S.NO.
1
2
3
EXISTING CLAUSE(s)
PART-A, Clause No. L(b) at
Page
10
of
117
:"The Geo-physical logging
probes shall include at
least SP, SPR, density,
caliper, resistivity, neutron
and natural gamma."
Part-B, Clause (B) (viii)
Page No. 33 of 117
"Prepare a comprehensive
forest rehabilitation and
conservation covering the
project as well as the
surrounding area."
Part-B Clause No. F, First
para, page No. 45 of 117:"Fee/payments
towards
conducting the DGPS/ETS
survey of the coal block
boundary
including
preparation of cadastral
based geo-reference coal
block map will be paid by
PFCCL directly to ORSAC."
4
Clause No. 11.9, page No.
52
of
117:"Any
statutory
fees/payments
to
the
Government authority(ies)
shall be made by PFCCL."
5
Clause No. 22.5, page No.
65
of
117:-
AMENDED CLAUSE(s)
PART-A, Clause No. L(b) at
Page
10
of
117
:"The Geo-physical logging
probes shall include at
least SP, SPR, density,
caliper, resistivity,
and
natural gamma."
Part-B, Clause (B) (viii)
Page No. 33 of 117
"Prepare a comprehensive
forest rehabilitation and
conservation plan covering
the project as well as the
surrounding area."
Part-B Clause No. F, First
para, page No. 45 of 117:"Fee/payments
towards
conducting the DGPS/ETS
survey of the coal block
boundary
including
preparation of cadastral
based geo-reference coal
block map will be paid by
PFCCL directly to ORSAC.
These payments shall not
be included in Bid Prices."
Clause No. 11.9, page No.
52
of
117:"Any
statutory
fees
/
payments
to
the
Government authority(ies)
shall be made by PFCCL.
These
fees/
payments
shall not be included in Bid
Prices."
Clause No. 22.5, page No.
65
of
117:-
REMARKS
Neutron
Geophysical
logging
is
deleted
from
scope
of
works
Typographical
error. Plan
word is added.
Clarification
given
for
correct
understanding
of bid prices.
Clarification
given
for
correct
understanding
of bid prices.
Clarification
given
for
"Any
statutory
fees/payments
to
the
Government authority(ies)
shall be made by PFCCL.
Any payment to ORSAC
shall be made directly by
PFCCL."
6
7
8
9
Form-6B, Sl.No.9 of Note,
Page No. 82 of 117:"Any
statutory
fees/payments
to
the
Government
authorities
shall be made by the
Client.
In addition to this any
payment to ORSAC will be
made
directly
by
the
Client."
Clause No. 22.1, Sl. No. 13
for Part-A, page No. 62 of
117:"On
receipt
of
MoC
approval for Mining Plan"
Form-6A, First Para, Line
1, 2 & 3 of Page No. 77 of
117:"I
_____________________________
____ (Name) on behalf of
_______________ (Name of
the
Consultancy Organisation)
herewith
submit
the
Financial
Pr
oposal
Consultancy
assignment for preparation
of Geological Report in
respect of"
Form 6A-1 S.No. 7 at Page
"Any
statutory
fees/payments
to
the
Government authority(ies)
shall be made by PFCCL.
Any payment to ORSAC
shall be made directly by
PFCCL.
These
fees/
payments shall not be
included in Bid Prices."
Form-6B, Sl.No.9 of Note,
Page No. 82 of 117:-"Any
statutory fees/payments to
the
Government
authorities shall be made
by PFCCL. In addition to
this,
any
payment
to
ORSAC
will
be
made
directly by PFCCL. These
fees/ payments shall not
be included in Bid Prices."
Clause No. 22.1, Sl. No. 13
for Part-A, page No. 62 of
117:"On
receipt
of
MoC
approval for
Combined
Mining Plan"
Form-6A, First Para, Line
1, 2 & 3 of Page No. 77 of
117:"I
_____________________________
____ (Name) on behalf of
_______________ (Name of
the
Consultancy Organisation)
herewith
submit
the
Financial
Proposal
Consultancy
assignment
for
preparation
of
Geological
Report
in
respect of"
Form 6A-1 S.No. 7 at Page
correct
understanding
of bid prices.
Clarification
given
for
correct
understanding
of bid prices.
Typographical
error.
Combined
word is added.
Typographical
error. Proposal
word
is
corrected.
Neutron
10
No.
79
of
117:"Bore hole Geophysical
Logging (SP,SPR, Density,
Cliper, Natural Gamma,
Neutron & Resistivity)"
Form 7C, First Para, Line 1
at Page No. 85 of 117:"We hereby enclose a brief
write up on the proposed
technical
&
financial
capability for"
11
------------ NIL
-----
No.
79
of
117:"Bore hole Geophysical
Logging (SP,SPR, Density,
Cliper, Natural Gamma &
Resistivity)"
Form 7C, First Para, Line 1
at Page No. 85 of 117:"We hereby enclose a brief
write up on the proposed
technical capability for"
Geophysical
logging
is
deleted
from
scope
of
works
Typographical
error.
"
&
financial
"
words
are
deleted.
Properly
aligned
the
para in line
with Sl No. 5
of Part-A at
page No. 57 of
117.
----------- New
Clause
No.24
is New
Clause
added at page No. 67 of added
117
as
follows:"24. Bidder's suggestion :Considering
the
availability
of
GR
for
Meenakshi Coal Block and
Preparation of GR for
Meenakshi-B and Dipside
of Meenakshi Coal Blocks,
timelines
/
completion
schedule (Clause No. 2.0,
page No. 45, 46 & 47 of
117) and methodology /
approach (Clause No. 3,
page No. 4 of 117) has
been finalised.
In
this regard, Bidders may
also
suggest
improved
methodology / approach
and timelines / completion
schedule based on their
experience in order to
achieve
approval
for
combined mining plan, EC,
all
other
approvals
/
clearances,
land
acquisition and forest land
diversion for all the blocks
together, keeping in view
the
end
objective.
Bidders may provide writeup detailing methodology /
approach and timelines /
completion
schedule
suggested
by
them.
However, Bid Evaluation
will proceed as per the
Tender Documents.