UrRisk04_example2

advertisement
UrRISK04
SRA 311.001
Fall 2014
Table/Row # 1
Student1 [bah5423]
Student2 [nxw5047]
Table of Contents
Introduction .................................................................................................................................................. 3
A)
Purpose ............................................................................................................................................. 4
B)
Scope of the Risk Assessment ........................................................................................................... 5
II. Risk Assessment Approach ....................................................................................................................... 6
III. System Characterization .......................................................................................................................... 9
IV. Threat Statement ................................................................................................................................... 10
V. Risk Assessment Results ......................................................................................................................... 11
A.
Threat/Vulnerability Pairs ................................................................................................................ 12
B.
Existing Risk Controls ....................................................................................................................... 13
C.
Likelihood: Discussion and Evaluation ............................................................................................ 14
D.
Impact: Discussion and Evaluation ................................................................................................. 15
E.
Risk Rating ....................................................................................................................................... 16
F.
Recommended Controls .................................................................................................................. 17
VI. Summary ................................................................................................................................................ 19
Reference List.............................................................................................................................................. 20
Attachment 1: Information Sheet .............................................................................................................. 22
Attachment 2: Structured Analytic Results ................................................................................................ 24
Attachment 3: Threat Analysis ................................................................................................................... 26
Attachment 4: Vulnerability Analysis .......................................................................................................... 27
Attachment 5: Risk Scenario Likelihood ..................................................................................................... 28
Attachment 6: Risk Scenario Impact ........................................................................................................... 29
Attachment 7: Risk Matrix .......................................................................................................................... 30
Attachment 8: Risk Rating .......................................................................................................................... 31
Attachment 9: Summary Table ................................................................................................................... 32
2
Introduction
This document is a risk assessment on the Lewistown, Pennsylvania Amtrak Station. The
structure of the risk assessment is based on the NIST 800-30 document. This introduction
outlines the purpose and scope of the risk assessment. Included next is an explanation of the
three-part risk assessment approach including a literature review, structured analytics, and a
virtual site visit. Following this, the system characterization is specified as an input-processoutput (IPO) model. Next, the threat statement specifies which threat categories are being
considered in the risk assessment and further defines these categories. Proceeding, the risk
assessment results include threat/vulnerability pairs, existing controls, likelihood, impact, risk
rating, and recommended controls. Lastly a high level summary is provided for the risk
assessment results. There are several supporting attachments as noted within the associated
sections of the document (Stoneburner, Goguen, & Feringa, 2002).
3
A) Purpose
The location of this risk assessment is the Lewistown, Pennsylvania Amtrak train station. This
station only has trains on the “Pennsylvanian” route which, runs between the cities of Pittsburgh
and New York. Furthermore, this station lacks several amenities offered by larger stations in
metropolitan areas such as a ticket office, kiosks, ATMs, elevators, lounges, storage, parking
services, handicap assistance, and passenger assistance.
A risk assessment is particularly important because a wide range of more than nine frequently
occurring factors, such as workload/mode transitions, expectations/situation awareness, and
equipment, contribute to preventable passenger train accidents. Furthermore, many single
accidents have several types of causal factors making the issue more complex and in need of
analysis (cross-reference Table 2: Causal Factors in Train Accidents in Attachment 1:
Information Sheet)
The point of view of this risk assessment is that of a train passenger. A train passenger is
concerned with two components of travel: safety and function. Safety is the assurance that the
passenger reaches his or her destination without injury or harm. The function is the train’s
ability to get the passenger from the source to the destination.
4
B) Scope of the Risk Assessment
The scope of this risk assessment is limited to the operational hazards of the train, as it
approaches and departs from the Lewistown station. There are several subsets of operational
hazards.
The first subset of operational hazards is severe weather, which includes the potential for
tornadoes and strong hurricane winds which have a strong impact on the structural integrity of
railroad tracks and trains. “Criteria for the safety risk from strong cross-winds may consider
overturning of the vehicle, the risk of a lateral track shift and the risk of a flange climbing
derailment” (Andersson, Häggström, Sima, & Stichel, 2004).
Another subset is the safety-critical control system that is in charge of controlling track
placement, acceleration, and braking. “The new train control systems employ newer technologies
and control architectures, such as positive train control (PTC) systems, train protection warning
systems, train collision avoidance systems, etc.” (Mokkapati, Tse, & Rao, 2009). While this
reduces the amount of human errors the train is susceptible to, it introduces more avenues for
potential threats and risks. “It is easy to refer to automation as if it were a well-defined and
homogenous category of technology. Clearly, however, this is not the case in reality” (Wreathall,
Woods, Bing, & Christoffersen, 2007).
The last subset is the human control of railroad operations, where the potential of outside
influence can be detrimental to set policies and standards. “Humans can play a very important
role in ensuring safety with the current train control systems” (Weathall, Roth, Bley, & Multer,
2003). Workers have access to a multitude of the train’s critical control systems and that creates
an inherent danger to people’s lives and properties.
Please reference Figure 1 below as a general diagram of the different areas of risk in a firm.
Each section is broken down into the specific risks that can be classified by that subgroup.
Please note that the scope of this risk assessment only includes operational risk. The product
market, financial, legal, regulatory, tax, and input risks will be beyond the scope of this risk
assessment.
Figure 1: General scope of enterprise risk sources (http://bit.ly/1icMuln)
5
II. Risk Assessment Approach
This risk assessment is being conducted by Student1 and Student2. Student1 is completing a
degree this year in Security and Risk Analysis (SRA) at The Pennsylvania State University. has
prior internship experience at KPMG, where he worked on a team to complete a technical
security assessment (vulnerability assessment and penetration test), as an installment to a risk
assessment. Student1 has extensive experience in technical security, research, and writing.
Student2 is also a senior at The Pennsylvania State University majoring in SRA with
specialization in information and cyber security. Student2 has conducted several in-depth reports
on system characterization and risk analysis that follow the NIST guidelines in his SRA courses.
This risk assessment uses a three-part approach to hazard identification including a literature
review, structured analytics, and a virtual site visit. The literature review contains a summary of
the relevant information provided from each professional source. The detailed literature can be
found in Attachment 1: Information Sheet.
The structured analytic technique used in this risk assessment is structured brainstorming. The
first step in structured brainstorming is divergence, which consists of freeform idea generation
without any criticism or constraints. The goal of this step is to generate as many ideas as
possible. The second step is convergence, in which ideas are placed into groups and ranked.
The result of this exercise is prioritized idea groups that can be seen in Attachment 2: Structured
Analytics (Glantz, 2014).
The virtual site visit part of the approach includes the analysis of site photos. By examining
these photos, risk that was previously unforeseen can be realized. For example, the gravel
ground surface and limited lighting which can be observed in Figure 2 and Figure 3 below
could pose a risk of passengers falling when exiting a train, which was not foreseen by the
structured analytic technique described above.
6
Figure 2 Lewistown, PA, Amtrak Station | 1 / 2 (Sturmovik, 2009)
Figure 3 Lewistown, PA PRR/Amtrak station (Whipp, 2014)
7
A risk matrix will be used to evaluate risk impacts and likelihoods. Each axis includes a numeric
scale so that comprehensive scores can be calculated by using products. For example, if the
impact is scored as a three and the probability is scored as a five, the overall severity score is
fifteen. Each cell is ranked by a very low, low, medium, high, or critical risk severity category.
The categories are based on the following ranges of risk severity scores: very low 1-5, low 6-10,
medium 11-15, high 16-20, and critical 21-25. In addition to their calculated score, these
categories are also designated by green, yellow, orange, red, and purple respectively. Please
reference Figure 4: Risk Matrix, below.
Probability
Impact
1
2
3
4
5
1
1
2
3
4
5
2
2
4
6
8
10
3
3
6
9
12
15
4
4
8
12
16
20
5
5
10
15
20
25
Figure 4 Risk Matrix
8
III. System Characterization
The flow of passengers entering and exiting the train safely can be visualized as a system. This
system can be modeled as an input-process-output (IPO) model. An IPO model helps to focus
threat, vulnerability, and asset identification.
This risk assessment is from the viewpoint of a passenger. As such, the set of IPOs in this model
directly relate to the passengers themselves. The input would be the passengers who board a train
at the station. The process is the safe transportation of passengers as they arrive at or depart
from the Lewistown station. The output is the passengers who exit their train at the station.
Figure 5: Basic Input, Process, Output Model, below is a visualization of an IPO model that
shows how a system can be broken down into three distinct categories for risk assessment.
Figure 5 Basic Input, Process, Output Model (Nickols, 2004, p. 2)
9
IV. Threat Statement
A threat-source is any circumstance or event with the potential to harm a system. There are three
threats sources being considered in this assessment: human, natural, and environmental. Natural
threats include acts of nature such as floods, earthquakes, tornadoes, landslides, avalanches, and
electrical storms. Human threats are either enabled by or caused by human beings, whether
unintentional or deliberate. Environmental threats are specific to the system being examined.
While it is important to consider all potential threat-sources, human threats and natural threats
are the main sources of threats covered in this report. Environmental threats are not extensively
considered because the number of potential mechanical engineering failures in a train system is
immense. Amtrak should more fully consider potential mechanical errors when purchasing new
trains or tracks. Attachment 3 provides a table showing the source, motivation, and actions for
each threat (Stoneburner, et al., 2002 p.13).
10
V. Risk Assessment Results
The following risk scenarios were developed based on researched threats and vulnerabilities for
the Lewistown, Pennsylvania Amtrak Station.
1.
2.
3.
4.
5.
Severe weather causes damage to station and track
Spread of harmful pathogens among passengers
Hijacking of train or robbery occurring on or near the train
Unsafe staff operation of trains
Unsafe passenger environment
11
A. Threat/Vulnerability Pairs
A threat is defined as the potential for exercise, either accidentally or intentionally, of a
specific vulnerability. A vulnerability is defined as a flaw or weakness in a system’s security
procedures, design, implementation, or internal controls that could be exercised, either
accidentally or intentionally, and result in a security breach or a violation of the system’s
security policy (Stoneburner, et al., 2002).
Risk Scenario #1’s vulnerability is the limited durability of Amtrak track and station
infrastructure against severe weather and natural disasters. Risk Scenario #2’s vulnerability
is that passengers do not follow proper hygiene precautions and procedures. Risk Scenario
#3’s vulnerability is the limited Amtrak prevention measures against hijacking and robbery.
Risk Scenario #4’s vulnerability is the unsafe procedures and human error of staff members.
Scenario #5’s vulnerability is the lack of physical security at Amtrak stations and tracks.
Attachment 4 contains a detailed vulnerability analysis which summarizes vulnerabilities
and their associated sources, and actions from the protector’s point-of-view (POV).
12
B. Existing Risk Controls
To protect against a number of natural and human threats, the U.S. Department of
Transportation has implemented a safety-critical train control system. Figure 6 shows a
simple Train Protection Warning System (TPWS) that monitors speed relative to other
traffic.
Figure 6: Simple Train Protection Warning System (Mokkapati, Tse, & Rao, 2009, p. 91)
The TPWS’s main function is to supervise train controls in order to relay alerts and warnings
back to the train’s operator. This system is used on active train lines to prevent signals passed
at danger (SPADs). The system sends out alerts that trains receive when they pass stop
signals without the required authorization, or rather commit a SPAD. This system links the
train and base stations together to provide each with important information such as current
speed, distance to closest trains, rotational speeds, etc. However, this system is not the only
control measure and is used in cooperation with the train’s conductor (Mokkapati, et al.,
2009).
13
C. Likelihood: Discussion and Evaluation
Likelihood is the first important factor which must be considered in order to quantify risk.
Likelihood refers to the probability of each vulnerability being exploited. In this risk
assessment, the likelihood of each risk scenario was rated on a scale from one to five, with
five being a very high likelihood, and one being a very low likelihood.
The likelihood of severe weather causing damage to the station or track is rated as a ‘one’ or
rather ‘rare’, because it would take an rare natural disaster such as a tornado or earthquake to
cause considerable damage. Only routine wear and tear would be suffered as a result of
ordinary severe weather such as a thunderstorm.
The likelihood of the spread of harmful pathogens among passengers is rated as a ‘four’ or
rather ‘likely’, because it is very easy to spread common illnesses such as the common cold
in public places. The spread of illness is even more likely in places where persons are in
close proximity with one another and are enclosed, such as a train.
The likelihood of the train being hijacked or a robbery occurring is rated as a ‘two’ or rather
‘unlikely’. This is because trains are not an ideal target for either crime. A robbery is
complicated with many potential witnesses and intervention by fellow passengers. The
hijacking of a train requires considerable planning and force, with little opportunity to
escape. Furthermore, Amtrak Police serves to deter crime at its various stations and on its
trains.
The likelihood of unsafe operation of trains by Amtrak staff is rated as a ‘three’ or rather
‘possible’. This is because human error is a vast source of error in all systems, including
train transportation. There are numerous situations in which a reckless, negligent, or simply
incompetent staff operation of the train could occur.
The likelihood of an unsafe passenger environment is rated as a ‘four’ or rather ‘likely’. This
is because there is a rather large gap in at the physical security of stations and tracks in
particular. Amtrak stations are only selectively and periodically patrolled by police, and the
tracks and trains themselves are typically left unguarded by Amtrak police while trains are in
transit.
Attachment 5 contains a table summary of the likelihood associated with each risk scenario.
14
D. Impact: Discussion and Evaluation
Impact is the second important factor which must be considered in order to quantify risk.
Impact refers to the magnitude of harm that could be caused by a threat’s exercise of
vulnerability. In this risk assessment, the impact of each risk scenario was rated on a scale
from one to five, with five being a very high impact, and one being a very low impact
(Stoneburner, et al., 2002).
The impact rating of severe weather causing damage to the station and track is a ‘two’ or
rather a ‘considerable to indefinite travel delay’. This is because damage to a station or track
delays train service. Depending on the extent of the damage there could be a moderate or
indefinite delay to train travel. This risk scenario was not rated as a ‘three’ because modern
weather and news capabilities make it easy for all regions to be aware of natural disasters.
These capabilities allow Amtrak to be aware of natural disasters which could cause major
track damage and thus injury to passengers.
The impact rating of the spread of harmful pathogens among passengers is a ‘three’ or rather
a ‘minor injury’ to passengers. This is because the spread of ordinary infections such as the
common cold, flu, and occasionally more deadly viruses such as Ebola can collectively be
considered minor. In most cases the common cold is spread and is a minor inconvenience to
a passenger who is infected, but occasionally the common cold could be a detrimental illness
to a very old or young passenger. A more rare but deadly disease such as Ebola could
potentially cause death. Collectively however, the harmful spread of pathogens among
passengers is a minor impact.
The impact rating of a hijacking or robbery on the train is a ‘four’ or rather a ‘moderate to
severe injury’. This is because the violent nature of a hijacking or robbery is likely to cause
severe injury to a passenger. For example, this can occur when a passenger is struck so that a
perpetrator can take her purse, or a passenger in a hijacking could be wounded by a gunshot
in order to show that perpetrators are serious in their demands.
The impact rating of unsafe staff operation of the train is a ‘five’ or rather ‘multiple serious
injuries or deaths’. This is because unsafe operation of the train can lead to derailment,
collision with another train, or dangerously abrupt acceleration and deceleration. All of
these events can cause death or life threatening injuries.
The impact rating of an unsafe passenger environment is a ‘five’ or rather ‘multiple serious
injuries or deaths’. This is because an unsafe passenger environment allows for a number of
hazards such as a bomb or chemical agent being planted on a station, train, or track. All of
these events can cause death or life threatening injuries to passengers.
Attachment 6 contains a table summary of the impact associated with each risk scenario.
15
E. Risk Rating
Attachment 8 shows the final calculated risk rating of each risk scenario that is the
combination of risk likelihood and risk impact. The final risk rating is on a scale of 1-25,
where 25 is an extremely high likelihood risk scenario that has a very high impact if
exploited. A score of 1 is a low likelihood risk scenario that has a low impact. Attachment 7
shows the risk matrix that was used to calculate the final risk scores. The risk rating was
calculated by multiplying the likelihood value by the impact value for each risk scenario.
Both the likelihood values and the impact values are ranged from 1-5, with 1 being the
lowest impact or rare likelihood, and 5 being high impact or almost certain likelihood.
Severe weather that causes damage to the track or station was given an overall risk rating of
2, which is very low. The harmful spread of pathogens among passengers due to close
proximity scored a 12, which is still considered low. The risk scenario of a hijacking or
robbery occurring scored a risk rating of 8, which is also considered low. Unsafe train
operations due to poor staff performance scored a risk rating of 15 which is considered a
medium risk level. The final risk scenario of an unsafe environment due to lack of physical
security was given an overall risk rating of 20, which is considered high.
16
F. Recommended Controls
When creating recommended controls for the risk scenarios, Figure 7: Probability/Impacts
Quadrants, was used to determine the appropriate types of controls. Depending on the
probability/impact of the risk scenario, different modes of controls can be utilized. For lowprobability/low-impact risks, the risks are accepted as controls would not be cost beneficial.
For low-probability/high-impact risks, the risks should be transferred or mitigated. For highprobability/low-impact risks, the controls aim to reduce the risk likelihood. Finally for highprobability/high-impact risk scenarios, the best control aims to avoid the scenarios all
together.
Figure 7: Probability/Impact Quadrants (Heiser, 2010, p. 4)
One of the highest rating risk scenarios is an unsafe environment that is due to a lack of
physical security that opens up an avenue for possible attacks. For this risk scenario a
recommended control is to explore options of physical security for the tracks and station.
While many big city Amtrak stations are guarded by private security, the outlier towns have
limited protections. Each station is recommended to have private security personnel on site
24/7 as well as security cameras. The tracks should also have protections such as barbed wire
fences surrounding the track and possibly small station posts at track/road intersections. This
control measure will avoid risks and threats from unsafe environments.
In regards to the unsafe train operations due to poor staff performance, a recommended
control is to install the PTC system more thoroughly throughout all trains and Amtrak lines.
These controls are currently only running on high load busy tracks but need to be
implemented everywhere. For the systems that this control has been installed, incident
likelihoods have decreased and this control will help avoid this risk scenario (Mokkapati, et
al., 2009). Furthermore, the training for employees should be greatly increased.
17
For the risk scenario that involves a harmful spread of pathogens among passengers, the
recommended control is to install hand sanitizing dispensers. This control method is
considered an avoid strategy that will decrease the probability of the scenario. These
dispensers will be located at both the station and on the trains.
The risk scenario of hijacking or robberies occurring fits into the low-likelihood/high-impact
quadrant. The control for this scenario is to devise an incident response procedure to mitigate
the impact. However, on-site security personnel can also be used to act quickly if the
scenario occurs.
The final risk scenario is for severe weather that can cause damage to the track and station.
This risk scenario was only given a risk rating of 2, which is considered very low. For this
risk scenario, the appropriate control is to simply accept the risk. However, a possible control
is storage near the facility that contains replacement wood, windows, tracks, and related
material on standby. In the event of a natural disaster, these supplies can be accessed and
used to repair any damages in a timely fashion. The option of structurally reinforcing the
tracks and stations would not be cost beneficial.
18
VI. Summary
This risk assessment identified, quantified, and recommended controls for five risk scenarios
faced by the Lewistown Amtrak Station. These scenarios include severe weather, pathogen
spread, hijacking/robbery, unsafe train operation, and unsafe environment. The highest risk
rating and therefore most pressing risk scenario is an unsafe environment due to a lack of
physical security. The recommended risk control for this risk scenario is the installation of
fences around all tracks and implementation of on-site security personnel. Refer to Attachment
9 for a complete summary of all risk scenarios, ratings, recommended controls, etc.
19
Reference List
Andersson, E., Häggström, J., Sima, M., & Stichel, S. (2004, May 1). Assessment of trainoverturning risk due to strong cross-winds. Proceedings of the Institution of Mechanical
Engineers, Part F: Journal of Rail and Rapid Transit, 218(3), 213-223. Retrieved
September 22, 2014, from http://pif.sagepub.com/content/218/3/213.full.pdf+html
Glantz, E. (2014, September 3). SRA 311 Week02: Critical Thinking. In Angel Course
Management System. Retrieved October 7, 2014, from
https://cms.psu.edu/section/default.asp?id=MRG-140422-142639-EJG8&goto=
Heiser, J. (2010). Risk Assessment 101: What You Need to Know. Retrieved October 23, 2014,
from http://goo.gl/FfxHxc
Mokkapati, C., Tse, T., & Rao, A. (2009, July). Practical Risk Assessment Methodology for
Safety-Critical Train Control Systems (No. DOT-FRA-ORD-09-15). Retrieved
September 24, 2014, from http://permanent.access.gpo.gov/gpo22485/ord0915.pdf
Nickols, F. (2004). Knowledge Management & Process Performance: Implications for Action. 2.
Retrieved October 7, 2014, from http://mail.nickols.us/KM_and_Process.pdf
Stoneburner, G., Goguen, A., & Feringa, A. (2001). NIST Special Publication 800-30. Risk
Management Guide for Information Technology Systems. Retrieved October 18, 2014,
from http://csrc.nist.gov/publications/nistpubs/800-30/sp800-30.pdf
Stoneburner, G., Goguen, A., & Feringa, A. (2002, July). NIST Special Publication 800-30 Risk Management Guide for Information Technology Systems. In National Institute of
Standards and Technology. Retrieved September 25, 2014, from
http://csrc.nist.gov/publications/nistpubs/800-30/sp800-30.pdf
Sturmovik. (2009) Lewistown, PA, Amtrak Station | 1 / 2 [Photograph], Retrieved October 9,
2014, from http://wikimapia.org/5627735/Lewistown-PA-AmtrakStation#/photo/1153641
20
Vancouver Island University. (2013). Risk Management Framework. Retrieved October 22,
2014, from
https://www2.viu.ca/riskmanagement/documents/July12_2013RiskManagementFramewo
rk.pdf
Whipp, C. (2014). Lewistown, PA PRR/Amtrak station [Photograph], Retrieved October 9,
2014, from http://static.panoramio.com/photos/large/105374606.jpg
Wreathall, J., Roth, E., Bley, D., & Multer, J. (2003, July). Human reliability analysis in support
of risk assessment for positive train control (No. DOT-VNTSC-FRA-03-03,). Retrieved
September 21, 2014, from http://ntl.bts.gov/lib/33000/33600/33684/33684.pdf
Wreathall, J., Woods, D., Bing, A., & Christoffersen, K. (2007, March). Relative risk of
workload transitions in positive train control. Washington, DC: U.S. Dept. of
Transportation, Federal Railroad Administration, Office of Safety and Research &
Development. Retrieved September 22, 2014, from
http://permanent.access.gpo.gov/gpo21449/ord0712.pdf
21
Attachment 1: Information Sheet
http://pif.sagepub.com/content/218/3/213.full.pdf+html
This assessment details the amount of force required by wind to cause damage or derailment.
There are several factors that may cause variations in wind such as altitude changes, long flat
paths, and pressure differences.
http://permanent.access.gpo.gov/gpo22485/ord0915.pdf
The severity of an accident can be represented by its associated damages to individuals, track,
and equipment. This estimate can be used to create a more accurate risk assessment because each
risk is valued not only on the likelihood but also on the resulting damage. This table shows the
cost of the damages associated with a train crash.
Table 1: Valued Estimations of Individual and Property Damage
Type of Damage
Cost
Injuries
$1,500,000
Fatalities
$3,000,000
Property Damages by a Low Speed Collision/Derailment (0-19 mph)
$2,500,000
Property Damages by a Medium Speed Collision/Derailment (20-49 mph) $5,000,000
Property Damages by a High Speed Collision/Derailment (50+ mph)
$10,000,000
http://csrc.nist.gov/publications/nistpubs/800-30/sp800-30.pdf
Appendix B of NIST 800-30 provides a sample risk assessment report outline. This provides
the appropriate structure and content for this risk assessment.
http://ntl.bts.gov/lib/33000/33600/33684/33684.pdf
Human reliability is often compared to the reliability of automated machines, however this 2003
document of human reliability analysis has found that “unsafe actions by individuals or teams
can reduce the effectiveness of the defenses, thereby making the likelihood of an accident
higher” (Wreathall, et al, 2003). This source points out that more often than not, humans are at
fault rather than automated machines.
22
http://permanent.access.gpo.gov/gpo21449/ord0712.pdf
This source by U.S. Department of Transportation provides data on the frequency of types of
errors that lead to passenger train accidents. This table consists of 13 preventable accidents from
1986 - 2003. Please also note that a single accident may have several causal factors.
Table 2: Causal Factors in Train Accidents
Causal Factor
Number
Percent of Total
Workload/mode transition
7
54%
Expectations/situation awareness
5
38%
Equipment
5
38%
Distractions
5
38%
Inexperience
4
31%
Fitness for duty
4
31%
Inattentiveness
4
31%
Communications
3
23%
Weather
0
0%
23
Attachment 2: Structured Analytic Results
In the divergent phase the team attempted to brainstorm all possible hazards. To facilitate
creativity the ideas were listed as they were thought of without any restrictive structure.
Divergent Results

Train derails as it arrives/departs from the station from high speeds.

Train derailment caused during mode transitions.

Train breaks down and is unable to start or move

Train is unable to function due to employee errors

Earthquake causes physical damage to track/station

Storm causes physical damage to track/station

Tornado causes physical damage to track/station

Strong winds causes physical damage to track/station

Robbery takes place on train

Hijacking of train

Viral Pandemic on train

Incoming train crashes with stationed train

Train is carrying material that is harmful to my well-being (Radioactive, Prisoners,
Fugitives, Chemicals, etc.)

Something located on tracks prevents arrival/departure

Engine pressure build up causes an explosion
24
Convergent Results
The convergent phase is used to group the unordered hazards into categories based on their
nature or root cause. These categories were then ranked by their priority from highest to lowest
in the following order: passenger-based hazards, train malfunctions, and employee error. Please
reference below Table 3: Convergent Brainstorming Results.
Table 3: Convergent Brainstorming Results
1. Passenger-Based
Hazards
Robbery on train
Train hijacking
Train is carrying harmful
materials (Radioactive,
chemical, prisoners,
fugitives)
Viral pandemic
2. Train Malfunctions
3. Employee Error
Train derailment from high
speeds
Train breaks down and is
unable to start/move
Explosion from engine
pressure
Train derailment during mode
transition
Employees poorly train and
unable get train moving
Something left on track that
prevents arrival/departure
Earthquake causes damage to
track/station
Storm causes damage to
track/station
Tornado causes damage to
track/station
Strong Winds cause damage
to track/station
Incoming train crashes with
stationed train
25
Attachment 3: Threat Analysis
Table 4 describes the threat source, type, motivation and action for the Lewistown Amtrak
Station and nearby tracks. Please note that these threats could be intentional or
unintentional. This table is modeled after the table included in NIST 800-30 (2002, p. 14)
Table 4: Threat-Sources, Motivation, and Threat Actions
Threat Source (Type)
Motivation
Threat-Action
Hazardous weather
(Natural)
Natural pressure differences
Strong winds/hard rain/lightning
Tectonic plates
(Natural)
Natural movement
Earthquakes
Pathogens (Human)
Dense population arrangement, poor
hygiene
Pathogen spreading between
passengers
People on-board
(Human)
Malicious needs, terrorism
Adversaries cause physical harm to
passengers or take control of the train
Excessive speed
(Human)
Poor regulations/safety controls
Train derailment
Staff Members
(Human)
Poor employee training, disregard of
controls/maintenance
Train unable to move, breaks down, or
gets damaged
Other trains
(Environmental)
Poor or lack of safety controls
Train on train collision
Objects on tracks
(Environmental)
Misplaced, or intentionally left
Object prevents incoming or outgoing
train, causing delays
26
Attachment 4: Vulnerability Analysis
Table 5 summarizes the possible vulnerabilities in the train station and tracks, as well as the
source and vulnerability-actions from the passengers’ perspective. This table is modeled after
the table included in NIST 800-30 (2002, p. 15-16).
Table 5: Vulnerability Source and Vulnerability-Action
Vulnerability
Source
Vulnerability-Action
Tracks/station are not built for
handling severe weather or
earthquakes
Tectonic plates and
hazardous weather
Tornado/strong winds/earthquakes
occur that cause damage to
tracks/station
Passengers do not follow proper
hygiene precautions and
procedures
Pathogens
Infected passengers or harmful supplies
infect other passengers/employees
Limited hijacking/robbery
prevention measures
Passengers/terrorists
Adversaries/terrorists rob/hijack the
passengers on the train
Unsafe staff procedures
Staff members
Short cuts are made that lead to damage
of train, derailment, or train on train
collisions
Lack of physical security
Adversaries or careless
workers
Objects are left on the tracks that
prevent incoming and out-going trains
27
Attachment 5: Risk Scenario Likelihood
Table 6 shows the likelihood of each risk scenario for the Lewistown Amtrak Station and nearby
tracks. The risk scenario is a combination of the threat source and vulnerability.
Table 6: Risk Scenario and Likelihood Analysis
Risk Scenario
Likelihood (15)
Severe weather causes damage due to limited durability of track/station
1
Harmful spread of pathogens among passengers due to close proximity required by
train travel
4
Hijacking or robbery occurs due to limited prevention measures
2
Unsafe train operation due to poor staff performance
3
Unsafe environment due to lack of physical security
4
Table 7 shows the descriptions associated with the selected likelihood values. These descriptions
were formulated for this report and are not generalized for all likelihood analyses.
Table 7: Likelihood Values and Descriptions (Vancouver Island University, 2014)
Descriptor
Likelihood Value
Rare (Less than 5%)
1
Unlikely (5-25%)
2
Possible (25-55%)
3
Likely (55-90%)
4
Almost Certain (90-99%)
5
28
Attachment 6: Risk Scenario Impact
Table 8 rates the impact of each of the risk scenarios on a scale of 1-5. Each risk scenario is
described by the vulnerability being used and its impact rating.
Table 8: Risk Scenario and Impact Analysis
Risk Scenario
Threat/Vulnerability
Impact
Severe weather causes damage due to limited
durability of track/station
Severe weather damaging the track and
station
2
Harmful spread of pathogens among passengers
due to close proximity required by train travel
Infectious pathogens spreading between
passengers
3
Hijacking or robbery occurs due to limited
prevention measures
Adversaries hijack or rob unprotected
trains
4
Unsafe train operation due to poor staff
performance
Unsafe train staff and operations causing
severe accidents or damage
5
Unsafe environment due to lack of physical
security
Lack of physical security protecting the
track and station
5
Table 9 shows the descriptions associated with the selected impact values. These descriptions
were formulated for this report and are not generalized for all impact analyses.
Table 9: Impact Values and Descriptions
Impact Descriptor
Impact Rating
Minor travel delay
1
Considerable to indefinite travel delay
2
Minor injury
3
Moderate to severe Injury
4
Multiple deaths / serious Injury
5
29
Attachment 7: Risk Matrix
A risk matrix will be used to evaluate risk impacts and likelihoods. Each axis includes a numeric
scale so that comprehensive scores can be calculated by using products (please refer back to
Table 7 and Table 9 for a description of each likelihood and impact numeric). For example, if
the impact is scored as a three and the probability is scored as a five, the overall severity score is
fifteen. Each cell is ranked by a very low, low, medium, high, or critical risk severity
category. The categories are based on the following ranges of risk severity scores: very low 1-5,
low 6-10, medium 11-15, high 16-20, and critical 21-25. In addition to their calculated score,
these categories are also designated by green, yellow, orange, red, and purple
respectively. Please reference Figure 8: Risk Matrix, below.
Figure 8: Risk Matrix
30
Attachment 8: Risk Rating
The risk rating is the final value that describes the relationship between likelihood and impact.
This is used when prioritizing risks and sorting scenarios by their overall risk level. Table 10
describes the final risk rating associated with the selected risk scenarios. The final risk rating was
calculated by multiplying the likelihood value by the impact value. The likelihood and impact
values were provided in Table 6 and Table 8 respectively.
Table 10: Risk Rating of Scenarios by Likelihood and Impact
Risk Scenario
Likelihood Impact Risk Rating
Severe weather causes damage due to limited durability of
track/station
1
2
2 (Very
Low)
Harmful spread of pathogens among passengers due to close
proximity required by train travel
4
3
12
(Medium)
Hijacking or robbery occurs due to limited prevention measures
2
4
8 (Low)
Unsafe train operation due to poor staff performance
3
5
15
(Medium)
Unsafe environment due to lack of physical security
4
5
20 (High)
31
Attachment 9: Summary Table
Table 11 summarizes the selected risk scenarios as well as the associated recommended controls.
The recommended controls are broken into the action priority, required resources, party
responsible for control implementation, and any maintenance that may be required for the
control.
Table 11: Summary Table of Risk Scenarios and Recommended Controls
Risk Scenario
Risk
Rating
Recommended
Control
Action
Priority
Required
Resources
Responsible
Party
Maintenance
Requirement
Severe weather
causes damage
due to limited
durability of
track/station
2 (Very
Low)
None, accept the
risk
Low
Tracks,
concrete,
wood,
windows,
labor,
contractor
Property
Owner
Reconstruct
building/track
if event occurs
Harmful spread
of pathogens
among
passengers due to
close proximity
required by train
travel
12
(Medium)
Hand sanitizing
dispensers
Medium
Hand
sanitizing wall
dispensers,
labor, sanitizer
bags
Property
Owner
Refill
dispensers
Hijacking or
robbery occurs
due to limited
prevention
measures
8 (Low)
On-site security
personnel,
incident response
procedures
Low
Documents,
security
employees
Security team,
Transit police
N/A
Unsafe train
operation due to
poor staff
performance
15
(Medium)
PTC system
implemented
more thoroughly,
better policies and
training
Medium
Circuitry,
manuals,
documents,
labor,
contractors
Property
Owner,
Training
management
PTC system
maintenance as
needed
Unsafe
environment due
to lack of
physical security
20 (High)
Install fences
around tracks, onsite security
personnel
High
Fences,
contractors,
security
employees,
contracts,
labor
Property
owner
Maintenance
on fences if
damaged
32
GRADING RUBRIC
Peer Reviewer: Assign total points here for composition, contribution, subject knowledge and APA
citations. Write specific comments into student’s paper.
Section _________
st
1 Author Name (Print): __________________ 2nd Author Name (Print): __________________
1st Peer Reviewer Name (Print): ________________ 2nd Peer Reviewer Name (Print): ________________
Peer
Reviewer
Points
Max
Possible
Points
25
25
25
15
(blank)
10
(blank)
100
Instructor
Total
Points
Item
Composition - Business professional writing with no grammatical or spelling
errors.
Contribution - Improves class learning by providing new information or
approach to topic under discussion.
Subject Knowledge - Knowledge of course content is illustrated by
integrating concepts into the essay. Does it appear that you know what you are
writing about? Are you aware of aspects of this covered in class?
Captions, References and APA Citations - Reference to article, book, or
magazine where new information or approach is provided, and appropriate
citation in text. Must follow APA format!!!
 In-Text Cite: Includes author/year, sometimes page number
 Reference List: Each single-spaced with hanging indent, doublespace between citations
 Captions: Tables/ figures must include complete captions with
citation
In-class peer review - Thorough and complete with specific comments (i.e.
NOT "good job" or "great opening") for what has been done well or what could
be done to improve the paper
Total
INSTRUCTOR/LA GRADER INITIALS ________
33
Download