Meraux Refinery Hurricane Preparedness Plan

Pre-Season General Checklist

To be filled and completed by June 1, 2011 – Wade Gauthreaux

General and Facilities Checklist

Safety Manager

1 Identify Sheltering Locations for Standby crew

2 Check flashlights and battery supply.

3

3

Check and stock supplies including:

Food and Water

Cots

Sanitary Supplies

Emergency Medical Supplies.

Explore arrangements for obtaining food supplies during a hurricane event.

9

Develop list of suppliers needed during the hurricane event and order list of supplies.

8 Check operability and fuel supply for diesel firewater pumps.

Maintenance Checklist

Survey roof coverings and repair as needed.

4

Safety Manager

Safety Manager

Safety Manager

Safety Manager

Safety Manager

Maintenance

Manager

Number: MerC00

Revision 05/10/2011

Page 1 of 2

Contracted arrangements to

Catering Cajun – 24hr response –

Currently 3day supplies.

Chalmette Bldg --

Purchase Batteries

Weekly Check

In process

In process

5

6

8

Inventory trailers and temporary portable buildings and ensure all are anchored especially those in the vicinity of critical equipment such as transformer stations.

Ensure that the telephone pole/guy wire inspection was conducted and that all work orders will be completed. Check all structures to see if additional guy wires are needed.

Survey emergency generating and standby equipment.

10

3

Review Emergency Energy Back-up

and ensure equipment is available and ready.

Discuss structural at risk issues (e.g. tower, stack, and tank integrity).

Maintenance

Manager

Maintenance

Manager

Maintenance

Manager

Maintenance

Manager

Maintenance

Manager

In process – this week

Out for bid

Meraux Refinery Hurricane Preparedness Plan

Pre-Season General Checklist

Operational Checklist

1 Review the Hurricane Shutdown Sequence and the

Shutdown PFSD (provided in Chapter 8).

2 Discuss planned special or unusual operations, which may impact the execution of the shutdown sequence, i.e. turnarounds, equipment outages.

3 Review the Operating Strategies for slop, crude, and clean products.

4 Review “Load Shedding Plans” and other utility requirements. (hydrogen/steam)

5 Discuss operating plans and options in the event crude or product pipelines shutdown.

6 Develop a plan to hold out vessels from the refinery docks.

Survey drainage. Make sure pumps are working.

7

Operations

Manager

Operations

Manager

Operations

Manager

Operations

Manager

Operations

Manager

Operations

Manager

Operations

Manager

5/10/11

5/10/11

Daily

5/10/11

5/10/11

5/10/11

Number: MerC00

Revision 05/10/2011

Page 2 of 2

Need to adjust sequence –

Complete

Complete

Daily review at 1:30 meeting

Procedures in system

Continuing to discuss options.

Authority in place to restrict vessels.

In process -- Check work-orders – check with area 3