Internal Audit Follow-Up Report Construction/Maintenance Inspection TxDOT Audit Office Construction/Maintenance Inspection TxDOT Internal Audit – MAP Follow-Up Objective Assess the status of corrective actions for high risk Management Action Plans (MAPs) previously communicated in Construction/Maintenance Inspection Audit Report issued March 11, 2013. Summary Results Testing included an evaluation of 11 MAPs to determine if corrective actions were implemented as agreed. MAP Status 7 Closed 4 Open 1 New Comments Corrective actions have been completed. Corrective actions that require completion to address identified risks from the original audit report. Corrective actions that were newly identified and further actions are necessary to properly address the remaining risks. Scope The audit was performed by Alma Alvarez, Anuradha Masand, and Vivian Cohn (Engagement Lead). The audit was conducted during the period from July 9, 2013, to July 31, 2013. Methodology The audit work included the following: Reviewing Construction Contract Administration Manual (CCAM), construction meeting minutes, and Houston District Full-time Employee (FTE) Survey Testing Site Manager’s segregation of duties controls for a sample of employees Testing a sample of Daily Work Reports and Storm Water Pollution Prevention Plan (SW3P) forms for consistency and accuracy Testing a sample of Storm Water Pollution Prevention Plan (SW3P) forms for timely corrective action Testing a sample of employees for compliance with mandatory training requirements Background This report was prepared for the Transportation Commission, TxDOT Administration and Management. The report presents the results of the Construction/Maintenance Inspection Follow-Up Audit Report which was conducted as part of the Fiscal Year 2013 Audit Plan. The Construction Division is responsible for overseeing all department construction projects and for providing support to districts with construction projects. The Construction Division provides administrative oversight for all department construction contracts. The division also provides general guidance to districts by publishing statewide policies and procedures and August 22, 2013 2 Construction/Maintenance Inspection TxDOT Internal Audit – MAP Follow-Up consults on project management, administration, inspection, and testing for each construction project during its life cycle. We conducted this follow-up engagement in accordance with Generally Accepted Government Auditing Standards and in conformance with the International Standards for the Professional Practice of Internal Auditing. Those standards require that we plan and perform the engagement to obtain sufficient, appropriate evidence to provide a reasonable basis for our conclusions based on our engagement objectives. We believe that the evidence obtained provides a reasonable basis for our conclusions based on our engagement objectives. August 22, 2013 3 Construction/Maintenance Inspection TxDOT Internal Audit – MAP Follow-Up Detailed MAP Follow-Up Report and Status MAP Status: Open Corrective actions that require completion to address identified risks from the original audit report. Original Audit Finding Number 1: Segregation of Duties MAP Owner: John Obr, Construction Division Director Roxana Garcia-Zinsmeyer, Construction Division Section Director MAP 1.2 – The Estimates Manual is obsolete. CST is currently working to incorporate any current policy/procedures found in the Estimate Manual into the CCAM or SM Contract Admin Manual. Original Completion Date: January 15, 2013 Revised Completion Date: January 15, 2014 Original Audit Finding Number 3: Untimely Correction of Storms Water Pollution Prevention Program (SW3P) Deficiencies MAP Owner: Eliza Paul, Houston District Construction Director Michael Hobbs, Fort Bend/Waller Assistant Area Engineer Jesse Garcia, West Central Harris Area Engineer MAP 3.1 – The contractor was made aware of their contract responsibilities related to SW3P at an informal partnering meeting and then by formal letter. The area office will monitor the contractor’s (and sub-contractor’s) performance and insure the corrections are performed according to the specifications for that job. The District Construction Office will meet with the area office personnel to discuss this finding and also conduct interim projects inspections to target the SW3P requirements and see if all deficiencies identified on Form 2118 are addressed. The monitoring is currently being done by the project manager or a project inspector in the area offices. The interim inspections will be conducted in fourth quarter of calendar year 2012. Original Completion Date: December 31, 2012 Revised Completion Date: November 15, 2013 MAP 3.2 – The SW3P inspections are being conducted by a consultant engineer whose experience using TxDOT Form 2118 is not adequate. The timeliness and neatness of the inspection were acceptable, but the findings were rarely removed and were actually carried over to the new inspection report without corrections being noted. The area office has provided the consultant additional guidance and will monitor the entries to insure the deficiencies are corrected and closed out. The District Construction Office will meet with the area office personnel to discuss this finding August 22, 2013 4 Construction/Maintenance Inspection TxDOT Internal Audit – MAP Follow-Up and also conduct interim project inspections to target the SW3P requirements and see if all deficiencies identified on Form 2118 are addressed. The monitoring of the noted consultant engineer’s reporting is currently being done by the project manager in the area offices. The interim inspections will be conducted in third or fourth quarter of calendar year 2012. Original Completion Date: December 31, 2012 Revised Completion Date: November 15, 2013 Original Audit Finding Number 5: Major Items of Work MAP Owner: Mike Alford, PE, Houston District Engineer MAP 5.1 –Long term actions Development of new consultant contracts (expected in April of 2013) and additional hiring of State employees (also spring or early summer 2013). Original Completion Date: June 1, 2013 Revised Completion Date: December 15, 2013 August 22, 2013 5 Construction/Maintenance Inspection TxDOT Internal Audit – MAP Follow-Up MAP Status: New Corrective actions that were newly identified and further actions are necessary to properly address remaining risks. Original Audit Finding Number 4: Mandatory Training for Inspectors FMAP Owner: Darwin Myers, Dallas District Ellis-Navarro County Area Engineer Vicki Zoch, Dallas District Management Analyst FMAP 4.1 – Dallas District Ensure identified employees complete the training. Develop a Standard Operating Procedure (SOP) that outlines a process for each manager to check all required training classes on a monthly basis to ensure compliance with our training program. Completion Date: August15, 2013 Closing Comments The results of this MAP Follow-Up engagement were discussed with/provided to Construction Division, Human Resources Division, Corpus Christi District, Dallas District, Houston District, Tyler District, and Waco District on August 8, 2013. The audit team appreciates the cooperation and assistance received during this engagement. August 22, 2013 6