Exhibit A

advertisement
MnDOT Contract No. 00384
Exhibit A
Scope of Work and Deliverables
As referred to herein, MnDOT refers to the State of Minnesota’s Department of Transportation. The
Project refers to the Maryland Avenue Bridge Design-Build Project, S.P. 6280-353. The Contractor refers
to the Contractor providing design and construction engineering services described hereinafter. DBC
refers to the Design-Build Contractor responsible for the design and construction of the Project.
Article 1
Project Background
MnDOT has scheduled a design-build project primarily located at the I-35E and
Maryland Avenue interchange in Saint Paul. Included is the design and construction of a
new bridge to replace the existing bridge over I-35E. The superstructure of the new
bridge will be constructed in a staging area and moved to its final constructed location
using Self-Propelled Modular Transporters (SPMT). Work under this contract involves
design and construction engineering services for this bridge identified as Bridge No.
62626.
MnDOT anticipates that the DBC will not be co-located with MnDOT and that they will
have staff working remotely. For these reasons, MnDOT has required the DBC to provide
a SMART Board at the Mendota Heights project office and at the office(s) of their
designer and Bridge Design SPMT Engineer. More information can be found in Book 2
Section 2 of the Project’s Request For Proposals.
The Contractor will serve as an extension of MnDOT’s staff by performing bridge design
and construction engineering services for Bridge No. 62626. All work will be in
accordance with the Contract Documents and Design Documents for the Project. The
Contractor will provide personnel for engineering support as needed. MnDOT anticipates
that the majority of the Contractor’s work can be performed remotely. Tasks where the
Contractor is required to be at the Project site are identified in this scope of work.
Article 2
Contract Administration
MnDOT will provide a Project Manager to give direction to the Contractor’s activities. It
will be the responsibility of MnDOT’s Project Manager to receive the work produced by
the Contractor, review the work for compliance with contract requirements, and to
recommend payment for such work.
The Contractor’s Project Manager will conduct the administration of the project, which
will include communication with MnDOT, invoicing, supplemental agreements, cost and
schedule updates, billing preparation, and other non-technical work.
No changes in the Contractor’s project management personnel will be made without
written notice to MnDOT. MnDOT will notify the Contractor if there are changes to
MnDOT’s project management personnel.
Article 3
Contractor Personnel Positions
The following is a detailed listing of the minimum, required personnel positions to be
provided by the Contractor to assist MnDOT with design and construction engineering
services for Bridge No. 62626. No more than two individuals may perform the duties of
each personnel position provided they collectively satisfy the minimum qualifications for
the position except that each person must satisfy all licensure requirements. MnDOT’s
Project Manager may direct the Contractor to change, reduce, and/or add staff at any time
during the Project.
-1-
MnDOT Contract No. 00384
Exhibit A
Scope of Work and Deliverables
All Contractor personnel must be familiar with the standard design and construction
practices of MnDOT and the Contract Documents prior to beginning services under this
contract.
3.1
Article 4
4.1
SPMT Engineer
An individual licensed to practice engineering within the State of Minnesota now or
within 1 month from contract award and experienced in the design and construction of
highway bridges moved with SPMT equipment (a minimum of two bridges moved with
SPMT equipment). Must have a minimum of five years experience designing prestressed
concrete beam bridges. Must have experience designing bridges as part of a design-build
team or assisting an owner with design verification on a design-build transportation
project. Must be on-site for the final pre-move walk through and during all bridge lifting
and moving operations. May also need to be on-site periodically for Project support.
Responsible for performing the duties outlined in Article 4.
Summary of Tasks
The following is a detailed listing of tasks to be performed by the Contractor to assist
MnDOT with bridge design and construction engineering services for Bridge No. 62626.
All issues identified by the Contractor will be immediately brought to MnDOT’s
attention with a recommended course of action.
Design Oversight (Activity Code 5912)
The Contractor will assist MnDOT by providing design oversight for Bridge No. 62626
to verify conformance to the Contract Documents. Design oversight will be limited to
elements affected by moving Bridge No. 62626 with SPMT equipment including but not
limited to girders, deck, and barriers. This includes but is not limited to the following:
a. Participate in the Project kick-off meeting, task force meetings, and design
workshops held by the DBC.
b. Perform over-the-shoulder reviews as requested by MnDOT and provide
comments.
c. Review Released for Construction Document submittals and the Superstructure
Monitoring Working Drawings, and provide comments using MnDOT’s
Document Management system, TRACS. Reviews are to be completed in
accordance with the review timeline requirements of the Projects Contract
Documents. Reasonable efforts are to be made to substantially reduce the review
timeline while providing a complete review.
d. Participate in comment resolution meetings as requested by either the DBC or
MnDOT.
e. Review any Notice of Design Change and provide comments.
4.2
Construction Oversight (Activity Code 5917)
The Contractor will assist MnDOT by providing construction oversight for Bridge No.
62626 to verify conformance to the Contract Documents. Construction oversight will be
-2-
MnDOT Contract No. 00384
Exhibit A
Scope of Work and Deliverables
limited to aspects of the Project affected by moving Bridge No. 62626 with SPMT
equipment including but not limited to the Bridge Staging Area, temporary supports,
Travel Path, SPMT lifting system, and SPMT management plans. This includes but is not
limited to the following:
a. Review SPMT Working Drawings and management plans, and provide
comments using MnDOT’s Document Management system, TRACS. Reviews
are to be completed in accordance with the review timeline requirements of the
Projects Contract Documents. Reasonable efforts are to be made to substantially
reduce the review timeline while providing a complete review.
b. Participate in comment resolution meetings as requested by either the DBC or
MnDOT.
c. Participate in each pre-move walk through held by the DBC.
d. Perform construction inspection of all bridge lifting and moving operations.
e. Provide a digital photograph record of all bridge lifting and moving operations
documenting the step by step process of the bridge move and any problems
encountered.
f.
4.3
Article 5
Review Field Design Change requests and provide comments.
SPMT Training (Activity Code 0601)
The Contractor will provide cross-training to MnDOT staff in SPMT design and
construction. The objective of the training is to transfer knowledge to MnDOT such that
MnDOT can execute a future bridge move without consultant assistance. Training may
be conducted while performing design and construction oversight duties, in separate
meetings or conference calls, or combination thereof. The main audience for the training
will be MnDOT’s Project level employees, however up to an additional six MnDOT
employees may also participate.
Deliverables
The following is a detailed listing of deliverables to be provided by the Contractor.
5.1
Design Oversight
a. Participation in Project kick-off meeting, task force meetings, and design
workshops
b. Over-the-shoulder reviews and comments
c. Released for Construction Document submittal reviews and comments
d. Participation in comment resolution meetings
e. Notice of Design Change reviews and comments
f. Timely response to questions
5.2
Construction Oversight
a. Working Drawing and management plan review and comments
b. Participation in each pre-move walk through
c. Construction inspection for bridge lifting and moving operations
-3-
MnDOT Contract No. 00384
Exhibit A
Scope of Work and Deliverables
d. Documentation (portable document format) of the bridge move with annotated
photographs
e. Digital photographs
f. Field Design Change reviews and comments
g. Timely response to questions
5.3
Article 6
SPMT Training
a. SPMT training to MnDOT staff
Items Furnished by MnDOT
6.1
Project Documents
One hard copy and one CD of the Contract Documents for the Project.
6.2
Office Space
MnDOT will be administering the Project from their Mendota Heights project office
located at 2229 Pilot Knob Road, Mendota Heights, MN 55120. MnDOT does not expect
the Contractor to be co-located, however office space at the project office will be
available for the Contractor if desired. The office space and/or project office will be
equipped with utilities including (heating, air conditioning, power, internet access, cold
and hot water, sewer, etc.), parking spaces, office furniture consisting of a desk and chair,
and office equipment inclusive of a SMART Board, copy machines, fax machines, and
general office supplies.
6.3
TRACS Access
Login ID’s and passwords will be provided to access TRACS via an internet connection.
6.4
Working Drawings and Management Plans
MnDOT will receive, log, and track all Working Drawings and Management Plans
related to the Project. MnDOT will make copies of these documents available to the
Contractor for review, comment, and distribution. Documents will be delivered either by
e-mail or available through TRACS.
Article 7
7.1
Items Furnished by the Contractor
Equipment
All Contractor equipment and software purchased and billed to the Project will become
MnDOT’s property at the conclusion of this contract. All purchases must receive prior
authorization from MnDOT’s Project Manager.
a. Safety equipment for the Contractor’s staff.
b. Appropriate vehicles, including their fuel and maintenance, to be used by the
Contractor’s staff. The vehicles will be identified on both sides with the company
name, and will be equipped with a flashing amber beacon light.
c. Computer equipment and software necessary for the Contractor’s staff.
Article 8
Communication
-4-
MnDOT Contract No. 00384
Exhibit A
Scope of Work and Deliverables
The Contractor is not to have direct communications with the DBC without the
knowledge and consent of MnDOT. The Contractor is not to provide direction to the
DBC in any form. All recommendations, suggestions, and opinions will be conveyed to
the DBC through MnDOT.
THE BALANCE OF THIS PAGE HAS BEEN INTENTIONALLY LEFT BLANK
-5-
Download