Document of The World Bank Report No: 69999-GZ RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE FIRST AND SECOND ADDITIONAL FINANCING GRANTS (TF092196 AND TF097081) FOR THE NORTHERN GAZA EMERGENCY SEWAGE TREATMENT PROJECT (P074595) August 12, 2004 TO THE PALESTINE LIBERATION ORGANIZATION (for the benefit of the Palestinian Authority) June 29, 2012 Sustainable Development Department Middle East and North Africa Region ABBREVIATIONS AND ACRONYMS AF AFD CMWU EU ESIA EMP NGEST Sida WWTP Additional Financing Grant L’Agence Française de Développement Coastal Municipalities Water Utility European Union Environmental and Social Impact Assessment Environmental Management Plan Northern Gaza Emergency Sewage Treatment Swedish International Development Agency Waste water treatment plant Regional Vice President: Country Director: Sector Manager / Director: Task Team Leader: Inger Andersen Mariam J. Sherman Francis Ato Brown Richard W. Pollard ii WEST BANK & GAZA NORTHERN GAZA EMERGENCY SEWAGE TREATMENT PROJECT (P074595) FIRST AND SECOND ADDITIONAL FINANCING GRANTS RESTRUCTURING PAPER FOR EXTENSION OF CLOSING DATES P070958 CONTENTS A. B. Page SUMMARY ........................................................................................................................... 1 PROJECT STATUS .............................................................................................................. 1 ANNEX 1: UPDATED RESULTS FRAMEWORK .................................................................. 4 ANNEX 2: UPDATED PROCUREMENT PLAN ..................................................................... 6 iii WEST BANK & GAZA NORTHERN GAZA EMERGENCY SEWAGE TREATMENT PROJECT (P074595) RESTRUCTURING PAPER A. SUMMARY 1. The Northern Gaza Emergency Sewage Treatment (NGEST) Project was approved by the Executive Board on September 7, 2004. A first additional financing (AF) grant was approved on March 18, 2008 to cover cost overruns for the effluent transfer civil works and environmental risk mitigation measures. A second AF grant was approved on July 30, 2010 to finance the repair of damage incurred during military operations in Gaza and increased costs for the waste water treatment plant. The proposed restructuring would extend the closing date of the first AF grant (TF092196) from June 30, 2012 to June 30, 2014, and that of the second AF grant (TF097081) from June 30, 2013 to June 30, 2014. This will allow the funds to be used to complete the activities that were agreed to be financed by each of the AFs by closing date for the project, which is 30 June, 20141. B. PROJECT STATUS 2. The development objectives of the NGEST Project are to: (i) Mitigate the immediate and gathering health and environmental safety threats to the communities surrounding the effluent lake at Beit Lahiya Wastewater Treatment Plant; and (ii) Provide a satisfactory long-term solution to the treatment of wastewater for the Northern Governorate in Gaza. The Project has been implemented in two phases, referred to as Parts A and B, to address the two development objectives. The Project consists of four components: (i) Effluent transfer (from Beit Lahiya to a new site) and risk mitigation measures; (ii) Technical assistance for implementing component 1 activities; (iii) Construction and operation of the North Gaza Wastewater Treatment Plant; and (iv) Technical assistance for implementing Component 3. 3. All civil works for the effluent transfer were completed in 2010 and the transfer system continues to be operated effectively by the Coastal Municipalities Water Utility (CMWU). The start of implementation of Part B was delayed substantially, primarily due to security issues that were beyond the control of the Project. As a result, the closing date for the project was extended on June 15, 2010 for four years, up to June 30, 2014. Implementation is now proceeding satisfactorily, and it is expected that the civil works will be completed and the waste water treatment plant will be commissioned in mid-2013 if no further delays occur. The contractor is also obligated to commission the plant and train CMWU staff to operate it following completion. The PDO indicator 1 has been fully achieved with the draining of the effluent lake. For PDO indicator 2, about 15,000 cubic meters out of the target 35,000 cubic meters of wastewater is treated per day. 1 The original closing date for the project was originally 30 June, 2010, but was extended in 2010 to June 30, 2014 to accommodate unexpected implementation delays. 1 4. Overall, the project is rated Moderately Satisfactory for progress toward achievement of the Development Objectives and for Implementation Progress. Disbursement of the original grant as of 31 March, 2012 stands at 99%. AF1 is over 35% disbursed and retains an undisbursed balance is US$7.76 million, which is needed for implementing risk mitigation measures. AF2, allocated for Part B, is over 28% disbursed, with a balance of US$5,020,898 remaining. The auditors issued unqualified opinions in the 2009 and 2010 audit reports. 5. The need for the closing date extensions for the first and second AFs is due to delays in project implementation which were external to the project and beyond the control of the implementing agency. The delays were severe and could not be anticipated by the World Bank team during project preparation. These delays were attributable to i) the unstable and deteriorating political and security situation in Gaza in the early years of implementation, which led to a protracted and ultimately failed initial bidding process for Part B and delayed the start of the Part B contract after a second bidding round by approximately three years, and ii) periodic lack of access to the project sites due to security risks, combined with extensive damage to project facilities that were incurred during military operations that occurred in late 2008, which caused about eighteen months of implementation delays. In total, factors external to the project have caused a total of more than four years of delays, which required the original project closing date to be extended to June 30, 2014. 6. The environmental risk mitigation activities (effluent recovery and reuse) that are intended to be financed with the remaining portion of the AF1 grant are contingent on the Part B activities being completed. The design work is completed and construction is expected to begin in late 2012, but cannot be completed prior to completion of the wastewater treatment plant. Furthermore, the construction and commissioning activities under Part B that are being financed with AF2 and bilateral contributions cannot be completed by June 30, 2013 due to the delays described above. 7. As stated in Para. 5 above, factors external to the project led to cumulative delays in implementation of more than 48 months. Extending the closing dates for the AFs would ensure that the project can properly complete the activities that are necessary to put in place the infrastructure and build the institutional capacity that is needed to achieve the project’s second Development Objective, which is to provide a satisfactory long-term solution to the treatment of wastewater for the Northern Governorate in Gaza. 8. Paragraph 15 (n) of the Additional Financing guidelines (as shared below) allows for this exception, when the delays experienced during implementation have been due to external factors outside of the project. (n) Extension of additional loan closing dates. Under OP 13.20, additional loans must close within three years. However, in exceptional cases the Bank may consider extending the closing date of an additional loan. This issue will be addressed in the new policy framework for investment lending that will be developed by FY11; hence, this guidance on extension is an interim approach. When implementation of the additional loan activities is delayed because of a factor that is clearly external to the operation and outside the control of the borrower or implementing agencies (e.g., delay in additional loan effectiveness, natural disaster, major political change), the task team may request an extension of the closing date for a 2 period that is equal to the delay due to the responsible factor. The RVP approves such a request. Any other requests for an extension beyond the three-year limit require approval by the RVP and clearance by the Vice President, OPCS. Such extensions are limited to 12 months, to allow teams to complete ongoing activities. The rationale for each such extension is considered on its own merits. 9. This will be the first extension for each of the respective additional financing grants. 10. The Project is financed with grants from L’Agence Française de Développement (AFD), Belgium, The European Investment Bank, the European Union (EU), and the Swedish International Development Agency (Sida). The Belgian, EU, and Sida contributions are channeled through trust funds managed by the World Bank. The cofinancing has been provided to cover a portion of the costs of civil works under the project, which is expected to be completed by mid-2013. The trust funds for the respective co-financing contributions all close on December, 2013 and no extensions are expected to be needed at this time. 3 ANNEX 1: Results Framework and Monitoring WEST BANK & GAZA: NORTHERN GAZA EMERGENCY SEWAGE TREATMENT PROJECT Project Development Objective (PDO): (i) to mitigate the immediate health, environmental, and safety threats to the communities surrounding the poorly treated and rapidly growing effluent lake in the Beit Lahia area of northern Gaza; and (ii) contribute to the provision of a satisfactory long-term solution for the treatment of waste water in the Northern Gaza Governorate. PDO Level Results Indicators* Effluent lake is drained and no longer a threat to the surrounding communities in the vicinity of the Beit Lahia wastewater treatment plant. Increase in quantity of wastewater being treated and properly managed. Core Revised Project Development Objective: N/A D=Dropped C=Continue N= New R=Revised Unit of Measure C Text C Cubic meters per day Cumulative Target Values Baseline Frequency 2011 Lake is full and is an environment al and health threat to the surrounding communities 12,000 New infiltration ponds completed. Effluent being transferred 15,000 2012 2013 Effluent lake drained Effluent lake drained 15,000 4 35,000 2014 Effluent lake drained Data Source/ Methodology Responsibility for Data Collection quarterly Project progress reports, supervision mission reports Palestinian Water Authority quarterly Project progress reports, supervision mission reports Palestinian Water Authority 35,000 INTERMEDIATE RESULTS Intermediate Result (Component One): Effluent is transferred to new site and sewage lake is diminished to an aeration basin and no longer a threat. Intermediate Level Results Indicators* Effluent transfer facilities – terminal pumping station, pressure pipe, and nine infiltration basins are completed and operational Core Revised Intermediate Result (Component One): N/A D=Dropped C=Continue N= New R=Revised Unit of Measure Cumulative Target Values Baseline No facility C Frequency 2011 Text 2012 Infrastructure built and infiltration ponds operational. Effluent transfer facilities effectively operated by CMWU. 2013 Effluent transfer facilities effectively operated by CMWU. 2014 Effluent transfer facilities effectively operated by CMWU. Data Source/ Methodology Responsibility for Data Collection quarterly Project progress reports, supervision mission reports Palestinian Water Authority quarterly Project progress reports, supervision mission reports Palestinian Water Authority quarterly Project progress reports, supervision mission reports Palestinian Water Authority quarterly Project progress reports, supervision mission reports Palestinian Water Authority quarterly Project progress reports, supervision mission reports, CMWU customer data Palestinian Water Authority, CMWU Intermediate Result (Component Two): Waste Water Treatment Plant and risk management facilities constructed and operational. Revised Intermediate Result (Component Two): N/A North Gaza WWTP with a capacity of 35,000 M3/day is constructed and operational. ESIA, EMP and remedial works are completed and recommendations adequately implemented No facility C Text No study was in place C Text No facility Risk management facilities are constructed and operational Number of people in urban areas provided with access to improved sanitation as a result of the project. C C Text Number 190,000 people inadequately served by dysfunctional WWTP at Beit Lahia. Contract signed, construction initiated. Construction underway. Draft RFP and TOR for supplementary ESIA (SESIA) prepared. RFP and TOR for SESIA finalized, construction finalized and work started Supplementary ESIA for effluent recovery & reuse completed. Remedial works design study completed Funding identified for Phase One of effluent recovery/reuse 150,000 people adequately served. 150,000 people adequately served. Phase One of Effluent recovery /reuse under construction upon SESIA completion. 350,000 people sustainably served by new WWTP. 5 WWTP construction completed. WWTP operated by CMWU with skills transfer from contractor. ESIA recommenda tions being implemented , impacts monitored. Phase One operational 350,000 people sustainably served by new WWTP. ANNEX 2: Procurement Plan North Gaza Emergency Sewage Treatment Project NGEST (P074595)- Procurement Plan for Non consulting services - Main Agreement/ additional finance I & II 7 09-Jul-09 5 5 10 19-Jul-09 15-Apr-10 17 02-May-10 9 15-Apr-10 17 02-May-10 15-May-12 4 19-May-12 7 19-Aug-09 19-May-10 21-May-10 8 21-May-10 21-May-10 20 11-Jun-12 11-Jun-12 7 12-Aug-09 11-May-10 8 9 13-May-10 3 22-May-12 Start Date Execution /b 02-Jul-09 WB No Objection Date Evaluation & Recomm. Interval /a 7 Expected Bid-Opening Date Completion Date 21 16-Sep-09 90 15-Dec-09 25-May-10 7 31-May-10 365 31-May-11 21-May-10 143 11-Oct-10 605 07-Jun-12 16-Jun-12 7 23-Jun-12 365 23-Jun-13 Interval /a 25-Jun-09 Invitation Date Interval /a Post WB No Objection Date Interval /a SH Submission/ Readiness Date Interval /a Review By Bank (Prior / Post) Interval /a Estimated Cost (US$) /Actual cost Location/ Description Interval /a Procurement System Ref. # Procurement Method Sl. # Plan vs. Actual Updated Procurement Plan May, 2012 Contract Award Date 7 26-Aug-09 4 SUPPLIER NAME COMMENTS Part A 5 provide non technical $ services through local water labratories to Ground Water Quality conduct sampling & monitoring NGEST-SH-59 analysing ground Water R Quality for the monitoring $ . P 84,748 AL-AZHAR UNIVERSITY LAB 84,748 Q2/2012 A Continuation for ground water and P $ 60,000 SH POST 15-May-12 waste water quality mointoring 6 5 Fourth round has been completed . The fifth and final round is in process. North Gaza Emergency Sewage Treatment Project NGEST (P074595)- Procurement Plan for Consultancy service/Main Agreement/ additional finance I & II Interval /a Interval /a Contract Award Date Interval /a Start Date Execution /b Completion Date $ 1,850,000 13-Jun-05 42 25-Jul-05 5 30-Jul-05 3 02-Aug-05 56 27-Sep-05 50 16-Nov-05 7 23-Nov-05 20 13-Dec-05 4 17-Dec-05 30 16-Jan-06 30 15-Feb-06 1284 22-Aug-09 $ $ 2,340,800 1,850,000 13-Jun-05 42 25-Jul-05 5 30-Jul-05 3 02-Aug-05 56 27-Sep-05 50 16-Nov-05 14 30-Nov-05 20 20-Dec-05 4 24-Dec-05 30 23-Jan-06 433 01-Apr-07 2100 30-Dec-12 13-Jun-05 42 25-Jul-05 5 30-Jul-05 3 02-Aug-05 56 27-Sep-05 50 16-Nov-05 14 30-Nov-05 20 20-Dec-05 4 24-Dec-05 30 23-Jan-06 433 01-Apr-07 2280 28-Jun-13 third addendum under preparation due to prolonging of construction period from 24 to 30 months No Objection Date Invitation for RFPs Date Interval /a No Objection Date Short Listing Interval /a Final Evaluation Date Review by Bank Prior / Post Interval /a Interval /a Expected Proposal Submission Date Interval /a Advertisement EOI/ Readiness Date No Objection Date Estimated Cost (US$) /Actual cost Interval /a Location/ Description of Assignment Interval /a Procurement System Ref. # Selection Method Sl. # Plan vs. Actual Updated Procurement Plan May, 2012 Technical Evaluation Date CONSULTANT NAME COMMENTS Part A completed Part B Construction Supervision Consultant** Northen Gaza / provide consultancy supervision & P NGEST-C-QCBS01-05 pre-contract services of The construcion supervision contract has started on 1/9/2010 NGWWTP construction and commissioning. A Q2/2010 Subtotal A SOGREAH The pre service contract has been completed , the Q4/2010 1221375 EURO 440460 QCBS USD q1/2011 1221375 EURO 440460 USD 13-Jun-05 42 25-Jul-05 5 30-Jul-05 3 02-Aug-05 56 27-Sep-05 50 16-Nov-05 14 30-Nov-05 20 20-Dec-05 4 24-Dec-05 30 23-Jan-06 433 01-Apr-07 2280 28-Jun-13 addendum no.3 has been submitted on 6/4/2011 , it is under revision to be discussed with the project manager . Q2/2011 1221375 EURO 440460 USD 13-Jun-05 42 25-Jul-05 5 30-Jul-05 3 02-Aug-05 56 27-Sep-05 50 16-Nov-05 14 30-Nov-05 20 20-Dec-05 4 24-Dec-05 30 23-Jan-06 433 01-Apr-07 2280 28-Jun-13 PWA & the consultant in process to finalize the third addendum . $ 2,708,988 13-Jun-05 42 25-Jul-05 5 30-Jul-05 3 02-Aug-05 56 27-Sep-05 50 16-Nov-05 14 30-Nov-05 20 20-Dec-05 4 24-Dec-05 30 23-Jan-06 433 01-Apr-07 2280 28-Jun-13 the no object for the third addendum was issued on 14/10/2011. The contract price has been amended $ 2,708,988 13-Jun-05 42 25-Jul-05 5 30-Jul-05 3 02-Aug-05 56 27-Sep-05 50 16-Nov-05 14 30-Nov-05 20 20-Dec-05 4 24-Dec-05 30 23-Jan-06 433 01-Apr-07 2280 28-Jun-13 work is going on $ 2,708,988 13-Jun-05 42 25-Jul-05 5 30-Jul-05 3 02-Aug-05 56 27-Sep-05 50 16-Nov-05 14 30-Nov-05 20 20-Dec-05 4 24-Dec-05 30 23-Jan-06 433 01-Apr-07 2280 28-Jun-13 work is ongoing 15-Sep-11 15 30-Sep-11 5 05-Oct-11 3 08-Oct-11 30 07-Nov-11 21 28-Nov-11 7 05-Dec-11 20 25-Dec-11 7 01-Jan-12 21 22-Jan-12 12 03-Feb-12 150 02-Jul-12 22-Nov-11 26 18-Dec-11 42 29-Jan-12 7 05-Feb-12 28 04-Mar-12 14 18-Mar-12 7 25-Mar-12 14 08-Apr-12 7 15-Apr-12 14 29-Apr-12 7 06-May-12 120 03-Sep-12 A * Q4/2011 A Q1/2012 A Q2/2012 1539850 EURO 568310 USD 68000$ 1539850 EURO 568310 USD 68000$ 1539850 EURO 568310 USD 68000$ Prior Environmental Plan Monitoring Consultant NGEST-C.QCBS 01-06 Supplemental ESIA for Effluent Recovery & Reuse schem and Q4/2011 Remediation $ R A Q1/2012 $ 100,000 22-Nov-11 26 18-Dec-11 39 26-Jan-12 3 29-Jan-12 52 21-Mar-12 13 03-Apr-12 03-Apr-12 12 15-Apr-12 15-Apr-12 14 29-Apr-12 7 06-May-12 120 03-Sep-12 A Q2/2012 $ 100,000 22-Nov-11 26 18-Dec-11 39 26-Jan-12 3 29-Jan-12 52 21-Mar-12 13 03-Apr-12 03-Apr-12 12 15-Apr-12 15-Apr-12 30 15-May-12 14 29-May-12 120 26-Sep-12 Remdial works Design $ and Supervision 175,000 QCBS Post 15-Sep-12 28 13-Oct-12 7 20-Oct-12 7 27-Oct-12 28 24-Nov-12 14 08-Dec-12 7 15-Dec-12 14 29-Dec-12 7 05-Jan-13 14 19-Jan-13 7 26-Jan-13 120 26-May-13 Further Studies as $ recommended by SESIA 50,000 QCBS POST 15-Sep-12 28 13-Oct-12 7 20-Oct-12 7 27-Oct-12 28 24-Nov-12 14 08-Dec-12 7 15-Dec-12 14 29-Dec-12 7 05-Jan-13 14 19-Jan-13 7 26-Jan-13 150 25-Jun-13 24-Nov-07 24-Nov-07 42 42 05-Jan-08 05-Jan-08 5 5 10-Jan-08 10-Jan-08 3 3 13-Jan-08 13-Jan-08 42 42 24-Feb-08 24-Feb-08 21 21 16-Mar-08 16-Mar-08 7 7 23-Mar-08 23-Mar-08 20 20 12-Apr-08 12-Apr-08 7 7 19-Apr-08 19-Apr-08 21 21 10-May-08 10-May-08 12 12 22-May-08 22-May-08 800 800 31-Jul-10 31-Jul-10 1,122,000 QCBS Prior 21-Apr-10 43 03-Jun-10 6 09-Jun-10 4 13-Jun-10 43 26-Jul-10 22 17-Aug-10 8 25-Aug-10 21 15-Sep-10 8 23-Sep-10 22 15-Oct-10 13 28-Oct-10 801 06-Jan-13 15-Jul-12 15-Jul-12 42 42 26-Aug-12 26-Aug-12 5 5 31-Aug-12 31-Aug-12 3 3 03-Sep-12 03-Sep-12 42 42 15-Oct-12 15-Oct-12 21 21 05-Nov-12 05-Nov-12 7 7 12-Nov-12 12-Nov-12 20 20 02-Dec-12 02-Dec-12 7 7 09-Dec-12 09-Dec-12 21 21 30-Dec-12 30-Dec-12 12 12 11-Jan-13 11-Jan-13 730 535 11-Jan-15 30-Jun-14 P p 100,000 QCBS Post A p A O&M Support to service provider P NGEST-C.QCBS 01-08 Subtotal R Q4/2010 Q2/2011 NG/provide consultancy services in the field of O&M of NGWWTP to support both PMU and CMWU designated staff managing the operation . $ A 7 the TOR and the short list have been completed The selection process Has been finalized, PWA is In The selection process Has been finalized, the negotitation process took place on 6 may 2012. the expected date for contract signature is 15th May 2012 3.Design &Supervision Consultant P NGEST-ADDC.QCBS 01-08 NG/ Concsultancy servieces to provid detail design and construction $ supervision for Effluent Recovery and Reuse Scheme. 900,000 $ 200,000 P1 QCBS Prior 20-Jan-08 21 10-Feb-08 9 19-Feb-08 3 22-Feb-08 30 23-Mar-08 02-Apr-08 09-Apr-08 16-Apr-08 N/A 7 23-Apr-08 N/A 7 N/A 9 30-Apr-08 7 07-May-08 120 11-Sep-06 30 10-Oct-06 730 09-Oct-08 15-Jul-08 7 22-Jul-08 120 19-Nov-08 13-Oct-08 7 20-Oct-08 120 17-Feb-09 14 25-Aug-06 7 02-Sep-06 20-Jan-08 50 10-Mar-08 9 19-Mar-08 50 08-May-08 30 07-Jun-08 10 17-Jun-08 7 24-Jun-08 7 01-Jul-08 7 A Q2/08 20-Jan-08 50 10-Mar-08 69 18-May-08 75 01-Aug-08 30 31-Aug-08 15 15-Sep-08 7 22-Sep-08 7 29-Sep-08 7 A Q3/08 20-Jan-08 50 10-Mar-08 189 15-Sep-08 1 16-Sep-08 48 03-Nov-08 15 18-Nov-08 7 25-Nov-08 7 02-Dec-08 7 7 06-Oct-08 7 09-Dec-08 7 16-Dec-08 7 23-Dec-08 120 22-Apr-09 p p Q4/08 Q1/09 20-Jan-08 20-Jan-08 50 50 10-Mar-08 10-Mar-08 189 189 15-Sep-08 15-Sep-08 1 1 16-Sep-08 16-Sep-08 48 48 03-Nov-08 03-Nov-08 15 15 18-Nov-08 18-Nov-08 7 7 25-Nov-08 25-Nov-08 7 7 02-Dec-08 02-Dec-08 7 7 09-Dec-08 7 09-Dec-08 7 16-Dec-08 16-Dec-08 75 150 01-Mar-09 15-May-09 120 120 29-Jun-09 12-Sep-09 p Q2/09 20-Jan-08 50 10-Mar-08 189 15-Sep-08 1 16-Sep-08 48 03-Nov-08 15 18-Nov-08 7 25-Nov-08 7 02-Dec-08 7 09-Dec-08 7 16-Dec-08 150 15-May-09 120 12-Sep-09 P Q2/2010 (NGEST/AF-CQCBS01-08/DD) 20-Jan-08 50 10-Mar-08 189 15-Sep-08 1 16-Sep-08 48 03-Nov-08 15 18-Nov-08 7 25-Nov-08 7 02-Dec-08 7 09-Dec-08 7 16-Dec-08 273 15-Nov-09 365 15-Nov-10 08-Jul-08 $ The contract have been signed on 30/6/2009 THE FIRM HAS REQUESTED 4 MONTHS EXTENSION 427,750 A Q3/2010 20-Jan-08 50 10-Mar-08 189 15-Sep-08 1 16-Sep-08 48 03-Nov-08 15 18-Nov-08 7 25-Nov-08 7 02-Dec-08 7 09-Dec-08 7 16-Dec-08 273 15-Nov-09 487 17-Mar-11 Q42010 20-Jan-08 50 10-Mar-08 189 15-Sep-08 1 16-Sep-08 48 03-Nov-08 15 18-Nov-08 7 25-Nov-08 7 02-Dec-08 7 09-Dec-08 7 16-Dec-08 273 15-Nov-09 592 30-Jun-11 R Q1/2011 20-Jan-08 50 10-Mar-08 189 15-Sep-08 1 16-Sep-08 48 03-Nov-08 15 18-Nov-08 7 25-Nov-08 7 02-Dec-08 7 09-Dec-08 7 16-Dec-08 273 15-Nov-09 547 16-May-11 Q2/2011 Delay due to political circumstances The negotiation meeting $ 900,000 R R One selection has been made and two contracts has been signed as below 04-Sep-08 11-Aug-06 Subtotal N/A 7 Q1/08 900,000 N/A 7 A $ N/A 10 NG/ Concsultancy servieces to provid detail design, bidding documents preparation and pre-contract services for Effluent Recovery and Reuse Scheme. 20-Jan-08 50 10-Mar-08 189 15-Sep-08 1 16-Sep-08 48 03-Nov-08 15 18-Nov-08 7 25-Nov-08 7 02-Dec-08 7 09-Dec-08 7 16-Dec-08 273 15-Nov-09 757 The firm has requested 4 months extension ,PWA the delay is due to the extensive investigation the draft biddining documents been The firm hashas granted extension up to 15/6/2011& the draft bidding decuments has been received by the consultant and its under revision by PMU,DUE due to the delay in land acquisition , the precontract service which is apart of this contract will start after the issuance of the tender , so additional time extension will be granted to the firm . 12-Dec-11 JV-CEP &Finish Consulting Group Infra &Enviromental (FCG)Iternational Ltd R A Q4/2011 op Q1/ 2012 R Q2/ 2012 P Q2/2010 (NGEST/AF-CQCBS01-08/CSM) R Q4/2010 (NGEST/AF-CQCBS01-08/CSM) 20-Jan-08 NG/ Concsultancy servieces to provid construction supervision and pre-commetioning $ services for Effluent Recovery and Reuse Scheme. NG/ Concsultancy servieces to provid construction supervision and pre-commetioning 388,000 50 50 #VALUE! 10-Mar-08 189 189 #VALUE! 15-Sep-08 1 1 #VALUE! 16-Sep-08 48 48 #VALUE! 03-Nov-08 15 15 #VALUE! 18-Nov-08 7 7 #VALUE! 25-Nov-08 7 7 #VALUE! 02-Dec-08 7 7 #VALUE! 7 09-Dec-08 7 #VALUE! 16-Dec-08 273 273 15-Nov-09 15-Nov-09 757 1050 12-Dec-11 The firm has granted extension up to 15/6/2011& the draft bidding decuments has been received by the consultant and its under revision by PMU,DUE due to the delay in land acquisition , the pre-contract service which is apart of this contract will start after the issuance of the tender , so additional time extension will be granted to the firm . 30-Sep-12 The firm has granted extension up to 30/09/2012 due to the delay in land acquisition, the pre-contract service which is a part of this contract will start after the issuance of the tender, so additional time extension will be granted to the firm. 20-Jan-08 50 10-Mar-08 189 15-Sep-08 1 16-Sep-08 48 03-Nov-08 15 18-Nov-08 7 25-Nov-08 7 02-Dec-08 7 09-Dec-08 7 16-Dec-08 273 15-Nov-09 1050 30-Sep-12 The firm has granted extension up to 30/09/2012 due to the delay in land acquisition, the pre-contract service which is a part of this contract will start after the issuance of the tender, so additional time extension will be granted to the firm. 20-Jan-08 50 10-Mar-08 189 15-Sep-08 1 16-Sep-08 48 03-Nov-08 15 18-Nov-08 7 25-Nov-08 7 02-Dec-08 7 09-Dec-08 7 16-Dec-08 273 15-Nov-10 905 08-May-13 The commencment will be after the completion of the detail design & the bidding stages . 1-Mar-11 20 21-Mar-11 15 05-Apr-11 1 06-Apr-11 48 24-May-11 10 03-Jun-11 7 10-Jun-11 7 17-Jun-11 7 24-Jun-11 7 01-Jul-11 14 15-Jul-11 913 13-Jan-14 The commencment will be after the completion of the detail design & the bidding stages . 8 The commencment will be after the completion of the detail design & the bidding stages . The commencment will be after the completion of the detail design & the bidding stages . The commencment will be after the completion of the bidding stages . The commencment will be after the completion of the bidding stages . R q1/2011 1-Jun-11 20 21-Jun-11 15 06-Jul-11 1 07-Jul-11 48 24-Aug-11 10 03-Sep-11 7 10-Sep-11 7 17-Sep-11 7 24-Sep-11 7 01-Oct-11 14 15-Oct-11 913 15-Apr-14 R q2/2011 1-Jun-11 20 21-Jun-11 15 06-Jul-11 1 07-Jul-11 48 24-Aug-11 10 03-Sep-11 7 10-Sep-11 7 17-Sep-11 7 24-Sep-11 7 01-Oct-11 14 15-Oct-11 913 15-Apr-14 R q4/2011 1-Jun-11 20 21-Jun-11 15 06-Jul-11 1 07-Jul-11 48 24-Aug-11 10 03-Sep-11 7 10-Sep-11 7 17-Sep-11 7 24-Sep-11 7 01-Oct-11 272 29-Jun-12 365 29-Jun-13 A Q1/2012 1-Oct-12 20 21-Oct-12 15 05-Nov-12 1 06-Nov-12 48 24-Dec-12 10 03-Jan-13 7 10-Jan-13 7 17-Jan-13 7 24-Jan-13 7 31-Jan-13 272 30-Oct-13 365 30-Oct-14 R Q2/2012 1-Oct-12 20 21-Oct-12 15 05-Nov-12 1 06-Nov-12 48 24-Dec-12 10 03-Jan-13 7 10-Jan-13 7 17-Jan-13 7 24-Jan-13 7 31-Jan-13 150 30-Jun-13 365 30-Jun-14 The commencment will be after the completion of the bidding stages . 11-May-11 416 30-Jun-12 Auditing for the financial year 2010 completed , the TALAL ABU GHAZALA auditing process for the year 2011 expected to start next quarter . External Auditing Consultant A External Auditing NG/provide consultancy services for external Auditing $ 26,392 Future External Auditing NG/provide consultancy services for external Auditing $ 48,608 P the procurment process had been conducted by MoF the procurment process will be conducted by MoF 9 North Gaza Emergency Sewage Treatment Project NGEST (P074595)- Procurement Plan for Goods - Main Agreement/ additional finance I & II 04-Jun-10 45 19-Jul-10 14 02-Aug-10 WB No Objection Date 7 09-Aug-10 Contract Award Date 7 16-Aug-10 Start Date 22 07-Sep-10 Execution /b 3 Evaluation & Recomm. Interval /a 01-Jun-10 Expected Bid-Opening Date Interval /a 01-Jun-10 Invitation Date Interval /a POST WB No Objection Date Interval /a Submission/ Readiness Date Interval /a Review By Bank (Prior / Post) Interval /a Estimated Cost (US$) /Actual cost Location/ Description Interval /a Procurement System Ref. # Procurement Method Sl. # Plan vs. Actual Updated Procurement Plan May, 2012 Completion Date 90 06-Dec-10 Funded by EU TF GARGOUR CO. The tipper truck is still stored at west bank water department stores in Ramallah till PWA gets the security clearance from the Israeli side to enter Gaza which is expected to take place within June , 2012. AL EKBAL CO. The acceptance certificated is expected to be issued by mid of June 2012, PWA is waiting for the supplier to provide the required spare tires and rim by the first week of June SUPPLIER NAME COMMENTS Part A P Tripper truck 4x2, 18 tons G.V.W, spare parts $ 140,000 NCB Q2/2012 A Tractor 4x4,WD, 80HP engine , with heavy duty spring loaded tiller and disc plough and spare P $ 111,800 $ 80,000 $ 65,483 $ 9,000 SH $ 9,680 $ 15,000 $ 11,221 $ 8,000 SH $ 4,000 $ 18,233 01-Jun-10 01-Jul-10 6 07-Jul-10 53 29-Aug-10 80 17-Nov-10 40 27-Dec-10 01-Jun-10 01-Jun-10 3 04-Jun-10 30 04-Jul-10 14 18-Jul-10 7 25-Jul-10 01-Jun-10 01-Jun-10 42 13-Jul-10 42 24-Aug-10 61 24-Oct-10 24-Oct-10 post 15-Apr-11 15-Apr-11 15-Apr-11 7 22-Apr-11 30 22-May-11 22-May-11 27 18-Jun-11 SH post 18-Apr-11 18-Apr-11 18-Apr-11 6 24-Apr-11 44 07-Jun-11 07-Jun-11 12 19-Jun-11 SH post 15-Oct-11 15-Oct-11 15-Oct-11 14 29-Oct-11 15 13-Nov-11 13-Nov-11 7 8-Apr-12 8-Apr-12 08-Apr-12 11 19-Apr-12 3 22-Apr-12 22-Apr-12 post 15-Mar-12 15-Mar-12 15-Mar-12 14 29-Mar-12 15 13-Apr-12 13-Apr-12 SH post 20-Mar-12 20-Mar-12 20-Mar-12 12 1-Apr-12 24 25-Apr-12 25-Apr-12 15-Dec-11 15-Dec-11 15-Dec-11 14 29-Dec-11 15 13-Jan-12 13-Jan-12 SH post 15-Jun-12 15-Jun-12 15-Jun-12 14 29-Jun-12 15 14-Jul-12 23-Jul-10 73 4-Oct-10 30 03-Nov-10 21 07-Sep-12 SH POST 30 27-Dec-10 42 07-Feb-11 280 14-Nov-11 01-Aug-10 22 23-Aug-10 90 21-Nov-10 03-Nov-10 25 28-Nov-10 525 06-May-12 18-Jun-11 7 25-Jun-11 1 20-Jun-11 23 13-Jul-11 20-Nov-11 2 22-Nov-11 30 22-Dec-11 4 26-Apr-12 3 29-Apr-12 30 5-Jan-00 7 20-Apr-12 2 22-Apr-12 30 22-May-12 25-Apr-12 1 26-Apr-12 30 26-May-12 7 20-Jan-12 2 22-Jan-12 30 21-Feb-12 14-Jul-12 7 21-Jul-12 2 23-Jul-12 30 22-Aug-12 14 17-Nov-10 30 17-Dec-10 14 31-Dec-10 731 31-Dec-12 14 21-Sep-12 7 28-Sep-12 28 26-Oct-12 150 25-Mar-13 7 Q2/2012 A p Q2/2011( PMU COMPUTERS ) NGESTSH-74 A P MAJIC TEC ELECTRIC AND ENGINEERING Photocopier ,Scanner ,Coloured Printer&shredder machine A Q2/2012 P QARAMAN CO. Stand by inverter for PMU server A Q2/2012 P R Q4/2011 Future PMU needs (CAPITAL INVESTMENT) $ 18,233 NG/ procurement of the required consumable materials for operating $ the NGWWTP two years. 1,584,000 $ 1,694,000 AL MERAJ WORKSHOP completed The photocopier has been delivered , The acceptance certificated and final Payment is expected to be issued by mid of June 2012. the system has been delivered,The acceptance certificated and the final Payment is expected to be issued by mid of June 2012. A Part B P A WWTP CONSUMABLE Q1/2012 ICB Prior 1-Jul-10 10 11-Jul-10 12 10 15-Jun-12 14 29-Jun-12 7 06-Jul-12 42 17-Aug-12 Part of the cosumable wil;l be stored in the NWWTP & the remaining will be stored at the CWMU stores . North Gaza Emergency Sewage Treatment Project NGEST (P074595)- Procurement Plan for Works - Main Agreement/ additional finance I & II WB No Objection Date Contract Award Date Start Date Execution /b Evaluation & Recomm. Interval /a Expected BidOpening Date Interval /a Invitation Date Interval /a WB No Objection Date Interval /a Submission/ Readiness Date Interval /a Review By Bank (Prior / Post) Interval /a Estimated Cost (US$) /Actual cost Location/ Description Interval /a Procurement System Ref. # Procurement Method Sl. # Plan vs. Actual Updated Procurement Plan May, 2012 Completion Date CONTRACTOR NAME JV STULZ PLANQUEA GMBH BERMEN & MASOUD & ALI CONTRACTING CO. COMMENTS Part A completed Part B 2 P Construction of NGWWTP ICB 01NGEST-2005 A Q2 /2012 P REMEDIAL WORKS R Q2 /2012 NG/The project consists of 800 mm DI Pressure Pipeline from TPS to $ NWWTP, 7,000 LM including valves, bends and valves chamber 24,500,000 $ 40,351,303 $ 230,000 $ 719,374 $ 2,740,139 NG/ provide proper cleaning and leveling at the dried effleunt lake and at the existing BLWWTP after putting the NGWWTP in operation. ICB Prior 2/15/2006 10 2/25/2006 12 3/9/2006 85 6/2/2006 30 7/2/2006 10 7/12/2006 28 8/9/2006 14 8/23/2006 730 8/22/2008 8/15/2009 4 8/19/2009 8 8/27/2009 90 11/25/2009 30 12/25/2009 10 1/4/2010 118 5/2/2010 124 9/3/2010 1396 6/30/2014 2/15/2006 30 3/17/2006 12 3/29/2006 85 6/22/2006 30 7/22/2006 10 8/1/2006 28 8/29/2006 14 9/12/2006 730 9/11/2008 POST 3/15/2013 14 3/29/2013 7 4/5/2013 35 5/10/2013 21 5/31/2013 14 6/14/2013 7 6/21/2013 28 7/19/2013 180 1/15/2014 NCB POST 15-Mar-12 14 29-Mar-12 7 05-Apr-12 35 10-May-12 21 31-May-12 14 14-Jun-12 7 21-Jun-12 28 19-Jul-12 365 19-Jul-13 NCB POST 15-Oct-12 14 29-Oct-12 7 05-Nov-12 35 10-Dec-12 21 31-Dec-12 14 14-Jan-13 7 21-Jan-13 28 18-Feb-13 365 18-Feb-14 ICB PRIOR 15-Mar-12 14 29-Mar-12 7 05-Apr-12 35 10-May-12 21 31-May-12 14 14-Jun-12 7 21-Jun-12 28 19-Jul-12 365 19-Jul-13 ICB PRIOR 15-Oct-12 14 29-Oct-12 7 05-Nov-12 35 10-Dec-12 21 31-Dec-12 14 14-Jan-13 7 21-Jan-13 28 18-Feb-13 365 18-Feb-14 NCB POST 15-Mar-12 14 29-Mar-12 7 05-Apr-12 35 10-May-12 21 31-May-12 14 14-Jun-12 7 21-Jun-12 28 19-Jul-12 365 19-Jul-13 NCB POST 15-Oct-12 14 29-Oct-12 7 05-Nov-12 35 10-Dec-12 21 31-Dec-12 14 14-Jan-13 7 21-Jan-13 28 18-Feb-13 365 18-Feb-14 NCB POST 15-Mar-12 14 29-Mar-12 7 05-Apr-12 35 10-May-12 21 31-May-12 14 14-Jun-12 7 21-Jun-12 28 19-Jul-12 365 19-Jul-13 NCB POST 24-Feb-13 14 10-Mar-13 7 17-Mar-13 35 21-Apr-13 21 12-May-13 14 26-May-13 7 02-Jun-13 28 30-Jun-13 365 30-Jun-14 NCB POST 15-Mar-12 14 29-Mar-12 7 05-Apr-12 35 10-May-12 21 31-May-12 14 14-Jun-12 7 21-Jun-12 28 19-Jul-12 365 19-Jul-13 NCB POST 24-Feb-13 14 10-Mar-13 7 17-Mar-13 35 21-Apr-13 21 12-May-13 14 26-May-13 7 02-Jun-13 28 30-Jun-13 365 30-Jun-14 ICB PRIOR 15-Mar-12 14 29-Mar-12 7 05-Apr-12 35 10-May-12 21 31-May-12 14 14-Jun-12 7 21-Jun-12 28 19-Jul-12 365 19-Jul-13 ICB PRIOR 24-Feb-13 14 10-Mar-13 7 17-Mar-13 35 21-Apr-13 21 12-May-13 14 26-May-13 7 02-Jun-13 28 30-Jun-13 365 30-Jun-14 NCB The revised cost estimate by the consultant was $ 42795758. The letter of acceptance has been issued on 2/5/2010 , Pwa signed the contract on 31/5/2010, the contract became effective on 2/9/2010 The work is going on. Three Change Orders were issued by the employer and accepted by the contractor , another three changing proposals are bending The Remedial Main activities will be determined in the Supplemental ESIA Report Phase I P R P R P A Construction of Recovery & Monitoring Wells and Well Piping Supply & installation of plant &equipment of effluent recover & irrigation scheme (15 recovery wells, well collection pipes, and 5 monitoring well Q2 /2012 Construction Of Booster Station & Concrete Reservoir one 4000 m3 water tank and installation of 5 pumping units and installation of control /automation system $ 2,740,139 $ 5,538,032 Q2 /2012 Construction Of Reuse & Distribution Pipe Network small works contract cover the irrigation networkfor 5000 donum $ 5,538,032 $ 3,691,174 $ 3,691,174 $ 1,112,933 Q2 /2012 The bidding documents have been submitted by the Consultant on 15th March, 2012 to be revised by PWA. The bidding documents have been submitted by the Consultant on 15th March, 2012 to be revised by PWA. The bidding documents have been submitted by the Consultant on 15th March, 2012 to be revised by PWA. Phase II P R P R P R Construction of Recovery & Monitoring Wells and Well Piping Supply & installation of plant &equipment of effluent recover & irrigation scheme (12recovery wells, well collection pipes and 5 monitoring well Q2 /2012 Construction Of Booster Station & Concrete Reservoir $ 1,112,933 $ 3,124,765 , one 4000 m3 pumping units and installation of 5 pumping units and installation of control /automation system Q2 /2012 Construction Of Reuse & Distribution Pipe Network $ 3,124,765 $ 12,097,435 small works contract cover the irrigation networkfor 10000 donum Q2 /2012 $ 12,097,435 11 The bidding documents have been submitted by the Consultant on 15th March, 2012 to be revised by PWA. The bidding documents have been submitted by the Consultant on 15th March, 2012 to be revised by PWA. The bidding documents have been submitted by the Consultant on 15th March, 2012 to be revised by PWA. 12