Report of Climate Change Officer To Corporate Director of Housing and Environment For Delegated Decision On 19 June 2014 Approval of Civic Centre Heating and Carbon Reduction Projects 1. SUMMARY 1.1 The purpose of this report is to approve the funding source for a heating replacement project at the Civic Centre that will enable the Council to reduce its energy use and carbon dioxide emissions, plus will ensure the continued use of the building and a more robust and flexible energy supply. 1.2 Key Decision – This is a key decision as the proposed projects meet the capital expenditure threshold (£250,000), therefore it is contained in the Register of Key Decisions. 2. RECOMMENDATION To be resolved by the Corporate Director of Housing and Environment (i) That capital funding from the Council’s Energy Efficiency Budget be used to replace the current coal fired heating at the Civic Centre with more energy efficient alternative forms of heating. 3. BACKGROUND 3.1 The Government has committed to reducing carbon dioxide emissions by 34% by 2020 and by 80% by 2050 (against a 1990 baseline), and to a target of 20% of UK energy being from renewable sources by 2020. In all climate and energy policy documents published by the Government, energy efficiency and increased use of renewable energy are seen as central to achieving carbon emissions reduction aims. Local government is a major consumer of energy and as a community and business leader it must set a good example and take a leading role in contributing to the achievement of these targets. 3.2 The Council signed the Climate Local Declaration in June 2013 and has been working towards an agreed carbon reduction target of 35% from 2008/09 to 2013/14 through its Carbon Management Plan 2011. The proposed project will make a contribution to achieving this target and future targets to be set in the summer of 2014. 3.3 The Council set aside resources to fund energy efficiency projects with a number of projects being undertaken since the Carbon Management Plan was set up in 2011 and any unspent resources have been carried forward from year to year. At its meeting on 4 March 2014, the Council approved the carry forward of £323,000 (this was split between the solar panel scheme [£180,000] and “other carbon schemes”, [£143,000]) for future schemes. When schemes are developed, the projects are individually assessed on their merits and overall cost and carbon dioxide savings compared against payback period to ensure those initiatives with the highest return on investment and/or carbon dioxide savings are prioritised. In 2010, delegated authority was also given to the Corporate Director for Housing, Operational and Property Services (now Corporate Director for Housing and Environment) to allow budgets to be approved at Capital Programme Board meetings to progress energy efficiency projects. 3.4 The Civic Centre is the final corporate building to be heated by coal, therefore in order to demonstrate continued action to tackle climate change, these boilers have now been prioritised for replacement. A direct replacement of the coal boilers with gas fired boilers have been estimated to reduce CO2 emissions by at least 40% with an additional saving coming from the offset electricity that will be created by an additional gas fired Combined Heat and Power (CHP) system. Approval to proceed with this project was given at a Capital Programme Board meeting on 13 May 2014. The Council also needs to prioritise the resources that it has available, therefore the decision was taken not to progress with the Solar Panel project and to use that budget for the work required to replace the coal fired boilers with gas fired boilers. 3.5 Installing conventional boilers would ensure compatibility with the existing distribution systems in terms of circulation temperatures, and ensure a reliable and robust installation for what is an important ‘hub’ building. This will also help to deal with concerns over heating supply stability, as the boilers are 28 years old and past their expected lifespan. The boilers are having to regularly be repaired as they are leaking, (six major repairs, on both boilers have been required in the last six months) and there are grave concerns from the Council’s Senior Facilities Maintenance Technician and Cofely (who run the maintenance contract on the boilers) about the boiler integrity, increased costs for maintenance, increased difficulty in locating spare parts and the reduced efficiency of the current system. 3.6 As the estimated costs for this work exceed £250,000, this project has been placed on the Register of Key Decisions for approval separately from the delegated authority approved in 2010. A further report will be prepared to allow the funds from the Carbon Schemes – Solar Panel budget (£180,000) to be vired to the unallocated Other Carbon Schemes budget (currently £143,000) to allow this work to be progressed. 4. OPTIONS AVAILABLE 4.1 The recommended option is to approve the use of the Council’s Energy Efficiency Budget to replace the current coal fired boilers at the Civic Centre. 4.2 Do nothing – this is not a viable option as it is not in keeping with the council’s position as a signatory of the Climate Local Declaration, it will not address the concerns over climate change or the need to address the Government targets over carbon dioxide reduction. It will also not address the Council’s energy and resource use issues and will not deal with the concerns over the continued use of the Civic Centre as a main Council asset. 6. RISK ASSESSMENT OF RECOMMENDATIONS Risk Risk Assessment Risk Level Risk Management What is the risk e.g. Explanation of the risk High/Medi um How the risk is to be mitigated. Reputation The failure to meet Climate Local and Government targets on Climate change will damage the Council’s green credentials Med The setting of a future challenging target for CO2 reduction and the continuation of the carbon management plan through the installation of more energy efficient heating systems. Timescales There is at least a six month lead in time for this project, because of the need to design and procure a suitable gas supply to the Civic Centre, on top of the heating system Med. Council failing to achieve its own targets for CO2 reduction The Council failing to meet its own CO2 reduction targets would be costly and would damage the Council’s green credentials Medium This project will be individually monitored against its own specific risks (contained within the Business Case submitted to CMT on 29 April 2014) by the Climate Change Officer and the Capital Programme Board. The board has already been made aware of a potential requirement for a contingency plan if the heating cannot be replaced before the current boilers become obsolete. The project will help the Council to cut its current CO2 emissions from the Civic Centre by at least 40% and make a dramatic impact on the Council’s emissions as a whole. 7. ALIGNMENT TO COUNCIL PRIORITIES 7.1 This will align with Mansfield Sustainable Community Strategy and the climate change agenda. The reduction in energy use will reduce emissions of all other pollutants as well as reducing CO2 emissions and this target will therefore contribute to the council’s own priority of a Clean, Green and Pleasant Environment. 8. IMPLICATIONS (a) Relevant Legislation – The Sustainable Energy Act 2003 – makes provision for the development and promotion of a sustainable energy policy in the United Kingdom. The Climate Change and Sustainable Energy Act 2006 aimed at encouraging energy efficiency and micro-generation and reducing fuel poverty. Part 1, section 2 (1) of The Local Government Act 2000 enables the council to do anything which it considers is likely to achieve economic, social, and environmental wellbeing of its area. In determining whether, or how to exercise the power under subsection (1), a local authority must have regard to their sustainable community strategy. One of the priorities for action within Mansfield’s community strategy is to tackle Climate Change and reduce carbon emissions across the District. This project therefore helps to achieve economic and environmental improvements, through reduced emissions and improved efficiency for the Council and helps towards mitigation against the predicted effects of Climate Change and other environmental impacts. (b) Human Rights – No implication. (c) Equality and Diversity – Any contractor engaged on work which is generated by this agenda will be required to show commitment to the council’s equality and diversity standards. (d) Climate change and environmental sustainability – Implicit in the report (e) Crime and Disorder – No implication (f) Budget /Resource – There is £323,000 remaining in the Energy Efficiency budget which is sufficient to undertake the heating work required. 9. COMMENTS OF STATUTORY OFFICERS (a) Head of Paid Service – No comments (b) Monitoring Officer – No specific comments. (c) Section 151 Officer – The resources within the Energy Efficiency Fund is sufficient to meet the estimated costs of these works. 10. CONSULTATION None 11. BACKGROUND PAPERS None Report Author Designation Telephone E-mail - Helen Bartle Climate Change Officer 463812 hbartle@mansfield.gov.uk