Analysis of the reports submitted by Member States on the implementation of directive 2008/1/EC, Directive 2000/76/EC, Directive 1999/13/EC and further development of the web platform to publish the information Draft report on subtask 3.1: Analysis of Member States implementation of IPPC and WI Directives – Annex A: Member States WI factsheets Report to the European Commission Unrestricted Commercial Issue1 April 2010 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Title Analysis of the reports submitted by the Member States and the further development of the web platform to publish the information Customer European Commission Customer reference ANV.C.4/FRA/2007/0011 Confidentiality, copyright and reproduction Unrestricted File reference Reference number Marie Leverton AEA Gemini Building Harwell IBC Didcot OX110QR UK t: 0870 190 2817 f: 0870 190 5545 AEA is a business name of AEA Technology plc AEA is certificated to ISO9001 and ISO14001 Author Name Approved by Name Liesbet Goovaerts (VITO) Katrijn Alaerts (VITO Ive Vanderreydt (VITO) Signature Date AEA Energy & Environment iii Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Table of contents Annex A iv 5 AEA Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Annex A Annex A sets out the detailed overviews of the Member States responses to the questionnaire. For each Member State a individual fact sheet is drafted containing: - The main text given in the response to each qualitative question by means of a short summary. This short summary presents the most relevant information provided by the MS in relation to each question. The questions are structured using the 6 main categories, used in the reporting tool. The qualitative questions are further split into subcategories providing an overview of specific practical approach and experiences of the Member States for each of the main categories. - Presentation of the Member States quantitative data in tables; - The completeness table, which indicates the degree to which the answers comply with the requirements of the questionnaire. The method described in the main report is used; - A summary on the status of implementation. This summary describes whether or not all requirements are implemented into a functional and effective practical systems. These fact sheets were presented to the Member States for approval. All comments, clarifications and additional information provided by the Member States were taken into account. These fact sheets are used as the basis for the analysis made in previous chapters. AEA Group 5 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report SPAIN Overview of the answers The table below presents the detailed analysis of Spain’s responses to each question of the questionnaire, by means of a short summary or standardised answer where appropriate. Comments regarding the adequacy of the answers in relation to the requirements of the questionnaire are added where necessary. AEA Group 6 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Table 1: Spain – overview of the answers Main category Question number – sub question reporting tool Subcategory: approach or experiences Summary of MS response Comments Question (Q) 1 Category: DEFINITIONS Subcategory: Specific Member States approach NO related questions asked Subcategory: Experiences of Member States 1.1 2 Please describe any problems with the definitions given in Article 3 identified when transposing and implementing the Directive? - Waste Hazardous waste General difficulty encountered in interpreting this definition for the two sections, specifically 2.a.ii. This has led to difficulties in applying specific requirements for some plants and hence in the application of emission ceilings as defined in Annexes II and V. - Mixed municipal waste Difficulties encountered - Incineration plant Difficulty encountered in interpreting this definition, especially with regard to gasification. - Co-incineration plant Existing incineration or co-incineration plant Difficulty encountered in discerning between existing incineration or co-incineration plants owing to the different time frames and situations described in this Article. - Nominal capacity Emission Emission limit value Dioxins and furans Operator Permit Residue - A description of these problems is not provided. Category: NUMBER OF INSTALLATIONS/PERMITS/WASTE (CO)-INCINERATED 7 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool Main category Subcategory: approach or experiences Summary of MS response Question (Q) Subcategory: Specific Member States approach NO related questions asked Comments Subcategory: Experiences of Member States 2.1 Please give information on number of installations, permits and permitted capacities that fall within the scope of the Directive See Table 2 below. 2.2 Have any mobile plants received permits under this Directive Please specify. Please give information on the waste that has been co-incinerated No 2.3 For cement kilns - Remarks: Capacity defined in terms of waste code is not available. Information on the total capacity of the waste co-incineration at 25 cement manufacturing plants is provided: 1 569 044 t/year. - waste oils: EU waste catalogue code: 08 03 19*, 08 04 17*, 12 01 06*, 12 01 07*, 12 01 10*, 12 01 19*, 13 01 09*, 13 01 10*, 13 01 11*, 13 01 12*, 13 01 13*, 13 02 03*, 13 02 04*, 13 02 05*, 13 02 06*, 13 02 07*, 13 02 08*, 13 03 06*, 13 03 07*, 13 03 08*, 13 03 09*, 13 03 10*, 13 04 01*, 13 04 02*, 13 04 03*, 13 05 06*, 19 02 07, 19 08 03*, 19 08 09, 19 08 10*, 20 01 25, 20 01 26* hazardous and non-hazardous solvents: hazardous/nonhazardous: EU waste catalogue code: hazardous filtercake: hazardous/nonhazardous: EU waste catalogue code: - - AEA Group 07 01 03*, 07 01 04*, 07 02 03*, 07 02 04*, 07 03 03*, 07 03 04*, 07 04 03*, 07 04 04*, 07 05 03*, 07 05 04*, 07 06 03*, 07 06 04*, 07 07 03*, 07 07 04*, 08 01 11*, 08 01 13*, 08 01 15*, 08 01 17*, 08 01 19*, 08 04 09*, 08 04 11*, 08 04 13*, 08 04 15*, 09 01 03*, 14 06 02*, 14 06 03*, 14 06 05*, 20 01 13* 05 01 15*, 07 01 09*, 07 01 10*, 07 02 09*, 07 02 10*, 07 03 09*, 07 03 10*, 07 04 10*, 07 05 09*, 07 05 10*, 07 06 09*, 07 06 10*, 07 07 09*, 07 07 10* 8 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool Main category Subcategory: approach or experiences Summary of MS response Comments Question (Q) - - - - - - hazardous wood waste: hazardous/nonhazardous: EU waste catalogue code: hazardous and non-hazardous plastics: hazardous/nonhazardous: EU waste catalogue code: non-hazardous textiles: hazardous/nonhazardous: EU waste catalogue code: RDF: hazardous/nonhazardous: EU waste catalogue code: non-hazardous fluff from shedding: hazardous/nonhazardous: EU waste catalogue code: non-hazardous other (please specify): hazardous/nonhazardous: EU waste catalogue code: 03 01 01, 03 01 04*, 03 01 05 02 01 04, 07 02 13, 12 01 05, 15 01 02, 16 01 19, 17 02 03, 19 12 04, 20 01 39 04 02 09, 04 02 21, 04 02 22, 15 01 09, 19 12 08, 20 01 10, 20 01 11 non-hazardous 19 02 08*, 19 02 09*, 19 02 10 , 19 12 10 19 10 04 01 05 05*, 01 05 06*, 02 01 02, 02 01 03, 02 01 07, 02 01 09, 02 01 99, 02 02 02, 02 02 03, 02 02 99, 02 03 99, 02 07 02, 02 07 03, 03 02 01, 03 02 02, 03 03 01, 03 03 02, 03 03 07, 03 03 08, 03 03 09, 03 03 10, 03 03 11, 04 01 03*, 04 01 05, 04 01 07, 04 01 08, 04 01 09, 04 01 99, 04 02 10, 04 02 14*, 04 02 15, 04 02 16*, 04 02 17, 04 02 19*, 04 02 20, 05 01 03*, 05 01 04*, 05 01 05*, 05 01 06*, 05 01 07*, 05 01 08*, 05 01 09*, 05 01 10, 05 01 11*, 05 01 13, 05 01 14, 05 01 17, 05 06 03*, 06 02 03*, 06 13 02*, 06 13 03, 07 01 01*, 07 01 07*, 07 01 08*, 07 01 11*, 07 01 12, 07 01 99, 07 02 01*, 07 02 07*, 07 02 08*, 07 02 11*, 07 02 12, 07 02 99, 07 03 01*, 07 03 07*, 07 03 08*, 07 03 11*, 07 03 12, 07 04 01*, 07 04 07*, 07 04 08, 07 04 11*, 07 04 12, 07 05 01*, 07 05 07*, 07 05 08, 07 05 11*, 07 05 12, 07 05 13*, 07 05 14, 07 06 01*, 07 06 07*, 07 06 08*, 07 06 11*, 07 06 12, 07 07 01*, 07 07 07*, 07 07 08*, 07 07 11*, 07 07 12, 07 07 99, 08 01 12, 08 01 14, 08 01 16, 08 01 18, 08 01 20, 08 01 21*, 08 02 02, 08 03 07, 08 03 08, 08 03 12*, 08 03 13, 08 03 14*, 08 03 15, 08 03 17*, 08 03 18, 08 04 10, 08 04 12, 08 04 14, 08 04 16, 09 01 01*, 09 01 02*, 09 01 04*, 09 01 05*, 09 01 9 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool Main category Subcategory: approach or experiences Summary of MS response Comments Question (Q) 06*, 09 01 13*, 10 01 01, 10 01 02, 10 01 25, 10 02 11*, 10 03 27*, 10 04 09*, 10 05 08*, 10 06 09*, 10 07 07*, 10 08 19*, 10 11 03, 11 01 13*, 12 01 08*, 12 01 09*, 12 01 12*, 12 01 14*, 12 01 15, 12 01 18*, 12 03 01*, 12 03 02*, 13 01 04*, 13 01 05*, 13 05 02*, 13 05 03*, 13 05 07*, 13 05 08*, 13 07 01*, 13 07 02*, 13 07 03*, 13 08 01*, 13 08 02*, 13 08 99*, 15 01 01, 15 01 03, 15 01 05, 15 01 06, 15 01 10*, 15 02 02*, 15 02 03, 16 01 03, 16 01 06, 16 01 07*, 16 01 13*, 16 01 14*, 16 01 15, 16 01 17, 16 01 18, 16 01 20, 16 01 99, 16 02 14, 16 02 15*, 16 03 05*, 16 03 06, 16 05 06, 16 05 07, 16 05 08, 16 05 09, 16 07 08*, 16 07 09*, 17 02 01, 17 02 04*, 17 03 01*, 17 03 02, 17 03 03*, 18 01 03, 18 01 06*, 18 01 07, 18 01 08, 18 01 09, 18 02 05*, 18 02 06, 18 02 08, 19 01 04, 19 01 06*, 19 01 10*, 19 02 04*, 19 02 05, 19 03 04*, 19 03 05, 19 03 06*, 19 03 07, 19 05 01, 19 05 02, 19 05 03, 19 06 04, 19 06 06, 19 08 01, 19 08 05, 19 08 11*, 19 08 12, 19 08 13*, 19 08 14, 19 09 01, 19 09 02, 19 09 03, 19 09 04, 19 11 01*, 19 11 02*, 19 11 03*, 19 11 04, 19 12 01, 19 12 06*, 19 12 07, 19 13 01*, 19 13 02, 19 13 03*, 19 13 04, 20 01 01, 20 01 17*, 20 01 27*, 20 01 28, 20 01 29*, 20 01 30, 20 01 32, 20 01 37*, 20 01 38, 20 01 99 hazardous/nonhazardous: hazardous and non-hazardous For combustion plants - Remarks Capacity defined in terms of waste code is not available. Information on the total capacity of the waste co-incineration at 3 plants is provided (data from one plant still pending):31 236 tonnes/year. - wood waste: EU waste catalogue code: 03 01 01, 03 01 05 non-hazardous other (please specify): hazardous/nonhazardous: EU waste catalogue code: hazardous/nonhazardous: hazardous and non-hazardous - 02 01 03, 02 01 07, 02 03 99, 03 03 01, 03 03 08, 07 02 08*, 07 05 04*, 17 02 01 Other industrial sector not covered under Annex II.1 or II.2 co-incinerating waste AEA Group 10 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Main category Question number – sub question reporting tool 2.4 3 Subcategory: approach or experiences Summary of MS response Question (Q) other (please specify): EU waste catalogue code: 1 03 07*, 02 01 08*, 02 02 02, 02 02 03, 02 02 99, 03 02 01*, 04 02 14*, 05 01 05*, 07 01 01*, 07 01 08*, 07 01 12, 07 02 08*, 07 07 99, 08 01 11*, 08 04 09*, 09 01 01*, 10 02 11*, 10 03 29*, 11 01 11*, 12 01 07*, 12 01 09*, 12 01 10*, 13 01 04*, 13 01 05*, 13 01 10*, 13 01 11*, 13 01 13*, 13 02 05*, 13 02 06*, 13 02 08*, 13 03 07*, 13 03 08*, 13 04 01*, 13 07 01*, 16 01 13*, 16 07 08*, 18 01 08*, 19 07 02*, 20 01 29* hazardous/nonhazardous: remarks: hazardous and non-hazardous How many co-incineration plants are subject to the emission limits provided in Annex V of the Directive (i.e. where co-incineration of untreated municipal waste is undertaken or more than 40 % of the heat release results from the combustion of hazardous waste)? Comments In addition to the codes indicated, one plant is authorised for chapter 02 waste. 121 906 tonnes per year of waste can be co-incinerated in 10 industrial sector plants not included in points 1 or 2 of Annex II. Information from two plants is pending. 3, one of which applies these limits when using glycerine and tyre waste as fuel. Category: PERMIT Subcategory: Specific Member States approach 3.1 3.1.1 What provisions are made within the permitting process for: Identifying the quantities and categories of hazardous waste that may be treated Article 4(5) of the WID has been transposed into national legislation (Article 6(3) of Royal Decree 653/2003 on waste incineration). The authorization process itself adheres to different national regulations (Royal Decree 653/2003, Law 16/2002 on integrated pollution prevention and control and regulations concerning hazardous waste). Amounts and categories of waste that can be treated, as well as maximum and/or minimum flows, are based on regional criteria. In many cases the category or type of hazardous waste is specified, unless there is a viable re-use or recycling solution, or a list of types of waste which cannot be 11 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool Main category Subcategory: approach or experiences Summary of MS response Comments Question (Q) incinerated is compiled. In most cases however, no amounts are specified If amounts are established, they are based on: the percentage of energy substitution the calorific value of the waste, the total heat released from the hazardous waste, which must not exceed 30-40% depending on the process and according to the project submitted and plant characteristics Best Available Technology the National Inventory of Dioxins and Furans in the cement sector sectoral studies control of the resulting emissions by means of prior tests (in one case). Waste products belonging to any of the authorised categories are subject to prior characterization and analysis to verify if their physicochemical properties are within acceptable limits. 3.1.2 The minimum and maximum flows of hazardous wastes to be treated See answer to question 3.1.1 3.1.3 The range of calorific values of hazardous wastes permitted In most cases, there are no special provisions in the authorisation process for determining the range of calorific values of authorised hazardous waste or restrictions on pollutant content. In cases where these ranges or restrictions were established, they were based on: information available from several studies (Mods documents, National Inventory of Dioxins and Furans in the cement sector, sectoral studies), establishing the minimum LHV and maximum halogen, chlorine and phenol levels of the waste allowed in the process a limit for PCB and PCP and for Cl based on emissions found in previous tests in accordance with the project submitted. 3.1.4 3.4 Restrictions on the content of pollutants e.g; PCB, PCP, chlorine, fluorine, sulphur, heavy metals See answer to question 3.1.3 For incineration plants, what measures are in place (in addition to the report requested under Article12(2), if any) to ensure that plants are designed, equipped, built and operated to so that the emission limit values (as set out in Annex V of the Directive) are not exceeded? - - AEA Group National legislation: o specifies that incineration plants be designed, equipped, built and used in such a way that escaping gases do not exceed the ELVs laid down in Annex V of the Directive and in other air quality regulations. (Art. 11(1) of Royal Decree 653/2003) o establishes the application of CEN standards for emission measurements and the use of calibration standards for automated systems. (Art. 14, 15 and 16 of Royal Decree 653/2003) Permits generally provide for: o technical specifications (e.g. gas purging, redundant control systems, preventive maintenance measures, etc), in accordance with the BAT 12 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool Main category Subcategory: approach or experiences Summary of MS response Question (Q) - - - 3.5 3.7 Comments o control of the continuous or quarterly emission data o measurements in accordance with national legislation The monitoring plans included in the Integrated Environmental Authorisations or the environmental plans approved by the competent authority must be complied with. Visits (initial and periodic) may be carried out and reports may be requested from the owner regarding certain parameters (operating times, gas temperature, emissions, types and amounts of waste being incinerated) in one region an air quality control campaign has also been conducted to study the possible impact of the plant. For co-incineration plants, what measures are in place (in addition to the report requested under Article12 (2), if any) to ensure that plants are designed, equipped, built and operated to so that the emission limit values (as set out in Annex II of the Directive) are not exceeded? National legislation includes a transposition of Art. 7(2) of the WID(Art. 11(2) of Royal Decree 653/2003). For releases to air from incineration and coincineration plants, have emission limit values additional to those given in Annex II or Annex V, as appropriate, been set? Yes Remarks In general no new ELVs were established except for an existing co-incineration plant in one region. The answer to question 3.4 also hold for co-incineration plants. ELVs below those resulting from applying the general co-incineration formula of Annex II of the WID were applied to the following parameters: Particles, CO, HCl, SO2, Sb+AS+Pb+Cr+Co+Cu+Mn+Ni+V. In some cases these ELVs were based on the BREF, while in others they were based on technical criteria deriving from the measurement history. In one region periodic measurements of PAH have been established for certain incineration plants, but for assessment purposes only. 3.7.2 3.8 If yes, where these data are available, please identify (optional). See Table 3 below How are emission limit values for discharges of waste water from flue gas cleaning equipment to the aquatic environment determined? Identical to Annex IV 13 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool Main category Subcategory: approach or experiences Question (Q) Remarks Summary of MS response Art. 8(2, 3, 4, 5) of the WID is covered in national legislation (Art. 12 of Royal Decree 653/2003). In most cases, these ELVs do not apply because: there is no waste water from flue gas cleaning given that dry cleaning systems are employed the discharge of waste water from any part of the process is prohibited. Comments Reference to the applicable national regulations is provided for in the original answer. In cases where the ELVs laid down in Annex IV of the Directive apply, also national and regional regulations concerning discharge into aquatic environments, the state of the receiving environment and the quality objectives established for the latter are taken into account in the environmental permit. Environmental authorisations must include the sampling and measurement procedures used, mentioning any specific regulations or methods that may be applicable. 3.9 3.10 3.11 Have emission limit values been set for pollutants discharged to water, in addition to the pollutants specified in Annex IV? Yes Remarks In general, no ELVs have been set for pollutants other than those specified in Annex IV, although the applicable sectoral regulation must also be applied, in this case the general water regulation. There is only one case in which additional ELVs have been set. If Yes, please specify See Table 4 below. What operational control parameters are set within the permitting process for waste water discharges? pH Temperature Flow Other (see remarks) Remarks Weekly flow volume, peak weekly flow. What provisions have been made to ensure protection of soil, surface waters or groundwater in accordance with Article 8(7)? Art. 8(7) of the WID is covered in national legislation (Art. 12(6) of Royal Decree 653/2003). A series of measures contained in the permit aim for ensuring protection of soil, surface waters and ground water: In most cases preventive measures in waste storage and handling and water treatment are applied, such as: o an impermeabilisation and watertightness maintenance programme o preventing direct contact of waste with soil o basins and collection systems with sufficient storage capacity, designed AEA Group All pollutants to be measured are listed in the original answer. 14 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool Main category Subcategory: approach or experiences Summary of MS response Comments Question (Q) to prevent and/or collect spills periodic inspections and tests of storage tanks and safety basins action protocols in the event of spills protection of work areas from precipitation compliance with national regulations governing the storage of chemical and inflammable products o control and monitoring programme for lavatory and rain water and for ground water by means of wells and bore holes o independent watertight systems for: the storage of chemical products and hazardous waste, the distribution of chemical products to processes and rain and waste water networks. Some regions include the filing of reports on soil and ground water quality and prohibit measures facilitating ground absorption of waste water. o o o o - 3.12 What criteria are used to ensure that storage capacity is adequate for waters to be tested and treated before discharge where necessary? National legislation (Art. 12(6) of Royal Decree 653/2003) provides that the storage capacity of sites for contaminated precipitation runoff or for waters from spills or firefighting operations must be adequate so that the said waters can be tested and treated before discharge as when necessary. Some regions also take into account the applicable sectoral regulation and general water regulation. All these regulations are taken into consideration for adequate plant design and dimensioning of water treatment plants. Criteria used for ensuring adequate storage capacity are not specified. 3.13 What provisions in general have been made to minimize the quantities and harmfulness of residues resulting from incineration or coincineration plants? Art. 9 of the WID is covered in national legislation (Art. 13 of Royal Decree 653/2003). No information is provided on measures for transport and physical and chemical testing. - - In general, plant operation must ensure the proper incineration and co-incineration of treated waste and proper management of waste generated. In most regions, specific measures have been introduced and are laid down in regional waste schemes or best practice manuals. In one region, regional legislation provides that waste incineration plants must reduce the amount and hazardousness of the ash produced in the incineration process as far as possible. This must be assessed, in accordance with technical and economic conditions, national and regional waste legislation. Specific measures have been adopted regarding the selective collection of organic matter and a charge has been introduced for the incineration of municipal waste at public and private incineration plants. In several co-incineration authorisations, waste minimising measures are included, based on the re-introduction as far as possible of waste from process cleaning systems. Otherwise waste is managed externally. 15 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool 3.14 Main category Subcategory: approach or experiences Question (Q) Are the requirements of the permit for the measurement of pollutants to air and process operation parameters identical to those set out in Article 11(2)? Remarks Summary of MS response Comments No National legislation (Art. 15(2) of Royal Decree 653/2003) includes the same requirements as Article 11(2) a) and b) of the Directive, but is more stringent than 11(2) c). If No is selected, please specify: 3.15 - reason for deviation from Article 11(2) More stringent requirements than those of Article 11(2) are applied - pollutant/parameter concerned and measurement requirement National legislation (Art. 15(2) c) of Royal Decree 653/2003) lays down a minimum of four annual measurements of heavy metals, dioxins and furans. During the initial 12 months of operation, measurements are taken at least every two months. Are the requirements of the permit for the measurement of pollutants to water identical to those set out in Article 11(14-15)? No Remarks National legislation (Art. 18(1) of Royal Decree 653/2003) lays down the same requirements as Directive Article 11(14) a), b) and c) but is more stringent than 11(14) d). If No is selected, please specify: 3.16 - reason for deviation from Article 11(1415) More stringent measurement requirements than those of Article 11(14-15) are applied - specify pollutant/parameter concerned and measurement requirement National legislation (Art. 18(1) d) of Royal Decree 253/2003) requires measurements of dioxins and furans at least quarterly. During the first 12 months of operation measurements are to be taken at least every two months. What provisions are made within the permitting process, as regards to air emissions, to ensure compliance with the provisions of National legislation (Art. 14, 15, 16,17,18 of Royal Decree 653/2003 of 30 May 2003) on waste incineration: provides that measurement requirements are to be stipulated in the authorisations establishes the frequency and conditions of the measurements lays down the conditions for compliance with limits for emissions into the atmosphere and water Sectoral regulations applicable to the atmosphere and waters must also be considered. Therefore, it is the environmental permit that includes the obligations envisaged in Article 11 of the Directive. Obligations relating to the atmosphere are always laid down, AEA Group 16 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool Main category Subcategory: approach or experiences Summary of MS response Comments Question (Q) while those relating to water emissions are included only when applicable. In cases where water emissions are included, environmental surveillance and control programmes have been established in accordance with Directive provisions (parameters, measurement frequency, remittal of reports to competent authorities, external checks by collaborating bodies, etc.). 3.16.1 Article 11 paragraph 8? Art. 11(8) of the WID is covered by Article 16(1) of Royal Decree 253/2003. 3.16.2 Article 11 paragraph 9? Article 11 paragraph 9 of the Directive is covered by Article 16(2) of Royal Decree 253/2003. Requirements for measurement and monitoring of parameters, conditions and mass concentrations related to the incineration process are included in the plant's authorisation and are conducted with the frequency, techniques and conditions laid down in national legislation (Art. 14, 15, 16 and Annex III of Royal Decree 653/2003). In many regions, environmental monitoring and control programmes are described in the authorisation, stipulating, with respect to emission and immission levels: measurement techniques in accordance with CEN standards quality assurance for the continuous control equipment in accordance with standards UNE 14181, UNE 13284-2, frequencies and pollutant record books In most regions the competent authorities must be informed of the results of the measurements, including real time transmission of continuous measurements in some cases. In many regions audits are conducted (initial and follow-up) by authorised control bodies or organisations collaborating with the authority, in accordance with the provisions of the environmental monitoring and control plans, including the taking of emission and immission air samples. 3.16.3 Article 11 paragraph 11 ? Art.11( 11) of the WID is covered by Art. 17(2) of Royal Decree 253/2003 3.16.4 Article 11 paragraph 12? Art. 11( 12) of the WID is covered by Art. 17(3) of Royal Decree 253/2003. What provisions are made within the permitting process, as regards to water emissions, to ensure compliance with the provisions of Article 11 paragraph 9 Art. 11 ( 9) of the WID is covered by Art. 16(2) of Royal Decree 253/2003. 3.17 No further information is provided on the guidance concerning the location of the measurement points. In cases where water emissions are included in the permit, environmental surveillance and control programmes have been established in accordance with Directive provisions 17 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool Main category Subcategory: approach or experiences Summary of MS response Comments Question (Q) (parameters, measurement frequency, remittal of reports to competent authorities, external checks by collaborating bodies, etc.). 3.18 What compliance regime is applied for emissions to air and water according to Article 11 paragraphs 10 and 16, respectively? Art.11( 10) and (16) of the WID are covered by national legislation (Art. 17(1) resp. 18(3) of Royal Decree 253/2003) For air: Option box: Identical to Article 11(10)/More stringent compliance regime Identical For water: 3.19 Option box: Identical to Article 11(16)/More stringent compliance regime A more stringent compliance regime is applied. If More stringent compliance regime is selected, please specify:___ National legislation (Art. 18(3) c) of Royal Decree 253/2003) provides that in the case of dioxins and furans, compliance with ELVs is assumed when measurements taken four times per year do not exceed the ELV laid down in Annex IV. Please describe any official guidance that has been developed to determine average emission data in accordance with article 11, paragraph 11? Art.11 (11) of the WID has been transposed into national legislation. In some regions, continuous data transmission is established, accompanied by a data validation protocol. One region has drawn up technical instructions stipulating data processing based on the values obtained by an automatic measurement system. These instructions specify among other things: calibration requirements the calculation of the confidence intervals to be used the calculation of the daily average data as in Art 11 (11) of the WID. In other regions, a sampling and measurement scheme is used, identifying sampling points and recognised measuring techniques. One control test per year is programmed. Calibration protocols of the measurement devices must adhere to CEN standards or, if unavailable, ISO standards. Measurements are made during operating time, excluding down time, operational AEA Group 18 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool Main category Subcategory: approach or experiences Summary of MS response Comments Question (Q) failures or plant maintenance. 3.20 What are the procedures for informing the competent authority in the event of breach of an emission limit? In some regions the competent authority receives validated data on a daily basis which is then reviewed daily. In most regions, the competent regional ministry is contacted by means of fax, post, electronic or direct communication and sometimes the local authority is contacted as well. In some regions the procedures are laid down in the civil protection legislation. Subcategory: Experiences of Member States 3.2 3.3 What wastes have been considered to be ‘inappropriate’ for representative sampling? some Type: Explosive and radioactive waste or waste liable to react and form toxic mixtures or vapours. Meat and bone meal. Waste received in sealed containers (e.g. bio-health, infectious or cytostatic materials). Vehicle tyres. Reasoning: In some cases these were considered inappropriate for sampling purposes. With regard to the furnace gas residence times and temperatures laid out in Article 6(1) and Article 6 (2): have any exemptions from the operating conditions been granted in accordance with Article 6(4)? No exemptions were granted in 2006-2008 3.3.1 If yes, how many exemptions have been granted? 3.6 For cement kilns co-incinerating waste, have any exemptions from the emission limits for NOx, dust, SO2 or TOC been granted in accordance with Annex II.1? Yes 3.6.1 If yes, how many exemptions have been granted? 9 3.6.2 If yes, where these data are available, please describe the reasoning for granting the derogation(s) for each case (optional) No real reasoning provided. 19 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Main category Question number – sub question reporting tool Subcategory: approach or experiences Question (Q) Remarks: Summary of MS response Comments Detailed information on all exemptions is unavailable. The following information is available: one exemption was due to the high SO2 content of the limestone as a raw material: installation capacity: 33 000 t/year types of co-incinerated waste: tyres and rubber, biomass (wood chips), glycerine ELVs for each plant: 1 200 mg/m3N (average daily value) of SO2 one exemption concerns SO2 and TOC: installation capacity: 730 000 t/year cement, 576 000 t/year clinker, types of co-incinerated waste: biomass and used mineral oil conditions of use provided in the permit plant ELVs: SO2: 200 mg/Nm3, TOC: 50 mg/m3 two exemptions for SO2 and TOC 4 Category: Public participation Subcategory: Specific Member States approach 4.1 What arrangements are made to ensure public participation in the permitting process? Remarks: - type of permit - public availability of the permit application period that the public is enabled to comment public availability of the final decision on the permit application - AEA Group In accordance with national legislation (Art. 19 of Royal Decree 653/2003), the processing procedure for new authorisations for incineration and co-incineration plants includes a public information process whereby observations may be submitted prior to the competent authority's decision on the granting of authorisation. Moreover other national provisions (and regional if applicable) concerning public participation must be respected. These public information procedures are typically carried out through the Official Journal of the Autonomous Community and occasionally through web page announcements. Reference to all relevant legislation is provided for in the original answer. No information provided. 20 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool 4.2 4.2.1 Main category Subcategory: approach or experiences Summary of MS response Comments Question (Q) With regard to the availability of information throughout the permitting process: Is there any information related to environmental aspects not publicly available on the application, decision process and subsequent permit? No Remarks: Information related to environmental aspects of permit applications, the decision-making process and the ensuing permit is publicly available (in many cases via a web page) in compliance with basic legal provisions on access to environmental information, except information that is considered confidential. If yes please specify: 4.2.2 Where these data are available, please specify whether this information is available free of charge (optional) Yes 4.3 For incineration plants and co-incineration plants with a nominal capacity of two tonnes or more per hour, what provisions are made to require an operator to submit an annual report on the functioning and monitoring of the plant to the competent authority? National legislation (Art. 19(2) of Royal Decree 653/2003) states that operators must draw up and submit to the competent authority an annual report on the operation and monitoring of the plant which at least covers the running of the process and emissions into the air or water compared to the emission levels regulated by this legislation. For incineration plants: The duty to submit this report is stipulated in the incineration plant permit. Depending on the region, the following is requested, in addition to the annual report: submission of data on a daily basis submission of periodic reports (monthly, quarterly, half-yearly and even annual) on different aspects (emissions, measures, waste generation, etc.) submission of a triennial certificate issued by the organisation collaborating with the authority submission of a report drawn up by an authorised control body on compliance with the environmental monitoring and control plan laid down in the permit. For co-incineration plants: In some regions the duty to submit this report is stipulated in the environmental permit. Depending on the region, the following is requested, in addition to the elements enumerated above for incineration plants: submission of a surveillance plan which must include measurement of immisions an annual report on the latter for submission to the environmental body. 21 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Main category Question number – sub question reporting tool Subcategory: approach or experiences Summary of MS response Comments Question (Q) 4.4 4.5 4.6 What information are these Annual Reports required to contain? - Remarks Following is a general overview of the information that may be included in the annual reports (typically stipulated in the authorisation): operating time, incidents, failures and invalid emissions data data on annual consumption of raw materials (water, energy, fuel, etc.), list of chemical products and amounts used (attaching safety specifications) annual summary of continuous and periodic emission measurement parameters (emissions report to be filed with the PRTR). In some cases these data are to be compared with the emission levels of national legislation/the E-PRTR. annual report of the results of immission levels or air quality checks discharges monitoring of surface and ground water, soil and vegetation quality noise waste production and/or management, waste description environmental audit report on waste management and production (biennial). How are the annual reports made available to the public? All annual reports are available from the competent authority upon request. Other (see remarks) Remarks: An individual citizen/the public at large may see that report upon request to the competent public authority. Also, E-PRTR data are public and can be viewed via the web page of the Spanish Ministry of the Environment and Rural and Marine Affairs. In one region an ad hoc participation committee has been created. For incineration or co-incineration plants with a nominal capacity of less than two tonnes per hour, how are these plants publicly identified? This varies from region to region: in some regions these plants are subject to the integrated environmental authorisation, being published in the Official Journal of the Province. in other regions these plants can be found on the authority web page in the list of waste managers. in some regions a public list is drawn up based on the incineration or coincineration capacity declared by the different plants. plant capacity is also determined through the E-PRTR. NO related questions asked Subcategory: Experiences of Member States 5 Account of the running of the process Emissions into air compared to standards set in the Directive Emissions into water compared to standards set in the Directive Types of waste that are incinerated Other (see remarks) Category: Abnormal operation of installations AEA Group 22 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Main category Question number – sub question reporting tool Subcategory: approach or experiences Summary of MS response Comments Question (Q) Subcategory: Specific Member States approach 5.1 5.2 What provisions are made within a permit to control the period of operation of an incineration or co-incineration plant during abnormal operation (i.e. stoppages, disturbances or failure of abatement or monitoring equipment)? A few specific provisions: immediate reporting of failures to the competent authority with full documentation development of a safety plan and action to be taken in emergency situations or action protocols for failures, accidents or over-limit ELVs power shut-off to the waste burning oven through a control loop based on: air pollution emission levels, a fall in temperature below the established threshold or in some cases breakdown/maintenance of the continuous measurement devices ensuring ideal combustion conditions maximum mitigation of effects due to discharge and accidental leaks implementation of preventive measures (calibrations, maintenance) prevention and repair of environmental damage compliance with a self-protection plan as required by national legislation identification of possible modes of abnormal operation requirements on minimum availability of measurement equipment limits on maximum abnormal operating periods For incineration and co-incineration processes what are the maximum permissible periods of operation during abnormal operation (i.e. before the plant must shut down)? Remarks Maximum periods of operation under the abnormal conditions are laid down in the permit in accordance with national legislation (Art. 20 of Royal Decree 653/2003), specifying the cases where plant operation must be interrupted. Some regions specify additional requirements. Maximum permissible period with exceedence of emission limit values No answer provided. Maximum permissible period with exceedence of emission limit values No answer provided. Subcategory: Experiences of Member States 6 The permit must comply with the provisions of Art. 13 of the WID NO related questions asked Category: Other 23 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Question number – sub question reporting tool Main category Subcategory: approach or experiences Summary of MS response Question (Q) Subcategory: Specific Member States approach NO related questions asked Comments Subcategory: Experiences of Member States 6.1 What information, if any, do you have to suggest that the Directive should be amended with regards to 6.1.1 Articles 10 - 6.1.2 Articles 11 - 6.1.3 Articles 13 - 6.1.4 Annex I - 6.1.5 Annex III - 6.1.6 Other (optional) - AEA Group 24 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Member State quantitative data Table 2: Answer to question 2.1 Requested information existing1 new total Number of installations within the scope of the Directive 50 32 82 Number of permits issued 42 32 74 0 8 8 1529201 2717163 4246364 33 26 59 Number of permits to be issued Total permitted capacities of waste throughput, if available (optional) (tonnes/year) Number of plants that recover heat generated by the incineration process 1 Existing plants are as defined in article 3 paragraph 6, new plants are all others 25 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Table 3: Answer to question 3.7 New/ existing Parameter Limit value Unit Averaging Monitoring period method coincinerator coincinerator coincinerator coincinerator existing particles 45 mg/Nm3 hhav continuous existing particles 20 mg/Nm3 dav continuous existing CO 1445 mg/Nm3 dav continuous existing CO 1470 mg/Nm3 other continuous Measurement period: average value of ten minutes (95% of measurements). coincinerator existing CO 1438 mg/Nm3 hhav continuous Measurement period: average half-hourly value (100% of measurements). coincinerator coincinerator coincinerator coincinerator coincinerator existing HCI 100 mg/Nm3 hhav continuous existing HCI 30 mg/Nm3 dav continuous existing SO2 1200 mg/Nm3 hhav continuous existing SO2 1100 mg/Nm3 dav continuous existing Sb+As+Pb+Cr+Co+Cu+Mn+Ni+V 4 mg/Nm3 other discontinuous Type AEA Group Remarks Average period: average value during a sampling period lasting at least 30 minutes and a maximum of 8 hours. 26 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Table 4: Answer to question 3.9 Pollutant Type New/ existing Limit value pH incinerator existing 5,5-9,5 COD incinerator existing 160 mgl BOD5 incinerator existing 40 mgl Total phosphorous incinerator existing 10 mgl Ammoniacal nitrogen incinerator existing 15 mgl Residual free chlorine incinerator existing 0,05 mgl Total coliform bacteria incinerator existing 1500 ufc/100ml Faecal coliform bacteria incinerator existing 300 ufc/100ml Faecal streptococci incinerator existing 100 ufc/100ml Suspended solids incinerator existing 0,5 mgl Sulphides incinerator existing 1 mgl Sulphites incinerator existing 1 mgl Unit Reasoning for applying this additional limit value For all cases: determined by the inter-community basin body on the basis of legislation currently in force. 27 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Analysis of completeness Table 5 presents the level of completeness of the report of Spain Table 5: Spain – Completeness analysis table Question number, subquestion 1.1 Level of completeness Comments A description of the problems concerning the interpretation of ‘mixed municipal waste’ and ‘incineration plant’ is not provided. 2.1 2.2 2.3 2.4 3.1 3.2 No real reasoning provided. 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11 3.12 Criteria used for ensuring adequate storage capacity are not specified. 3.13 No information is provided on measures for transport and physical and chemical testing. 3.14 3.15 3.16 3.17 3.18 3.19 28 Q 3.16.4: No further information is provided on the guidance concerning the location of the measurement points. Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report 3.20 4.1 No information provided for the sub questions. 4.2 4.3 4.4 4.5 4.6 5.1 5.2 Maximum permissible periods are not specified. 6.1 29 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report Analysis of implementation status Spain has provided an extensive, clear and complete overview of the national legislation and legal provisions in place to ensure compliance with the WI Directive. Spain has 82 installations (including 50 new installations) falling within the scope of the Directive, of which 59 apply heat recovery (33 new and 26 existing installations). The total permitted capacities of waste throughput is 4 246 ktonnes/year. 25 cement kilns co-incinerate in total 1 569 ktonnes/year, both waste oils, solvents, wood waste, textiles, fluff, plastics, RDF and other waste. Combustion plants co-incinerate in total 31 ktonnes/year wood waste and other waste. Additionally 10 industrial sector plants (not covered under Annex II.1 or II.2) can co-incinerate 122 ktonnes/year. 3 of these co-incineration plants are subject to the emission limits of Annex V of the WID. Spain ensures full compliance with the provisions of the WI Directive regarding the normal and abnormal operating conditions, ELVs for emissions to air and water, residues, monitoring, control and measurement requirements and public participation procedures is ensured by means of the requirements laid down in national legislation. For some aspects however, exemptions are applied or more stringent requirements are adopted. For one installation, in addition to the pollutants as specified in Annex IV, ELVs for water discharge have been set for several parameters (including phosphorous, sulphides, sulphites and several biological parameters). For emissions to air the measurement frequency is specified as minimum four annual measurements for dioxins and heavy metals. For emissions to water the minimal measurement frequency for dioxins is quarterly. For new installations, for these parameters the measurement frequency is raised to at least every two months. In addition to the more stringent measurement frequency, for dioxin emissions to water the compliance with the ELV is assumed when measurements taken four times per year do not exceed the ELV laid down in Annex IV. Public participation in the permitting process is ensured by national legislation. The annual reporting requirement is laid down in the permit and in national legislation for incineration plants. National legislation specifies the content of this report, according to the requirements of the WID. For co-incineration plants however, the submittance of an annual report is not applicable in all Spanish regions. Information on plants with a capacity of less than 2 tonnes/h is always available, although it depends on the specific region in which form or format. A specific listing is not drawn up. Control and duration of abnormal operating conditions is regulated as specified by the WID, and laid down in both national legislation and the permit. 30 Unrestricted Analysis of the reports submitted by the Member States Framework contract No. ENV/C.4/FRA/2007/0011 Draft Report The Gemini Building Fermi Avenue Harwell International Business Centre Didcot Oxfordshire OX11 0QR Tel: 0845 345 3302 Fax: 0870 190 6138 E-mail: info@aeat.co,uk www.aeat-env.com 31