Phase 4 – Stakeholder Engagement for Main ESIA in Greece West 1 INTRODUCTION 1.1 This Report In the course of the Environmental and Social Impact Assessment (ESIA) process for the Trans Adriatic Pipeline (TAP) Project, a phased stakeholder consultation programme is performed, as set out in TAP AG’s Stakeholder Engagement Plan (SEP). This report presents the outcomes of the stakeholder engagement activities undertaken during the main preparation phase of ESIA. This phase of engagement represents the fourth phase of stakeholder engagement for the TAP Project, following Pre-Scoping, Route Refinement and ESIA Scoping Disclosure Engagement activities (see Table 0-1). Table 0-1 Phases of Stakeholder Engagement in Greece and Progress to Date Phase Completed/ Planned Phase 1: Pre-scoping Completed Phase 2: Route Refinement Completed Phase 3: ESIA Scoping Completed Phase 4: Main ESIA Phase Completed (Subject of this Report) Phase 5: ESIA Disclosure and Consultation Planned Phase 6: Ongoing Engagement during Project Implementation Planned The objective of this fourth phase of stakeholder engagement, conducted during September and October 2011, was to complement the scoping engagement held in June and July 2011 in order to ensure that stakeholders at the local level had an opportunity to learn about the Project, to ask questions and raise concerns. Municipality representatives, heads of communities and the public in potentially affected settlements were the primary focus. The engagement was also used by the Project team to gain information on local particularities of importance for consideration in the assessment of impacts and development of mitigation measures. During consultations, the Project team also informed stakeholders about the grievance mechanism as well as the next phases of the Project. In addition to local level consultation, supplementary engagement was undertaken during traffic and cultural heritage surveys carried out in April 2012 and May 2012 respectively. These surveys were carried out in order to re-confirm issues that were raised during the ESIA process concerning these areas of interest. The municipalities and settlements consulted during the main ESIA phase are presented in Table 1-1 below. Table 1-1 Administrative Entities and Settlements crossed by the Pipeline Route Municipality Settlement Region of Central Macedonia Chalkidona Municipality: Aghialos, Mikron Monastirion, Valtochorion, Nea Mesimvria, Parthenion, Gefira Pella Municipality: Agios Loukas, Liparon Skydra Municipality: Naousa Municipality: Kalivia, Aspron, Rizon, Loutrochorion Plevroma, Petrea Polla Nera Edessa Municipality: Agia Fotini, Ano Grammatiko, Kato Grammatiko Region of West Macedonia Eordea Municipality: Purgoi, Pentavrussos, Perdikkas, Galateia, Droseron, Foufas Amyntaio Municipality: Maniaki, Antigonos, Variko Kastoria Muncipality: Kleisoura, Lithia, Verga Agia Paraskevi (monastery), Krepeni, Dispilio, Korissos, Chiliodentro, Poreia, Tsakoni, Mesopotamia , Agia Kuriaki, Oinoi Militsa, Ampelokipi Orestida Municipality: 1.2 Background and Steps Leading to the ESIA Process The Route Refinement phase evaluated socioeconomic and cultural feasible pipeline heritage potential criteria with routes the aim using of technical, identifying environmental, the technically route alternative with the least environmental, socioeconomic and cultural heritage impacts. Once the preferred alternative had been identified, TAP AG produced a Scoping Report which was disclosed in the meetings that followed. The process of Scoping allows key issues to be identified and addressed in the ESIA. It should be noted that in accordance with the regulations pertinent in Greece at the time when the ESIA process was started, the Environmental Impact Assessment (EIA) in Greece for the Project section between Nea Messimvria to the Greek-Albanian border is carried out in the following two phases: • Preliminary Environmental Impact Assessment (PEIA); and • Environmental Impact Assessment (EIA). A Special Environmental Authority within the Ministry of Environment, Energy and Climate Change (EYPE/YPEKA) is in charge of both phases of the EIA process. The PEIA Study is submitted to the Special Environmental Authority (EYPE/YPEKA) for consideration and the PEIA phase consultation is limited to national public authorities. During the EIA phase, when the ESIA report is completed, but prior to its approval, the study is submitted to the regional authorities involved and is subject to public disclosure. One public disclosure meeting is mandatory to be organised in each region. The PEIA was prepared following the compilation of the ESIA Scoping Report, filling a similar role in the ESIA process but meeting the specific requirements of Greek environmental legislation. An additional dedicated PEIA consultation phase was thus not considered meaningful as it would have provided no additional value to stakeholders or to the Project at that stage and could have created ‘stakeholder fatigue’. The PEIA was submitted to the Ministry in September 2011 for a completion check and then resubmitted after some design changes in February 2012. The updated PEIA report was also submitted to 27 national and regional authorities as required by national legislation. 2 2.1 ENGAGEMENT PROCESS DURING THE MAIN ESIA PHASE Summary of Engagement Meetings During ESIA main phase, settlement engagement meetings were held within the 2 km corridor along the pipeline route to provide information about the Project, to discuss impacts and mitigation measures, to answer questions and understand concerns of those that will be most affected by the Project. A few settlement meetings were also held outside the corridor due to their potential ownership or use of land within the corridor. Additionally focus group discussions and key informant interviews were held. Although these were organised primarily to collect information for the social baseline element of the ESIA, they also served as a forum for these groups to communicate their opinions and concerns regarding the TAP Project. In total, 1,052 participants were consulted during 95 consultation events. Meetings were organised through national and regional authorities and heads of communities. Additionally, a media campaign was coordinated by TAP AG’s office in Greece which included the following activities: • 2 weeks prior to consultation, adverts were placed in 4 northern based newspapers (published twice – 1 per week): Odos, Ptolemaios, Paratiritis and Makedonia. • The same adverts were announced on the regional radio stations: Radio Almopia, Radio Agapitos, Pella FM, Radio Kastoria and Antennes FM. • Consultation posters were sent to heads of the local communities for distribution prior to the consultation. Posters were also placed in public places by TAP AG representatives 2-3 days in advance of the meetings. Meetings were only held in the evening following the request of the local communities, in order to maximise the possibility of public participation. Meetings were held in a variety of locations such as municipality offices, coffee shops, community social areas and general stores. Consultation meetings involved a presentation of the Project followed by a question and answer session. Focus groups and key informant interviews were guided by a protocol to enable targeted discussions about specific topic areas for baseline data collection. Detailed aerial maps of the potential Project route were also used at stakeholder meetings in order to provide visual orientation and facilitate discussion. Issues raised during meetings were recorded and are summarized in Section 4 below. Stakeholders were also invited to submit follow-up questions and comments by post or through the Project website. All communication materials included information on the TAP grievance mechanism. 2.2 Traffic and Cultural Heritage Field Surveys and Stakeholder Consultation Between April and May 2012, traffic and cultural heritage surveys were carried out to collect additional data for the ESIA and to identify impact and mitigation measures relating to these areas of concern. This allowed for supplementary consultation to be conducted with stakeholders not previously consulted during the ESIA preparation phase engagement. Consultation on Construction Traffic Impacts: In the course of the traffic counts undertaken at traffic nodes that, based on preliminary construction traffic prognoses from the logistics planning would be critically affected, consultations were held with key statutory stakeholders in charge of regional traffic issues. The main objective of the traffic survey was to present the potential pipeline route and affected roads in order to discuss areas potentially affected by the TAP Project. Table 2-3 provides a list of meetings held during the traffic survey. Table 2-1 Traffic Survey Meetings Date Stakeholder 23.04.12 Traffic Police – Department of Nea Chalkidona 24.04.12 Traffic Police – Department of Highways 25.04.12 Traffic Police – Department of Pella 26.04.12 Mr.Athanasios Matthaiou, Director of Operation, Maintenance and Commercial issues, Egnatia Odossea, Thessaloniki 27.04.12 Traffic Police – Department of Kastoria 27.04.12 Traffic Police – Department of Ptolemaida Consultation on Cultural Heritage: The purpose of cultural heritage field survey, carried out in May 2012, following a request from the Greek Ephorates of Antiquities, was to provide support to the agencies in performing field surveys under the framework of their appraisal and interagency consultation process with the Ministry of Culture (Large Projects Department) and the Ministry of Environment for the PEIA. Maps were provided to the Ephorates prior to visiting sections of the pipeline route together with the PEIA report. The schedule and stakeholders attending the field activities held in relation to this survey are listed in Table 2-4. Table 2-2 Details of Cultural Heritage Field Survey (May 2012) Date Stakeholder 14.05.12 • T. Keramaris, Archaeologist of the 16 EPCA • A. Chadjiioannidis, Archaeologist of the 9th EBA • Ms. K. Mylona, guard of antiquities of the 17 EBA • Mr. Y. Chorozidis and D. Penoglidis, guards of antiquities of the 30th EPCA • Mr P.Tsokas, Archaeologist of the 16th EBA • Mr. P. Chrissostomou, Archaeologist of the 29th EPCA • Ms. A. Skreka and Ch. Sariyiannidou, Archaeologists of the 16 EBA • Ms. E. Naoum, Archaeologist of the 29th EPCA • Mr. N. Pandazopoulos, guard of antiquities of the 29th EPCA 15.05.12 16.05.12 17.05.12 th th th Notes: ECPA stands for „Ephorate of Prehistoric and Classical Antiquities“ and is an administrative unit of the Greek Ministry of Culture responsible for a specific area (usually one or two prefectures). Field notes of these surveys, anecdotal evidence and detail of any discussions with the Ephorate representatives are documented in the report ‘ESIA Greece – Supplementary Cultural Heritage Field Visit with Authorities Report (June 2012)’. 3 3.1 OUTCOMES OF ENGAGEMENT Summary of Outcomes of Phase 4 Engagement during ESIA preparation During stakeholder engagement in the ESIA preparation stage, issues raised during the previous phases were reiterated, especially those relating to land acquisition and compensation, economic development and employment. The impact of the Project on landowners and natural resources were also stressed as key concerns. The main issues raised during the meetings were the following: Impact on Land, Properties and Livelihoods and Compensation: Impacts to land based livelihoods and the relevant compensation were key areas of concern, especially in Pella, Skydra, Naousa and Eordea where there is a high level of agricultural productivity such as the cultivation of peaches on the pipeline route. Annual crops are also of particular importance in Eordea towards the western part of the route. Additionally, concerns regarding potential depreciation of land value and restrictions to building were raised. TAP Project Detail and Pipeline Route: Consultees sought information about the detail of the Project including depth of the pipeline, construction and the exact route. A diverse range of questions were raised to gain further clarity on the Project, particularly around the technical aspects of the pipeline, including construction. Other questions were regarding the pipeline routing and location of block valve stations. The technical standards that the Project would apply (Greek/EU/international) were also a common area of interest. Management of Impacts: Questions were raised with regard to management of a range of impacts. Examples include: irrigation, in particular boreholes which are no longer allowed to be constructed or require permits (which in former times was not required); Reinstatement of land especially in areas of high agricultural productivity and fertile soil; Forest degradation and how this would impact the natural environment in terms of oxygen levels and scenery; noise and disturbance, potential contamination of water resources; disruption to access routes; interaction with local development areas and cultural heritage. Project Benefits: Many stakeholders asked questions with regard to benefits that they might receive from the Project, in particular funds gained from the Project which could be distributed to the local community and investments made by TAP AG. The possibility of access to gas and employment were seen as benefits the “Project should provide”, and consultees felt that if these opportunities were not available, there would consequently be no benefits. Health & Safety: There was some concern with regard to public health and safety implications of the gas pipeline, especially with regard to the pressure of gas and how the block valve stations would prevent gas explosions and leaks. Consultees were also concerned about how the pipeline would be managed in the case of an emergency. Furthermore, some concerns were raised regarding old machinery, including deep ploughs used for cultivation, which work to a depth of 60 - 70 cm. Stakeholder Engagement Process and the Role of the Government: Stakeholders were very keen to remain informed about the Project and be able to provide further views as Project plans develop. However, there were strong feelings of resentment and scepticism towards both the government and TAP AG which stems from past experiences with other development projects. The current economic situation is also having its impact on the general feeling of anxiety and negativity among local population. The results of the consultation evaluation process indicate that stakeholders were generally satisfied with the consultation process and were able to ask all the questions that they wanted to ask. Nonetheless, stakeholders were keen to be provided with more detail regarding the exact route and specific land plots that would be affected by the Project in order to establish whether they would be compensated. 3.2 Outcomes of the Traffic and Cultural Heritage Surveys and Consultations During the traffic surveys and related consultations, no issues were raised by road agencies or traffic police highlighting concerns regarding the impact of the TAP Project. However, key areas of interest are highlighted below in Table 3-1. Table 3-1 Location Key Issues Raised During the Traffic Survey Issue Description Thermi Thessaloniki • • • Nea Chalkidona, Central Macedonia • • • Nea Malgara, Central Macedonia • • Kastoria, Central Macedonia • • • • Pella • • • • • Ptolemaida • • • • Segments of the road from Thessaloniki to the West will serve many of the transportation needs of the TAP Project. Capacity of the road is more than adequate for the current traffic volumes. No planned developments. During winter in some segments there may be problems in case of heavy snowfall or adverse weather conditions, but there are emergency crews that keep the road always open. In a series of tunnels (in sections from Grevena towards Igoumenitsa) there is not still a permit for entering vehicles carrying hazardous materials (they have to use alternative roads). Main Proposed Follow-up Stakeholder(s) Action Who Raised The Issue Egnatia Odossa An official application requesting statistical data regarding traffic accidents is required. TAP AG to follow-up. TAP AG to obtain risk assessment studies for large transportations in the area. Capacity of roads is adequate for the current traffic volumes. Planned road (vertical to Egnatia Motorway) to bypass Chalkidona and reach Gianitsa to be connected to the new road to Edessa. East-West traffic volumes on main road are high. Junction only serves as entrance/exit to Valtochori village, which is a small village with very limited traffic throughout the year. National Road Highway (e.g. Patra – Athina Thessaloniki National Highway, from Thessaloniki to Kleidi segment) is of adequate capacity to receive all current traffic load without any problem. No planned developments. Traffic Police – Department of Nea Chalkidona Traffic Police – Department of Highways, An official application requesting statistical data regarding traffic accidents is required. TAP AG to folllow-up. Capacity of roads is adequate for the current traffic volumes. No planned developments. Some problems could be encountered during summer period at National Road Kastoria –Nestorio axis due to increased traffic by tourists. There has been a decrease in traffic volumes the last 2 years due to the economic crisis (e.g. gasoline rate reached nowadays almost 2 euros/litre) giving a relief to traffic conditions at major Highways. Capacity of the road is adequate for the current traffic volumes. No planned developments. Faults in some sections of the asphalt layer as a result of heavy loads traffic (e.g. fruits production transport) increasing the risk for accidents in those section. Major problems created due to the fact that (although it is a National Road network) traffic has to pass through Rizon which is a residential area. During summer period traffic volume is relatively high due to transport activities of the fruits producers, especially the segment of the road the south of Loutrochori village. Capacity of roads in the survey area are adequate for the current traffic volumes. No planned developments. No specific traffic problems, with the exception of the Ptolemaida South junction which is the main entrance/exit for city of Ptolemaida and therefore experiences increased traffic levels. Traffic Police – Department of Kastoria An official application requesting statistical data regarding traffic accidents is required. TAP AG to folllow-up. Traffic Police – Department of Pella An official application requesting statistical data regarding traffic accidents is required. TAP AG to folllow-up. An official application requesting statistical data regarding traffic accidents is required. TAP AG to follow-up. TAP AG to obtain plan for the new road to be built in Chalkidona. Traffic Police – Department of Ptolemaida Information required regarding bulk loads/traffic movement to the PPC Power Generation Facility. The issues raised by the Ephorates are summarized in Table 3-2. Table 3-2 Key Issues Raised During the Cultural Heritage Survey Location Issue Description Main Stakeholder(s) Proposed FollowWho Raised The up Action Issue Ptolemaida • Contemporary Church (Church of Assumption) within the centreline of the pipeline route in the area of Ptolemaida. Ephorates Representatives • Opposite the church, approx. 300 metres to the south-west of the centreline, there is a wooded hill named Kouri, where a Neolithic site has been excavated. TAP AG to refine route to avoid structure and maintain safe stand-off distance • Church of the Assumption in Foufas. • Site of a byzantine aqueduct. The site lies outside the 500 m. buffer zone. Ephorates Representatives No specific followup action by TAP AG required at this stage • The mountain edge to the north-east of the Ephorates village, in which the contemporary monastery of Representatives Gregorios Palamas and the Church of Ayios Rafail are located, is regarded an archaeologically sensitive area. No specific followup action by TAP AG required at this stage. • A coin hoard was reported In Mesagros. • There have been a number of excavations of a byzantine cemetery in the Ampelia area to the south of Filotas. This site was included in the baseline study of the route refinement excercise. • In the Variko area, on Profitis Elias hill, possibly within 1 km from the pipeline, there are indications of a fortification wall. Variko has been relocated to the current site; therefore the older settlement should be sought in the vicinity. Foufas Antigonos (Florina prefecture) • Remains of stone bridge possibly from the Roman period reported in Verga, Vassiliada area. Ephorates Representatives • Remains of ancient Via Egnatia located on the right of Giole stream. Mesolithic chance finds are also located along this stream. No specific followup action by TAP AG required at this stage Korissos • Land redistribution has taken place in this area, Ephorates Representatives therefore it is possible that it is the old field boundaries and road systems that show on the satellite images. No specific followup action by TAP AG required at this stage Krepeni • Along the valley just below Aghios Nikolaos Kremastos pottery scatters have been traced. Ephorates Representatives • Remains of ancient Via Egnatia are believed to be located on the right of the Giole stream. Mesolithic chance findings are also reported along this stream. No specific followup action by TAP AG required at this stage Verga Militsa • Indications of pottery kilns. The whole area Ephorates between Aghios Dimitrios and Aghia Paraskevi in Representatives Militsa is of high archaeological potential. Poria to Paravella area • The whole area considered archaeologically sensitive Ephorates Representatives No specific followup action by TAP AG required at this stage No specific followup action by TAP AG required at this stage For the time being, no specific follow-up activities for TAP AG were flagged by the Ephorates. They will provide their appraisal results in the course of their interagency consultation for the PEIA appraisal to the Ministry of Culture/Large Projects Department and the Ministry of Environment being in charge of the PEIA decision. The PEIA appraisal will inform TAP AG on any required activities. 4 EVALUATION OF ENGAGEMENT An evaluation of engagement was carried out at the end of each local level meeting which was designed to be; • free of manipulation, interference, coercion, and intimidation, and • conducted on the basis of timely, relevant, understandable and accessible information in a culturally appropriate format. During ESIA engagement, there were three ways in which consultation was evaluated: 1. Orally in which consultees were asked their opinion about the quality of the meetings. 2. A written questionnaire survey which required consultees to rate the quality of the meetings. 3. A participatory approach which required consultees to rate the quality of consultation by placing stickers on a poster containing 3 questions as shown in Box 4-1. Box 4-1 Poster Evaluation Questions 1. Has the meeting been organised in a way to facilitate your attendance? 2. Were you able to ask the questions that you wanted? 3. Were you satisfied with the answers provided? /was the information provided clear and sufficient? The options to respond to each question were ‘Yes’, ‘No’ and ‘Partially’. (Note: Consultees were informed that ‘Partially’ referred to an aspect of the meeting that they were not 100% satisfied with. For example, the meeting was well organised and presentation well articulated, but responses to questions were not complete, such as value of compensation or exact plots of land affected.) Picture: Evaluation of consultation in Korissos (Kastoria municipality, Western Macedonia) The results of the oral and poster evaluation suggest that overall people were satisfied with the way in which meetings were organised to accommodate attendance. However in some cases where attendance was low, it was mentioned that members of the community were still in field and that a different time should have been arranged to maximise attendance. Since ESIA engagement was carried out prior to the ESIA assessment, the level of detail that was provided to stakeholders regarding the TAP Project was limited. However, further information will be disclosed during the next phase of engagement, Phase 5 - ESIA Finalisation and Disclosure, which will provide communities with more clarity about the Project, particularly in relation to the pipeline route, loss of land and impacts and mitigation measures and opportunities. TAP AG will continue to monitor and evaluate engagement activities throughout the Project to maximise effectiveness.