Documentation Guide for the ICT Two Pass Review Process

advertisement
Documentation Guide for the ICT Two Pass Review Process
Documents
Business Case
Project Plan
Governance Plan
Risk Plan and
Register
Agency
Capability
Investment Plan
1st 2nd
Pass Pass
Definition
Provide a summary of the business problem and a range of response options, including a status quo option. The preferred option should be identified in
consultation with Finance. Detail the financial and non-financial costs and benefits from implementing each option, along with project cancelation costs.
Provide a summary of the schedule, by each option, to support phased implementation. Discuss how the business case supports the agency’s and the
Commonwealth’s business and ICT strategic objectives. Detail any legislative or Cabinet authority for the business case and discuss compliance with
 
whole-of-government policies such as security, privacy and procurement. Summarise corporate governance arrangements and address capability
limitations identified in the P3M3® assessment. The First Pass Business Case should detail the activities and the cost to develop the option(s) for the
Second Pass Business Case.
Outline how the project deliverables will be organised, controlled and managed to ensure achievement of schedule, scope and budget targets; provide a
high level summary of the project scope; provide a summary of supporting plans; and provide a project schedule identifying each project stage and
 
milestone.
Define the governance structure, roles, responsibilities and reporting channels for managing the programme / project, including: the board / working
 group, the change / configuration / assurance authorities, and any other oversight provided by the agency.
Detail how the project will identify, manage and report risks, including the personnel responsible for risk management. Detail each project risk and
 mitigation / treatment strategies. Risks should relate to the business and technical issues likely to impact on schedule, scope and budget targets.
Provide the agency’s P3M3® Assessment, conducted during the preceding 12 months; the Capability Improvement Plan and evidence of independent
validation of agency capability provided by a P3M3® Accredited Consulting Organisation.
 Var
Provide a prioritised list (no more than two or three pages) of agency approved and unapproved ICT investments over the next four years, with summary
annual cost estimates and a short descriptive statement for each investment.
 Var
Detail the project's measurable benefits and the method and metrics to be used for tracking, reviewing and reporting when and if benefits are realised.
Benefits Plan and
VarBenefits are to be agreed between the programme / project office, sponsors, stakeholders and Finance.
Register
Solution
(Architecture)
Design
Outline the solution to be developed to address the business problem identified in the business case. Outline the scope of the proposed solution within
the context of the agency’s current ICT environment. The architecture of the proposed solution covers, for example: technology (hardware), applications,
security, information (data models) and system integration / migration. The Solution Design should be of sufficient detail to support further post-approval
Var 
design (as applicable) of the solution. The Solution Design is a primary input for the build and testing phases of the project. May be used to support
industry engagement activities.
Updated: 08 August 2014
Documentation Guide for the ICT Two Pass Review Process
Requirements
Specification
Procurement
Plan
Security Plan
Product
Breakdown
Structure
Quality Plan
Outline the business and technical requirements of the solution, and provide sufficient detail to support the ongoing design, cost estimation and schedule
management of the products to be delivered. The document may also detail the users, transactions, process flows and business rules; the basis of a sizing
Var method such as a use-case or function point count. Outline any hardware capacity and performance requirements. Out of scope requirements may be
detailed. Complements the Solution Design and may be used to support industry engagement activities.
Detail how the project will acquire the services, hardware and software required to implement the solution; supports the Project Plan and outlines the
Var strategy for any industry engagement activities.
Reference and explain how the proposed solution will align with the Protective Security Policy Framework, comply with the Information Security Manual,
including addressing the Top 4 Strategies to Mitigate Targeted Cyber Intrusions (mandatory for Australian Government agencies), and other security
policies and guidelines; provide additional security details beyond the Solution Design and Requirements Specification; and engage the agency’s IT
Var
Security Advisor. See Estimates Memorandum 2014/04 Cyber Security Requirements in Business Cases for ICT-Enabled New Policy Proposals available from
Finance or the agency’s CFO area.
Provide a hierarchy of products to be delivered by the project, with each descending level of the hierarchy providing a more detailed component product,
Varwith associated costs. A work breakdown structure may also be provided. Related to the Solution Design and Requirements Specification.
Define the approach, standards, techniques and processes to ensure that the project's products meet specified acceptance criteria; establish document
change control, auditing and configuration management processes. Outline the process of quality rectification for build, integration and installation
 Var
activities, as applicable.
Change Plan
Detail a change management strategy for implementing the solution within the agency; covers stakeholder engagement, communication activities and
identifying any training needs as the basis to develop a user training solution after Second Pass approval.
Var
Workforce Plan
Var


Var
Detail how an appropriately skilled and experienced workforce will be acquired, managed and retained to complete project deliverables.
Required
Not required
The requirement for this supporting document varies,
depending on the complexity of the proposal and as agreed
between Finance and the agency.
Updated: 08 August 2014
Download