TENDER 0518 – HIGH LEVEL OVERFLOW ACROSS POW SPORTS GROUND Question 1. Is the disposal of the excess contaminated material to be excavated from the high flow stormwater site allowed to be dumped at the Jackson Street Tip and if so would we expect this to be free otherwise how much would we expected to be charged? 2. To what standard is the reinstatement of the sports ground required to be completed to and the extent because generally the whole area will be excavated or damaged. Reinstatement is mostly in regard to the ground levels, topsoil depths and can we assume that we can reuse the original topsoil there now? 3. Also is it required that the high level stormwater duct be staged in such a way that it would allow access to at least one of the two sports grounds for sporting activities during the construction period or can we assume full access to the whole area at all times? 4. Now more importantly we feel that the time schedule to these projects needs adhering to. Firstly the tender period doesn’t allow a sufficient time, with effectively only about 2 weeks for the tenders to be compiled together. With some project areas requiring high detail, information and collaboration between organisations the tenders can only be expected to of a reasonable level. Page 1 Clarification Council advise excess materials excavated from the high level overflow will be accepted at the Jackson Street tip at no cost to the success for tenderer. Council’s expectation with regards to reinstatement shall be reinstated to the same condition as a minimum prior to construction. Only if there is no additional cost to Council for this tender. Assume full access and provide extra over for staged construction if required. Extension of time granted. Please see notice to tenderers no. 2 issued on 11/1/12. Question 5. With many design elements needing time and cooperation, an extension to the due tender date would enable us to produce better detail and quality, thus the projects pricing estimations overall will be of a higher accuracy. We are requesting an extension to the due tender date of one week which will also subsequently push back the projects time line by the same amount. If the tender date isn’t extended then most likely various parts will not be fully designed by the due date leaving unknown aspects to the project and attributed vague pricings. The construction period is also worrying with 14 weeks specified leaving a tight schedule, we see that 6 weeks of this period would easily be taken up by investigations, design (there will be some, tender date extension or not), documentation and compiling and waiting for approvals. Leaving 8 weeks to construct and finish the job; an insufficient amount of time for these projects. Allowance for the previously mentioned items into the construction period should be considered, we see this needing an extension of 8-10 weeks to accommodate appropriately for both projects on offer at this present time. 6. What is the invert level of the existing 1800dia pipes? 7. From the long section it seems the invert level of the proposed overflow culvert is 1.50m, is this correct? 8. If the new overflow culvert is set higher than the existing 1800dia pipes, wont Gepp Road still be inundated in the event the 1800’s capacity is exceeded? Page 2 Clarification Council notify tenderers that an extension of time for construction has been granted from 14 weeks to 20 weeks. Approx. 1L 0.5m AHD. Please see pickup drawing within the tender documents Gepp Parade 29/4/96 sheet 1. This is correct The invert of the new culvert is set slightly above the centreline of the existing DN1800 to accommodate excess flow prior to the DN1800 pipes capacity being exceeded. 9. A request for an extension to the current closing date of the tender. Our preferred tender closing date being Wednesday 15th February 2012. We request this extension due to the timing of the tender period coinciding with the Christmas/New Year period in which a number of key potential suppliers and subcontractors are unavailable to provide pricing or design alternatives. An extension of time would also facilitate the opportunity to explore design options and optimisations to ensure that we can be in a position to offer a quality design combined with a competitive price structure. 10. Could you please confirm that GCC will accept at no charge to the Contractor all surplus and/or contaminated fill material at the Glenorchy Waste Centre. The Contractor being essentially responsible for including in our tender price the site handling, loading and cartage of such material to the GCC Waste Centre for disposal. 11. I have been having a look at the provided documentation and there is very little detail on what happens at SF001/04 which is the large pit on the Brooker Highway. There are some indicative line drawings from Council’s GIS showing the alignment of the stormwater pipes but these do not show pipe sizes or invert levels and the only other detail plan is a copy of the DPW plan of the twin 1800 pipes under the highway which is in imperial units to presumably an imperial datum. Can you provide me with some details of the pipe configuration at the Brooker Highway to the same datum please? Page 3 Notified of extension of time. Been answered previously. Invert level of existing DN1800 diameter pipes is approx 0.5m AHD. Other dimensions/levels should be determined from the provided drawings Question 12. What I have done here is prepare a DRAIN model of the line to see what variations in overflow culvert are possible whilst still meeting the maximum water level limits for the 1 year and 20 year flows. 13. Table 3, section 2.3.2 of part D – Specification, specifies the design flow rate through the culvert as 8,880 l/s (1 year ARI) and 22,500 l/s (20 year ARI). Can you please confirm if these flow rates are for the new culvert only, or for the combined new culvert/existing dual pipe system? 14. Are details of the existing dual DN1800 pipe system and outlet structure available please? Design/construction drawings including RL’s would be of assistance. Page 4 Clarification No answer required. New culvert only Sorry no other additional information or drawings available, other than what is in tender documents and explained above.