Re: Authorization to Discharge under General Permit 3-9030
Notice of Intent No. 6297-9030
Dear Mrs. Larkin:
The Stormwater Program hereby approves the Engineering Feasibility Analysis (EFA) Report and
proposed best management plans (BMP plans) for the Holiday Inn Express (Harbor Inn), located on
1720 Shelburne Road in South Burlington, discharging to Bartlett Brook. The approved BMP plans are
as follows:
Approved EFA Report and BMP Plans: This project shall be constructed and operated in accordance
with the EFA Report and the following BMP plans and details prepared by Krebs and Lansing
Consulting Engineers, Inc. (Sheets C-1, C-2, C-3, C-4, C-5, C-6, all dated 6/13/12; Detail sheets 8 and
9, dated 7/1985, revised 6/20/11; Sheet 2 titled “Grading, Drainage and Erosion Control,” dated
5/1985, revised 6/20/11; Sheet 4 titled “Utility Plan,” dated 5/1985, revised 6/20/11; and supporting
information).
The approved analysis and BMP plans will be posted on the Department’s website for public access and
review. The analysis and BMP plans will remain on the website for a period of fifteen (15) days.
By no later than eighteen (18) months after the Secretary’s approval of the analysis and BMP
plans, the permittee shall implement the BMP plans for the designated discharge in accordance with the
approved plans.
Within sixty (60) days of completion of implementation of the identified BMP plans, the permittee
shall submit to the Stormwater Program a written statement signed by a designer that the identified
BMPs have been built or implemented and are currently operating in compliance with the plans and
General Permit 3-9030. As-built-plans shall be submitted with the certification to reflect any
modifications of the BMPs from the original plans submitted to the Stormwater Program.
Please also note that your authorization to discharge treated stormwater runoff under General Permit 39030 includes inspection, maintenance, and reporting requirements. Please read the permit and the
previously issued authorization carefully. If you have any questions pertaining to this permit,
please contact the Stormwater Management Program’s Environmental Analyst assigned to your
district, Helen Carr at 490-6170 or by email at anr.wsmdstormwatergeneral@state.vt.us.
To preserve, enhance, restore, and conserve Vermont's natural resources, and protect human health, for the benefit of this and future generations.
Additional Stormwater Management Program contact information and stormwater permitting
information is available at http://www.watershedmanagement.vt.gov/.
Sincerely,
Padraic Monks
Stormwater Program Manager
Watershed Management Division
cc:
William H. Nedde III, Krebs & Lansing Consulting Engineers, Inc.
Helen Carr, Environmental Analyst, Stormwater Program
Thomas J. DiPietro, Stormwater Superintendent, City of South Burlington
Peter Keibel, Act 250 District Coordinator
To preserve, enhance, restore, and conserve Vermont's natural resources, and protect human health, for the benefit of this and future generations.
Download