Tom Wiener, P.E. MnDOT Project Controls Engineer Matt Reid, P.E. HDR Engineering, Inc. Allows for Breakdown of L.S. Cost ◦ Validate Costs of the L.S. Better Quality Control Better Progress Control and Monitoring ◦ Earned Value / Revenue Techniques Schedule of Values Contractor Consultant (Low Bid Contract) Lump Sum Bid items are Cost Accounts in P6 that align with Unit Rate bid items Schedule of Values Contractor Consultant Challenges Faced We’ve Never Done This Before ($14.2M QBS) Office of Audit/Validation of Costs Creating Negotiated Work Packages from RFP Schedule Was a Learning Curve for Consultant • Provides Method for Equity Control • Allows for Schedule Risk to be Reduced • Reduces Fears of Lump Sum • Lump Sum • Encourages Innovation • Scope Diligence • Streamlined Payment Administration Lump Sum Contract Requirement 1st Design Contract – Lump Sum CPM Use of MnDOT SWIFT Codes ◦ ◦ ◦ ◦ ◦ ◦ 1010 – Project Management 1250 – Misc. Engineering & Support 2824 – Special Studies ABUT DECK PIER Oracle Primavera P6 Baseline Schedules – 1st plan for executing work and progress measured from Update Schedules – record of progress on a monthly basis; actual dates, remaining durations, actual cost, earned value. Revised Schedules – Re Baseline if necessary Schedule built locally Coordination with Functional Leads and MnDOT Baseline Acceptance Baseline Uploaded to MnDOT Hosted P6 Environment Similar to MnDOT CPM Const Specs – 1803 Activity Durations 5-20 days Activity must have Predecessor/Successor No Lags/Leads Constraints Contract Time, Delays, Impacts, Failure to complete work on time Schedule Activities – 465 Logic Relationships – 750 Constraints – 14 Initially, 2 Afterward Critical Activities – 40, less than 10% of Project, no more than 30% per spec SWIFT Codes Differentiate Subs – Multiple Entries Reporting Schedule Updated Monthly ◦ Purposes of CPM ◦ Coordination with Design Functional Leads ◦ Schedule Narrative Highlights Anticipated/Final Milestones Critical Coordination Activities Change in Schedule Logic ◦ Payment - Invoicing Organization Communication Analysis ◦ Define deliverables in an organized format ◦ Ensure all contracted deliverables are accounted for ◦ Activities have agreed upon budget ◦ Relationship between disciplines and other parties ◦ Responsibility - activities are assigned to companies, DOT ◦ When deliverables are required logically ◦ On time – baseline comparison and float analysis ◦ On budget – Internal earned value/percent complete analysis ◦ Risk or Impact mitigation – All parties can identify and mitigate potential risks, allocate or shift resources Was it worth it? Yes • Validated Scope of Work • Consultant buy-in to the process • Truly managed schedules (Earned Revenue Mngt) • We needed this design done on time • Streamlined Payment administration – Auditing History Project In Construction Phase Contractor’s build schedule in our network 1/1/13 Piloting BIM and CTD schedules 3/1/13 Select Unit Rate project Resource and Cost Loaded 3/1/13 Role and Resource Loaded of CE&I staff 6/1/14 Projects in Scoping and Design Phase Programmed Projects Role and Resource Loaded 6/30/13 All planned projects Role loaded by June 30, 2014 Taxpayer Transportation Accountability Act