I-225 Rail Line 13th Avenue Station Information Meeting Thursday

advertisement
I-225 Rail Line
13th Avenue Station Information Meeting
Thursday, July 25
Doors open at 5:30 p.m., Presentation begins at 5:45 p.m.
Aurora Municipal Center, 15151 E. Alameda Parkway, City Council Chambers
Join us to learn about the design of the future 13th Avenue Light Rail Station. Opening in 2016, the I-225 Rail Line
will provide connections to:



City of Aurora
Anschutz/Fitzsimons Medical Campus
East Rail Line to Denver International Airport and downtown Denver
If you are unable to attend this meeting but have specific questions or comments about this project, please call Mindy
Parnes, Planning Case Manager, at 303-739-7238. You may also put your comments in writing and send them to
mparnes@auroragov.org or City of Aurora, Mindy Parnes, Case Manager at 15151 E. Alameda Pkwy. #2300,
Aurora, CO 80012.
For more information visit, http://www.rtd-fastracks.com/i225_1, email I-225@rtd-fastracks.com, or call the
construction information line at 720-863-8505.
COMMUNICATION ASSISTANCE AVAILABLE:
The following communication assistance is available for all RTD public meetings: language interpreters, signlanguage interpreters, assisted listening devices, alternate formats such as large print or reasonable
accommodations for special needs. Contact RTD at 303-299-6902 at least 72 hours prior to the meeting to discuss
your special needs and request for accommodations.
_____________________________________________________________________________________________
Lane Restrictions on Iliff Avenue at S. Abilene Street to Begin Week July 15, 2013
Segment 1 – Nine Mile to Iliff Station
• Ongoing closure/detour on E. Harvard Avenue through summer 2013
Area A – Iliff Station to Exposition Avenue
• East/westbound lane restrictions on Iliff Avenue at Abilene Street scheduled to start the week of July 8th were
delayed to re-evaluate and reduce traffic impacts. Westbound lane restrictions could start as early as the end of the
week of July 15 or the beginning of the week of July 22
• Right lane closure southbound Abilene Street from Mississippi to Jewell Avenues
• Intermittent lane restrictions and traffic delays on Abilene Street between Iliff Avenue and Mississippi Avenue for
Xcel Energy utility work
• Wall construction in multiple locations within the designated construction areas
• Look for trucks entering and leaving construction areas
_____________________________________________________________________________________
Kiewit crews will begin construction activities on Iliff Avenue at the S. Abilene Street intersection the week of July 8,
2013. Work will require lane restrictions with at least one lane in each direction remaining open. The first work
activities will involve the installation of a storm sewer line across Iliff Avenue. Once this work is complete, crews will
be beginning construction of the center pier for the light rail train bridge over Iliff Avenue. Storm Sewer installation will
occur in three phases and will begin at the northeast corner of the intersection.
• Phase One - three right lanes (including turn lane) on westbound Iliff Avenue closed
• Phase Two - two left lanes of eastbound and two left lanes of westbound Iliff Avenue closed
• Phase Three - three right lanes (including turn lane) on eastbound Iliff Avenue closed
Lane restrictions for bridge construction will change with the work activity; look for signage to direct you.
Although Iliff Avenue will remain open and access to local business will be maintained, through traffic is encouraged
to use Yale or Mississippi Avenues for travel east and west in the area. Motorists wanting to access Abilene Street
between Iliff and Mississippi Avenues should use S. Blackhawk Street to E. Evans Avenue to S. Abilene Street.
For more information.
Encourage your neighbors and co-workers to sign up for future I-225 Rail Line Construction Alerts.
Get More Information:
Website: I-225 Light Rail Line
Email: I-225@rtd-fastracks.com
Construction Information Line: 720-863-8505
* Construction activity updates reported are weather dependent and subject to change during design/build process.