Asansol Durgapur Development Authority
Archived Tender / Quotation Notice
Sl.No. Name of the Work
Estimated
Area
Amount
9,88,820.00 City Centre
Remarks
1
Electrical works for two storied building at Urban
Haat, City Centre, Durgapur-16.
( 2nd Call)
2
Area development of College Compound by
cutting, filling of earth within SIHM College
Campus, Durgapur (2ndCall)
15,52,526.00 DMC Area
Work order yet to
be issued
3
Construction of boundary wall of Silampur
Primary Health Centre within Kanksa Block.
34,58,355.00 Kanksa Block.
Work order yet to
be issued
4
Repairing of road at City Centre Bus Stand,
Durgapur-16 (2nd Call)
34,03,184.00 DMC Area
Work order yet to
be issued
5
Consultancy services for Development of a
Nature Park at City Centre adjacent to Sahid
Khudiram Sarani. (2nd Call)
DMC Area
Work order yet to
be issued
6
Construction of Concrete approach road for
Crematoria at bank of Kunur, Telipara.
(3rd Call)
7
Construction of bituminous road and drainage
work by the side of J.P. Avenue for newly
developed plots at Sagarbhanga, Durgapur713211.
8
Construction of Link road up to WBM stage
between Sokna & Keten village within Kanksa
Block. (2nd Call)
1,01,30,263.00 Kanksa Block.
Work order yet to
be issued
9
Improvement of road from Durga Mondir to West
Bamunara village, under Kanksa Block. . (2nd
Call)
21,48,520.00 Kanksa Block.
Work order yet to
be issued
5,14,134.00 Kanksa Block
44,21,230.00 DMC Area
Work order yet to
be issued
Work order yet to
be issued
Work order yet to
be issued
Asansol Durgapur Development Authority
List of Running Projects / Scheme
Sl.No. Name of the Work
Estimated
Area
Amount
1
Repairing of Bidhannagar Govt. Spond. Girls
4,87,615.00 DMC area
High School .
2
Construction of Children Park at Bidisha
2,94,086.00 DMC Area
Housing Co-Opt at City Centre.
3
Repairing and strengthening of Dr. Martin
92,10,000.00 DMC Area
Luther King road at Bidhannagar.
4
Construction of Concrete road and allied drain
50,31,290.00 Pandaveswar
at Gobindpur village.
Block
5
Construction of two storied building at Urban
1,16,73,326.00 DMC Area
Hatt at City Centre,
6
Construction of Bituminous road around
32,83,805=00 DMC Area
PANCARD CLUBS LTD. at Bidhannagar,
Durgapur-12.
7
Supplying Laying ,fitting and fixing of 100 mm
2,64,423=00 DMC Area
dia. D.I. pipe line from Kali Mandir to Street no.
27&28, Urvashi Ph-II, City Centre, Durgapur16.
8
Construction of concrete road and drainage
35,57,463=00 Kanksa Block
system at Birudiha village passing through
Ruidaspara, Bauripara and other area within
Kanksa block.
9
Construction of SIHM Building at Fuljhore
8,61,14,677=00 DMC Area
10
Construction of approach road for SIHM
90,41,516=00 DMC Area
College, Durgapur
11
Renovation of Printika Bus Stand and its
40,36,452=00 DMC Area
adjacent road at Benachity.
12
Construction of shopping complex at zonal
1,05,34,763.00 DMC Area
centre Bidhannagar
13
Construction of Boundary wall at SIHM ,
85,70,990.00 DMC Area
Durgapur
14
Construction of Kiosk at City Centre, Bus stand
59,79,382.00 DMC Area
15
Construction of shopping complex at Zonal
1,05,34,763=00 DMC Area.
market, Bidhannagar.
16
Construction of Bondary wall at SIHM,
85,70,990=00 DMC Area.
Durgapur
Electrical Works
11
Electrical wiring & distribution (LT) with area
67,25,645.00 DMC Area
lighting at State Institute of Hotel Management,
Fuljhore, Durgapur.
12
Street lighting arrangement for new Colombia
3,81,533.00 DMC Area
Street at Sec.-2B, Bidhannagar, Dgp.-12.
13
500KVA Sub-Station (11/0.433 KV) with allied
32,46,539.00 DMC Area
LT works for State Institute of Hotel
Management, Fuljhore, Durgapur.
Remarks
In progress
In progress
In Progress
In progress
In progress
In progress
In progress
In progress
In Progress
In progress
In Progress
In Progress
In Progress
In Progress
In Progress
In progress
In progress
In progress
Asansol Durgapur Development Authority
List of Completed work for the year 2014-15
Sl.No. Name of the Work
Remarks
1
Estimated
Area
Amount
Construction of Concrete road at Akandara
46,73,646 Kanksa Block
village.
Completed.
2
Construction of concrete road and drainage
system at Ukhra Gurudawara road.
15,54,772.00 Andal Block.
Completed.
3
Construction of concrete road and drainage
system at Molandighi Village .
47,55,600.00 Kanksa Block
Completed.
4
Construction of concrete road and drainage
system at Dhupchuria village.
51,45,083.00 Andal Block
Completed.
5
Repairing of Bituminus road at Dhupchuria
village.
6,50,757.00 Andal Block
Completed.
6
Construction of road from Bamunara Hattala to
Tetultala Adibasi Para.
25,00,181.00 Kanksa Block
Completed.
7
Renovation of 11 Nos.Anganwari Center within
ward No-1, DMC area
8
Constructioj of Concrete road and allied work
at Palaskol village .
20,09,161.00 Panvadeswar
village
Completed.
9
Repairing of Sahid Sukumar Banerjee Sarani
at Durgapur.
78,11,556.00 DMC area.
Completed.
10
Repairing of Neteji Subas Ch. Bose Road at
Ukhra village.
18,24,425.00 Andal Block
Completed.
11
Improvement of Road from Ram Chand Murmu
Sarani to Urvashi PH-II
12,71,324.00 DMC Area
Completed.
2,85,500.00 DMC Area
Completed.
Asansol Durgapur Development Authority
List of Completed work for the year 2011-12
Sl.No. Name of the Work
Remarks
1
Estimated
Area
Amount
Improvement of road from Dakshinkhanda to
79,26,408.00 Andal Block
Damari Bandh.
Completed
2
Construction of road and drain at North side of
ADDA Guest House.
7,84,270.00 DMC Area
Completed
3
Providing Temporary Aproach at SIHM at
Fuljhore .
5,58,650.00 DMC Area
Completed
4
Constructionof drainage system
Mahallah, South Bazar, Andal.
61,32,415.00 Andal Block
Completed
5
Renovation of Internal road at Urvashi Ph-I &
Ph-II at City Centre.
26,14,000.00 DMC Area
Completed
6
Improvement of Road at Aranyak Purbanchal,
at Sector 2A, Bidhannagar.
29,24,477.00 DMC area
Completed
7
Construction of Box Culvert at ADDA near
Tetultala Colony.
17,25,296.00 DMC Area
Completed
8
Improvement of road from Bilpahari to Suri
Road within Pandavaswar Block.
3,61,49,957.00 Pandavaswar
Block.
Completed
9
Construction of approach road at New
Township Police Station (MAMC)
12,28,231.00 DMC Area
Completed
10
Improvement of Balful Sarani at Sagarbhanga
84,08,202.00 DMC Area
Completed
11
Construction of Concrete Road at Dannya
Village at Pandaveswar.
49,51,682.00 Pandaveswar
Block
Completed
12
Construction of concrete and Bituminus road
from NH-2 to Sree Pally at Benachity.
47,94,239.00 DMC area
Completed
13
Constructioin of Ichapur By Pass
Completed
14
Reconstruction of road from Mahal more to
South Samla Rly line.
46,01,143.00 Durgapur
Faridpur Block
36,60,478.00 Pandaveswar
Block
15
Construction
of
Boundary
Raghunathpur Primary School.
22,41,136.00 DMC Area
Completed
16
Improvement of road at South of GT Road .
2,01,41,440.00 DMC area
Completed
at
Wall
Iraki
at
Completed
Sl.No. Name of the Work
Remarks
17
Estimated
Area
Amount
Infrastructure development at Satya Sai Co-Opt
16,85,813.00 DMC Area
Housing at Bidhannagar.
Completed
18
Construction of Drain at South of G.T. Road
near VAMBAY Colony.
61,40,640.00 DMC Area
Completed
19
Repairing of Staff Quarters at Galsi _ Block
BPHC.
25,59,932.00 Galsi Block
Completed
20
Construction of Concrete Road and drain at
Ramnagar Village.
59,13,733.00 Pandaveswar
Completed
21
Shifting of 350mm dia HDPE pipe for NeoMetalics Ltd.
2,04,027.00 Kanksa Block.
Completed
22
Construction of Concrete Road and drainage at
Ukhra Bus Stand.
42,54,761.00 Andal Block
Completed
23
Construction of drain at City Centre VAMBAY
Colony.
61,40,640.00 DMC Area.
Completed
Electrical Works
01.
Street lighting arrangement for peripheral street
of Gr. Fd. Residency , City Centre, Durgapur16.
367399.00
Durgapur
Completed
02.
Street lighting arrangement for Gyanchandra
Ghosh Sarani & connecting street of SSB
Sarani & Gyanchandra Ghosh Sarani,
Bidhannagar, Durgapur.
683218.00
Durgapur
Completed
03.
Extension of elect. Distribution for newly
developed plots at Bidhannagar, Sec.-2A near
Kalibari.
80994.00
Durgapur
Completed
04.
Electrical Works at B1 Shopping Complex,
Durgapur.
1213242.00
Durgapur
Completed
05.
Electrical Works at Urban Haat (Durgapur
Haat), City centre, Durgapur.
3120284.00
Durgapur
Completed
Asansol Durgapur Development Authority
List of Completed work for the year 2012-13
Sl.No. Name of the Work
1
Estimated
Area
Amount
Construction of approach road from NH-2 to
1232474 Kanksa Block
Randiha More .
2
Repairing of road from Galf Club more to
Ichapur Village.
3
Remarks
Completed
5501386.00 DurgapurFaridpur Block
Completed
Construction of road and allied work at Ukhra
6173686 Andal Block
Completed
4
Construction of Concrete road and drainage
system at Sri Pally Arraha village.
4121390 Kanksa Block
Completed
5
Construction of Concrete drain at Baghatpally.
6
Construction of Concrete road and allied work
at Kuldiha village.
10275414.00 Kanksa Block.
Completed
7
Construction of link road at Ramnagar Feeder
Road .
1406701.00 Pandaveswar
Block
Completed
8
Repairing of Cross drainage
Raghunathpur – Molandighi road.
1067277.00 Kanksa Block.
Completed
9
Infrastructure development of land at Urvashi
Ph-III, City Centre.
7666515 DMC Area.
Completed
10
Construction of Concrete road and drain at
Ramnagar village.
5913773.00 Pandaveswar
Block
Completed
11
Construction of road and drainage system at
Rabindra Nagar Housing Colony.
1736317 Kanksa Block
Completed
12
Construction of drain at Industrial plot at ITI
College.
1845184.00 DMC area
Completed
13
Construction of Concrete road and drain at
Ramnagar village.
5913773.00 Pandaveswar
Block
Completed
14
Construction of waiting shade at 1500 more
Bus Buss stop at Bidhannagar Durgapur-12.
2,94.001=00 DMC Area
Completed
15
Providing 150 dia pipe line for Junction Mall to
Pathik Hotel at City Centre, Durgapur-16.
4,94,282=00 DMC Area
Completed
16
Laying of 100dia D.I pipe line from Ashabari
Sarani to Hindol Sarani Main line Sector 2(A),
Bidhannagar , Durgapur-12.
73,467,=00 DMC Area
Completed
work
at
3457262.00 DMC Area
Completed
Sl.No. Name of the Work
17
Estimated
Area
Amount
Replacing the 100mm dia. C.I pipe line by D.I
8,24,561=00 DMC Area
pipe along Collins Path, Bidhannagar,
Durgapur-12.
Remarks
Completed
18
Improvement of road and drainage system from
the gate of Ultratech Cement factory upto EPIP
main road at Durgapur.
1,55,13,169=00 Kanksa Block
Completed
19
Replacement of sand from Rapide Gravity Filter
Bed No.1,2,3 at HFCL W.T.P, Durgapur. Under
the control of ADDA.
2,27,174=00 DMC Area
Completed
20
Supplying and laying of 150 mm dia. D.I pipe
from Rotary to 3rd line at Urvashi ph-II.
5,24,999=00 DMC Area
Completed
21
Construction of Box Culvert across Banaful
Sarani near Sagarbhanga Zonal Centre,
Durgapur.
10,85,648=00 DMC Area
Completed
22
Construction of waiting shed at 1500 More,
Bidhannagar.
2,94,001.00 DMC Area
Completed
23
Repairing of Internal Road at Urvashi Ph-II.
34,07,263.00 DMC Area.
Completed
24
Construction of Biomedical west, kitchen, etc.
at Panagarh BPHC.
33,96,849.00 Kanksa Block
Completed
25
Construction of Road and sladge drain at
Mangalpur WTP.
11,02,391.00 Raniganj
Completed
Electrical Works
01.
Electrical wiring, distribution & installation for
new Isolation Ward, Kitchen Block & Generator
Room at Ukhra (Khandra) BPHC.
164563.00
Andal Block,
Ukhra
Completed
02.
Electrical wiring, distribution & installation for
new Isolation Ward, Kitchen Block & Generator
Room at Panagarh (Kanksa) BPHC.
153087.00
Panagarh,
Kanksa Block
Completed
03.
Providing 11KV power to Piyala Pumping
Station-II of DMC, City Centre, Dgp.-16. (Under
15 MGD Water Project of Durgapur)
926370.00
Durgapur
Completed
04.
Street lighting arrangement for the street
generating from Sahid Ranchand Murmu
Sarani passing behind ADDA Guest House for
Staff Plots, City Centre, Durgapur-16.
249302.00
Durgapur
Completed
05.
Installation of new pump motor set
at
Bidhannagar Pump House, Dgp.-12 (2nd
Phase).
568216.00
Durgapur
Completed
Sl.No. Name of the Work
06.
Estimated
Area
Amount
Installation of new pumps at B-2 Pumping
1098656.00
Durgapur
Station, MAMC, Durgapur.
Remarks
Completed
07.
Providing 11KV power at Angadpur Water
Treatment Plant-II of DMC(Under 15 MGD
Water Project of Durgapur)
662200.00
Durgapur
Completed
08.
Electrical wiring & distribution for Self-Help
Group Building (SABALA) at South of GT Road,
Durgapur-16.
837337.00
Durgapur
Completed
09.
Electrical wiring, distribution & installation for
new Isolation Ward, Kitchen Block & Generator
Room at Pursha (Galsi) BPHC.
199553.00
Pursha, Galsi
Block
Completed
10.
Renovation of electrical wiring at ADDA office,
1st Admn. Bldg., City Centre, Durgapur-16.
677358.00
Durgapur
Completed
Asansol Durgapur Development Authority
List of Completed work for the year 2013-14
Sl.No. Name of the Work
Estimated
Amount
Area
Remarks
1
Repairing of road from NH-2 to Nabawaria
village.
580142 DMC Area
Completed
2
Repairing of JL Avenue from Baghat Singh
More to SAP More, Durgapur.
4526753.00 DMC Area
Completed
3
Construction of Parking Lot with Toilet Facility
in front of Junction Mall, Durgapur.
5254772.00 DMC Area
Completed
4
Construction of Wayside Kiosk at Urvashi
Township.
1416006.00 DMC Area
Completed
5
Construction of concreter pavement and drain
at Bishnupur village .
7936147 Kanksa Block
Completed
6
Construction of Concrete Road and Drainage
system at Arraga Bidhan Park.
5186182.00 Kanksa Block
Completed
7
Construction of Concrete Pavement and
drainage system at Rupganj Village.
7073256.00 Kanksa Block
Completed
8
Construction of Concrete Road from Regional
Workshop to Sreenekation Temple at Ukhra
Village.
697366 Andal Block.
Completed
9
Repairing of Bituminous road from Bajpie More
to SBI at Ukhra.
1249237.00 Andal Block.
Completed
10
Repairing of road from Rajbandh Lock gate to
Biherpur and Keten Village.
7916703.00 Kanksa Block
Completed
11
Construction of Concrete Road from main road
Anandapur village.
2500968.00 Kanksa Block
Completed
12
Blacktopping of approach road within Junction
Mall area.
2755014.00 DMC Area
Completed
13
Repairing of road in front of City Centre Police
Station.
887135.00 DMC Area
Completed
14
Repairing of Khiudiram Sarani at City Centre.
1818457.00 DMC Area.
Completed
15
Construction of Shade at Bidhannagar Govt.
Girls High School .
536016.00 DMC area
Completed
16
Construction of Concrete Road at Manikara
Village.
666120.00 Kanksa Block
Completed
Sl.No.
17
18
Name of the Work
Construction of road at ITI College at Durgapur.
Construction of Burning Ghat and Shade at
Telipara Village on the bank of Kunur river
19
Cleaning of 4 Nos. Overhead Water tanks and
1 No. underground water reservoir within the
Jurisdiction of ADDA by mechanical means.
20
Supplying and laying of 150 mm dia. D.I pipe
from Rotary to Group Housing at 29th street ,
Urvashi ph-II,City Centre, Durgapur -16.
21
Supplying and laying of 100 mm dia. PVC pipe
line from HFCL township to VAMBAY Colony,
Shastri Avenue, Bidhannagar, Durgapur.
22
Construction of Bituminous link road from
Rajbandh to Manikara and Nutangram within
Kanksa Block.
23
Construction of concrete road and allied
drainage work from Hari Mandir to Shibtala and
two branch road at Arrah Village, Durgapur.
24
Construction of concrete road and drainage
work at Rakhit pur village under Molandijhi G.P.
within Kanksa Block.
25
Supplying and laying of 150 mm dia. D.I pipe
for water supply at Urvashi ph-II, City Centre,
Durgapur-16.
26
Construction of out fall drain along Sardar
Ballov Bhai Patel road from Kaliganj More to
SAP more Starting from back side of S.D.
Hospital through word No.25&26 of DMC.
Construction of Boundary wall at Urvashi Puja
Maidan Ph-I.
Repairing of daily market at City Centre
Repairing of Zonal Market at Bidhannagar,
Durgapur.
Construction of Water Tank at Khandra BPHC
Electrical Works
01.
LT UG & surface distribution lines for Zonal
Market Staff Qtrs., Durgapur.
02.
Electrical works at Kiosk within Urvashi
Township, City Centre, Durgapur-16.
03.
Electrical wiring & distribution (LT) with area
lighting at State Institute of Hotel Management,
Fuljhore, Durgapur.
04.
Street lighting arrangement for new Colombia
Street at Sec.-2B, Bidhannagar, Dgp.-12.
Estimated
Area Remarks
Amount
2763263.00 DMC Area.
Completed
703673.00 Kanksa Block Completed
1,99,760=00 DMC Area
Completed
5,31,546=00 DMC Area
Completed
2,78,813=00 DMC Area
Completed
35,84,003=00 Kanksa Block
Completed
74,36,400=00 Kanksa Block
Completed
57,03,427=00 Kanksa Block
Completed
7,29,838=00 DMC Area
Completed
3,34,00,641=00 DMC Area
Completed
4,18,628=00 DMC Area
Completed
13,59,693=00 DMC Area.
27,21,000=00 DMC Area.
Completed
Completed
4,48,928=00 Andal Block.
Completed
301474.00
DMC Area.
Completed
37334.00
DMC Area.
Completed
6725645.00
DMC Area.
In progress
381533.00