Detailed Specification

advertisement
Detailed Specification
The aim of this document is to provide a framework for prospective contractors to design
and build a 3G playing surface for Langley Academy, replacing the current natural playing
field
Langley Academy – Detailed Specification
CONTENTS
SECTION 1
General Conditions and Preliminaries
1.1.0 Project particulars
1.2.0 Summary of Works
1.3.0 The Site and Existing Buildings
1.4.0 Description of the Project
1.5.0 Contract Details
1.6.0 Quality Standards, Testing and Control
1.7.0 Operation/Maintenance of the Finished Facility
SECTION 2 – DESIGN AND CONSTRUCTION REQUIREMENTS
2.1.0 Construction Design and Performance Criteria
2.2.0 Drainage
2.3.0 Perimeter Edgings
2.4.0 Foundations
2.5.0 Engineered Base (optional)
2.6.0 Shockpad Layer
2.7.0 Surfacing Jointing and Play Lines
2.8.0 Full Size Pitch Markings
2.9.0 Seven-a-side Pitch Field Markings
2.10.0 Fencing
2.11.0 Floodlighting
2.12.0 Sports & Maintenance Equipment
2.13.0 Quality Control Tests
2.14.0 Warranties
2.15.0 References
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
1
Langley Academy – Detailed Specification
SECTION 1 - GENERAL CONDITIONS & PRELIMINARIES
1.1.0 PROJECT PARTICULARS
It is Langley Academy’s requirement that a fully porous ‘third generation’ synthetic grass pitch shall
be designed and constructed to suit the requirements for playing 11 and 5/7/9-a-side football
matches. The pitch shall meet the requirements of the FIFA Quality Program and FIH National.
This specification sets out the minimum requirements for the construction of a new synthetic 3G pitch
on the site of the existing grass pitches at Langley Academy, Langley Road, Slough, Berkshire SL3 7EF.
The area will be primarily for football and hockey use plus cross-field play. The pitch facility generally
would be expected to fall into the intense use category in terms of overall utilization.
The synthetic grass surface shall have dimensions 106m long x 70m wide. The synthetic grass surface
shall be line marked for a 100m long x 64m wide 11-A-Side football pitch. Cross field markings will be
specified as required.
The pitch shall have a 3 metre wide run-off area all around the pitch.
The installation work, details of which are contained in this specification, must be carried out such
that it conforms to the performance characteristics set out in the FA document – Design Brief for
Artificial Turf Pitches 2010. Notwithstanding this, the facilities to which this specification relates
should be constructed using proven methods of construction and proven materials to the highest
standards of workmanship and quality, which will give a good useable, and guaranteed, life for the
playing surface of a minimum of 8 years and guarantee of any shockpad and base works for 2 carpet
lifetimes, (minimum of 16 years). The design should take account of future maintenance requirements
of the synthetic surface. The Contractor is to provide a proposed maintenance regime and monitoring
system to ensure all guarantees and warranties remain valid at the completion of the works.
The form of construction proposed must meet all the specified requirements detailed in Section 2 and
the synthetic grass manufacturer’s recommendations. The Contractor shall provide documentary
evidence, in the form of independent test reports by a FIFA approved laboratory that the overall
construction complies fully with all the relevant performance requirements.
The Contractor shall indicate, at tender stage, the method he proposes to adopt for levelling and
preparing the formation, to ensure long-term stability of their subsequent base works.
It should be noted that the specification and design herein recognizes the existence of UK and
European registered patents for the new generation synthetic turf system (long pile synthetic turf)
and the potential of a patent infringement. The product UK patent numbers are as listed below:
2329910B / 2348890B
23508438 / 2358026B
2357571B / 2356639B
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
2
Langley Academy – Detailed Specification
The contractor must demonstrate that they have made the necessary enquiries to ensure that the
products offered do not infringe these or any other patents which may exist. In addition to this, the
Contractor and his supplier shall indemnify the Client against any action by whosoever may exercise a
right to protect the patents against any prosecution, which may arise.
The Turf Manufacturer should be a member of the FIFA preferred producer scheme and is to provide
evidence of such at tender stage.
1.1.1 Tendering/Subletting
The Employer does not bind itself to accept any design or tender.
Contractors tendering do so at their own cost
Tenders shall remain open for acceptance for a period of 90 days after the due date for submission.
The Contractor may be asked to attend an interview at the Employer’s office to explain their tender
proposals. This will include the methods of construction, the construction programme and
management structure to be used to control and progress the works.
The Contract Sum is a fixed price and will not be subject to any adjustments save only in respect of
any provisional or prime cost items or where the Employer shall have issued a written change in design
instruction.
By submitting a tender the Contractor agrees that should obvious errors in pricing or errors in
arithmetic be discovered before acceptance of his offer in the Tender Sum Analysis, the errors shall
be corrected in accordance with Alternative 2 contained in Section 10 of the NJCC “Code of Procedure
for Tendering for Design and Build” dated 1996.
The Contractor shall further agree that until this tender is incorporated in such a formal contract,
executed under deed by the Employer, this tender together with written acceptance thereof will
constitute a binding contract.
Master Design and Construction Programme: The Contractor shall prepare and submit their proposed
draft programme for the execution of the works for comment by the Employer at tender stage.
Criteria for selection of successful tender, the tender will be awarded on a 60-40 Quality cost basis
depending on the quality of tender return documents to include all information and samples set out
in the tender and written explanations of experience, quality management, construction methodology
and health and safety.
1.1.2 Draft timescale for completing the works





Tenders out: 17th February 2015
Tender Returns received back: 17:00 - 3rd March 2015
Tender Acceptance: March 2015
Start On Site: March 2015
Practical Completion June 2015
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
3
Langley Academy – Detailed Specification
1.1.3 Management of the Project
Site Administration and supervision: The Contractor shall allow for all necessary site administration
and supervision for the proper execution of the Works. Prior to commencing the works on site the
Contractor shall confirm to the Employer the name of the person in charge of the site together with
brief details of his experience. This person is not to be changed without the prior agreement of the
Employer, which shall not be unreasonably withheld.
Insurance: The Contractor shall ensure that the works and the site are properly protected and secured
at all times, including any works outside the site boundary, and that the Employer is indemnified
against any claim for loss, damage, theft or the like.
Statutory Regulations: The Contractor shall allow for complying with any such regulations or
requirements concerning pedestrian or vehicular traffic control, the loading and unloading of or
waiting by vehicles on the public highway, site ingress and egress, safety precautions, and the
protection of adjacent water courses from pollution caused by the works.
The Construction (Design and Management) Regulations 2007: This Contract will be executed strictly
in accordance with the Regulations. The Contractor named in the articles of agreement of the chosen
form of contract will be deemed the Principal Contractor.
The Contractor shall:
•
•
•
•
Submit a Construction Phase Health and Safety Plan for the project within 2 weeks of
acceptance of tender and prior to starting on site and shall execute the whole of the Contract
strictly in accordance with this.
The CDM Co-ordinator should have access to the Works and be afforded every reasonable
facility for the performance of their duties.
Co-ordinate with the CDM Co-ordinator, execute the Health and Safety Plan and contribute as
required to the Health and Safety File.
Allow for compliance with the requirements to fulfil the pre-tender and construction phase
Health and Safety Plans.
Design and Construction Programme: Thereafter the Contractor shall amend and revise the
programme as required by the Conditions of Contract or as requested by the Employer. The
programme shall be represented on a bar chart showing each primary stage of construction. When
updated this shall show the percentage of works completed up to the date of reporting.
Method Statement: The Contractor should provide, at the time of tendering, a statement describing
their proposed general and detailed arrangements and methods for carrying out the works.
The Method Statement should include the following:
•
•
•
How all stages of the works will be executed
Procedures to ensure the specified parameters are obtained
The appropriate climatic conditions in which the surfacing can be laid
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
4
Langley Academy – Detailed Specification
•
•
The appropriate Health and Safety requirements and training and experience of those
personnel working on site
Indicate areas of work that will be sub-contracted and detail the company(s) that will be
employed
Site meetings: The Contractor will ensure the following:
•
•
•
•
Provision of accommodation for site meetings every 2 weeks.
Digital colour site photographs, dated and issued, by email every Thursday of a quantity
sufficient to identify the level of site progress achieved every week.
Attend all meetings and advise subcontractors or suppliers when their presence is required
Provide a weekly progress statement, by email every Thursday, by reference to the design and
construction Master programme.
Control of cost: The Contractor is to provide, at the initial site meeting, a breakdown of expected
interim valuations and payments due for the duration of the contract.
Materials off site are an item within the tender pricing document.
1.1.4 Security/Safety/Protection
Pre-tender Health and Safety plan: This is a separate document to be read in conjunction with the
preliminaries and general conditions.
The Construction Phase Health and Safety plan: must be submitted to the Employer, CDM Co-ordinator
and Employer’s Agent not less than two weeks before the proposed date for start of the construction
work. The Contractor may not start the construction work until the Employer has received
confirmation in writing that the Construction Phase Health and Safety Plan, including procedures and
arrangements required by CDM Regulations, has been adhered to.
Trespass and Nuisance: All reasonable means shall be used to avoid inconveniencing adjoining owners
and occupiers. No persons employed on the works shall be allowed to trespass on adjoining
properties. The Contractor shall indemnify the Employer against any claims or action for damage on
account of any trespass or other misconduct of the Contractors' employees.
Site Security and Temporary Fencing: The Contractor shall provide all temporary and permanent
fencing as necessary to ensure the Works remain protected from all unauthorised entry. The
Contractor must provide for situating their temporary buildings and offices and the storing of
materials etc. within the site boundaries. The site is to be maintained in a secure state until completion
at which time all temporary fencing, building materials and equipment is to be removed and all works
made good.
The site is also to be left in a safe and tidy state at the end of each working day.
Control of Noise and Pollution: The attention of the Contractor is drawn to the provision of Section 60
of the Control of Pollution Act 1974 with references to the control of noise in relation to any
construction works, and must comply therewith.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
5
Langley Academy – Detailed Specification
The Contractor is recommended to confer with the local Chief Environmental Officer in relation to
proposed method of construction and noise level.
Safety, Health and Welfare of Work people: The Contractor shall allow for providing and maintaining
all welfare and safety measures to a standard not inferior to that laid down in statutory instruments,
rules and orders and subsequent amendments thereto for all workmen employed on the site including
the employees of subcontractors.
Sanitary accommodation for workpeople and staff shall be provided, connected to existing drainage
where practicable, and maintained in a thoroughly clean, deodorised and orderly condition. All huts
and other temporary facilities shall be removed, and contaminated soil disinfected and all damage
made good on completion of the Contract.
The Contractors' attention is particularly drawn to their obligations under the Health and Safety at
Work Act etc., 1974.
Maintenance of Roads, public paths, etc.: The Contractor shall maintain all public and private roads,
footpaths, paved areas, boundary walls and fences on, or adjacent to, the site in their present
condition and on completion, make good any damage arising from the works and reinstate to the
satisfaction of the Employer.
Damage to existing property, roads etc.: The Contractor is to make good any damage caused to any
land, public and private roads, footpaths, services under, kerbs, paved areas, boundary walls, and
fences etc. by his own and by subcontractors and suppliers plant, transport and activities, at his own
expense or pay the cost and charges in connection therewith.
Photographic survey: The Contractor is to carry out a photographic survey of the site boundaries,
footpaths and roads and agree their condition with the Employer prior to works commencing.
Storage of Materials: No storage of materials will be allowed on the adjoining roads or pavements.
Keeping Roads etc. clean: The Contractor shall keep any public, private and existing roads, drains,
footpaths and paving on, or adjacent, the site or used by traffic entering or leaving the site in a clean
and unobstructed and safe state to the satisfaction of the Employer, the Police and the Local Authority.
The Contractor shall use all means to prevent mud or rubbish of any kind being carried on to such
roads, footpaths and paving, by vehicles being used to carry out the Works to the reasonable
satisfaction of the Employer. Where, however, in spite of such precautions, mud or rubbish is carried
on to the roads, footpaths or paving, the Contractor shall immediately clean up such mud or rubbish
at his own expense by scraping, brushing, shovelling and removing to tip. Special attention must be
given to prevent mud becoming embedded in the road and footpath surfaces.
Removing Rubbish etc. and Cleaning Works on Completion: The Contractor shall allow for removing all
rubbish, protective casings, coverings and debris from the site.
Limitations of Working Space: The Contractor shall confine everything pertaining to the Contract
within the area of the proposed works and as marked on the drawings provided. The Contractors
operations required to carry out the works shall be executed carefully so as to cause minimum
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
6
Langley Academy – Detailed Specification
nuisance and inconvenience to the users of adjoining facilities. Access (including deliveries of goods
and materials) to the site will not be permitted during the hours of 8pm – 7am.
Limitations of Working Times: Subject to statutory limitations.
Site Access and Temporary Roads, Hard Standings etc.: The contractor may use site access off
Trelawney Avenue to allow the works to be undertaken during the agreed contract period. Site access
should be kept clean and clear and on completion of the Works the contractor shall ensure the access
is left in an “as found” state.
Temporary Accommodation for use by the Contractor: The Contractor shall allow for providing and
maintaining all necessary temporary services and offices or storage for materials for his own
requirements. The Contract manager will be expected to be available by mobile phone and email on
site.
No offices, stores or temporary buildings shall be erected on site without first obtaining the consent
of the Employer as to the position in which they are to be erected.
Water, lighting and power: Temporary water, lighting and power supplies to be arranged by the
Contractor.
The use of explosives is not included.
Only approved pesticides may be used by a licensed and trained pesticides user.
Burning of materials on site is not permitted.
Noise shall be kept to a minimum so as not to disrupt neighbouring properties. The Contractor may
not operate heavy machinery between the hours of 8pm – 8am.
Details of proposed pollution control measures are to be provided and agreed at the initial site
meeting and in place prior to works being carried out which may cause pollution.
The Contractor is responsible for the protection of work and all parts of the works, including work
carried out by others throughout the contract.
Existing services are to be protected, details are provided as part of the Contract Documents.
The Contractor is to provide a photographic survey of all existing party walls and fences which adjoin
the site and will be held responsible to ensure that these walls and fences are repaired should they be
damaged by any personnel or vehicle visiting the site for the Contract works.
1.1.5 Name of Test House
Dr. Colin Young, Labosport UK, Aerial Way, Hucknall, Nottingham NG15 6DW – UKAS/FIFA/FIH
Accredited
1.1.6 Employer’s Agent
Bob Breen – Breen Associates - Tel: 07557 906898
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
7
Langley Academy – Detailed Specification
1.2.0 SUMMARY OF WORKS
The Contractor shall design and carry out all base works, associated drainage, artificial turf, fencing
and lighting necessary to achieve Langley Academy’s requirements as set out in this specification.
These works shall generally conform to the requirements of the FIFA Quality Program and FIH
National.
The pitch shall comply with the School’s stated design requirements and performance criteria. Any
alteration must be approved by the School, or their representative, before incorporation into the
Contractor's design solution.
The client’s representative shall reserve the right at all times to approve or reject any aspect of the
Contractor’s design solution.
The objective of the project is to install a durable surface, which will perform well throughout the
serviceable life of the synthetic system installed. The design of the 3G Pitch shall conform to the
dimensional requirements of this specification, these shall concur with those of given in the contract
drawings. The pitch shall be constructed within the defined boundaries as described in the contract
drawings. The Contractor will, having undertaken the necessary ground works and drainage detailed
in this specification, install a system of synthetic grass over a base layer, which will meet the
performance and durability requirements of this specification. All aspects of infrastructure as required
should all meet the minimum standards given.
1.2.1 Dimensions
The turf system is 106m long and 70m wide. Total area of synthetic surface will be c. 7,420m².
1.2.2 Tender and Contract Documents
List of documents:
•
•
•
•
•
Site/Location Plan – General layout
Detailed Layout
Proposed Levels
Floodlighting design
Utilities and Services
1.3.0 THE SITE/EXISTING BUILDINGS
The Site: As defined on the Location Plan
Existing Mains/Services: Shown on utilities drawings provided with the tender documents, it is the
responsibility of contractor to establish the exact location and depths of these services in order to
avoid them.
Site investigation, Soil and ground water information: Utilities/Services Reports available
Topographical Survey: Levels provided
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
8
Langley Academy – Detailed Specification
It is the responsibility of the Contractor to satisfy himself and ensure he has adequate knowledge of
the nature of the existing ground, and its bearing capacity, and confirm the required sub-base design
for the project.
The responsibility for the sub-base and drainage design lies entirely with the Contractor and no
increase in the tender price or subsequent Contract Sum will be allowed for any costs of whatever
nature.
On the award of the contract the successful Contractor will have been deemed to have undertaken
any site investigations they consider necessary. No claims will be accepted for lack of information or
inaccuracies in this respect.
Disposal of spoil and arisings: The Contractor is to provide alternatives for the minimisation of spoil to
be removed from site.
Access to the site: Direct from Trelawney Avenue. Contractors are to consider peak traffic movements
around site and adjoining areas when planning vehicle movements. A wheel washing facility may be
required at the egress from the site so as to ensure that Trelawney Avenue is not affected by mud
from the site.
Parking of the Contractor’s employee’s vehicles: To be agreed
Use of site: Contractors may not use the site for any proposes other than carrying out the Works.
Advertisements: All rights of advertising on the site shall be reserved by the Employer and any Funding
Agencies. The Contractor shall take all necessary measures to ensure that no unauthorised advertising
takes place. A site signboard is to be provided as part of the contract giving the following information:
·
·
·
·
Name of development: Langley Academy, Langley Road, Langley - 3G Artificial Pitch (FIFA/FIH)
Site start date and expected date of completion:
Funding bodies – if necessary
Pitch Consultant – Bob Breen - Breen Associates
Publicity: No information, either written or verbal, nor photography or drawings concerning the
Contract shall be supplied by the Contractor to any persons without the written authority of the
Employer.
Surrounding Land /Building uses: The Contractor is to be aware of the surrounding land uses, buildings
in Trelawney Avenue and surrounding not to be disrupted.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
9
Langley Academy – Detailed Specification
1.4.0 DESCRIPTION OF THE PROJECT
Supply and install a FIFA 1 star/FIH National pitch as shown on the contract drawings.
Supply and lay concrete edgings to the perimeter of the new pitch. Construct new 3G Pitch 106m x
70m including a 3m run off all around.
Supply and erect all sports equipment including goals.
The Contractor should allow for a full FIFA 1 star field test to be carried out by the chosen testing
laboratory. Full completion of the pitch and start of annual maintenance will be taken from the date
of a successful field test, certified by the testing laboratory.
All access roads must be kept free of mud and other site detritus at all times the contractor’s
arrangements for maintaining the access roads shall be provided to the employer before
commencement of any site works. It may be necessary to provide a wheel wash facility.
1.5.0 CONTRACT DETAILS
The contract is being tendered by recognised pitch contractors linked to carpet manufacturers who
are members of the FIFA Preferred Producer Scheme.
Where this document refers to the Contractor it relates to the corporate body with whom the contract
will be let. Tenderers should offer documentary proof of successful installations of the proposed pitch
system. The responsibility of the performance of the final pitch, its civil engineering make up and
surfacing, lies entirely with the contractor at all stages of the project.
In order to be considered as an acceptable pitch system the main contractor is to produce test
certificates relating to the proposed pitch system as part of the tender submission. In order to be
acceptable, the pitch system must be up to the standard set out in the FIFA Quality Program for
Football Turf and FIH National.
The artificial pitch including the sub-base and artificial carpet are to be guaranteed against failure for
a minimum of eight years for the carpet from date of final acceptance. This acceptance date will be
based on the FIFA field test. Failure will be defined as falling below the performance standards set out
in FIFA & FIH testing standards, where normal maintenance alone will not restore the pitch to that
standard.
Where main contractors wish to provide an optional variant which falls outside the specification for
below carpet build up; only pitch systems which achieve the performance standards required by FIFA
& FIH plus the requirements of the warranty, (See Para. 2.14.0) will be considered. Optional variants
will not be considered without a tender for the specified system as well.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
10
Langley Academy – Detailed Specification
1.6.0 QUALITY STANDARDS, TESTING AND CONTROL
1.6.1 Supervision, inspections & sampling:
Where the Contractor has given notice that a particular operation or stage of the works will be ready
for inspection by the Employer and they then find that the works are not complete on that date so
that the inspection cannot be carried out or completed necessitating a further visit, the additional cost
incurred, including all expenses, will be borne by the Contractor.
The performance of the artificial turf depends upon the preparation of the sub-base and composition
of the existing sub-soil. Therefore the installed turf will not only be tested in the laboratory but will be
required to undergo field-testing as well.
Where materials, products and workmanship are not fully specified they shall be as recommended in
‘The FA Guide to Artificial Grass Pitches’ 2nd Edition, January 2010.
FIELD-TESTING MUST BE CONDUCTED WITHIN THE PERIOD SIX WEEKS AFTER INSTALLATION OF THE
PITCH WHERE PRACTICALLY POSSIBLE.
The period of six weeks between partial hand-over and testing is to allow the School and Community
to play on the pitch and assist in a settling-in period.
The Employer or their representative including the approved Test House will take samples of all
materials and have them tested for compliance with the Contractor's tender submission and this
document. Test methods to be employed will be in accordance with current practice. The Contractor
shall allow for the taking of such samples and the proper recording of the location to which the
samples relate, as directed by the Employer and detailed in the documents.
Samples for test shall be delivered within 48 hours of being instructed by the Employer. Any delay to
a scheduled inspection or preparation of a report by the Test House arising from late delivery of the
samples for test or from failure to keep proper records as required, shall not relieve the Contractor
from his responsibility with regard to completion within the Contract Period.
1.6.2 Failure of tests - Defective work
Should any samples or intermediate stages of construction tested be found, in the opinion of the
Employer, to be unsatisfactory or likely to produce unsatisfactory work, the defective material or the
consignment which the sample represents shall be removed from the site or suitable corrective action
taken, as approved by the Employer, to achieve the specified performance outcome. Notwithstanding
that, any sample or intermediate work stage, which has been accepted by the Employer or their
representative, may subsequently be rejected if they shall decide that the quality has in any way
deteriorated.
The Contractor shall, at their own expense, remove and replace all rejected materials, or correct any
intermediate work stage shown to be outside specification.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
11
Langley Academy – Detailed Specification
Any delays consequential upon the rejection of any sample or work stage:
•
•
•
Shall not in any way relieve the Contractor from their responsibility with regard to completion
within the contract period
Will not be considered as grounds for extension of time
Will be at the expense of the Contractor
Work corrected or materials replaced for these reasons will be re-checked or retested by the Employer
or their representative. The additional costs of testing any material replaced for this reason or reinspecting any work stage subjected to remedial works shall be recovered from the Contractor by an
appropriate deduction from the contract sum.
1.6.3 Quality of materials and workmanship
Proposals for rectification of defective work/Products: Where and to the extent that materials,
products and workmanship are not fully specified they are to be:
i.
ii.
iii.
Suitable for the purposes of the Works stated in or reasonably to be inferred from the contract
documents.
In accordance with good building and/or engineering practice, including the relevant
provisions of current British Standards.
In accordance with the Code of Practice for the Construction and Maintenance of Artificial
Grass Sports Pitches as published by the Sports and Play Construction Association.
1.7.0 OPERATION/MAINTENANCE OF THE FINISHED FACILITY
1.7.1 O&M Manual
The operation and maintenance manual (incorporating the Health and Safety File and subtitled
accordingly) is to be a comprehensive information guide for the Employer and end users providing a
thorough understanding of the facility and it’s systems which will enable it to be operated and
maintained safely. The Contractor is required to submit the manual at completion of the Works
1.7.2 Training of Employer’s Staff:
Before completion of the Works, the Contractor will explain and demonstrate to the Employer’s
maintenance staff or other appointed representative, the purpose and operation of the installation
systems. Allow for not less than 2 days.
1.7.2 Maintenance
The Contractor will supply, as part of the contract, a tractor, drag brush and rake for daily/weekly
maintenance of the pitch surface. Any tractor used must be suitable for maintaining a 3G pitch and
have a rear power take-off and a crawler gear.
1.7.3 Spare parts:
The Contractor is to submit a schedule of spare parts that should be obtained by the Employer for the
maintenance of the services installation.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
12
Langley Academy – Detailed Specification
SECTION 2 - DESIGN & CONSTRUCTION REQUIREMENTS
2.1.0 CONSTRUCTION DESIGN & PERFORMANCE CRITERIA
2.1.1 Access Road & Changing Rooms
Preliminaries/Site Set Up
Prepare H&S file, site management, storage, transport of plant and equipment, signage, as built
drawings and O&M Manuals include for Temporary fencing, Welfare facilities
Tarmac Access Road (c.578m2)
Allow to replace existing grasscrete roadway with tarmac roadway suitable for Lorries
Break up and remove existing grasscrete
Supply and install suitable road base, edging kerbs and 2 coat tarmac comprising 70mm dense base
course and 30mm wearing course.
Tarmac Area for Changing Rooms (c. 1,093 m2)
Allow to create a suitable sized area to enable siting of changing rooms and secure container
Excavate topsoil and dispose of offsite. Grade formation.
Supply and install 300mm layer of type 1, surface with 2 coat tarmac
60mm base course and 25mm wearing course.
Install perimeter edging kerbs.
Install services including power, water, and foul and sw drainage ready for relocated changing rooms.
Removal of existing pitch topsoil to an average depth of 300mm to areas within the confines of the
site, proposed levels. The contractor is encouraged to remove excess topsoil from the site at no cost
for landfill tax to the project.
Preparation and grading of sub-base to an engineered tarmac finish to achieve a minimum of 5% CBR
based on SI Report and site findings.
Relocate Existing Changing Rooms



Allow to disconnect services etc., make good existing area.
Dismantle changing room building, load onto suitable Lorries and cart to new location.
Unload and place changing rooms as required. Allow to rebuild and connect to new services.
2.1.2 The Contractor shall install the 3G artificial grass surface on a suitable sub base
The synthetic grass surface shall be laid with an overall slope in any direction not greater than 1 in
200. The surfaces shall be through draining with a minimum drainage rate of 180mm/hr when filled,
and shall be laid flat.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
13
Langley Academy – Detailed Specification
Any localised bumps or hollows shall be such that when a 3 metre long straight edge is placed in any
position on the surface, the gap between the straight edge and the surface shall, at any point, not be
greater than 3mm. Deviation from the finished plane shall not be greater than +/- 25mm at any point,
as described in BSEN 15330 2007. Additionally there shall be no ridge, groove, crease or change in
surface texture anywhere on the playing area.
Full details of the method to be used for installing the surfaces, forming the seams and inlaid lines,
including level checks, methods of adjusting level inaccuracies etc., shall be submitted as part of the
Tender response.
The sand and rubber granulate infill shall be installed to the manufacturer’s recommendations.
The design and performance criteria of the pitch shall also be in accordance with the relevant table
detailed in FIFA Quality Program for Football Turf – Handbook of Requirements 2010 edition for a One
Star Category Pitch which forms part of these Employer’s Requirements.
2.1.3 The final design of the pitch construction build up is the responsibility of the Contractor based
on the information provided which also forms part of these Employer’s Requirements.
2.1.4 Formation preparation:
Pitches need to be founded on competent ground. Topsoil, turf and vegetation are not suitable and
therefore must be stripped from the site. The area of the works shall be stripped of all vegetation and
topsoil to a depth of at least 300mm, the exact depth to be determined by reference to trial hole/s
recorded during any ground investigation survey.
The formation shall, after preparation of the sub grade drainage and before the laying of an
appropriate geotextile membrane, have been fine-graded by the Contractor to a surface tolerance of
+/- 10mm relative to the design levels. Any soft, loose or damaged materials shall be excavated and
backfilled as required or directed by the Client’s appointed agent. The finished formation should have
a California Bearing Ratio of (CBR) 5%.
The formation shall be free from slurry and mud and will have no areas of freestanding water.
Where areas fall outside of the given tolerances the contractor will be required to trim the formation
back or augment the shortfall with sub-base materials this will be at the contractor’s expense.
The formation shall not be left continuously exposed to rain or be uncovered overnight. Under no
circumstances shall construction plant or other traffic use the exposed formation.
The ground shall be trimmed and levelled using cut and fill as required. All filling should be carried out
in layers not exceeding 150mm thickness, and each layer should be compacted to the requirements
of BS 1377:1990, before the next is spread.
Any soft spots shall be excavated and replaced with imported crushed rock, free from detritus
material, in accordance with the Department of Transport Specification for Highway Works (Class 6F1
or 6F2).
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
14
Langley Academy – Detailed Specification
The formation should be treated as part of the finished pitch. It is vulnerable to softening in wet
weather and therefore has to be covered as soon as possible. Any soft spots in the formation must be
dug out and replaced with imported crushed rock, such as that used for the sub-base. The finished
formation should be trimmed to a tolerance of ±25mm.
Following excavation and levelling, the site should be treated with an appropriate non-residual
herbicide. Application should be by a competent person trained in accordance with Health and Safety
regulations.
2.1.5 Soil (arising from excavations in the pitch)
All topsoil and excavated material not required shall be removed from the site by the pitch contractor.
2.1.6 Excavations
The contractor shall ensure that excavations for foundations and trenches are stable at all times.
Sheeting and excavation supports if used shall not be left in place over night. Excavations requiring
backfilling shall remain open only for the minimum period necessary.
The base of all excavations shall be to the intended line and level. The employer must be informed of
all excavations, which are required to remove soft spots or localised loose materials.
Excavations and cuttings may be halted if weather conditions prevent the continuation of works
however there must be at least 300mm of materials for weather protection left in place above the
formation.
All loose, fragmented or soft materials in the finished cut must be removed and replaced.
2.1.7 Capping Materials
Capping materials shall be type 1 sub-base materials.
2.1.8 Sub-Base Material
Foundations should be constructed using hard, clean, crushed frost-resistant aggregates. The grading
of the sub-base material must be such as to provide stability while at the same time remaining porous.
The material should be laid in layers not exceeding 150mm, each layer being compacted before the
next is laid.
The minimum compacted thickness of sub-base stone should be 300mm. Upon completion there
should be no detectable movement under the roller. The sub-base material should be compacted to
the requirements of BS 5835: 1980. The surface level tolerance should be within ±10mm of the design
level, and, when checked with a 3m straight edge, there should be no deviation greater than 10mm.
The sub-base material shall be a non-frost susceptible crushed granular stone complying with the
requirements of the Department of Transport Specification for Highway Works (3) specification for a
Type 1 sub-base. It must meet all the requirements as defined in this specification
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
15
Langley Academy – Detailed Specification
Sub-base shall be transported, laid and compacted without segregation or drying out. Compaction
shall be completed as soon as possible after laying and should be carried out in accordance with Table
6/4 SHW Method of Compaction for Earthworks.
During placement and compaction, the surface profile should be controlled such that on completion,
it is within a tolerance of plus 10mm to minus 10mm of the contractors intended profile for this layer.
Sub-base shall have a porosity of 3000mm/hr when laid, shall achieve a compacted density of 95% of
the maximum dry density when tested in accordance with BS5835 and have a bearing capacity of 40
k/N when tested using BS1377 Plate test with minimum deformation under the plate.
2.1.9 Levels
The pitch strip will mean that following shaping and grading the pitch should be level from end to end
with a cross fall of 1:200.
The design of the sub-base should be given careful consideration, as it is desirable to minimise
disturbance to the base structure and build the pitch to allow proper drainage of the facility.
2.1.10 Reinstatement
The contractor shall carry out all reinstatement to any damaged areas and make good all areas
affected by the construction works to the satisfaction of the employer.
2.1.11 Weed killing
The prepared formation shall be treated with a total non-residual, systemic Glyphosate-based weedkiller selected to minimise the risk of future weed growth within the construction. The form of weed
killer to be used shall be agreed prior to use and it shall be applied strictly in accordance with the
manufacturer’s specified application rate. Applications are to be by a competent person trained in
accordance with Health and Safety regulations.
2.1.12 Geotextile
A separator membrane is required on this site. An approved geotextile membrane shall be laid over
the formation. The material shall meet the requirements of The Department of Transport Specification
for Highway Works – Clause 609: Geotextile used to separate construction layers or similar approved
(3). The membrane should be a polypropylene type and have a minimum tensile strength of 20 kN/m.
Membranes shall be protected against mechanical or chemical damage. If they are susceptible to
damage by light, membranes should not be left exposed between manufacture and installation.
Temporary exposure shall not exceed 5 hours.
Joints shall overlap by at least 300mm.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
16
Langley Academy – Detailed Specification
2.1.13 Vehicle Access Hard standing
Any porous bitumen macadam hard standings should support vehicle access with a minimum of 100
DBM with a sub base of 250 mm compacted type 1.
2.2.0 DRAINAGE
A new drainage system will be required to support the expected run-off from the pitch. The drainage
should be designed such that it will achieve a satisfactory discharge rate, which will cope with a 1 in
100 year rainfall event. Runoff will be attenuated on-site through the base layer. It should be noted
the water table in the area has not been assessed however the site is described by locals as free
draining. The drainage of the pitch should lead to a specified outfall in close proximity to the pitch.
A perimeter drain shall support the pitch drainage this shall be not less than 160mm diameter (100%
around the pitch) this shall tie into all lateral drains at 8m centres, which shall be fully connected via
a proper ‘T’ piece connection, to the perimeter drain. The run-off collected by the under pitch drainage
shall be directed to the outfall.
The Contractor is to satisfy himself that the system of surface water drains will:
i.
Protect the installation from the effects of ground or surface water from the areas
surrounding the pitch.
ii.
Ensure that all surface water shall be removed from the site at the rate of porosity specified
for the surface to ensure that no surface flooding will occur during heavy storms, or the facility
will not be lost either through rain at the highest intensity which may be expected to occur
once every five years or through continuous rainfall of 50mm over a 24 hour period.
iii.
Ensure no water remains present in the construction so that it may result in a reduction of the
load bearing capacity of the formation or in any frost damage to the constructions.
Drainage works should be undertaken in accordance with the relevant clauses of the Department of
Transport Design Manual for Roads and Bridges, Volume 4.
2.2.1 Pipe jointing and capping
The ends of lateral drains are to be capped to prevent contamination, and connectors must be used
when joining lateral drains to collector drains. Collector drains and all associated covers are to be
located on the outside of the perimeter edging. Rodding eyes, with cast iron covers, shall be installed
at each corner of the pitch.
2.2.2 Silt/inspection chambers
Silt/inspection chambers are to be constructed where perimeter/collection drains change direction,
and the provision of rodding eyes must be included at the head of collector drain runs for ease of
access for maintenance. Rodding eyes to be located outside the pitch area.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
17
Langley Academy – Detailed Specification
2.2.3 Drains and Bedding
Drains are to consist of perforated plastic pipes, bedded on, and backfilled with, clean stone. No drains
should have less than 300mm cover over the top of the pipe, and no drain should be laid to a fall of
less than 1:200 unless advised by manufacturers’ instructions.
Drains are to be discharged into the designated outfall.
2.2.5 Drainage Connection to outfall
Drainage trenches shall be a minimum of 450mm deep from formation by 300mm wide and contain
100mm (minimum diameter) perforated-plastic drainage pipe in accordance with BS 4962. Trenches
shall be back filled with clean graded round/sub-rounded gravel or similar. All drainage pipes shall be
laid to a minimum fall of 0.5% with connection to the outfall in close proximity to the pitch.
2.2.6 Existing Drains
Any existing flowing drains cut through during the construction of the pitch shall be reconnected into
the new system. It is not expected that any drains currently exist beneath the pitch area.
2.3.0 PERIMETER EDGINGS AND MOWING MARGINS
The Contractor shall design and install edging details at the abutment between the playing surface
and the surrounding margin such that they facilitate the maintenance of the playing surface and
surrounding areas, but minimise the risk of mechanical damage to or contamination of the playing
surface from the maintenance of the adjoining surfaces and present no trip or void.
Precast concrete kerbs shall be hydraulically pressed complying with the requirements of BS 7263:
Part 1 (14). They shall be bedded in accordance with BS 7263: Part 2 (14), on a graded ST1 concrete
foundation. The dimensions of the edgings shall be a minimum 150mm x 50mm. All kerbs must be
fitted to make due allowance for the subsequent fitting of the synthetic turf system, including
shockpad, to be utilised. Thus, an upstand is necessary and should be selected by the contractor as
appropriate. All adjacent porous hard-standings are to fall away from the pitch all edgings are to be
flat-topped to allow water flow across the hard standings to the grass edge and perimeter drains.
Whichever detail is chosen it must be firmly bedded in concrete and be straight and level. There should
be no deviation detectable by the human eye, and the level tolerances of a maximum of 2mm under
a 300m straight edge should apply. Edgings shall be haunched in concrete in accordance with the
Department of Transport Specification for Highways Works. The haunching shall incorporate
movement joints at 6m spacings.
2.4.0 FOUNDATIONS
The depth of the sub-base shall be determined by the contractor to satisfy the specified design criteria
and taking into account the findings of any ground investigation. In all cases the depth shall be equal
to or greater than the minimum requirements of Clause 1.5 of the Code of Practice for the
Construction and Maintenance of Artificial Grass Sports Pitches.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
18
Langley Academy – Detailed Specification
In order to prevent contamination from the sub-grade an approved geotextile membrane (2.1.12)
must be installed on the formation prior to installation of the sub base.
Joints shall overlap by at least 300mm
2.4.1 Current CBR Values
Current CBR values are all expected to be in excess of 5%. The contractor should price for a minimum
300mm thickness modified, low fines, type 1 dynamic stone base to allow for emergency or
maintenance vehicle traffic.
2.4.2 Sub-base
The sub-base shall be laid and compacted so the in-situ density shall be not less than 95% of the
maximum dry density when tested in accordance with BS 1377 part 4 (2.5kg method). Consolidation
shall be by laser controlled roller. Vibrating rollers may be used on this site.
The Contractor shall design and install a sub-base to the pitch that shall
•
•
•
•
•
Resist the effects of frost or drought that may be expected to occur in a return cycle of 50
years
Provide stability to the finished surface such that in use it shall not move outside the
tolerances for surface regularity over a period of 10 years
It should be capable of supporting – and transmitting to the existing ground – the loads of all
vehicles, plant, machines and materials to be used in the construction and maintenance of the
pitch, without causing deformation of the site.
After the pitch is built, the sub-base should be capable of supporting and transmitting all loads
on the playing surface without permanent or long-term deformation of the playing surface.
Such loads arise mainly from players and maintenance equipment.
It should ensure that water, whether rainwater or natural ground water, will drain away freely
through the sub-base material, either into the natural subsoil or into the drainage system.
2.4.1 Aggregate Materials
Foundations should be constructed using hard, clean, crushed frost-resistant aggregates. The grading
of the sub-base material must be such as to provide stability while at the same time remaining porous.
The material should be laid in layers not exceeding 150mm, each layer being compacted before the
next is laid and finishing with a blinding layer.
The compacted thickness of the sub-base stone should be designed against the prevailing ground
conditions. There should be a minimum of 300mm of stone base above the drainage runs.
2.4.2 Foundation Completion
Upon completion there should be no detectable movement under the roller. The sub base material
should be compacted to the requirements of BS 5835: 1980. The surface level tolerance should be
within ±10mm of the design level, and, when checked with a 3m straight edge, there should be no
deviation greater than 10mm.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
19
Langley Academy – Detailed Specification
2.5.0 ENGINEERED BASE (Optional)
Engineered base, consisting of a single course of open-textured bituminous macadam to BS EN 13108.
On the pitch sub-base lay an open textured binder course consisting of 40mm nominal compacted
thickness of 10mm nominal sized aggregate to BS EN 13108.
Laid using a specialised laser grader. This is required to achieve the necessary tolerances on this layer.
This sub-base layer is to be checked, recorded and confirmed as acceptable by the approved testing
house prior to the laying of the shockpad.
The surfacing course shall be laid to satisfy the surface regularity requirements of the FIFA Quality
Program for Football Turf (2009 edition).
2.6.0 SHOCKPAD LAYER
The introduction of a resilient shockpad layer between the sub base and the artificial grass carpet can
be used to provide a degree of comfort to players and to create the defined playing characteristics
required of the tests set by FIFA & FIH and to provide some protection to the stone layer beneath.
2.6.1 Requirements of a Shockpad Layer
The Contractor shall lay shockpad to the full extent of the playing surface and run off area. The
shockpad may be a pre-fabricated system or a poured in-situ pad.
An in-situ shockpad should include a composite of granulated recycled rubber bound in a
polyurethane resin, mixed on site and compacted and cured to form a flat continuous pad upon which
the synthetic carpet is laid:
•
•
•
A high quality binder of sufficient quantity to deliver a fit for purpose shockpad
A high bulk density (>550kg/m3)
Small dominated SBR particles (2-6mm)
The proposed shockpad system will be designed by the Contractor to ensure the performance
characteristics of the FIFA 1 star and FIH National standards.
The shockpad should deliver the following properties:
•
•
•
•
•
•
Dimensional stability to ensure that rucking, creasing or movement does not occur
Robust enough to withstand vehicle loads associated with maintenance or emergency access
Carry a minimum 15 year guarantee against decay or degradation
Be resistant to bacteria, fungi and chemicals
Must not constitute a hazard to the school when replaced
Must be of a uniform thickness ± 2mm
A reference sample of the whole depth certified pitch system must be produced as part of the tender
return documents so that the installed shockpad can be checked for consistency of material.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
20
Langley Academy – Detailed Specification
Generally, the shockpad shall retain its elastomeric properties and remain dimensionally stable within
a moisture content and temperature range commensurate with field conditions over the design life
of the facility. The thickness, density and weight per unit area of the shockpad shall match those of
the reference sample to within 10% of the specified value.
The regularity of the installed shockpad shall be in accordance with the requirement for the final
playing surface as given in the FIFA Quality Program for Football Turf – Handbook or Requirements
2010 edition for a One Star Category Pitch which forms part of this specification.
The design of the shockpad and carpet backing shall ensure that slippage of the synthetic turf carpet
does not occur.
The shockpad thickness will be ± 2mm from the contractor-designed thickness to achieve the
requirements. This is specified to ensure that there is consistency in ball playing characteristics across
the field. Thickness will be measured by obtaining cut-outs in the laid pad, these will be provided by
the Contractor in a timely fashion so that proper quality control of the works can be exercised. The
thickness at any point in the mat of laid pad must lie within the specified value.
At the time of laying the shockpad the contractor is to prepare a reference samples for each pour.
Prepared on site and cured in the same conditions as the pitch the sample is to be prepared in a steel
tray filled with the shockpad to the same depth as on the pitch. The contractor will arrange for these
samples to undergo the tensile test to the recognised industry standard BS EN 12230, with samples
cut to a dumb bell shape 25mm wide by 150 mm long and strained to failure at a rate of 50 mm/min.
The Contractor shall submit a detailed method statement for laying the shockpad; this must be
supplied before any site works are carried out. Special precautions may be required to carry out works
during the winter period – a method statement to this effect will be required prior to any works being
carried out.
2.7.0 SURFACING, JOINTING AND PLAY LINES
The synthetic surface will be used mainly for Soccer. The level of use expected should be considered
‘intense’ use. The synthetic carpet will comprise of a long pile sand/rubber in-filled turf system. This
will overlie a dynamic layer (with an option of tarmac). Drainage will be designed to allow for a 100year rainfall event and it is expected that the synthetic pitch will remain free of surface water i.e.
unsaturated in all weather conditions.
2.7.1 Grass Carpet Specification Requirements
The Contractor is to supply a laboratory test report by a FIFA accredited sports laboratory, for the
proposed carpet and shockpad working together. The report is to include details of the infill material
the system was tested with alongside lab test results.
The synthetic carpet will have a face weight, pile length and construction as described in the table
below. Technical data sheets illustrating the key parameters must be included with the tender
submitted. No alternative product will be considered unless it is accompanied with a data sheet and
technical specification for its performance. A long pile carpet to the specification given below is the
desired option.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
21
Langley Academy – Detailed Specification
The colour shall be two-colour green and match the reference sample to within one position of BS
5252/4800 (11). Actual colour parameters should be supplied with the tender.
Synthetic carpets that have to be stored for more than one week (7 days) should be stored such that
the synthetic carpet is supported off the ground. A carpet boom or similar would be acceptable for
this purpose.
The synthetic carpet shall be loose laid over the substrate.
PRODUCT DESCRIPTION - 3G Synthetic Turf System - Long Pile sand/rubber in-filled
Materials Description
Tufted sand/rubber filled grass carpet – straight stitch pattern - 100% polyethylene monofilament
Pile Height
=40mm
Pile Weight
=>1,050g/m2
Gauge
=<5/8
Tufts per m2
=>10,000
Lisport cycles
=>20.200 cycles
Dtex
=>12,000/6 Dtex
Yarn
Structured =>300 microns
Colour
Two tone green
UV Stabilized
Din 53387
Primary Backing
100% PP Double thickness U.V. stabilized
Backing weight
=>260g/m²
Coating weight
=>1000g/m²
Secondary Backing
SBR Latex compound with evenly spaced drainage holes
Shockpad
>12mm prefab or >15mm In-situ rubber to be specified by supplier
2.7.2 Carpet Movement
The carpet, infill and base layers are to act as one system and contractors are to ensure that suitable
measures are in place to ensure no carpet movement. Where adhesives are used these must be used
in adherence to manufacturer’s instructions in particular reference to Health and Safety and
effectiveness under adverse climatic conditions.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
22
Langley Academy – Detailed Specification
2.7.3 Carpet Jointing
The method of jointing and seaming, including all in-laid line markings, shall be such that no ridge,
groove, crease, or change in surface texture shall be apparent along any joint or seam to the extent
that it may cause or result in the deviation from a straight line of a football rolling across the joint or
seam at an angle of 10° and at a speed of 1 metre/sec + 10%. Notwithstanding this requirement, there
shall be no height difference or separation at the joints of greater than 2mm.
Adjacent carpets must be glued together using a glued backing strip with a minimum width of 300mm.
The carpet must satisfy the requirements for tensile properties. The joint strength will be considered
acceptable provided they are within the requirements below.
The strength of seams is tested in accordance with BS EN 12228.
Property Test Method Requirement
Peel strength of bonded seams before and after water-ageing
BS EN 12228: Method 2, 2002
BS7044 Section 2.4 Method 3, 1989 _ 75N/100mm
2.7.4 Infill comprising of sand/rubber
The infill materials shall be a mixture of uniformly graded rubber granules and silica sand installed to
form a stable structure within the synthetic carpet. There shall be no rubber dust or excessive shred
in the bulk materials supplied. The Engineer reserves the right to reject suspect rubber.
Sand in-filling shall consist of non-abrasive, non-staining, well-rounded and dust free particles (sub
angular or sub rounded sands will be rejected) and shall match the reference sample. No chemical
treatments are permitted. The rubber shall be cryogenic granulate or a suitable alternative which
meets the criteria.
At tender stage, the Contractor is to provide confirmation as to the recyclable capabilities of the infill
material or whether any special environmental considerations exist when disposing of the infill
material.
2.7.5 Top Dressing
The contractor shall allow for a minimum of two applications of infill; 1 to initially complete the
installation ready for play. Then to carry out a full re-dressing within six months, this should be allowed
for in the bid price and material provided in bags at practical completion. The aim to ensure that free
pile remains within the 15 – 20mm range after use and normal compaction.
The Contractor must make due allowance for providing a further 1 tonne of SBR rubber to Langley
Academy at the handover of the contract; for the purpose of topping up from time to time.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
23
Langley Academy – Detailed Specification
2.7.6 Environmental Considerations
The infill materials must be inert i.e. they must not leech out contaminants which would find their way
into local water courses, drains or affect users playing on the surface. The Contractor is to supply
certification of this requirement.
2.7.7 Play Lines
The contractor shall provide details of the line markings system and method of incorporation into the
carpet in the tender return.
The Contractor shall ensure that line markings are accurately set out and installed.
The top surface of all line markings shall be within a tolerance of plus/minus 2mm of the adjacent
carpet surface when measured under a 300mm straight edge regardless of type.
Good practice methods in forming strong adhesive bonds, between the back of the carpet and the
seam jointing tape, are very important and must always meet the joint strength specifications set out
below.
•
•
•
Use of correct quality and width of jointing tape and positioning of seam joint centrally along
tape (wider [450mm] tape required for line installation)
Application of adequate pressure to the bonded seam whilst adhesive curing takes place
Awareness of limitations of adhesive in adverse weather conditions
Where possible the lines to the perimeter of the pitch are to be tufted in to the fabric of the carpet.
All other play lines are to be cut and stuck into the playing surface leaving no surface irregularities.
Contractors are to price for tufted-in lines where practical, and cut-in and taped play lines.
The play lines are to be laid out as shown on the drawings incorporating a 100x64m football pitch.
The Contractor is to be aware of, and take account of, the potential use of the carpet for cross field
play mode when designing the synthetic turf system.
2.8.0 11-A-SIDE FOOTBALL FIELD MARKINGS
All lines are to be white and of uniform width, 100mm wide.
100 x 64m plus 3m run-off areas as set out in drawings. The field of play is divided into two halves by
a halfway line.
The centre mark is indicated at the midpoint of the halfway line. A circle with a radius of 9.15 m (10yds)
is marked around it.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
24
Langley Academy – Detailed Specification
2.8.1 The Goal Area
A goal area is to be defined at each end of the field as follows:
Two lines are drawn at right angles to the goal line, 5.5 m (6yds) from the inside of each goalpost.
These lines extend into the field of play for a distance of 5.5 m (6yds) and are joined by a line drawn
parallel with the goal line. The area bounded by these lines and the goal line is the goal area.
2.8.2 The Penalty Area
A penalty area is defined at each end of the field as follows:
Two lines are drawn at right angles to the goal line, 16.5 m (18yds) from the inside of each goalpost.
These lines extend into the field of play for a distance of 16.5 m (18yds) and are joined by a line drawn
parallel with the goal line.
Within each penalty area a penalty mark is made 11 m (12yds) from the midpoint between the
goalposts and equidistant to them. An arc of a circle with a radius of 9.15 m (10yds) from each penalty
mark is drawn outside the penalty area.
2.8.3 Corner Flags
A flexible post, not less than 1.5 m (5ft) high, with a non-pointed top and a flag is to be installed at
each corner of the main pitch. These are to be removable but fixed for play by way of suitable cast
concrete foundations beneath the carpet and are to be supplied by the Contractor, the flags and posts
must be FIFA approved.
2.8.4 The Corner Arc
A quarter circle with a radius of 1m (1yd) from each corner flag is drawn inside the field of play. Main
pitch only.
2.8.5 Goals
FIFA Standard goals, supplied by the Contractor, must be placed on the centre of each goal line. The
Contractor is to provide:
•
•
1 pair of Mark Harrod FOT - 600 Full size aluminium elliptical goals. 7.32 x 2.44m (24ft x 8ft)
self- weighted goal set
I set of Mark Harrod FOT - 205 Spring back removable corner poles with suitable socketed
foundations concreted in to the base formation
Notes: 11-A-Side goals are to consist of two upright posts equidistant from the corner flag posts and
joined at the top by a horizontal crossbar. The distance between the posts is 7.32m and the distance
from the lower edge of the crossbar to the ground is 2.44m.
Both goalposts and the crossbar are to have the same width and depth. The goal lines are to be the
same width as that of the goalposts and the crossbar. Nets may be attached to the goals, provided
that they are properly supported and do not interfere with the goalkeeper. The 7-a-side goals and the
11-a-side goals are to be moveable self-weighted goals with retractable wheels for ease of movement.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
25
Langley Academy – Detailed Specification
The Contractor is to supply pitch protection measures to reduce damage to pitch surface by freestanding goals, these are to be easily carried by one man.
The goalposts and crossbars must be white. These are to be free-standing but capable of being fixed,
or weighted, to the ground and incorporate wheels for ease of movement when required.
2.9.0 SEVEN-A-SIDE PITCHES FIELD MARKINGS (supply goals only)
FIFA Standard goals supplied by the Contractor to provide:
•
2 pairs of Mark Harrod FOT - 605 self-weighted mini soccer goals 3.6m x 1.83m (12ft x 6ft) for
storage in existing pavilion.
7-A-Side goals are to consist of two upright posts equidistant from the corner of the 7-a-side side lines
and joined at the top by a horizontal crossbar. The distance between the posts is 3.6 m and the
distance from the lower edge of the crossbar to the ground is 1.83m.
Both goalposts and the crossbar are to have the same width and depth which do not exceed 125mm
(5ins). The goal lines are to be the same width as that of the goalposts and the crossbar. Nets may be
attached to the goals, provided that they are properly supported and do not interfere with the
goalkeeper.
2.10.0 Fencing
Supply and install a 3.0m high rigid weldmesh fence along each side of the pitch. Posts and panels to
be galvanised and powder-coated (colour TBC). All fencing works shall be undertaken in accordance
with the appropriate sections of BS 1722.
All mesh and posts shall be galvanized in accordance with BS EN ISO 1461. Post caps shall be fitted to
tops of all hollow section posts. Where required, powder coating shall be in accordance with BS EN
6497.
-
Supply and install a 4.5m high rigid weldmesh fence along each end of the pitch (incl. goal
recesses). Posts and panels to be galvanised and powder-coated (colour TBC)
Allow for 1 no. Double gate and 2 no. single gates to match above
Allow for 40m section of 8m high Ball stop netting at each end
Allow for 2 mechanical, fully netted pitch dividers
There shall be no protruding fence (or other) fixings within the pitch boundaries. All fixing bolts shall
be assembled with heads inside and bolts trimmed to within 6mm of the nut. The trimmed ends should
be burred and treated or shear head nuts used. On low level fencing no mesh ends or straining wire
shall cause hazards to players, or spectators, particularly children.
In accordance with planning permission and drawing S14-158-001A the existing fence line in the South
East corner should be straightened with the removal and relocation (within the site) of 3 young trees
to facilitate the relocation of the changing rooms.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
26
Langley Academy – Detailed Specification
2.11.0 Floodlighting
The floodlighting scheme should be designed by recognised Sports Lighting Contractor to meet CIBSE
Guide to Sports Lighting recommendations.
System to achieve 223 Lux maintained.
Construct concrete foundations suitable for floodlight columns. Allow for installation of holding down
bolts, in-situ concrete footings and formwork.
Excavate cable trenches around the perimeter of the pitch. Allow to lay cables onto sand/dust bed
and surround. Backfill to surface with “as dug” material.
Supply and install onto concrete foundation 8no. 13m high, raise and lower columns providing an LED
lamp system to meet the required Lux standard – See AAA LUX WS Series from Abacus, or similar and
approved. As an option please provide a costing for the alternative M/H system - 20no. 2kW
floodlights.
Allow to supply and install a feeder pillar and connect to mains supply.
Floodlighting design criteria
The floodlighting system shall meet the specified lighting and uniformity levels as required and be in
full compliance with any conditions of the planning approval for the project.
The works shall include the provision of all luminaries, cowling, columns, mains distribution switch
gear, sub-circuit protective devices, metering, and control devices and the associated cabling,
trenching, ducting & draw pit installation, back filling and making good.
All works shall be carried out in accordance with the latest edition of the IEE Wiring regulations.
Floodlighting column bases
The Contractor shall take full account of the ground conditions when designing the bases for the
floodlighting columns. Base plates shall be arranged to ensure all fixing bolts are concealed and cannot
constitute a trip hazard.
Floodlighting system protection
System protection shall include Mccb’s, rates for the prospective load of the proposed installation and
selected to match the required fault level. The arrangement of the power distribution at the
distribution point shall provide short circuit and excess current protection for all sub-circuits.
Adequate discrimination between main Mccb and sub-circuit protective devices shall be included.
Floodlighting earthing
All necessary earthing and cross bonding shall be provided in accordance with the current edition of
the IEE Wiring Regulations.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
27
Langley Academy – Detailed Specification
Floodlighting system management
Individual Mccb protection shall be provided for each control circuit.
A master time clock with battery backup shall be provided to turn off the floodlights at the
programmed time. The clock shall allow for the seasonal changeover from GMT to BST. A key switch
for manual override shall be provided.
The management system shall include a system of visual warning to warn users the cut-off time is
approaching. This shall be achieved by switching a flashing beacon mounted on the floodlight column.
One beacon shall be installed for each operational section of the pitch. The beacons shall be
programmed to operate five minutes before the cut-off time. They shall only operate if any element
of the floodlighting is in use.
The management system shall ensure one luminaire on each operational portion of the pitch remains
in operation for five minutes after cut-off of the main pitch lighting.
A set of manual override switches shall be provided for test and emergency control of the lights.
A Kwhr meter shall be provided to monitor the total power used by the floodlights. An ‘hours run’
facility shall also be provided to identify the cumulative time each group of floodlights serving the
pitch has been in operation.
Floodlighting cables
Cabling at the central distribution point and to columns shall be carried out in correctly sized XPLESWA
cable.
All necessary control cables shall be provided for the connection of controls within column gear trays
to the main switchgear position.
Cables in the soft ground shall be buried in trenches to a minimum depth of 500mm. Where applicable
(as detailed in the IEE Wiring Regulations) cables shall be laid on a bed and surround of sand 150mm
thick.
Buried cables shall be identified along their entire length with yellow marker tape installed
150mm from ground level. The marker tape shall be labelled DANGER-ELECTRIC CABLE BELOW.
Floodlighting ducting & draw pits
Cable ducting shall be installed in all hard landscaping so, in conjunction with draw pits, they provide
an underground containment system to allow the future re-cabling of the lighting system.
Unless otherwise specified ducting shall comprise 100mm diameter minimum rigid plastic ducting
pipe, with flexible ducting where necessary. All ducting shall be buried to a minimum depth of 450mm
and cable warning marker tape shall be laid 150mm above ducting. Service ducting and draw pits shall
include secured draw ropes.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
28
Langley Academy – Detailed Specification
Draw pits shall be installed at each floodlight column and at all changes of direction. They shall be preformed, be a minimum of 450mm diameter or 450mm by 450mm square and have lockable removable
lids. They shall be installed prior to the installation of the ducting. Where stacked plastic sectional
draw pits are used duct entries shall be drilled to avoid weakening of the structure.
Allow for an additional 110mm diameter duct with draw cord to hold cables for Fire Alarm and CCTV.
These may or may not be installed during construction or retrospectively.
Small power
Single socket outlets, common key controlled and RCD protected, shall be provided to at least two
floodlight columns (or more if specified by the Employer). Each shall be terminated within the base
of the column. The fitting shall be of a proprietary make and weatherproof. Where columns are sited
outside the perimeter fencing of the pitch, provision for passing plugs through the fence from the
pitch to the columns shall be made.
2.12.0 SPORTS & MAINTENANCE EQUIPMENT
The Contractor shall supply and erect sports & maintenance equipment and fixtures as stated above.
All equipment shall be in accordance with the relevant rules of the sport and comply with all relevant
British Standards.
•
•
•
•
•
•
1 x set of Football goals (full size) shall comply with BS EN 748. Nets shall be heavy duty
3 x sets of Seven-a-side metal goals shall comply with PAS 36-1. Nets shall be heavy duty
1 x set of full-size self-weighted Hockey goals
Ride-on Tractor – e.g. Single Cylinder 15hp Briggs & Stratton Engine (Series 5; Series 3.5)
Maintenance – Dragmat & Flexicomb, or similar
Corner Posts and flags
All football goals shall be self-weighted and supplied with retractable wheels for ease of movement.
All full-sized equipment to be to FIFA or FIH standards.
2.13.0 QUALITY CONTROL TESTS
All laboratory and field tests are to be arranged, coordinated and paid for by the Contractor.
2.13.1 Test houses
Testing institutes must be accredited by FIFA. Testing institutes can therefore only be chosen if they
can demonstrate that they have the appropriate experience and ISO accreditation.
It will be the responsibility of the testing institutes to satisfy themselves that the product installed is
the same as the product submitted for type testing prior to tender.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
29
Langley Academy – Detailed Specification
This will be achieved by undertaking the following steps:
•
•
•
All products manufactured must submit a certificate of compliance to the effect that the
product dispatched is the same as the product submitted for type testing in accordance with
procedures to be run under their IEC 17025 1999/ISO 9002 or similar scheme. These
certificates must be dispatched and have been received by the institute before any product
leaves the place of manufacture for the installation site
If the testing institute has any reasonable cause for concern, it may request samples of the
manufactured products for product identification
Any minor change in the product profile must be proven to satisfy the requirements of the
scheme. Any significant change will require a complete re-evaluation of the product
All the equipment used must be registered within those procedures. It is not sufficient to only have
certain pieces of equipment complying with the demands and not others.
Furthermore the same pieces of apparatus must be utilised in both the laboratory tests and the field
tests to ensure consistency. Variations on equipment cannot be accepted. The test institutes must
provide the appropriate certification to verify this and that the certification is maintained.
The Test Institutes must also provide evidence of the experience of all the staff that would be used to
undertake the testing. The use of inexperienced casual staff is not acceptable.
Testing of the synthetic pitch should be undertaken by a test house that is:
•
•
•
•
Accredited as a FIFA testing house
Accredited by the United Kingdom Accreditation Service (UKAS) or other recognised
accreditation services or the relevant sport governing body
The chosen laboratories must therefore be within the ISO schemes ISO/IEC 17025 1999 and
ISO 4502
A member of SAPCA’s Professional Services Group
2.13.2 Sampling
An artificial surface is defined as the total system including the support layers.
Therefore the testing of the surface will occur both within a Laboratory environment (type testing)
and upon the completed installation. Certification according to ISO 17025 is a requirement. A product
will undergo a series of tests to establish its suitability for installation.
Once installed the performance requirements together with the construction requirements will be
checked. Only a product that has completed both the laboratory and field-testing will it have filled the
requirements of this specification. Accordingly only the fully certified pitch will be considered
completed upon the return of successful testing certificates from a recognised artificial sports pitch
testing house.
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
30
Langley Academy – Detailed Specification
2.13.3 Seam Testing
During each day of the synthetic turf installation and play line installation the contractor shall prepare
a seam sample measuring at least 500mm by 500mm with the seam running down the middle. The
samples shall be left adjacent to the synthetic pitch for at least 48 hours before being sent to the
nominated test house for the determination of seam strength.
Test specimens shall be prepared in accordance with manufacturer’s instructions. All field test
specimens (other than those being prepared for simulated use, tests at ambient and elevated
temperatures and artificial weathering) shall then be conditioned prior to test by passing a handpulled roller over the test specimen for 50 cycles (one cycle comprises one outward and one return
path)
2.13.4 Preparation of Test Specimens
Test specimens shall be prepared in accordance with testing laboratory instructions.
All filled test specimens (other than those being prepared for simulated use, tests at ambient and
elevated temperatures and artificial weathering) shall then be conditioned prior to test by passing a
hand-pulled roller over the test specimen for 50 cycles (one cycle comprises one outward and one
return path)
2.13.5 Pre-Tender Performance Tests
Tests on the proposed sample system, carpet and shockpad, will be required to be carried out by a
certified sports surfaces testing laboratory at no cost to the project and arranged by the sports
surfacing supplier. The results of laboratory tests on the whole synthetic pitch system proposed are to
be provided as part of the Contractor’s tender return documents.
The following tests are to be carried out and the results supplied pre-tender those marked with an
asterisk are to ensure that the proposed carpet system can be laid to the current FIFA 1 star and FIH
National standards:
•
•
•
•
•
•
•
•
•
Ball Rebound*
Shock Absorption*
Vertical Deformation*
Ball Roll* – wet and dry
Angle Ball Roll* – wet and dry
Rotational Resistance – wet and dry
Stud Slide – wet and dry
Stud Deceleration – wet and dry
Water Permeability
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
31
Langley Academy – Detailed Specification
2.13.6 Performance Tests Required for Completion
Upon completion of the construction the Contractor will arrange a field test in accordance with FIFA
1 star. Samples will be taken from the live field and further testing will take place in the laboratory to
identify the type and standard of the finished system and to ensure that it matches what was originally
lab tested.
2.14.0 WARRANTY
The Contractor shall provide a written warranty that the properties of the combined surface and
foundation construction shall be retained within the limits given in this document for a period of eight
years or throughout the period stated in this document, whichever is greater, subject to correct
maintenance and the stated patterns of usage.
The Contractor shall provide a written warranty that the properties of any shockpad shall be retained
for a period equal to two carpet lifetimes, subject to the correct maintenance and the stated patterns
of usage.
The Contractor shall provide clear and concise explanation of methods and checks by which Langley
Academy can ensure that any circumstances under which the warranty may become void are identified
early, and in particular, before any warranties are affected.
2.15.0 REFERENCES
•
•
•
•
•
•
The Specification for Highway Works (December 1991 reprinted 1993), Department of
Environment
BS 5835-1: 1980. Recommendations for testing of aggregates Compactibility test for graded
aggregates
BS 1377: Part 2 and Part 9:1990, Methods of test for soils for civil engineering purposes
Classification tests
BS 4962:1989 Specification for plastics pipes and fittings for use as subsoil field drains
BS 882:1992, Specification for aggregates from natural sources for concrete
BS 5911: Part 2:1982, Precast concrete pipes, fittings and ancillary products
Specification
•
•
•
•
•
•
For inspection chambers. BS EN 124:1994, Gully tops and manhole tops for vehicular and
pedestrian areas
Design requirements, type testing, marking, quality control BS 3148: 1980, Methods of test
for water for making concrete (including notes on the suitability of the water)
BS 812: Part 103: 1985, Testing aggregates, methods for determination of particle size
distribution. Sieve tests
Specification for constituent materials and for mixtures.
BS 7263: Part 1:1994, Pre-cast concrete flags, kerbs, channels, edgings and quadrants.
BS15330: Part 1: 2005 Surfaces for sports areas — Synthetic turf and needle punched surfaces
primarily designed for outdoor use – Specification for Synthetic Turf
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
32
Langley Academy – Detailed Specification
Tender ChecklAist








Completed pricing document
Draft program of works
Technical Data Sheet for 3G system proposed
FIFA/FIH Laboratory Reports for system proposed
Current FPP Certificate
List of references
Overview of experience, CDM capability, Quality Management, Health & Safety & Insurances
Samples of proposed artificial turf and shockpad
Prepared by Breen Associates Tel: +44 (0)1753 647622 or +44 (0)7557 906898 or
e-mail: bob@breenassociates.co.uk
33
Download