Water Quality and Quantity Management 2012 Drilling of private boreholes. In 2012 the Water Development Department (WDD) issued 751 licences for the drilling of irrigation boreholes and 484 licences for the drilling of boreholes for domestic purposes, of which 435 and 105, respectively, were issued with respect to boreholes that had already been drilled illegally. As we were informed by the Director of the WDD, due to repeated extensions granted by the House of Representatives regarding the amnesty for issuing permits for boreholes that were drilled illegally, Cyprus may not comply with the Water Framework Directive (2000/60/EC) and it is likely that financial sanctions will be imposed by the European Union. The Director also noted that Cyprus is required to achieve good status in its aquifers by 2015, while continuing extensions of the amnesty encourage continued illegal drillings and pumping water from aquifers that have become brackish, without the WDD being able to take action against offenders. Purchase of water from desalination plants. Following the recent completion of the desalination plants in Vassiliko and Episkopi, the annual total capacity of the desalination plants amounts to 92 million m3. According to the contracts that have been signed, the State is bound to cover the capital cost and part of the operating expenses in the case of a plant being put in standby mode, e.g. in periods of high rainfall. As mentioned in our 2012 report on adaptation to climate change, the WDD proceeded with the construction of desalination plants of a capacity greater than the total needs for potable water supply, without a prior feasibility study to determine the optimum number, type (temporary or permanent) and capacity of the plants. We expressed the view that, rather than relying solely on desalination plants for meeting potable water demand, it would be more economical to combine the use of desalinated water with the use of water stored in dams, the treatment cost of which is significantly lower. The cost of purchasing water from desalination plants in 2012 was €34,17 million plus VAT, representing the value of 17,4 million m3 of water, compared to €63.78 million for 47,17 million m3 in 2011. The increase in the average cost of production of desalinated water, from €135/m³ in 2011 to €1,96/m³ in 2012, is mainly due to the fact that the desalination plants of Paphos and Episkopi were in standby mode and, although no water was produced by these plants, the cost of their operation was €9,65 million. The Director of the WDD informed us that the increase is mainly due to the increasing cost of electricity, and the fact that desalination plants were placed either in standby mode or in reduced operation. He also noted that the decision to construct desalination plants was a political one, and the WDD acted in accordance with the decisions of the Council of Ministers, based on which the aim was to achieve full independence of water supply from weather conditions. The Minister of Agriculture, Natural Resources and Environment, stated that, in 2012, the total contractual obligation for desalinated water production was 52,6 million m³/year, while in 2013, with the completion of two new plants in Episkopi and Vassiliko and the termination of the temporary desalination plant of Garyllis, the total contractual obligation amounted to 82,1 million m³. He also noted that the contract of the Paphos temporary desalination plant expires at the end of 2013. Domestic Sewage and Industrial Waste Processing Unit in Vathia Gonia – Recycled water production. During 2012, a total of 2.422.958 m3 of recycled water (1.930.266 m3 in 2011) was produced by the Vathia Gonia Unit and the wastewater treatment plant of the Sewerage Board of Nicosia, of which only 800.000 m3 (925.827 m3 in 2011), or 33% of total production, was used for irrigation. As mentioned in our previous Report, the difference between produced and distributed quantities of recycled water arises due to its disposal during the winter months as a result of reduced demand. On 5.12.2012, the WDD signed a contract for the construction of a 500.000m3 earthen reservoir in Vathia Gonia, to store the water produced by the wastewater treatment plants. Production and management of water from tertiary wastewater treatment plants. In 2012 20,2 million m3 of recycled water were produced in urban wastewater treatment plants, excluding the Mia Milia plant which lies in the occupied part of the island, of which 9,5 million m3 were used for irrigation, 3,8 million m3 were used to supplement the Ezousa aquifer, 0,2 million m3 were stored in the Polemidia dam, 3,6 million m3 were dumped in the sea and 0,8 million m3 were released in the Ovgos river over the winter period. We were informed that the inability of the WDD to ensure utilisation of the treated water is mainly due to the lack of infrastructure such as irrigation systems for water distribution and storage reservoirs in which to store water during the winter months, when demand is low. The Minister of Agriculture, Natural Resources and Environment noted that the Mia Milia wastewater treatment plant, which, during 2012, had produced 8,5 million m3, is situated in an area which is not under the control of the Republic, a fact which implies that the construction of infrastructure is necessary to convey the water through the buffer zone to the Vathia Gonia plant, an extremely difficult endeavour under the present circumstances. In case the infrastructure is completed, 21.000m3/day will be conveyed to Vathia Gonia, a quantity that could not be utilised locally, given the increasing production of the Vathia Gonia Plant. The issue was examined in the past by the WDD and it was suggested to desalinate the water and use it to irrigate the Kokkinohoria area through the South Conveyor system. The proposed solution caused intense reactions due to the disposal of brine into the sea. The matter was re-examined in 2010 and a final conclusion was reached to use the recycled water in the broader Nicosia area to irrigate municipal parks and cultivations. We repeated the view that the WDD should consider ways of improving the use of recycled water produced, so that water stored in dams is released for other uses. The Director of WDD informed us that the Department has performed feasibility studies and environmental impact studies of possible uses of the recycled water produced by the plants in Larnaca and Anthoupolis, however the necessary funds to complete the infrastructure are not available. Furthermore, the Director noted that the Department has repeatedly raised the issue of the increasing quantities of recycled water that will result with the completion of the second phase of the Larnaca sewerage system and the subsequent problems in the use of this water. Water supply to golf courses. As is described more extensively in our previous Reports, on 16.2.2005 the Council of Ministers approved a policy to encourage investment in golf courses, explicitly noting that no applications to irrigate new golf courses using boreholes or government dams will be approved, with the exception of the four existing golf courses in Paphos District, which would continue to be irrigated according to previously reached agreements. With its later decision dated 5.2.2009, the Council of Ministers approved that the water supply from governmental water works to three of the existing golf courses is terminated, and that the courses are irrigated with water produced by a desalination plant operating on electricity produced by renewable energy sources. Furthermore, with its decisions dated 3.6.2009 and 27.1.2011, the Council of Ministers approved annual extensions for the supply of water to the licensed courses under the agreed regime, so that the necessary time is given for the investors to conform with the provisions of the Decision dated 5.2.2009. Given the lengthy procedures required for the licencing and construction of the private desalination plants, the Ministry of Agriculture, Natural Resources and Environment suggested to the competent Ministerial Committee that the licensed courses are given a time extension of two years, i.e. up to 3.6.2013. Despite the fact that the suggestion was not adopted or put before the Council of Ministers for approval, the WDD continues to provide water to these courses from government water works. Consequently, in 2012 398.365 m3 of water were supplied for this purpose from the Paphos Irrigation Project and 365.698 m3 from the Ezousa aquifer, which is supplemented with recycled water. The WDD, with its letter dated 3.12.2012 to the Permanent Secretary of the Ministry of Agriculture, Natural Resources and Environment, repeated the need for the Council of Ministers to reach a decision on whether to grant a further extension for the supply of water to licensed golf courses from government water works / sewerage systems. Alternatively, the WDD recommended that the matter is dealt with by the Ministerial Committee, as per the Decision of the Council of Ministers dated 3.6.2009, according to which the Committee can negotiate the terms of each complex, without submitting the matter to the Council, unless in the case of a dispute between its members. As described in our previous Reports, the imminent operation of a wastewater treatment plant in Polis Chrysochous is expected to produce large quantities of recycled water and we suggested that timely arrangements are made for the utilisation of any quantities remaining after satisfying agriculture needs, for the irrigation of golf courses in the area. Based on our suggestion and following the request of an investor for the irrigation of two golf complexes with recycled water produced by the tertiary wastewater treatment plant in question, the matter was forwarded to the Council of Ministers which granted its approval on 30.8.2012. Additionally, at the request of interested companies and following a technical evaluation of the relevant government departments (Department of Environment and WDD), the terms for the water supply to certain golf complexes were modified with subsequent Decisions of the Council of Ministers dated 31.1.2012 and 30.8.2012. These Decisions approved the provision of recycled water to serve the irrigation needs of another three complexes and the provision of potable water to these from government desalination plants or dams. The applicants have undertaken to construct and operate the necessary water conveyance infrastructure. Furthermore, the WDD has prepared a proposal for the revision of the arrangements of water supply to golf complexes, which was approved by the Ministerial Committee on 5.6.2013 and was sent to the Ministry of Energy, Commerce, Industry and Tourism, to be incorporated into the Proposal to be submitted to the Council of Ministers. According to the Proposal, all irrigation needs of golf complexes could be covered by tertiary sewage treatment plants and the recycled water provided will be invoiced based on the full cost of tertiary treatment and conveyance, plus environmental costs. Potable water supply may be covered by government water systems and dams, and the price charged will be equal to the price of potable water supplied from government water systems plus environmental costs. Quality of potable water in Communities. As is extensively described in our previous Reports, according to the results of a relevant study completed in May 2010, the sources and boreholes used for water supply in several Communities are continuously degrading due to the increased water demand, the repercussions of over-pumping and insufficient replenishment as a result of climate change. In our previous Reports we expressed the view that the problem of ensuring adequate water supply to affected Communities should be addressed by the WDD so that the timely measures are taken to deal with it. The WDD has completed a census of all boreholes used for potable water supply and carries out regular monitoring lab tests to boreholes used as the sole drinking water source in Communities with no other water sources. Upon application of the procedures protocol in 2010, local authorities are promptly informed in cases of results beyond tolerable levels. However, in certain cases, local authorities of Communities that are connected to an urban water supply network, continue to use water from problematic boreholes for cost saving purposes, placing public health in potential risk. We noted that, based on the Law on the Quality of Water for Human Consumption (Monitoring and Control), the responsibility for maintaining the quality of water supplied to the public lies with the local authority. However, the Law does not define sanctions in cases of non-compliance. The competent Authority for the implementation of the Law is the Director of Medical and Public Health Services. The Director of WDD informed us that the procedures protocol is being implemented and the system operates without serious problems. Protection zones for potable water supply boreholes. According to Regulatory Administrative Act (RAA) 707/2004, the WDD is defined as the competent Authority for determining protection zones around each borehole for potable water supply, with the objective of limiting groundwater pollution. The WDD has so far defined protection zones for 140 out of the roughly 475 potable water boreholes that were recorded by the WDD in December 2011. Furthermore, the WDD is in the process of issuing a Decree for another 60 boreholes and, in consultation with the Department of Town Planning and Housing regarding the review of the urban area plans, the WDD preliminarily defined zones for another 201 boreholes. Following the conclusion that the method followed to define protection zones based on Decree 45/96 does not sufficiently protect the water from chemical pollutants, the Geological Survey Department, in collaboration with the WDD, is promoting its modification. Due to the upcoming modification of Decree 45/96, the issue of Decrees to define new protection zones has been suspended since 2011. Protection zones for dams used for potable water supply. According to the Water Framework Directive (2000/60/EC) “member states shall implement the necessary measures to prevent deterioration of the status of all bodies of surface water" and for this purpose “may establish safeguard zones for those bodies of water". In Cyprus, the surface sources of potable water consist of 11 dams (reservoirs), while another two dams are planned to be used for potable water supply. In order to determine protection zones for these 13 dams, the WDD has submitted a draft Decree to the Law Office of the Republic for legal review. Directive 2000/60/EC of the European Parliament and of the Council establishing a framework for Community action in the field of water policy. (a) Water pricing policies. According to the provisions of the above Directive, member states should have ensured, by 2010, that water-pricing policies provide adequate incentives for users to use water resources efficiently and thereby contribute to the environmental objectives of the Directive, while the water-pricing policies are such that enable the recovery of the costs of water services. In order to conform with the Directive, the WDD prepared draft Regulations on water pricing, which were approved by the Council of Ministers in July 2011 and were submitted to the House of Representatives for enactment. Following a request by the substitute Permanent Secretary of the House of Representatives, the Regulations were withdrawn and the Permanent Secretary of the Ministry of Agriculture, Natural Resources and Environment re-submitted them on 24.4.2013, while new withdrawals and re-submissions were made on 5.7.2013 and 13.9.2013. (b) River Basin Management Plan and Programme of Measures. In order to meet national obligations resulting from the Water Framework Directive, the Council of Ministers approved, on 9.6.2011, the River Basin Management Plan, which was submitted to the European Commission, while procedures have been initiated for the implementation of the Programme of Measures which was prepared as per article 11 of the Directive. According to article 11(7) of the Directive, the programmes of measures should be operational by the end of 2012 at the latest. According to the report submitted by the WDD to the European Commission on 22.12.2012 regarding the progress on the implementation of the Programme of Measures, satisfactory progress has been noted in the implementation of the Programme in terms of achieving the environmental targets of the Directive, particularly considering the difficulty in ensuring the necessary funds. The report notes that the implementation of 24% of the basic measures and 32% of the supplementary measures has not yet begun. It is also mentioned that the measures that have not yet been implemented involve considerable financial cost and for this reason their implementation will be postponed until 2015, as per the Decision of the Council of Ministers dated 9.6.2011. We noted that these measures include water pricing, since the enactment of the relevant legislation is still pending, as well as measures on the monitoring and restoration of groundwater bodies at risk, the implementation of which is hindered by the continuous extensions granted for legalising non-licenced boreholes. The WDD considers these measures to be the most important for the fulfilment of the national obligations under the Framework Directive. (c) Report from the European Commission to the European Parliament and the Council on the implementation of the Water Framework Directive. According to the provisions of article 18 of the Water Framework Directive, the European Commission submitted to the European Parliament and the Council a report on the implementation of the Directive. The report includes, inter alia, a review of the progress made in the implementation of the Directive and the River Basin Management Plans, including proposals to improve future Plans. The report is accompanied by working documents with detailed assessments of plans submitted by each member state. The document regarding Cyprus provides recommendations regarding the completion of the first Plan (2009-2015) and the preparation for the second Plan (2015-2021), which include: (i) Improving the quality of monitoring. (ii) Measures to tackle water demand and illegal abstractions. (iii) Increasing the reuse of treated waste water in existing irrigation networks. (iv) Designing a clear strategy in the agriculture sector, that defines the basic/mandatory measures that all farmers should adhere to and the additional supplementary measures that can be financed. (v) Cost-recovery for a broad range of water services, also when they are "self-services", for instance self-abstraction for agriculture. Illegal dams/extractions (a) Illegal construction of private dam. As discussed in our previous Reports, around 1973 a small diversion dam was illegally constructed near the mouth of the Ha river, and was extended in 2002-2003. Since then, the water stored in the dam, of a total capacity of 500.000 m3, has been used by a company to irrigate a nearby golf course with no charges being imposed by the WDD with regard to the quantities of water used. On 20.11.2012 the Council of Ministers approved the issue of a licence to the company for use of part of the river according to terms approved by the competent Ministerial Committee, and the company applied for the re-issue of the planning permit revoked, following the rejection of the company’s application for a permit to intervene in government land by the Council of Ministers in 2008. The WDD, with its letter to the Department of Town Planning and Housing dated 5.3.2013, suggested the inclusion of terms on the permit to be issued, regarding, inter alia, the fulfilment of legal provisions regarding the dam’s safety and the payment to the WDD of a resource and environmental cost corresponding to the quantities extracted, initially set at €0,11/m3. (b) Construction of a private dam in the "Anatoliko" area in Paphos District. The dam in question was constructed illegally by the Holy Monastery of St. Neophytos for the irrigation of plantations in the area. The dam was subsequently managed by a paper mill cooperative, which upgraded the dam with improvement works, such as adding an overflow. Following the closure of the industry, the dam is again used by the Holy Monastery of St. Neophytos. We were informed by from the Paphos District Engineer that the WDD has not taken, nor plans to take, any measures to address the issue. (c) Part use of a riverbed by the packing plant of a private company in Nicosia. The WDD, in its letter dated 23.3.2007, informed the Nicosia District Officer that a company engaged in growing and packing fruit and vegetables, has illegally constructed three small embankments / storage dams on the bed of Pedieos river, which store water during the winter, for the irrigation of about 6 decares of farm land. Since the constructions were completed without the necessary studies, the WDD requested the submission of hydrological, stability and safety studies, as well as a study regarding the strengthening or modification of the existing structures, in order to be able to express an opinion with respect to the licensing of the embankments / dams. On 18.1.2010 the company applied to the District Officer requesting permission to use part of the riverbed and the District Officer forwarded the hydrological study prepared by the company, to the WDD, on 16.3.2010. The WDD identified several safety issues, which the company undertook to resolve. As we were informed by the Department, the company proceeded to fence in the embankments as requested, and remove pumping mechanisms from the river. The Nicosia District Officer filed a lawsuit against the company, following which the Nicosia District Court, with its decision dated 22.6.2012, imposed a fine of €550 and issued an order for demolition of the embankment within two months. As we were informed by the Director of the WDD, in consultation with the District Administration Officer, it was decided that the structure is not demolished, provided that the company will perform all the corrective measures suggested by the WDD, will terminate use of the structure and ownership of the project is transferred to the WDD, which will decide on its use as deemed appropriate. (d) Illegal water abstraction by a company in Lakatamia. A company with extensive cultivations in Lakatamia, has constructed an artificial lake/reservoir, which it uses to store water for the irrigation of its crops, without having obtained a licence in accordance with the provisions of the Law. As a result of unlicensed abstractions, no fees are imposed on the company for the quantity of water extracted from the reservoir. The Director of the WDD informed us that the water stored by the company is recycled and purchased from the Anthoupolis wastewater treatment plant. The WDD will consider both licensing the project and the issue of a water abstraction licence under the provisions of the Water Law. (e) We inquired whether other similar incidents of illegal abstractions or constructions of illegal water works such have been identified by the WDD, in addition to those mentioned above. According to information we received from the Director of the WDD, the Department has launched a program to detect diversions from rivers, which is about 80% completed, and identified 300 diversions, both licenced and illegal. In some of these cases the WDD requested the owners to provide information regarding the design, construction method and general technical characteristics of these projects with a view to first ascertain their safety. However, no response has been received so far.