outstanding policy issues. We continue to visit companies. In line with earlier reported impressions, there is a wide range in the understanding of the issues and preparedness. In many cases WOCs are well advanced in their thinking and planning. There is now a good understanding about the MAP activities over the next six months or so. The aim is to finalise the market design and freeze the codes and procedures (at least insofar as they impact the information processing capability that is being procured for the MO). The target date for the MAP (Final Recommendations post vendor appointment) is 30 September 2015. We have also planned a MAP (pre vendor appointment recommendations) for July 14 2015. The Codes Panel would review any changes following the 30 September (see below). We continue to have regular meetings with Ofwat and Defra to review each organisation’s plans and to understand the interfaces between their workstreams. We have made some progress on the assessment of risks and the descriptions of mitigations available but this work is hampered by the lack of a clear transition plan and allocation of responsibilities between those that will be charged with delivery. 3 OWML Board Paper no 16-03c - 15th April 15 CONFIDENTIAL Work Areas In the last programme leader report, I outlined the proposed transition to six work streams. The scope of these work streams was not discussed owing to time constraints. They are outlined again below. Area of work Scope of activity 1. Programme Management Currently an OWML activity and Assurance Responsible for establishing and maintaining the work plan for the delivery of all MOSL activities. Responsible for managing change control of the plan and developing and maintaining a risk register and an issues log. Communicating to work stream leads performance against the plan. Responsible for managing MOSL assurance to OFWAT/DEFRA Responsible for collecting assurance statements from the individual companies. Responsible for commissioning individual elements of assurance needed to build confidence in the overall market arrangement 2 MOSL Governance and Responsible for MOSL set up (a MOSL activity): the establishment of the • member registrations and explanation Market Operator • initial members' meeting • appointments to Board • selection of non-executives • ensure that MOSL has appropriate financial, governance and HR policies • manage recruitment of specialists to contribute to overall programme delivery Market Operator set up (currently, an OWML activity although not currently a major focus of resources): • appointment of Chief Executive • development of new articles • agreement of new articles with HM Treasury, securing private status • explain new articles to MOSL members and members yet to join MOSL (e.g. separate retail arms) • manage resignation and joining process for new MO MOSL • Board elections • Staff training 3 Engagement / Company This is currently an OWML activity except for the external (promotional) communications element support [1] This activity will be outlined below, for which Ofwat is assuming supported by one of the responsibility. technical specialists. The work stream is responsible for: Senior engagement with companies 4 OWML Board Paper no 16-03c - 15th April 15 CONFIDENTIAL Communicating key strategic and policy aspects of market opening and describing how these impact company choices listening to senior executive feedback and ensuring delivery of information needed for company strategic decision making Support to companies[1] communicating a business planning process to companies supporting companies as they develop and implement their business plans Business customer engagement and awareness building through general business fora such as CBI, MEUC, FSB events: individual meetings with key national and regional business organizations; and Advertising and promotion. Regulatory stakeholder engagement DEFRA; SEMD; DWI; EA; OFWAT; WRAS; Scottish Government; WICS; Local Government External communications management (to be the responsibility of Ofwat) Appointment of relevant contractors; Web site use, management and development; and Social media Internal communications management Team meetings; Intranet; and Board secretariat • This is currently an OWML activity. 4 Codes and design authority • Responsible for ensuring that all the necessary codes, processes and procedures are agreed and in place to support successful market opening. • This work stream would also encompass establishing and operating a design authority to act as custodian of the market design, capable of operating on an enduring basis (including code escrow arrangements to allow for a change in MO if required) • The design authority links the procurement activities, the transition and data work streams, through participation in the review and approval of central system requirements, design and testing specifications, and data upload, market testing, and quality criteria specifications, to ensure that they meet the requirements as set out in the codes. • It would also maintain a log of all suggested changes, decisions taken and timetables changes that are to be made to the codes and to the systems. 5 MO Procurement and This is currently a MOSL activity Operations Responsible for managing the design, development and delivery of the central systems to allow for timely, accurate and effective registration and settlement. 5 OWML Board Paper no 16-03c - 15th April 15 CONFIDENTIAL 6 Transition and data This is currently an OWML activity Deals with the range of transition issues that are required to be completed by companies in order that the market can open in April 2017. This includes: o defining the specification of data o setting out guidance for plans for both the MO and the companies in order to: o prioritise, cleanse, upload and test data, o develop central and company IT systems; o build operational capability, o enable training and culture change o Allow for end to end system and operational testing. Programme Management and Assurance Deloitte has now been appointed as the contractor for the assurance framework. They will hold a couple of work shops with the industry before providing their recommendations at the end of April. Engagement and Company Support Progress in this area has been limited by the resignation of Claire Nichols. She is a big loss to the programme. Resource constraints now mean that focus of this team is wholy on the preparations for MAP 3. Going forward, the Engagement and Company Support team will need to be expanded to seven: a leader, three company liaisons, one central policy and two juniors. The company liaisons would work with a technical and a governance/ codes specialist in conducting regular company visits to assist in explaining what needs to be done. This work will be consistent with the Transition Plan. Each small team would be responsible for working with six companies. Codes and Design Authority There was a further series of successful workshops with the industry. 6 OWML Board Paper no 16-03c - 15th April 15 CONFIDENTIAL Similarly, there have been successful ‘Task and Finish’ Groups, facilitated by Water UK, with DWI and EA. We are on track to include fully the views of EA and DWI in the MAP 3 codes, processes and procedures. We have provided advice to Ofwat on the establishment of a Codes Panel. The composition of this panel is likely to be in line with the decision of the Ofwat Board. Unlike in some other industries, wholesalers will be represented on the Panel. The market operator (MO) and procurement The size limit on the bidders for the central systems has resulted in some of the smaller and more experienced players in the development of central systems to have to work with a partner. While this may allow a financially stronger counterparty to be appointed, it will have increased the costs of the system. It is not clear that the financial recourse available for any shortfall in the delivery of the central systems could ever compensate for the reputational damage of not being able to open the market on time. Transition and Data We will include an appendix in MAP 3 outlining the issues that companies should consider in preparing themselves for market opening. Oxera, SMC and Gemserv are responsible for the preparation of the ‘Transition Overview’. 7