DSCI 3870.001: Management Science Exam # 3 Version: Blue December 13, 2012 Time allotted: 120 minutes Name: SID#: Please read this carefully The questions, which you attempt today, consist of True/False and multiple-choice questions worth 133 points total. Some of these questions are based on descriptive cases. There are a total of 40 questions. Please answer all the questions on the scantron sheet provided. After you are done, please turn in the scantron and this question booklet. Please note that you have to enter your name and Student ID Number (SID#) in the above area and on the scantron. Failure to do so will result in a grade of zero . This is an open book exam. You are allowed to use a programmable calculator and/or laptop computer. Besides the textbook, you are allowed to use only those notes, which have been handed out in class, and notes, which you have recorded during, class sessions. Be sure to allocate you time wisely between the multiple choice and T/F questions. Acronyms such as LP, IP, NLP LHS (left-hand side), RHS (right-hand side) etc. may have been used. If you are unsure about an acronym, please ask me/the invigilator immediately. Best of luck!! 1. Consider a maximal flow problem in which vehicular traffic entering a city is routed among several routes before eventually leaving the city. When represented with a network, a. the nodes represent stoplights. b. the arcs represent one way streets. c. the nodes represent locations where speed limits change. 2. a. b. c. A sensitivity analysis report for integer linear programming is available through MS Excel has precisely the same interpretation as that from linear programming. is not available through MS Excel. 3. Let x1 and x2 be 0 - 1 variables whose values indicate whether projects 1 (x1) and 2 (x2) are not done (0) or are done (1) respectively. Which choice below indicates that project 2 can be done only if project 1 is done? a. x1 + x2 = 1 b. x1 – x2 < 0 c. x1 – x2 > 0 4. In case of nonlinear programming, a feasible solution is a global optimum if there are no other feasible points with a better objective function value in the feasible region. a. True b. False 5. In class I discussed a puzzle that involved opening a safe with 6 dials and showed that the problem could be modeled as a _______________. a. spanning tree problem b. non-linear programming problem c. binary integer programming problem 6. Setting of the “Tolerance” option to anything other than zero in an integer programming model runs the risk of: a. not getting a feasible solution b. getting a sub-optimal integer solution c. getting a solution outside of the integer feasible region 7. Consider the network and the optimal solution in MS Excel for the Max Flow model Max Flow Model Capacity From\To Node 1 Node 1 Node 2 Node 3 6 5 Node 2 Node 3 Node 4 Node 5 8 4 3 4 Node 4 6 Node 5 3 Capacity From\To Node 1 Node 2 Node 3 Node 4 Node 5 Node 6 Total From Node 1 0 6 3 0 0 0 9 Node 2 0 0 0 6 3 0 9 Node 3 0 3 0 0 2 0 3 Node 4 0 0 0 0 0 6 6 Node 5 0 0 0 0 0 3 3 Total To 0 9 3 6 3 9 Question: Based on the output, what is the maximum flow? a. 6 b. 9 c. 11 8. Node 6 8. Consider the network below for a shortest path model. Bidirectional arrows () indicate that travel is possible both ways. If we were to formulate an LP model to find the shortest path from Node 1 to Node 7, then the constraint for Node 6 would be written as: a. X16 + X56 X64− X67 = 0 b. −X16−X56 +X64+X65 +X67 = 0 c. −X16−X56 +X64+X65 +X67 = 1 The next five questions refer to the following case and the table that follows: A company has six projects, each of which must be completed in-house or fully subcontracted. Labor hours are limited to 6000. Data on project costs and labor requirements is given below. Project Profit (in-house) Profit (subcontract) Labor requirements 1 $10,000 $5,000 1,200 2 $20,000 $4,000 1,000 3 $22,000 $3,000 1,500 4 $15,000 $8,000 1,100 Let, Xi = 1 if project i is done in-house, 0 if not Yi = 1 if project i is subcontracted, 0 if not where i = 1,2,3,4,5,6 9. The most appropriate labor hours constraint is given as: a. 1200 X1 + 1000 X2 + 1500 X3 + 1100 X4 +1300 X5 +1600X6 = 6000 b. 1200 X1 + 1000 X2 + 1500 X3 + 1100 X4 +1300 X5 +1600X6 ≤ 6000 c. 1200 Y1 + 1000 Y2 + 1500 Y3 + 1100 Y4 +1300 Y5 +1600Y6 ≤ 6000 d. 1200 Y1 + 1000 Y2 + 1500 Y3 + 1100 Y4 +1300 Y5 +1600Y6 = 6000 5 $11,000 $6,200 1,300 6 $24,000 $4,500 1,600 10. If part of the optimal solution were, X1=0, X2=1, X3=0, X4=1,X5=1,X6 =0 then the optimal profit would be, a. $58,500 b. $50,000 c. $102,000 d. $18,200 . 11. If no more than 4 projects can be done in-house. This could be modeled as the constraint: a. X4 ≥ 1 b. X4 ≤ 1 c. X1+X2+X3+X4+X5+X6 ≤ 4 d. X1+X2+X3+X4+X5+X6 ≥ 4 12. The director of the company adds the requirement that if projects 4 or 6 (or both) are done inhouse then project 2 has to be done in-house. This could be modeled as the constraint(s): a. X2 ≤ X4 and X2 ≤ X6 b. X2 ≤ X4 and X2 ≤ X6 and X2 ≥ X4 + X6 -1 c. X2 ≥ X4 + X6 d. X2 ≥ X4 and X2 ≥ X6 13. If the director of the company adds the requirement that exactly one of projects 1 and 5 must be done in-house. This could be modeled as the constraint: a. X1 + X5 ≤ 1 b. X1 + X5 ≤ 0 c. X1 + X5 ≥ 1 d. X1 + X5 = 1 The next three questions refer to the following case and the picture that follows: GoodDrinks produces two kinds of drinks: Thai Tea and Regular Coffee. The company is adding a new special drink, which it hopes will help attract new customers. Management is planning to promote this new drink in two media: radio and direct-mail advertising. A media budget of $5000 is available for this promotional campaign. Based on past experience in promoting its other drinks, GoodDrink obtained the following estimate of the relationship between sales and the amount spent on promotion in these two media. S = 3R2 12 M2 6 R M + 15 R + 42M where, S = total sales in thousands of dollars R = thousands of dollars spent on radio advertising M = thousands of dollars spent on direct-mail advertising GoodDrinks would like to develop a promotional strategy that will lead to maximum sales subject to the restriction provided by the media budget. 14. What would be the sales if $3000 is spent on radio advertising and $2000 is spent on direct-mail advertising? a. - $ 110.874 Million b. $ 3000 c. $ 16000 d. $ 18000 15. The optimization model to solve GoodDrinks’ problem may be best classified as a: a. Linear Programming Model b. Mixed Integer Programming Model c. Non-linear Integer Programming Model d. Constrained Non-Linear Programming Model 16. Consider the feasible region (shaded) and the iso-contours (dotted) of the objective function shown in the figure below with objective value displayed for two of the iso-contours. Approximately how much should GoodDrinks spend on radio and direct-mail advertising respectively in order to achieve their stated objective? a. Nothing on radio, $3000 on direct-mail b. $ 3500 on radio, $1500 on direct-mail c. $ 1000 on radio, $1500 on direct-mail d. $ 2500 on radio, Nothing on direct-mail The next four questions are based on the following case: Consider the Excel implementation and subsequent Sensitivity Analysis for a typical portfolio optimization model below. Let x, y and z represent the fraction invested in stocks AT&T, GM and USS respectively. The “Average Return” and the information in the “Covariance Matrix” represent basic statistical analysis performed on returns data provided to us for AT&T, GM and USS. The optimization model embedded in MS Excel appears below the covariance matrix. Average Return Covariance Matrix AT&T GM USS Decision: Stock % Requirements Expected Return 15.29% 11.86% 11.61% AT&T 0.0348 0.0131 0.0280 GM 0.0131 0.0137 0.0069 USS 0.0280 0.0069 0.0659 Total 62.38% <=75% 9.54% 37.62% <=75% 4.46% 0.00% <=75% 0.00% 100% =100% 14% Portfolio Variance 0.0216 >=14.0% Sensitivity Analysis Variable Cells Cell $C$19 $D$19 $E$19 Name Decision: Stock % AT&T Decision: Stock % GM Decision: Stock % USS Final Value 0.623786408 0.376213592 0 Reduced Gradient 0 0 0.015404637 Name Decision: Stock % Total Expected Return Total Final Value 1 0.14 Lagrange Multiplier 0.065264295 0.775240433 Constraints Cell $F$19 $F$21 17. The appropriate objective function is given as: a. Max. 0.0954x + 0.0446y + 0.000 z b. Max. 0.0348x2 +0.0137 y2 + 0.0659 z2 + 0.0131 x y + 0.028x z +0.0069y z c. Min. 0.0348x +0.0137 y + 0.0659 z + 0.0262 x y + 0.056 x z +0.0138 y z d. Min. 0.0348x2 +0.0137 y2 + 0.0659 z2 + 0.0262 x y + 0.056x z +0.0138 y z 18. One of the constraints in the problem would be: a. 0.6238x + 0.3762y + 0.0 z ≤ 0.75 b. 0.0954 x + 0.0446 y + 0.0z = 0.14 c. 0.1529 x + 0.1186 y + 0.1161 z ≥ 0.14 d. 0.0954 x + 0.0446 y + 0.0z ≥ 0.14 19. a. b. c. d. 20. If the investor demands one percent more return, then the additional risk that he/she will have to bear would be approximately: 1.0216% 0.00775 0.065 0.0154 If the investor demands that at least 1% of the portfolio be USS stock, then the optimal portfolio variance would _____ as compared to its current value. a. decrease b. increase c. stay the same 21. Consider the shaded feasible regions shown below: a. b. c. d. both regions are convex Region A is non-convex and Region B is convex Region A is convex and Region B is non-convex both regions are non-convex The next three questions are based on the following case: Consider the following integer programming problem and partial graphical solution which follows. Answer the next two questions based on this information. Objective function: 3 x + 5 y Subject to: 2 x + 3 y < 16 x + 4y > 6 2x-y>3 x > 0, y > 0 x – Integer, y – Integer y 4 : 1.0 x + 4.0 y = 6.0 : 2.0 x + 3.0 y = 16.0 3 : 2.0 x - 1.0 y = 3.0 2 1 0 0 1 2 3 4 5 6 7 8 x : 2.0x + 3.0y <= 16.0 : 1.0x + 4.0y >= 6.0 : 2.0x - 1.0y >= 3.0 22. If the objective function were to be minimized, then the linear programming relaxation of the problem would yield an objective function value: a. slightly more than 11 b. slightly less than 40 c. slightly less than 11 d. exactly the same as the integer program 23. If the objective function were to be maximized, then the optimal objective function value for the integer program would be. a. 25.6 b. 25 c. 24 d. 40 24. In order to solve the problem by complete enumeration, we would have to calculate the objective function value, a. 2 times b. 4 times c. 12 times d. ∞ times Read the following case and answer the four questions that follow: The new Keller Museum of Contemporary Art (KMCA) is considering installing a video camera security system to reduce its insurance premiums. A diagram of the nine display rooms that KMCA uses for exhibits is shown in the figure below; the openings between the rooms are numbered 1-13. A security firm proposed that two-way cameras be installed at some room openings. Each camera has the ability to monitor the two rooms between which the camera is located. For example, if a camera were located at opening number 4, rooms 2 and 4 would be covered; if a camera were located at opening 9, rooms 7 and 8 would be covered; and so on. KMCA management decided not to locate a camera system at the “Main Entrance” to the display rooms. However, they would like to provide surveillance for rooms and of course spend as little as possible on the cameras installed, all of which are identical and cost the same. 1 if a camera is located at opening i xi Let 0 if not Room 1 1 3 2 5 Room 4 Room 2 4 6 7 8 Room 6 Room 7 9 11 Room 8 Room 3 10 Room 5 13 12 Room 9 25. The minimum number of constraints (excluding non-negativity) for the most concise IP formulation of the above problem would be: a. 9 b. 10 c. 11 d. 13 26. The appropriate objective function for the problem is: a. Max. x1 x13 b. Min. x1+ 2 x2 + 3 x3 +4 x4 + 5 x5 + 6 x6 + 7 x7 + 8 x8 +9 x9 c. Min. x1+ x2 + x3 + x4 + x5 + x6 + x7 + x8 + x9 d. Min. x1+ x2 + x3 + x4 + x5 + x6 + x7 + x8 + x9 + x10 + x11+x12 + x13 27. The inequality x5 + x6 + x9 ≥ 1 represents the constraint for: a. Room 4 b. Room 6 c. Room 7 d. Rooms 4, 6 and 7 28. The constraint x1 + x2+ x4 + x6+ x7 3 would indicate that: a. Room 4 needs surveillance with at least 3 cameras b. Room openings 1,2,4,6 and 7 need three cameras c. Rooms 1,2,4,6 and 7 need three cameras d. Room 1 cannot have surveillance from openings 1,2,4,6,7 Read the following case and answer the four questions that follow: Starbucks coffee company makes two types of Coffee: Arabian Mocha Java and Decaf Espresso Roast. These two types of coffees are made by blending three varieties of coffee beans, Plantation X, Plantation Y and Plantation Z. Further, the coffee beans are flavored by an ingredient called chicory and the coffees must meet restrictions on chicory content. Too much chicory content spoils the taste of coffee. The three varieties of coffee beans are shipped, mixed together in two delivery trucks to the retail center. Plantation X, is shipped in truck 1, Plantation Z is shipped in truck 2, and Plantation Y is shipped in truck1 and/or truck 2. No more than 1500 pounds of Arabian Mocha Java and 2400 pounds of Decaf Espresso Roast may be sold. Using the data in the table below, we want to formulate a profit-maximizing non-linear program. COFFEE Arabian Mocha Java Decaf Espresso Roast SALES PRICE per POUND ($) CHICORY CONTENT (%) 37 NO MORE THAN 3 41 NO MORE THAN 8 COST PER POUND ($) Plantation X Plantation Y Plantation Z 30 6 26 4 19 7 Assume the following: X = pounds of Plantation X purchased Y1, Y2 = pounds of Plantation Y purchased and shipped in trucks 1 and 2 respectively Z = pounds of Plantation Z purchased TS1, TT1 = pounds of beans from truck 1 blended into Arabian Mocha Java and Decaf Espresso Roast respectively TS2, TT2 = pounds of beans from truck 2 blended into Arabian Mocha Java and Decaf Espresso Roast respectively TC1, TC2 = chicory content percentage of beans in trucks 1 and 2, respectively 29. The objective function can be represented as: a. Max. 37 (TS1+TS2) + 41(TT1+TT2) b. Max. 37(TS1+TS2)+ 41(TT1+TT2)– 3TC1 – 8TC2 c. Max. 37(TS1+TS2)+ 41(TT1+TT2)– 6X – 4(Y1 + Y2) – 7Z d. Max. 37(TS1+TS2)+ 41(TT1+TT2)– 30X – 26(Y1 + Y2) – 19Z 30. The chicory percentage of beans in Truck 1 is given as: a. TC1 = 0.06X + 0.04Y1 b. TC1 = (0.06X + 0.04Y1) / (X + Y1) c. TC1 = (0.06X + 0.04Y1) / (Y1 + Y2) d. TC1 = (X + Y1) / (0.06 X + 0.04Y1) 31. The coffee shipped in truck 2 satisfies which of the following constraints: a. Y2 + Z = TS2 + TT2 b. Y + Z = TS2 + TT2 c. Y2 = (TS2 + TT2)/Z d. Both a and c are acceptable 32. The restriction on chicory content for Arabian Mocha Java is captured by the constraint: a. TS1 TC1 + TS2 TC2 < 0.03 b. TS1 TC1 + TS2 TC2 <= 0.03 c. TS1 (0.06X + 0.04Y1) / (X + Y1) + TS2 (0.07Z + 0.04Y2) / (Z + Y2) <= 0.03 d. TS1 (0.06X + 0.04Y1) / (X + Y1) + TS2 (0.07Z + 0.04Y2) / (Z + Y2) <= 0.03 (TS1+TS2) The next three questions are based on the following case: Peaches are to be transported from three orchard regions to two canneries. Intermediate stops at a consolidation station are possible. Orchard Supply Station Cannery Capacity Riverside (R) 1200 Waterford (W) Sanderson (S) 2500 Sunny Slope (SS) 1500 Northside (N) Millville (M) 3000 Old Farm (OF) 2000 Shipment costs (cij) of the flow (Xij) on arc (i,j) are shown in the table below. Where no cost is given, shipments are not possible. The network flow diagram is given below. R R SS 1 OF W N 5 4 5 OF 6 3 N 2 2 4 5 9 S M M 3 SS W S 2 33. Which of the following represents the objective function? a. Max. 3XRS+ 5XRW +1XRSS +4XSSW +5XSSN +6XOFW +3XOFN +2XWN +2XNW +2XWS +4XWM +5XNS +9XNM +2XMS b. Min. 3XRS+ 5XRW +1XRSS +4XSSW +5XSSN +6XOFW +3XOFN +2XWN +2XNW +2XWS +4XWM +5XNS +9XNM +2XMS c. Min. 3XSR+ 5XWR +1XSSR +4XWSS +5XNSS +6XWOF +3XNOF +2XNW +2XWN +2XSW +4XMW +5XSN +9XMN +2XSM d. Min. XRS+ XRW +XRSS +XSSW +XSSN +XOFW +XOFN +XWN +XNW +XWS +XWM +XNS +XNM +XMS 34. The overall flow constraint at Waterford is given as: a. +XRW+ XSSW +XOFW +XNW +XWN +XWS +XWM ≤ 0 b. +XRW+ XSSW +XOFW =XNW +XWN +XWS +XWM = 1 c. +XRW+XSSW +XOFW +XNW –XWN –XWS –XWM ≥ 0 d. –XRW–XSSW –XOFW –XNW +XWN +XWS +XWM = 0 35. Which nodes are “pure” transshipment nodes i.e. with no net demand or supply? a. R, S and OF b. W and N c. S and M d. SS,W, N and S Read the following case and answer the three questions that follow: Mary has 5 textbooks: Applied Science (A), Biology (B), Chemistry (C), Decision Science (D), and Economics (E). She wants to change them into eBooks, so she hired four people to help her with different typing speed. The expected finishing time (in hours) for each person of each book are shown in the table. Mary wants to assign the people to books so that she can get the eBooks as soon as possible. Assume that the variables are Xij where i=1,2,3,4 denote each person and j=A,B,C,D,E denote textbooks, and making sure that each book is assigned to a single person and each person works on at most one textbook. Textbooks A B C D E 1 28 22 27 28 21 2 32 19 22 24 25 3 25 39 30 32 20 4 22 24 26 24 29 Person# 36. a. b. c. d. The constraint for Biology is given as: 22X1B + 19X2B + 39X3B + 24X4B =1 X1B + X2B + X3B + X4B > 1 X1B + X2B + X3B + X4B < 1 X1B + X2B + X3B + X4B =1 37. a. b. c. d. The constraint for person 3 is given as: X3A + X3B + X3C + X3D =1 X3A + X3B + X3C + X3D + X3E =1 X3A + X3B + X3C + X3D < 1 25X3A + 39X3B + 30X3C + 32X3D + 20X3E > 1 38. Using the Greedy Heuristic discussed in class, what would be the assignment of cars to workers? a. 1-Chemisty , 2-Biology, 3-Economics,4-Applied Science b. 1-Decision Science, 2-Applied Science, 3-Biology,4-Economics c. 1-Chemisty , 2-Economics, 3-Decision Science,4-Applied Science d. 1-Economics , 2-Biology, 3-Applied Science,4-Decision Science 39. The Lone Star Bank recently budgeted the opening up of new zonal office in Texas and solved a Max Cover problem for the same (as we have seen in class). In the picture of the optimal solution shown below, how many zonal offices were budgeted to be opened? a. 5 b. 30 c. 35 d. 254 40. Consider the optimal solution to the “Set Cover” version of problem 7.15 posted online and discussed in class. Based on this optimal solution, which counties receive double coverage? a. 9,10,11,12 b. 1,3,4,5 c. 5,6,7,8 d. None ----------------- END of EXAM ------------------------