The Potential Synergy between Noise Mitigation and Weatherization for the Green Line Extension Prepared by Ian Adelman, Meg Howard, and Doug Piatt The Potential Synergy between Noise Mitigation and Weatherization for the Green Line Extension Prepared by Ian Adelman, Meg Howard, and Doug Piatt Executive Summary The Green Line Extension through Somerville will create noise impacts to many residential and institutional buildings along the corridor. MassDOT has proposed initial plans for a noise mitigation project intended to adequately mitigate the noise impacts in accordance with the Federal Transit Administration guidelines. This report shows that many of the affected residences are in Environmental Justice areas as defined by Massachusetts. We also show that many of the residences were constructed before 1900 and therefore likely to be very energy inefficient. In addition to impacting these areas with increased noise, there is concern the Green Line Extension may result in the displacement of many of the low-income residents that the project intended to serve. We looked closely at the proposed noise mitigation measures for the Green Line Extension, various other noise mitigation projects, and spoke with noise mitigation experts at Jones Payne Group. Our research enabled us to better understand the synergy between noise mitigation and weatherization. Many of the treatments are identical; many noise treatments provide energy benefits; and, many weatherization treatments provide noise benefits. We also reviewed the FTA’s guidelines for noise mitigation and various noise mitigation projects and proposals in Massachusetts to understand the precedent set for MBTA and MassDOT transit projects. Massachusetts’ interpretation and implementation of a noise mitigation project is to spend at least two percent of hard construction costs, up to $5,000 per residence per decibel of mitigation (up to $30,000 per residence) and to allow noise mitigation funds to be spent on mitigations that do not provide noise reductions. The noise mitigation plan for the Green Line Extension has not been formalized, but from what has been drafted it does not appear to be following this precedent. In addition to being equitable, MassDOT should maintain its standard for noise mitigation plans for the Green Line Extension because it can be used to combat displacement of low income and racial minority residents. A plan that recognizes the sound insulation and weatherization synergy and provides maximum energy benefits for residences will decrease living costs and improve quality of life while providing adequate noise mitigation. A plan that is substandard and ignores energy benefits will be inequitable and will exacerbate displacement. Introduction The extension of the Green Line through Somerville will cause noise impacts to many buildings along the corridor. The Final Environmental Impact Report identified 164 homes and businesses that will receive noise mitigation measures as part of the cost of the Green Line Extension. For many of the homes and businesses along the route, noise mitigation will be in the form of a noise barrier. In addition to or in place of the noise barriers several buildings will receive sound insulation treatments. Many of the impacted buildings were built at the turn of the century, are likely to be energy inefficient and are located in environmental justice areas. The noise barriers will be a crucial step to ensuring that outdoor space, like this garden below, remains useable. Sound insulation treatments have the potential benefit of providing weatherization improvements to the affected areas, especially if sound treatments are done with weatherization taken into consideration. This will save energy and reduce utility bills for these residents while still providing adequate noise mitigation. This report provides maps of the existing housing and environmental justice conditions overlaid by the impacted buildings. It compares weatherization and sound insulation measures, outlines available weatherization funding and reviews other noise mitigation projects. From this review and analysis we conclude that a noise mitigation project for the Green Line Extension informed by the synergy between sound insulation and weatherization will prevent displacement by reducing energy costs and providing adequate noise mitigation. Where as, a noise mitigation project that ignores the synergy will disproportionately impact low income and minority residents and increase displacement. Proposed Noise Impacts and Mitigation for the Green Line Extension The Green Line will be a new source of noise impacts along the corridor. The project will cause additional noise impacts by relocating the commuter rail tracks in some places by up to 18 feet (FEIR, 7-13). Future noise levels along the west side of the tracks are projected to generally increase by one to two decibels. In some locations, however, the noise increases will be higher (five decibels at the Alston Street near Cross Street) (FEIR, 7-14). Any increase in noise levels along the tracks may be considered as moderate or severe impacts because of the already high noise levels. MassDOT and MBTA estimate that the extension would expose 121 residential buildings to moderate noise levels and 43 residential buildings to severe noise levels. In addition to the residential buildings, Tufts Science and Technology Center, Outside the Line Artist’s Studio and Bacon Hall at Tufts University will be impacted by moderate noise levels and Walnut Street Center will be impacted with severe noise levels (FEIR, 7-14). (See the included maps for details on location and level of impact) MasDOT proposes to “mitigate for both moderate and severe noise impacts wherever feasible and wherever noise levels are above 65 dBA” (FEIR, 8-8). “Noise mitigation including noise barriers and potential sound insulation treatments would be feasible, reasonable and effective in mitigation of all potential noise impact due to the Propose Project” (FEIR, 7-15). MassDOT determined noise barriers would not be feasible or effective mitigation at the following locations: Brickbottom Lofts, Apartment complex on Pearl Street, Visiting Nurses Association, Tufts Science and Technology Center, Outside the Lines Art Studio, Tufts Bacon Hall and Walnut Street Center in Union Square (FEIR, 8-10). Sound insulation treatments to these buildings will be necessary. According the FEIR, MassDOT considers sound insulation, “costeffective if it can improve the noise reduction of the building by five decibels or more” (FEIR, 7-15). Existing Conditions Our group developed a series of maps to show the proposed Green Line corridor through Somerville. These maps highlight the houses that the Final Environmental Impact Report calls out for severe noise impact (red) or moderate noise impact (orange). The parcel for each of these houses is color coded based on the year built. This shows that many of the houses along the Green Line corridor were built before 1900. These houses most likely have minimal insulation, making them particularly vulnerable to noise pollution and cold weather. The maps also highlight the 2000 Massachusetts Environmental Justice areas. The state uses census data to define environmental justice areas by income, race, percent foreign born and percent English speaking. For more information about the definition of environmental justice communities in Massachusetts see: http://www.mass.gov/mgis/cen2000_ej.htm Finally, the maps also show the proposed station locations and the proposed locations of noise barriers. These maps are followed by a series of pictures of the current housing stock. Residences use backyards for gardening and decks. Older housing stock—with many homes built before 1900--may especially benefit from weatherization. Historic properties require special attention. “Construct noise barriers with materials and colors compatible with adjacent historic properties. Provide noise mitigation (sound insulation) for sensitive historic structures that cannot be protected using noise barriers.” -FEIR No noise barrier proposed for this location. No noise barrier proposed for this location. Standard Noise Mitigation Measures In addition to reducing the noise that the trains make, MassDOT has two basic means to reduce noise impacts for buildings along the corridor: noise barriers and building sound insulation. The table below details the proposed measures for the Green Line Extension. Most sound insulation treatments for transit projects are only concerned with the side of the building facing the tracks. Noise Mitigation Measures Sound insulation treatments Noise barriers Description Adding an extra layer of glazing to windows Sealing any holes in exterior surfaces that act as sound leaks Providing forced ventilation and air conditioning so that windows do not need to be opened Noise barriers would range from six to 12 feet tall and Barriers would block the view of the right-of-way from adjacent homes. Source: FEIR Executive Summary Page 27 Standard Weatherization Measures Many of the homes adjacent to the Green Line Extension right of way were built around the turn of the last century (see maps in the previous section) and therefore have old windows and doors and little insulation. Weatherization Measure Windows and doors Insulation Description Replace old, poor quality windows with well insulating new ones Outside doors are replaced with better insulating doors and resealed Storm doors and windows can be installed for added insulation Reseal old doors and windows Insulation, cont. Insulation injected into exterior walls to increase the R-Value Foundations can be better insulated on the outside with high-density foam board panels Attic access hatches replaced with Air sealing higher R-Value ones, or resealed Ventilation ducts are wrapped in insulation Floors above basements are insulated to improve heat efficiency in the rooms above Air sealing of any spaces that leak air in or out of the building As a part of painting or siding process, sealants and caulking are used to seal exterior gaps Expanding foam is used to seal opening where pipes penetrate floors and walls The synergy is obvious Comparing the two tables, there is an obvious overlap between weatherization and noise insulation measures. Combining noise mitigation and weatherization into one cost efficient program should work well for the Green Line Extension Project. When we met with Jones and Payne to discuss the idea, they indicated that combining the two is a growing practice that they are starting to suggest to clients. One of the most common measures they use to insulate for both noise and weather is to replace windows. New windows that work well are double or triple pane, with one of the panes having a two-layer laminate of glass that further reduces noise penetration as well as beneficial weatherizing qualities. Having good storm windows installed also makes a big difference in reducing sound and temperature transfer. The main difference between noise mitigation and weatherization is whether or not the whole house or “building envelope” is treated. A noise mitigation program would replace only windows in “line of sight” of the direction the train noise is coming from and maybe a couple others in a room so as to make all the windows match. Weatherization programs usually replace all the windows at one time so they all match and the whole building becomes better insulated. The difference between these two approaches comes down to the amount of funding available and possibly getting the building owner involved in special financing incentives that enable the purchase of the windows not included in the noise mitigation. Potential Cost for Noise Mitigation The MBTA considers it reasonable to allocate at least two percent of hard construction costs toward noise and vibration mitigation (see section on precedents for details). Assuming hard construction costs to be $763 million (80 percent of total costs), the MBTA should have allocated at least $15,264,000 for noise and vibration mitigation. The FEIR currently estimates $2.7 million will be spent for noise barriers (FEIR, 8-9), but says, “costs for sound insulation and noise barriers to be determined in the next phase.” An additional $9.4 million is allocated for vibration mitigation. Currently, the total allocation for noise and vibration mitigation would be approximately $12.1 million or approximately $3.164 million below our estimate of two percent of hard construction costs. A sound insulation program that follows the precedent set by the MBTA’s agreement with the Town of Scituate concerning the Greenbush Line (see section on precedents for details) would provide an average of $30,000 for severely impacted residences, $18,269 for moderately impacted residences and $7,000 for low impact residences. For the Green Line Extension this would add up to a total of $3,500,549 (121 moderately impacted residences and 43 severely impacted residences). If MassDOT provided estimates for the number of low impact residences this figure could be much higher. Sources of Funding for Weatherization in Somerville Weatherization has become a priority in Somerville’s effort to become more energy efficient. Some funding may be available for weatherization efforts, especially for low-income areas, this funding could be used to supplement any additional measures beyond what is necessary for noise mitigation. Funding sources include: The Menotomy Weatherization Assistance Program. Households earning below 60% of the AMI are eligible for this funding, which serves around thirty Somerville residences a year for an average of $1,437.33 per unit. State and utility incentives The Housing Rehabilitation Program: Offers qualified households zero percent loans for up to $25,000. Household earning below 80% AMI are eligible for this program. The Office of Sustainability & Environment. This city department is currently developing a program to support home energy retrofits. Current Procedure for Mass Save Weatherization Make an appointment for an energy audit. A representative stops by and changes light bulbs to compact fluorescents and gives out a programmable thermostat at no charge. Gives out brochures on the types of programs that are supported. Sets up an appointment for an insulation audit to be done. Representative for the insulation audit comes over and does tests to determine how well insulated the exterior walls and ceilings are. Rep. explains how much insulation is inside the exterior walls and if there is a need to further insulate them. A blower-door air seal test is done that measures the air leaks in and out of the building. This test uses air and or vacuum pressure to test for leaks. A written quote is mailed to the house explaining how much additional insulation will cost and how much of the cost will be covered by government programs. The methods of injecting insulation into existing walls are also reviewed. The NSTAR rebate covers $2000 worth of insulating work, the quote received for a two family house in Somerville was for $8900 Review of case studies and precedents A review of recent noise mitigation projects, mitigation agreements, an MBTA environmental consequences report and Federal guidelines establish a precedent for future noise mitigation projects in Massachusetts. The examples and guidelines suggest that funding for residential sound insulation programs should be used to provide energy benefits in addition to adequate sound insulation at the discretion of the residences. The Federal Transit Administration’s “Transit Noise and Vibration Impact Assessment” manual provides guidance for appropriate mitigation measures. It suggests that severe noise impacts should be avoided when possible, but when unavoidable severe noise impact mitigation will be incorporated into the project (FTA, p 3-11). Moderate noise impacts should be mitigated when reasonable (FTA, p 3-11) and in coordination with community input (FTA, 3-12). The document does not define reasonable cost thresholds but does offer guidance. The median cost threshold for sound barriers is $24,000 per residence. The FTA considers $25,000 to $30,000 per benefitted residence to be a reasonable cost (FTA, p 3-13). The manual also provides guidance concerning effective building insulation treatments. These include caulking and sealing gaps, installing new doors and windows that meet acoustical standards, sealing vents and ventilation openings and relocating them to a side of the building away from the noise source (FTA, p 6-43). There is no published and publicly available MBTA and MassDOT interpretation of the FTA guidance manual. However, the Blue Line noise mitigation project, the noise mitigation agreement between the MBTA and the Town of Scituate and the “Environmental Consequences Report: Noise” for the South Coast Rail project establish standard practices in Massachusetts and should be applied to the Green Line Extension. The MBTA went beyond standard sound insulation treatments for noise mitigation for the Blue Line. They extended treatments to the whole building envelope, including supplemental wall and ceiling work and upgrades to through wall air conditioners (Jones Payne, 2001). The above average treatments were intended to match noise mitigation measures for properties that were receiving noise mitigation through a MassPort program. The “Environmental Consequences Technical Report: Noise” for the South Coast Rail recommended allocating, “two percent of the hard construction costs of a project for avoidance or mitigation of noise and vibration impacts. If this sum proves insufficient to complete the NMP, then additional funds will be requested so that the entire NMP can be implemented” (EOT, p 6-2). It also stated that Measures will be considered cost-effective by EOT if the total cost of the wall or other measures is less than $30,000 per dwelling unit and the wall is found to be effective in reducing noise levels below the impact threshold (EOT, p 6-3). Cost-effectiveness limit for building noise mitigation will be $5,000 per dwelling unit per decibel of noise impact projected above the Severe Noise Impact Level (not to exceed $30,000 total) (EOT, p 6-3). The owners of properties that are affected by noise above the Severe Noise Impact Level, and who may be eligible for building noise mitigation will be consulted during the design phase, and will be allowed to identify preferred building noise mitigation measures from a list of potential measures (EOT, 6-3,4). Potential measures list will include measures, such as window replacement or sound insulation in the house. Homeowners may elect, singly or in concert with others, to install measure that may not reduce exterior noise levels, or may not be fully effective in reducing interior noise levels, such as air conditioning (EOT, p 6-4). The mitigation agreement between the MBTA and the Town of Scituate for noise impacts caused by the Greenbush Line provides a clear precedent for the MBTA’s noise mitigation process. The owners of noise impacted properties where sound insulation mitigation was proposed were permitted the option of using all or a portion of their allocated sound insulation funds for sound insulation treatments to the residence or other expenses (MBTA and Scituate, p 6). The MBTA agreed to spend $755,000 to provide sound insulation to 59 residences for an average cost of $12,796 per residence. However, only two of those residences were severely impacted and MBTA spent $30,000 on mitigation for each. 31 residences were low impact and received an average of $7,000 and 26 were medium impact and received an average of $18,269. MBTA used a formula of providing $5,000 for sound insulation mitigation per household per dB of mitigation, even for low impact residences (MBTA and Scituate, Attachment 4). Lessons from Precedents Residents should play a role in determining what noise mitigation measures are desired. The MBTA has a precedent for spending $5,000 per dB of noise reduction per residence, up to $30,000 for severely impacted residences. It is appropriate to spend noise mitigation funds on treatments that do not provide noise benefits if that is the desire of the residences. Contrary to the FEIR for the Green Line Extension, it was considered cost-effective to pay for treatments that resulted in less than five decibels of noise reduction. Our Recommendations MassDOT has recognized the need for noise mitigation, but has not yet created a mitigation plan. This is the opportune time for CCP to intervene and present MassDOT with a plan supported by the community that addresses energy benefits in addition to noise impacts. CCP needs to ensure that MassDOT and the MBTA develop the Green Line Extension through Somerville with the same standards they used in other communities. CCP should recognize that following the precedent from the Greenbush Line, the South Coast Rail and the Blue Line is an opportunity to prevent displacement and improve the quality of life for environmental justice communities along the corridor. The sound insulation industry recognizes the synergy with and support for weatherization. Unfortunately there is no definitive published research yet that outlines the correlation. However, there is forthcoming research. A pilot study is being conducted in the area around the Forth Lauderdale-Hollywood International Airport. The “Early Action Volunteer Residential Sound Insulation Pilot Program” is an attempt to evaluate the energy benefits of sound insulation treatments. Their study will conclude in less than a year from now. Additionally, the Federal Aviation Administration, which funds numerous residential sound insulation projects when airports expand, is developing new noise mitigation guidelines. Jones Payne Group is working with the FAA to make sure the new guidelines incorporate the connection between sound insulation and weatherization. When these guidelines are complete, we recommend they be applied to transit projects as well. Jones Payne Group is conducting research as well. They are looking at the change in energy use before and after a building is insulated for noise. Their study is in the preliminary stage, but will provide crucial data for quantifying the connection. We recommend CCP contact Jones Payne Group for the study details and as a potential resource for developing a “community noise mitigation plan.” CCP should coordinate stakeholders to be involved in the development of a “community noise insulation plan” to best leverage mitigation funds. Residents living along the corridor can also be consulted for anecdotal data. We spoke with one family that upgraded their insulation and noticed a significant improvement in both noise reduction and energy use. There are likely numerous other residents with similar experiences that should be considered resources. In addition to homeowners and renters, rental property owners should be considered important stakeholders. Many of the impacted residential buildings are likely to be rentals. Landlords should recognize that a well-designed noise mitigation plan is an opportunity to improve their properties and the stability of their renters. CCP should recommend a noise mitigation plan that creates a pilot program to test the synergies between noise mitigation and weatherization. In the pilot program, as well as, the first step in sound insulation for every treated house, a blower door test and energy audit should be conducted. Instead of just replacing window inserts or providing another layer of glazing, windows and doors in their entirety should be replaced, sealed and gasketted. Line of sight treatments should be extended to the entire house. MassSave funding, as well as, Somerville’s own energy efficiency retrofit program should be combined with the noise mitigation funds to provide the most comprehensive weatherization treatments. References and additional resources Executive Offices of Transportation and Public Works (EOT). (2009) “Environmental Consequences Technical Report: Noise.” Prepared by Vanasse Hangen Brustlin, Inc. Boston, MA. Available at: http://southcoastrail.eot.state.ma.us/downloads/EC_Noise%20Report%20w ith%20Figures.pdf Federal Transit Administration (FTA). (2006) “Transit Noise and Vibration Impact Assessment.” Available at: http://www.fta.dot.gov/documents/FTA_Noise_and_Vibration_Manual.pdf Fort Lauderdale-Hollywood International Airport. (2010) “Early Action Voluntary Residential Sound Insulation Pilot Program.” Available at: http://www.fllsoundinsulation.com/index.html Jones Payne Group. (2001) Blue Line Residential Sound Insulation Program 19962001. Available at: http://www.jonespayne.com/projects/pdf/nm_rail_mbta.pdf MBTA and Town of Scituate. (2002) “Mitigation agreement concerning the Greenbush Line Project in the Town of Scituate.” Available at: http://www.town.scituate.ma.us/documents/mbtafinal.pdf