NMDOT FORMS MANAGEMENT SOLUTION PROJECT PROJECT CHARTER FOR CERTIFICATION EXECUTIVE SPONSORS Tom Church, Cabinet Secretary, NMDOT Eric Roybal, Acting Chief Information Officer, NMDOT BUSINESS OWNERS Bruce Oakeley, Information Systems Manager, NMDOT Jeff Woodman, Web Supervisor, NMDOT ISM Bureau PROJECT MANAGER Sal Hernandez, Principal, Integratus Solutions ORIGINAL PLAN DATE: JUNE 24, 2013 REVISION DATE: JANUARY 6, 2014 TABLE OF CONTENTS TABLE OF CONTENTS ............................................................................................................................................ I 1. PROJECT BACKGROUND ..................................................................................................................................1 1.1 EXECUTIVE SUMMARY - RATIONALE FOR THE PROJECT ...................................................................................1 1.2 SUMMARY OF THE FOUNDATION PLANNING AND DOCUMENTATION FOR THE PROJECT .........................................1 1.3 PROJECT CERTIFICATION REQUIREMENTS ...........................................................................................................2 2.0 JUSTIFICATION, OBJECTIVES AND IMPACTS ..........................................................................................3 2.1 AGENCY JUSTIFICATION ......................................................................................................................................3 2.2 BUSINESS OBJECTIVES .........................................................................................................................................4 2.3 TECHNICAL OBJECTIVES ......................................................................................................................................4 2.4 IMPACT ON ORGANIZATION .................................................................................................................................5 2.5 TRANSITION TO OPERATIONS ...............................................................................................................................5 3.0 PROJECT/PRODUCT SCOPE OF WORK .......................................................................................................6 3.1 DELIVERABLES ....................................................................................................................................................6 3.1.1 Project Deliverables....................................................................................................................................6 3.1.2 Product Deliverables ................................................................................................................................ 11 3.2 SUCCESS AND QUALITY METRICS ................................................................................................................ 12 4.0 SCHEDULE ESTIMATE ................................................................................................................................... 13 5.0 BUDGET ESTIMATE ........................................................................................................................................ 13 Description ...................................................................................................................................................................... 13 FY13 ................................................................................................................................................................... 13 Staff - Internal ................................................................................................................................................................. 13 5.1 FUNDING SOURCE(S).......................................................................................................................................... 14 5.2. BUDGET BY MAJOR DELIVERABLE OR TYPE OF EXPENSE - ............................................................................... 14 5.3 BUDGET BY PROJECT PHASE OR CERTIFICATION PHASE.................................................................................... 14 6.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE ......................................................... 15 6.1 STAKEHOLDERS ........................................................................................................................................... 15 6.2 PROJECT GOVERNANCE PLAN .................................................................................................................. 16 THE DIAGRAM ABOVE ILLUSTRATES THE GENERAL REPORTING STRUCTURE FOR THE IMPLEMENTATION PROJECT. OTHER KEY STAKEHOLDERS INCLUDE NMDOT HR AND INSPECTOR GENERAL. .................................................... 16 6.3 PROJECT MANAGER ..................................................................................................................................... 16 6.3.1 PROJECT MANAGER CONTACT INFORMATION ................................................................................ 16 6.3.2 PROJECT MANAGER BACKGROUND Sal Hernandez, with Integratus solutions has had past project management experience in New Mexico State Government to include work with the Taxation and Revenue Department. Bill Bigley from 4Point has managed implementations of Adobe LiveCycle for large organizations such as Orange County, California. ............................................................................................ 17 6.4 PROJECT TEAM ROLES AND RESPONSIBILITIES ................................................................................... 17 6.5 PROJECT MANAGEMENT METHODOLOGY ........................................................................................................... 19 7.0 CONSTRAINTS .................................................................................................................................................. 19 8.0 DEPENDENCIES ................................................................................................................................................ 20 9.0 ASSUMPTIONS .................................................................................................................................................. 20 10.0 SIGNIFICANT RISKS AND MITIGATION STRATEGY ........................................................................... 21 11.0 COMMUNICATION PLAN FOR EXECUTIVE REPORTING .................................................................. 22 12.0 INDEPENDENT VERIFICATION AND VALIDATION - IV&V ............................................................... 22 13.0 PROJECT CHARTER AGENCY APPROVAL SIGNATURES .................................................................. 24 i 14.0 PROJECT CHARTER CERTIFICATION APPROVAL SIGNATURE ..................................................... 24 ii Revision History REVISION NUMBER DATE COMMENT 1.0 June 24, 2013 Initial NMDOT Plan 1.1 December 18, 2013 Submitted to Project Certification Committee iii PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 1 1. PROJECT BACKGROUND 1.1 EXECUTIVE SUMMARY - RATIONALE FOR THE PROJECT The New Mexico Department of Transportation relies thoroughly on the forms catalog within the agency for the management and data collection of its business processes. The information management practices around the usage of these documents are essential to the functioning of its business. There have been over three hundred forms identified as used for different areas within the agency. These forms are currently created using an older methodology, which makes the information management practices cumbersome, manual-intensive and prone to human errors and delays. The manual process calls for forms to be printed and then delivered (via mail or fax) to the agency. The form submission process is decoupled from the process flow. Furthermore, These forms reside on an aging system that requires it to be replaced before it begins to degrade service within the agency. NMDOT has chosen to modernize and substantially improve the form submission process. Modernization Improvements will include digitizing the document submission process as well as improving the form submission lifecycle, this will reduce process times and errors. The intrinsic benefits include creating a more productive and responsive agency thereby increasing customer satisfaction. 1.2 SUMMARY OF THE FOUNDATION PLANNING AND DOCUMENTATION FOR THE PROJECT NMDOT performed an analysis of current agency forms processes, including a master list of forms including form format and whether the form was for internal or external customers. We evaluated several electronic workflow systems including Adobe LiveCycle, EMC XCP, and a custom in-house workflow system. PAGE 1 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 2 1.3 PROJECT CERTIFICATION REQUIREMENTS Does the project fit into the criteria for certification? Which and how? CRITERIA YES/NO EXPLANATION Project is mission critical to the agency YES Reduce the cost of paper, ink/toner, personnel services, overtime, and equipment charges Project cost is equal to or in excess of $100,000.00 YES Cost is estimated to be $523,000 Project impacts customer on-line access YES Project will provide paperless, on-line access to forms and signatures for NMDOT’s Office of the Inspector General Project is one deemed appropriate by the Secretary of the DoIT YES Meets NM IT Strategic Plan objectives sponsored by DoIT. Will an IT Architecture Review be required? Yes Architecture review will be conducted after the site assessment and project plans are complete. PAGE 2 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 2.0 JUSTIFICATION, OBJECTIVES AND IMPACTS 2.1 AGENCY JUSTIFICATION NUMBER DESCRIPTION NMDOT 1 Create a paperless, web-based environment that allow NMDOT users to route administrative requests (travel, leave, new employee hiring packets etc.) electronically across different sections of the agency without being printed for manual signatures. NMDOT 2 Find and retrieve electronic insurance document images quickly without having to search manually through filing cabinets or boxes of paper. NMDOT 3 Reduce the labor costs of moving content from one section of the agency to another. NMDOT 4 Reduce the number of redundant and obsolete data records. NMDOT 5 Minimize the need for physical storage of boxes and paper. NMDOT 6 Increase productivity and user satisfaction by quickly routing the right information to the right person for approval and signature. NMDOT 7 Improve the audit-readiness of NMDOT records with better-organized, electronic records that can be located and searched much faster than paper records. NMDOT 8 Improve the agency’s ability to identify bottlenecks in the form approval processes with reliable, electronic records of how long each form sits at each approval point before being processed forward.. NMDOT 9 Improve the agency’s record-keeping of backup copies, archives, and remote storage for disaster recovery. PAGE 3 3 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 2.2 BUSINESS OBJECTIVES NUMBER DESCRIPTION BUSINESS OBJECTIVE 1 Increase efficiency and productivity via the electronic workflow and signature solution BUSINESS OBJECTIVE 2 Improve services to NMDOT staff and management and taxpayers BUSINESS OBJECTIVE 3 Reduce cost of paper, ink/toner, personnel services, overtime, and equipment charges BUSINESS OBJECTIVE 4 Improve accountability with check-in/check-out, version control security for business documents. BUSINESS OBJECTIVE 5 Optimize business process by decreasing the number of administrative processing steps, and allowing staff labor to be redirected to more valuable work 2.3 TECHNICAL OBJECTIVES NUMBER DESCRIPTION TECHNICAL OBJECTIVE 1 The new electronic workflow will be designed to interface with NMDOT’s existing NMDOT Adobe CQ-5 Content Management System, giving NMDOT internal staff access to navigate forms via the existing internal web site “INTRANS”. TECHNICAL OBJECTIVE 2 System will have Indexing and archival functionality and abilities. TECHNICAL OBJECTIVE 3 System will have scalability for future anticipated growth. PAGE 4 4 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT TECHNICAL OBJECTIVE 4 System will support Microsoft Active Directory for authentication. TECHNICAL OBJECTIVE 5 Transmission of data between NMDOT’s workstations and servers will be Secure Socket Layer (SSL) transactions, in full compliance with NM DoIT's Enterprise Architecture Requirements. 2.4 IMPACT ON ORGANIZATION AREA DESCRIPTION END USER Training will be defined and all end-users within NMDOT will be thoroughly trained. Tests will be conducted with random end-users to ensure performance and ease-of-use BUSINESS PROCESSES General procedures for handling form data will change for many business units with the implementation of electronic form routing. Employees will begin using electronic signatures frequently. IT OPERATIONS AND STAFFING Training will be defined and all end-users within NMDOT will be thoroughly trained. Tests will be conducted with random end-users to ensure performance and ease-of-use 2.5 TRANSITION TO OPERATIONS AREA DESCRIPTION PRELIMINARY OPERATIONS LOCATION AND STAFFING PLANS Staffing and Administration will be facilitated at the NMDOT General Office located at 1120 Cerrillos road, Santa Fe, NM 87504. The NMDOT IT Web-Unit will administer and support the system. They will be trained on the new system and follow and Procedures Manual provided by the Vendor who helps with Migration of data. PAGE 5 5 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT AREA DESCRIPTION DATA SECURITY, BUSINESS CONTINUITY The Transmission of data between NMDOT staff workstations and the Adobe LiveCycle Server are web-based and in compliance with NM DoIT Enterprise Architecture Requirements. System will also meet disaster recovery and business continuity requirements. MAINTENANCE STRATEGY The infrastructure and related software will be maintained by the agency web team, including installation of updates, hot fixes, and service packs. NMDOT will procure Technical Support from Adobe annually. INTEROPERABILITY The LiveCycle System will interoperate with the agency document repository as well as the agency web content management system. 3.0 PROJECT/PRODUCT SCOPE OF WORK 3.1 DELIVERABLES 3.1.1 PROJECT DELIVERABLES DELIVERABLE NUMBER DELIVERABLE PRJ-DEL-001 Initiation - Project Initiation and Scope Focus Meetings PRJ-DEL-002 Initiation - Initiation Phase Certification Form PRJ-DEL-003 Initiation - Project Charter PRJ-DEL-004 Initiation - Initiation Phase Certification PRJ-DEL-005 Initiation - Form Evaluation and Enumeration PRJ-DEL-006 Initiation - Identification of forms for electronic workflow & signature PRJ-DEL-007 Initiation - Change Management process for implementation phase PAGE 6 6 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT DELIVERABLE NUMBER DELIVERABLE PRJ-DEL-008 Initiation - Identification of workflow end points for top 30 priority forms. PRJ-DEL-009 Initiation - Identification of workflow participant categories PRJ-DEL-010 Initiation - Project JAD Session PRJ-DEL-011 Initiation - System Requirement Specification (SRS) PRJ-DEL-012 Initiation - System Requirement Specification (SRS) Evaluation and Review - Round 1 PRJ-DEL-013 Initiation - Project Status Reports (Internal) PRJ-DEL-014 Initiation - Initial Risk Assessment Report PRJ-DEL-015 Initiation - Initial Business Continuity Plan PRJ-DEL-016 Initiation - Initial Project Communication Plan PRJ-DEL-017 Initiation - Initial Project Operations and Support Plan PRJ-DEL-018 Initiation - Initial Project Test Plan and Strategy PRJ-DEL-019 Initiation - Initial Project Management Plan PRJ-DEL-020 Initiation - Initial Active Directory Update Plan PRJ-DEL-021 Planning - Planning Phase Certification Form PRJ-DEL-022 Planning - Revise Project Management Plan PAGE 7 7 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT DELIVERABLE NUMBER DELIVERABLE PRJ-DEL-023 Planning - IV&V Selected and Contract Negotiated PRJ-DEL-024 Planning - Project Status Reports (Internal) PRJ-DEL-025 Planning - System Requirement Specification (SRS) Evaluation and Review - Round 2 PRJ-DEL-026 Planning - Technical Architecture Document PRJ-DEL-027 Planning - Revise Risk Assessment Report PRJ-DEL-028 Planning - Revise Business Continuity Plan PRJ-DEL-029 Planning - Revise Project Communication Plan PRJ-DEL-030 Planning - Revise Project Operations and Support Plan PRJ-DEL-031 Planning - Revise Project Test Plan and Strategy PRJ-DEL-032 Planning - Revise Active Directory Update Plan PRJ-DEL-033 Planning - Initial Cutover Plan PRJ-DEL-034 Planning - Evaluate Electronic or Digital Signature Solution PRJ-DEL-035 Planning - ELECTRONIC SIGNATURE - Signature Collection Plan Strategy PRJ-DEL-036 Planning - DIGITAL SIGNATURE operations and support plan for digital sig. services. PRJ-DEL-037 Planning - Determine Active Directory fields needed for Live PAGE 8 8 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT DELIVERABLE NUMBER DELIVERABLE Cycle function PRJ-DEL-038 Planning - Determine which support staff will update non-GO portions of Active Directory PRJ-DEL-039 Planning - Technical Team Training PRJ-DEL-040 Implementation - Implementation Phase Certification Form PRJ-DEL-041 Implementation - Updated Project Management Plan PRJ-DEL-042 Implementation - IV&V Reports Submitted PRJ-DEL-043 Implementation - Technical Architecture Approved PRJ-DEL-044 Implementation - Project Status Reports (Internal) PRJ-DEL-045 Implementation - LiveCycle ES4 Server Installation and Configuration PRJ-DEL-046 Implementation - Active Directory Updates - Mass Update PRJ-DEL-047 Implementation - Active Directory Updates - District Level Updates PRJ-DEL-048 Implementation - ELECTRONIC SIGNATURE - Design / Develop web service interface for existing signature server PRJ-DEL-049 Implementation - Design / develop scripting to extract and rename guid-named forms from OIG form server PRJ-DEL-050 Implementation - Existing Form Migration PAGE 9 9 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT DELIVERABLE NUMBER DELIVERABLE PRJ-DEL-051 Implementation - New Form Development PRJ-DEL-052 Implementation - Workflow Development PRJ-DEL-053 Implementation - Implement Electronic or Digital Signature Solution PRJ-DEL-054 Implementation - Web Interface for Active Directory Organizational Maintenance PRJ-DEL-055 Implementation - End User Training for AD Web Interface PRJ-DEL-056 Close - Closeout Phase Certification Form PRJ-DEL-057 Close - Final IV&V Reports Submitted PRJ-DEL-058 Close - Project Closeout Report PRJ-DEL-059 Close - Lessons Learned PAGE 10 10 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 11 3.1.2 PRODUCT DELIVERABLES Requirements Documents The requirements will be defined and documented during the Planning phase. This will define NMDOT goals, business processes, critical factors, current environment, sizing requirements, # of users, work process requirements etc.. Design Documents Contractor will be required to deliver design documents for authentication Systems Specifications The Adobe LiveCycle software is a canned package web application that will integrate with our Adobe CQ-5 Web Content Management System and will not require additional desktop software to run. Systems Architecture Contractor will produce a System Requirements Specification outlining the general architecture of the LiveCycle solution. System and Acceptance Testing IT Web-IT staff and end-users will test system functionality, performance, reporting accuracy and response times. Operations requirements Contractor will include general operations requirements with the system requirements specification, to include administrative topics. Form Conversion Contractor will perform conversion of a percentage of NMDOT forms to include workflow implementation; Remainder of forms will be converted by NMDOT staff after knowledge transfer. PAGE 11 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 3.2 SUCCESS AND QUALITY METRICS NUMBER DESCRIPTION QUALITY METRICS 1 Project does not exceed budget QUALITY METRICS 2 The project schedule, assigned tasks and milestones are met within project plan. QUALITY METRICS 3 System can provide reports. QUALITY METRICS 4 All NMDOT Form Server Data is successfully converted and migrated into the Adobe LiveCycle platform. QUALITY METRICS 5 System is Secure and stable. QUALITY METRICS 6 Staff is Trained to maintain is operability. QUALITY METRICS 7 Data Integrity is maintained. PAGE 12 12 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 13 4.0 SCHEDULE ESTIMATE Identifier Task/Activity Name Resource Name Milestone (Y/N) SA-001 Active Directory Configuration Conce Fresquez / District IT Staff SA-002 Web Interface for AD organizational relationship maintenance Jeff Woodman SA-003 Installation and configuration of LiveCycle ES Server SA-004 Form Development Effort/ Duration Start Finish Y TBD TBD Y TBD TBD Alfred Lopez TBD TBD Vendor / Implementation Team TBD TBD Dependent Task 5.0 BUDGET ESTIMATE BUDGET Comments: DESCRIPTION STAFF INTERNAL NMDOT IT Staff Consulting Services Professional Services Training FY13 FY14 FY15 FY16&After Total 0 0 $218,000 $218,000 Adobe Live Cycle Training $25,000 $25,000 Hardware Use of existing 0 0 Software Adobe Live Cycle TOTAL $280,000 $523,000.00 PAGE 13 $280,000 $523,000.00 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 14 5.1 FUNDING SOURCE(S) SOURCE AMOUNT ASSOCIATED RESTRICTIONS $523,000 NONE STATE ROAD FUND 5.2. BUDGET BY MAJOR DELIVERABLE OR TYPE OF EXPENSE ITEM COST ESTIMATE ADOBE LIVECYCLE PURCHASE $273,000 PROJECT INITIATION DISCOVERY $18,500 PROJECT COORDINATION, PLANNING PHASE $59,000 RESOURCE TRAINING $25,000 PROJECT MIGRATION VENDOR $120,000 5.3 BUDGET BY PROJECT PHASE OR CERTIFICATION PHASE PHASES PLANNED CERTIFICATION INITIATION JUNE 2013 PLANNING/PROJECT JANUARY 2014 MANAGEMENT $303,300 $54,500 IMPLEMENTATION APRIL 2014 $108,850 CLOSING JUNE 2014 $28,850 PAGE 14 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 15 6.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE 6.1 STAKEHOLDERS NAME STAKE IN PROJECT ORGANIZATION TITLE Tom Church Overall Program NMDOT Secretary Eric Roybal Program Admin Responsibility NMDOT CIO Bruce Oakeley Overall Program NMDOT ISM Manager Jeff Woodman Quality Assurance IT System Admin NMDOT WEB Supervisor PAGE 15 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 16 6.2 PROJECT GOVERNANCE PLAN The diagram above illustrates the general reporting structure for the Implementation Project. Other key stakeholders include NMDOT HR and Inspector General. 6.3 PROJECT MANAGER 6.3.1 PROJECT MANAGER CONTACT INFORMATION NAME ORGANIZATION PHONE #(S) SAL HERNANDEZ INTEGRATUS SOLUTIONS 817-583-3738 BILL BIGLEY 4POINT 916-967-2002 PAGE 16 EMAIL PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 17 6.3.2 PROJECT MANAGER BACKGROUND Sal Hernandez, with Integratus solutions has had past project management experience in New Mexico State Government to include work with the Taxation and Revenue Department. Bill Bigley from 4Point has managed implementations of Adobe LiveCycle for large organizations such as Orange County, California. 6.4 PROJECT TEAM ROLES AND RESPONSIBILITIES ROLE RESPONSIBILITY Executive Project Sponsor The point person will be the highest level of NMDOT. Responsibilities include: Champion project Consider changes facing the organization and its impacts Responsible for finding budget to complete project Participate in planning sessions Ultimate project responsibility Steering Committee Tasked with overall direction and support of the project Participate in meetings Review and accept deliverables Review and provide comment on documentation provided by project team. Review project funding and its sources Business Owners Persons within the OIG and IT that are responsible for all operations and management of all activities of the LiveCycle project. Maintain responsibility for project direction/implementation Ensure staff availability Empower Project Manager and IT Staff Project Manager Person responsible to the participating entities who make decisions related to the operation of the project. Problem Solving Reviews of work of Consultants Participate in Changes to project Diagnose potential problems on project PAGE 17 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT ROLE RESPONSIBILITY Determine roles of IT personnel Ultimate project success Budget planning Project Schedule Training plans Contract Management Ensure Communications between vendor and project owner Project Team Members Staff assigned to Project. Define Business Needs Scheduling of meetings System Administration Testing Purchasing and processing Data integrity Data Input Technical Staff Staff assigned to defining infrastructure requirements and providing support to project indefinitely Duties Include: System infrastructure Specifications Integration of other NMDOT systems Data backups Storage requirements Security Data Migration Systems install and updates Network connectivity Provide test/development environments System Maintenance System Reporting Database tools (reporting) Disaster recovery Anti-Virus Protection Provide OEM PAGE 18 18 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 19 6.5 PROJECT MANAGEMENT METHODOLOGY The Project will be structured using a mixture of process-based and agile approaches. In addition, project reporting structures will be adjusted to meet timelines and phase gates defined by the PCC. 7.0 CONSTRAINTS NUMBER 1 2 DESCRIPTION Time – Project will need to be closed out by June 30th 2014 Budget – Project not to exceed 500K 3 Scope – Project scope need not exceed existing project estimates and increased scope be addressed/approved or denied by project steering committee 4 Software – Project technical deliverables need to be developed with Adobe LiveCycle software and related tools 5 Resources - Project will need to be completed with a mix of NMDOT and Contractor resources 6 Budget – Project need not cause a dramatic shift in operational cost causing financial constraint. 7 8 Process – Project to adhere to applicable NM DOIT methodology Agency – Project to adhere to applicable NM State and NMDOT policies and regulations. 9 Agency – Project technical deliverables to meet existing service agreements and response times. 10 Infrastructure – Software to configured and operate alongside existing NMDOT infrastructure PAGE 19 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 20 8.0 DEPENDENCIES M- Mandatory dependencies inherent to the work being done. D- Discretionary dependencies are sequences defined by the project management team that are not mandatory in the project life cycle. E- External dependencies involving activities outside the project such as purchasing/procurement. NUMBER DESCRIPTION TYPE M,D,E 1 ACTIVE DIRECTORY - ENSURE A PROPER MANAGEMENT INTERFACE EXISTS FOR THE ACTIVE DIRECTORY MANAGEMENT AS WELL AS ENSURE CONTENT IS UP TO DATE M, E 2 TRAINING - DELIVER PROPER DEVELOPMENT TRAINING FOR FORMS AND PORTAL DEVELOPERS M 3 INSTALLATION AND CONFIGURATION - ENSURE THE PROPER HARDWARE, SOFTWARE AND INFRASTRUCTURE IS MADE AVAILABLE M, E 4 ORGANIZATIONAL BUY-IN - ENSURE EXECUTIVE AND SME BUY-IN FOR NEW TECHNOLOGY AND PROCESS M 5 TECHNOLOGICAL - ENSURE PROPER IMPLEMENTATION OF TBD APPROACH (ELECTRONIC V DIGITAL SIGNITURES) M 6 ORGANIZATIONAL - ENSURE SUBJECT MATTER EXPERTS ARE EXCESSIBLE – BOTH FUNCTIONAL AND TECHNICAL SME’S ARE REQUIRED M 9.0 ASSUMPTIONS NUMBER DESCRIPTION 1 All system users exist in NMDOT’s Active Directory. All system users are internal to the agency. 2 3 Business rules for form data and routing relating to existing forms are known and fixed. Servers and client workstations meet or exceed the minimum requirements of the technology stack. PAGE 20 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 21 NUMBER DESCRIPTION 4 The form templates will be developed using a proper common format. If such a format is not possible, then the form will be provided in an alternative format and will be served as fill and print forms. 5 Project team will have access to functional and technical SMEs 10.0 SIGNIFICANT RISKS AND MITIGATION STRATEGY 1.6 INITIAL PROJECT RISKS IDENTIFIED [Risk 1 Active Directory] Probability EXPECTED Description – Active Directory entries are incorrect thus effecting forms with workflow Impact HIGH Mitigation Strategy – 2 fold strategy Initial and On-going 1. Initial – There is an initial effort to clean up Active Directory entries in bulk, especially for those Users/Groups identified as prospects for forms with workflow. 2. On-going – An interface will be developed for the Human Resources department to actively monitor and update Active Directory entries. Major Events (Hire to Fire) will trigger an resource to update the Active Directory. Contingency Plan 1. Continuous efforts to clean up the Active Directory entries on a regular interval [Risk 2 – Software Features] Description - Features and Probability LOW capabilities of the product may be wrong, incomplete, or too complex and that may not satisfy the requirement. Impact MEDIUM Mitigation Strategy 1. Complex scenarios were given to vendor during Proof of Concept initiative. 2. Additionally, ensure that all functionality is defined before development begins. Contingency Plan 1. Co-Develop more difficult scenarios with PoC vendor or engage them for support as needed 2. Extend product as needed with custom integration layers. PAGE 21 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT [Risk 3 – Software Training] Probability LOW Description – Resource training on software is inadequate or has not taken place Impact MEDIUM Mitigation Strategy 1. Training Plan to be developed for technical developers and support staff 2. Engage PoC vendor for development as needed Contingency Plan 1. Engage PoC vendor for development or support as needed and engage in over-the-shoulder development until adequate training plan can be established. [Risk 4 – End User Adoption] Description – End users are Probability LOW slow to adopt forms development 22 Impact HIGH Mitigation Strategy 1. Continuously involve end users at the appropriate level of detail. Contingency Plan 1. Executive mandate of solution set 11.0 COMMUNICATION PLAN FOR EXECUTIVE REPORTING The Project Manager will be responsible for creating periodic internal reports for NMDOT stakeholders, and will also assist in preparing materials for presentation to DoIT and the PPC. The Project Manager will work in conjunction with the Technical Lead to gather data for these reports. 12.0 INDEPENDENT VERIFICATION AND VALIDATION - IV&V The following check list is based on Exhibit A of the OCIO IV&V Contract Template, and the Information technology template. It is included here to provide a high level of the type of IV&V accountability the project envisions: Project/Product Area Include – Yes/No Project Management Y Quality Management Y Training N PAGE 22 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT Requirements Management N Operating Environment Y Development Environment N Software Development Y System and Acceptance Testing N Data Management Y Operations Oversight N Business Process Impact N PAGE 23 23 PROJECT CHARTER - NMDOT FORMS MANAGEMENT SOLUTION PROJECT 24 13.0 PROJECT CHARTER AGENCY APPROVAL SIGNATURES SIGNATURE DATE EXECUTIVE SPONSOR BUSINESS OWNER PROJECT MANAGER 14.0 PROJECT CHARTER CERTIFICATION APPROVAL SIGNATURE SIGNATURE DOIT / PCC APPROVAL PAGE 24 DATE