131iii_BOD_MH-Land-Sale-reduction-Board-November-2013

advertisement

Report to the Meeting of the Oxford Health NHS Foundation Trust

Board of Directors

For Approval

27 November 2013

MANOR HOUSE LAND SALE

Executive Summary

This paper provides an update on the status of the Tindall and Manor House land sale and considers the impact of retaining part of the Manor House site previously identified for disposal. This proposal is supported by the Finance and Investment Committee.

The Manor House business case was approved on the basis that the surplus site released as a result of the development would be disposed off generating a capital receipt of c.

£6.4m. This valuation was based upon the achievement of the following receipts for each site:-

Tindall £2.5 million

Manor House £3.9 million

The FY14-FY18 capital programme was approved on the basis that this funding was available to support capital investment.

Discussions at the Finance and Investment Committee (FIC) and Executive Director meetings have indicated that it could now be strategically advantageous for the Trust to retain part of the land on which the Sue Nicholls building is located rather than dispose of it as previously planned.

Retaining this part of the site previously identified for disposal would result in the loss of capital receipt of c. £2.15m, and would therefore require alternative capital receipt(s) to be identified or a reduction in capital expenditure of the same value. The capital programme has been reviewed to assess the potential for a reduction in capital expenditure in FY14-FY16 and opportunities have been identified for reduced investment to mitigate the loss of capital receipt. The proposal would result in an improved discounted cashflow, improved cash balances and have a neutral impact on the Trust’s financial risk rating.

Recommendation

The Finance & Investment Committee recommends to the Board of Directors that approval is given to retaining part of the Manor House site previously planned for disposal (as defined in this paper), subject to the loss of capital receipt being offset by a reduction in capital expenditure in FY14-FY16 and that the scope of the Manor House Project be amended accordingly to reflect this change on the basis that the underlying financial business case remains valid.

Author and title: Paul Dodd, Deputy Director of Finance

Claire Dalley, Director of Estates

Lead Executive Director: Mike McEnaney , Finance Director

[ A risk assessment has been undertaken around the legal issues that this paper presents and there are no issues that need to be referred to the Trust Solicitors.

]

Manor House Land Sale

Introduction

This paper provides an update on the status of the Manor House land sale and considers the impact of retaining part of the Manor House site previously identified for disposal. This proposal has been considered by the Capital Programme Board in October and November

2013 and is recommended by the Finance and Investment Committee (FIC) for approval by the Board of Directors.

Background

The Manor House business case was approved by the FIC and Board of Directors on the basis that the surplus site released as a result of the development would be disposed off generating a capital receipt of c. £6.4m, based upon obtaining the receipts identified below:

Tindall £2.5 million

Manor House £3.9 million

The FY14-FY18 capital programme was approved on the basis that this funding was available to support capital investment.

Discussions at FIC and Executive Director meetings have indicated that it could now be strategically advantageous for the Trust to retain part of the land on which the Sue Nicholls building is located (and immediately adjacent to) rather than dispose of it as previously planned.

Current Status and Options

BNP Paribas have been appointed to progress the sale of the Manor and Tindal sites, and a programme for the disposal, which reflects the potential to retain part of the Manor site is being developed. As part of their appointment BNP Paribas provided a market valuation of the sites. This valuation is substantially lower than the £6.4 million previously obtained and incorporated within the Whiteleaf Business Case. BNP Paribas identified that the original land value could be achieved if the Local authority reduced the required affordable housing requirement and section 106 contributions. The Trust has written to the Local Authority requesting that this be considered, and requesting a meeting to discuss. We await a response from the Planning Officer assigned to this case.

The District Valuer has been commissioned to review the land and provide a reasoned assessment of the market value, to provide a firm current position to support our discussions with the Local Authority. BNP Paribas have also been requested to provide to provide further evidence and examples to support our position.

As noted above, it is suggested that the retention of either part or all of the old Manor Site would be of a strategic benefit for the Trust. There exists the potential for the Trust to develop community care services within Buckinghamshire, and the old Manor Site is ideally placed to provide a Community Hospital base to support these services.

It is suggested that the Trust retain the land identified as area 2 (coloured pink) on the plan below. We have however asked the District Valuer to review the most suitable place to

“divide” the Manor site to enable us to receive best value from the sale of the unretained

area (coloured yellow)

The potential impact on the receipts anticipated by the Whiteleaf Development Business case of retaining this area of the site is summarised below:-

Business case predicted income

Estimated best case predicted income

Partial Retention of land (best predicted income) (area 2)

£2.85 million £2.85 million Sale of Tindall

Site

£2.5 million

Sale of Manor

Site

Total income

£4 million

£6.5 million

£3.58 million

6.43 million

Impact on planned income (reduction)

£1.5 million

£4.35 million

£2.15 million

Financial Implications

The approved capital programme for FY14-FY18 provides for capital investment of £65.6m funded as follows:

£m

CAPITAL PROGRAMME

PLAN Forecast Forecast Forecast Forecast TOTAL

FY14 FY15 FY16 FY17 FY18

29.5

9.1

9.0

9.0

9.0

65.6

ASSET SALES

OPERATING CASH FLOW

LOAN DRAWN FY13

PDC RECEIVED

CASH BALANCES b/fwd

12.7

9.2

4.3

0.7

2.6

-

9.1

-

-

-

-

9.0

-

-

-

-

9.0

-

-

-

-

9.0

-

-

-

12.7

45.3

4.3

0.7

2.6

TOTAL SOURCE OF FUNDS 29.5

9.1

9.0

9.0

9.0

65.6

The capital programme was underpinned by £12.7m of capital receipts, comprising Manor

House £6.4m and Park Hospital £6.3m (the latter was received in September 2013).

Retaining part of the Manor House land previously identified for disposal, and accommodating the potential maximum reduction in market value would result in the loss of capital receipt of c. £ 2.15 m as detailed above.

The capital programme has been reviewed to assess the potential for reduced capital expenditure and the following opportunities have been identified for reduced investment due to under-spends on existing schemes and reduced investment on planned schemes:

Scheme

Manor House

Value

£000

Reason

500 Projected under-spend/savings inc. SSB

(Peach Tree House)

Manor House

Eating Disorders

Windrush

300 Capex avoided through retention of land

1,100 Proposed scheme removed

300 Reduced scope/proposed investment

Marlborough House Reception

Inpatient wards

ICT schemes

Medical equipment

250 Reduced scope/proposed investment

790 Refocus investment on compliance risks

335 Various

100 Replacement programme not yet established

Various Estates schemes

Unallocated contingency

Total

273 Under-spends

259 Contingency removed

4,207

The revised FY14-FY18 capital programme is attached, including details of the proposed changes. The reduced capital expenditure would avoid capital charges of c. £300k pa.

A discounted casflow analysis has been undertaken to compare the two options: (a) Current

Plan – sale all of the land and use the receipt for capital expenditure purposes (b) Proposed

Plan – retain part of the land resulting in a reduced capital receipt off-set by reduced capital expenditure and capital charges.

The proposed option to retain part of the land results in a benefit to the calculated Net

Present Value (NPV) as shown in the following tables:

Current Plan - full receipt

Capital Receipt

Capital Expenditure

Net cash outflow

Discount Factor @ 3.5%

NPV

Year

£m

£m

£m

0

-29.5

-29.5

1.00

-29.5

1

6.4

-9.1

-2.7

0.9662

-2.6

2

-9.0

-9.0

0.9335

-8.4

3 4

-9.0

-9.0

0.9019

-8.1

-9.0

-9.0

0.8714

-7.8

5

-9.0

-9.0

0.842

-7.6

Total

6.4

-74.6

-68.2

-64.0

Proposed Plan - partial receipt

Capital Receipt

Capital Expenditure

Capital Charges reduction

Net cash outflow

Discount Factor @ 3.5%

Year

£m

£m

£m

0

-27.5

0.1

-27.4

1.00

1

4.3

-6.9

0.1

-2.55

0.9662

2

-9.0

0.1

-8.9

0.9335

3

-9.0

-9

0.9019

4

-9.0

-9

0.8714

5

-9.0

-9

0.842

Total

4.3

-70.4

0.3

-65.85

NPV £m -27.4

-2.5

-8.3

-8.1

-7.8

-7.6

-61.7

In addition, the proposed option results in a positive impact on cash balances across FY14-

FY16 as shown below, due to the reduction in capital expenditure being greater than the reduction in capital receipt:

Cash Balance @ 31 March

Current Plan

Changes:

- capital receipt slippage

- reduced capital receipt

- reduced capex

- capex slippage

- reduced capital charges

- working capital management

- cash gain in FY15

2014

18.8

-6.4

2.0

1.0

0.1

3.3

2015

18.8

6.4

-2.1

2.2

-1.0

0.1

-3.3

2016

19.4

0.1

2.3

Proposed Plan 18.8

21.1

21.8

The proposed option has a neutral impact on the Trust’s financial risk rating, remaining at ‘3’ under both options.

Recommendation

The Finance & Investment Committee recommends to the Board of Directors that approval is given to retaining part of the Manor House site previously planned for disposal (as defined in this paper), subject to the loss of capital receipt being offset by a reduction in capital expenditure in FY14-FY16 and that the scope of the Manor House Project be amended accordingly to reflect this change on the basis that the underlying financial business case remains valid.

Download