Project Turnover and Closeout A Guide for Project Administration Contents Introduction to Project Turnover and Closeout ....................................................3 Who’s Involved in Project Turnover? ..............................................................3 Who’s Involved in Project Closeout? ...............................................................3 Project Turnover.......................................................................................................4 Planning for Turnover ......................................................................................4 Identifying Stakeholders ..............................................................................6 Planning Pre-Turnover Activities ................................................................7 Processing Punch Lists and Conducting Inspections .......................................7 The Contractor’s Punch List and Request for Final Inspection ...................8 The Final Inspection ....................................................................................9 The Final Inspection Record (Associate’s Punch List)...............................9 Resolution of Punch-List Items .................................................................12 Approving Project Record Deliverables .........................................................12 “Wages and Hours” Affidavit ....................................................................13 Guarantees and Warranties ........................................................................13 Ensuring Site Cleanup ....................................................................................14 Accepting the Finished Project .......................................................................14 Issuing the Certificate of Warranty Commencement.................................14 Issuing the Certificate of Completion ........................................................14 Notifying Stakeholders ..............................................................................17 Conducting Walk-Throughs.......................................................................17 Providing Training and Documentation.....................................................17 Project Closeout ......................................................................................................19 Closing Construction Contracts ......................................................................21 Processing a Reconciliation Change Order Form ......................................21 Approving Final Pay Applications, Affidavits, and Releases of Retainage .........................................................................21 Closing Design Contracts ...............................................................................23 Checking Associate Deliverables ..............................................................23 Reconciling Fees and Expenses .................................................................23 Approving the Associate’s Final Pay Application .....................................25 Forwarding Project Records ...........................................................................25 Figures Project Turnover and Closeout February 2003 Page 1 1 Record of Final Inspection (Associate’s Punch List) 2 Certificate of Warranty Commencement 3 Certificate of Contract Completion 4 Change Order Form for Reconciliation 5 Amendment for Contract Closeout Chart 1 Process Flow for Project Turnover 2 Process Flow for Project Closeout Page 2 February 2003 Project Turnover and Closeout Introduction to Project Turnover and Closeout Project turnover and project closeout are distinct but closely related phases of project administration. Turnover encompasses all the activities involved in a project’s transition from construction or renovation to occupancy and use. At project turnover, the University accepts the completed project from the Contractor and formally assumes the responsibilities of ownership. Closeout refers to the activities involved in terminating the project’s construction and design contracts, transferring information to the project Accountant for financial closeout, and archiving all project records. This chapter describes project administration activities during project turnover and closeout. Who’s Involved in Project Turnover? University’s Construction Management and the Project Administrator Associate Architect/Engineer (A/E), if the project has one Construction Contractors End users/occupants Commissioning Agent from UC Facilities Management, and other Facilities representatives as required UC Information Technology (UCit) UC Public Safety Who’s Involved in Project Closeout? University’s Construction Management and the Project Administrator The assigned Project Accountant Associate Architect/Engineer (A/E), if the project has one Construction Contractors Document Control Commissioning Agent from UC Facilities Management, and other Facilities representatives as required Project Turnover and Closeout February 2003 Page 3 Project Turnover Outcome The University has accepted the finished project from the construction contractors. A Certificate of Completion has been issued. The University has assumed the responsibilities of maintenance, security, and insurance for the new or renovated facility, which is ready to be occupied. In the Project Turnover phase, the Contractor presents the finished project to the University. When the Contractor has fulfilled all requirements of the contract documents, the University accepts the work. The University’s and Associate Architect’s (if applicable) activities in this phase include the following: 1. Planning for project turnover, 2. Processing punch lists and conducting inspections, 3. Approving project record deliverables, 4. Ensuring site cleanup by the contractor, and 5. Accepting the finished project. The following sections present details of each of the above activities. Chart 1 shows the process flow for project turnover. Planning for Turnover Not all project turnover activities take place at or near the end of the project. Certain aspects of turnover can be planned even when the project is just getting started. The Project Administrator and team should identify and involve all major stakeholders within the University as early in the project as possible. This approach enhances the stakeholders’ opportunity to contribute to a smooth turnover. The size, complexity, and purpose of a new or renovated facility will determine who the stakeholders are and what the specific turnover procedures will be. In particular, the turnover process for a capital project is likely to differ from that of a renovation project. Page 4 February 2003 Project Turnover and Closeout Design 1. Plan for turnover Identify stakeholders and contact people Facilities contacts review 95% complete construction documents as appropriate Associate/Project Administrator, contacts establish project-specific turnover procedures Construction Facilities contacts, maintenance personnel observe construction at various stages 2. Process punch lists and conduct inspections Contractor submits punch list, request for final inspection, and project record deliverables Is project ready for final inspection? Yes Associate or Project Administrator conducts final inspection Associate or Project Administrator prepares punch list No Contractor completes work and resubmits punch list, request for final inspection Turnover and Acceptance 3. Approve project record deliverables 5. Accept the finished project Contractor submits any outstanding project record deliverables Associate or Project Administrator issues Certificate of Completion; University accepts project Associate and/or Project Administrator and Facilities Management approve project record deliverables Project Administrator issues copies of completion notice to Facilities, Risk Management, Public Safety Contractor arranges training on systems, equipment for Facilities Management, end users Contractor terminates liability insurance; University assumes liability coverage 4. Ensure site cleanup Facilities Management views completed project and receives project record deliverables Contractor corrects punch-list deficiencies (within 30 days) Contractor cleans work site to University's standards Facilities assumes maintenance; Public Safety assumes security responsibilities Associate and/or Project Administrator and Facilites Management evaluate, approve site cleanup Project Administrator notifies occupants of completion Occupancy/use can begin Chart 1: Process Flow for Project Turnover Project Turnover and Closeout February 2003 Page 5 Identifying Stakeholders Other than Construction Management and the future occupants, University stakeholders in a construction project usually include Facilities Management, Public Safety, UCit, and other University departments as appropriate. For each project, the Project Administrator and team must determine which functions need to become involved. The table below shows some possible participants in project turnover (the list is not all-inclusive). Facilities Management Public Safety UCit www.uc.edu/pubsafety/ www.ucit.uc.edu Others Parking Services Network and Housing and Food Telecommunications Services (www2.uc.edu/housing) Services † Environmental Health Electronic Classroom Planning and Safety (http://ehs2.uc.edu/) and † Support Services • Lab exhaust controls www.uc.edu/facmgmt Maintenance and Operations •Carpentry •Painting •Electrical •Plumbing •HVAC •Elevators •Grounds •Maintenance Security Fire Protection • Indoor air quality • Hazardous materials management (chemicals control; tracking, storage, and containment) Housekeeping Utilities * Radiation Safety Office (http://www.uc.edu/radsafety/) See the supplemental topic “Underground and Concealed Utilities” for additional information about Construction Management’s interactions with this department. * † See the supplemental topic “UCit and Construction Management Project Procedures” for additional information about Construction Management’s interactions with this department. Page 6 February 2003 Project Turnover and Closeout Planning Pre-Turnover Activities Listed below are some examples of turnover-related activities that can be planned early in the project: During Program Statement: Gain agreement on project communication procedures, particularly formal notifications from Construction Management to stakeholders During Design: Have discipline contacts in Facilities Management and other departments review 95% complete construction documents Before Construction: Make provisions to ensure that building equipment used by contractors during construction is maintained Before Construction: Stipulate that startup and commissioning be in accordance with the University’s Design Guidance: Commissioning document During Construction: Seek consultation and input as needed from stakeholders; arrange for discipline contacts in Facilities Management to observe construction in progress; conduct commissioning tests and activities as required by a project’s Commissioning Plan Before turnover: Distribute project documentation (for example, O&M manuals and as-built drawings) for stakeholder review as appropriate Before turnover: Schedule Facilities Management’s inspection of project components and systems as required (particularly any elements that will undergo commissioning) Before turnover: Arrange for the Contractor to return all keys as part of project closeout Before turnover: Work with contractors, the Associate, and stakeholders to develop procedures for addressing deficiencies and/or warranty issues The next section presents turnover activities that take place late in the Construction phase. Processing Punch Lists and Conducting Inspections As construction nears its end, the Contractor initiates the activities that will lead to the University’s acceptance of the project. Prime contractors and Associate Architects (or the Project Administrator acting as the Architect) have specific responsibilities in the Contract Documents for preparing and responding to punch lists. Project Turnover and Closeout February 2003 Page 7 The Contractor’s Punch List and Request for Final Inspection Late in construction, each prime Contractor develops a punch list of items known to be incomplete or to need correction. When work on the punch list is at least 90 percent complete, the Contractor can submit the punch list and request a final inspection. The punch list should provide expected completion dates for any unfinished items. If the project has a lead Contractor, its representative collects all punch lists and submits them to the Associate (or Project Administrator, depending on the project). If there is no lead Contractor, each prime Contractor must deliver its punch list to the Associate or Project Administrator. Along with the punch list(s), the lead Contractor or prime Contractor submits the following items to the Associate: A letter requesting final inspection of the work Project record documents, including but not limited to: Operation and maintenance (O&M) manuals (four sets) for major systems. The manuals must be organized in binders with identifying covers for easy use. As-built drawings accurately representing the finished construction and showing the locations of any concealed utilities, systems, or components. The Associate or Project Administrator will use the as-built drawings to revise the original contract drawings. The revisions then become the project’s Drawings of Record. Required certificates and approvals, as available at the time of the final inspection request. These include but are not limited to the Certificate of Occupancy issued by the Ohio Department of Commerce, Division of Industrial Compliance; inspection certificates for any systems that require them (e.g., pressure piping, plumbing, elevators, electrical systems); and the State Fire Marshal’s approval of the fire suppression system. Once all these inspections have been completed, the State performs a general inspection. Guarantees and warranties issued in the University’s name as required by the Contract Documents. (See the section “Guarantees and Warranties” in this chapter for specific requirements.) Commissioning documentation as required by a project’s Commissioning Plan for commissioned projects and systems. A current list of names, addresses, and telephone numbers for all contractors, subcontractors, and suppliers, including information for after-hours contact. Affidavits attesting that the Contractor has paid all subcontractors and material suppliers, and has complied with Ohio’s “Wages and Page 8 February 2003 Project Turnover and Closeout Hours on Public Works” law (ORC 4115). (See the section “Approving Project Record Deliverables” in this chapter for specific requirements.) Certified final payroll reports demonstrating that the Contractor’s employees have been paid for their work. Note: Project record deliverables that are required by the General Conditions (Contract for Construction) must be provided in electronic format on a CDROM. The project’s specific Contract Documents may require the submission of additional project record deliverables. Note: Some project record deliverables may not be available at the time of the final inspection request. However, all deliverables must be approved before the University will issue the Contractor’s final payment, retainage, or Certificate of Completion. See the section “Approving Project Record Deliverables” for more information. The Contractor will continue working on incomplete items while awaiting the final inspection. The Final Inspection Within 7 days of receiving the Contractor’s punch list and request, the Associate or Project Administrator determines whether the project is ready for final inspection. The Associate/Project Administrator’s assessment of progress (from ongoing field observation) and the level of completeness reflected on the punch list will factor into this determination. If the Associate or Project Administrator judges the work to be insufficiently complete for inspection (for example, if a major system is not finished), he or she notifies the Contractor by letter. The Contractor will resubmit the request, punch list, and documentation after bringing work to the required completion level. Before conducting a final inspection, the Associate or Project Administrator informs the Contractor of the inspection date and time. The University also must be notified. The Final Inspection Record (Associate’s Punch List) During the final inspection, the Associate or Project Administrator determines whether the Contractor’s work meets the requirements established in the Contract Documents. After inspecting the work, the Associate or Project Administrator prepares the Record of Final Inspection of the Contractor’s Work (Figure 1). This form, also called the Associate’s punch list, documents the Project Turnover and Closeout February 2003 Page 9 Associate or Project Administrator’s observations on the completeness and quality of the work as well as the status of other deliverables. The final inspection record must be provided to the Contractor not later than 3 days after the final inspection date. Note: The Associate’s final punch list also serves to document the eventual turnover from Construction Management to Facilities Management. See the section “Providing Training and Documentation” in this chapter. Page 10 February 2003 Project Turnover and Closeout Division of the University Architect Department of Construction Management PO Box 210181 Cincinnati, Ohio 45221-0181 02999 Project No.: Project Name: Contractor: VBC, Inc. Smart Residence Hall Addition RECORD OF FINAL INSPECTION OF THE CONTRACTOR'S WORK For use by the Associate according to Article 10 of the General Conditions. Final Inspection Attendees: James Knox, VBC Inc. Brian King, C.P. Jones & Associates Annmarie Thurnquist, University of Cincinnati Contractor's list of incomplete or deficient items associated with the work Date to be Completed Install correct tile in east restroom Install splashguards behind counters in kitchen Complete all sodding and landscaping 10 August 2002 10 August 2002 19 August 2002 Note of any deficiency in Contractor's Project Record Document Submittals: O&M Manuals for the heating and cooling systems are incomplete Need final, certified payroll reports Need contact information for all subcontractors, manufacturers and suppliers Note of any deficiency in Contractor's As Built Drawing Submittal: As-built drawing package needs Contractor’s signature and date Note of any deficiency in Warranties required by the Contract Documents: None Note of the quality of final cleaning performed by Contractor: Final cleaning to be performed by 19 August 2002 Associate notes: Contractor to correct all above-noted deficiencies by 19 August 2002 Submitted by: Brian L. King 15 July 2002 Associate Date Figure 1: Record of Final Inspection (Associate’s Punch List) Project Turnover and Closeout February 2003 Page 11 Resolution of Punch-List Items Within 30 days of receiving the final inspection record, the Contractor must resolve all outstanding punch-list items or request additional time to complete punch-list work. Any request for a time extension must be adequately justified to the Associate and the University. Sometimes weather conditions prevent the completion of work. In such a case, the University may allow the Contractor to delay completion until site conditions improve. Under the General Conditions, if completion were deferred, the University would be authorized to deduct two times the cost of any deferred work from the Contractor’s payment until the Contractor completed the work. The General Conditions specify remedies the University may take if a Contractor does not fulfill all contract obligations. They include: Hiring other contractors or consultants to finish or correct the work, and deducting the cost from the delinquent Contractor’s pay; and/or Demanding payment from the delinquent Contractor’s surety if the amount owed the Contractor is less than the cost of the work. Approving Project Record Deliverables Between the final inspection and the agreed-upon contract completion date, the Contractor works to complete any unfinished items of work. During this time the Contractor must also finish any incomplete project record deliverables, as cited in the final inspection/punch list, and submit them to the Associate or Project Administrator for approval. The University’s Facilities Management department should also be involved in reviewing and approving these documents. The University will not issue a Certificate of Completion, issue the Contractor’s final payment, or release retainage until all project record deliverables have been approved. Note: The complete list of project record deliverables required from the Contractor appears under “Processing Punch Lists and Conducting Inspections” in this chapter. The following subsections present specific information the Associate or Project Administrator needs to know about approving certain project record deliverables. Page 12 February 2003 Project Turnover and Closeout “Wages and Hours” Affidavit Each Contractor must include a signed and notarized “Affidavit of Contractor” with its final pay application. In signing the affidavit, the Contractor attests that its subcontractors and material suppliers have been paid in full, and that the Contractor, subcontractors, and suppliers all have complied with ORC 4115 (“Wages and Hours on Public Works”). The University’s Office of Contract Compliance reviews the Contractor’s affidavit and final pay application before final payment is made. Note: Any Contractor known to have violated prevailing wage law must not receive payment until any payments or penalties associated with the violation have been paid in full. If a Project Administrator receives notice that a Contractor has violated this law, the Project Administrator should not approve the pay application and should notify the Project Accountant and the UC Office of Contract Compliance. Guarantees and Warranties The guarantee that the University requires of all Contractors contains two major stipulations: Work must conform to the standards established in the Contract Documents, and Work must be free of any defects in workmanship, materials, or equipment. The University requires the guarantee to be in effect for at least 1 year. However, the Certificate of Contract Completion issue date is not necessarily the start of the warranty period. Warranties must begin as soon as there is any University occupancy of the facility or use of equipment, including any occupancy or use that begins before contract completion. Some projects have longer guarantee periods specified in the Contract Documents. The Contractor must maintain a bond for the duration of the guarantee period. Article 11.3 of the General Conditions describes the rights the University will exercise should any defects become apparent during the warranty period. See “Issuing the Certificate of Warranty Commencement” in this chapter for further information. Project Turnover and Closeout February 2003 Page 13 Ensuring Site Cleanup The project cannot be accepted until the work site has been cleaned to the University’s satisfaction. In general, contractors are required to remove all work-related waste and debris from the site and to return all unaffected property to its original condition. The Associate or Project Administrator must not issue a Certificate of Contract Completion without verifying that the site cleanup meets the University’s standards. Facilities Management should also be involved in assessing the cleanup. Article 11.4 of the General Conditions presents the University’s site cleanup requirements in detail. If two or more contractors disagree as to which contractor bears responsibility for any part of site cleanup, the University can hire a different contractor or a professional cleaning service to perform the work. This additional cost would then be deducted from the final payments due any contractors who did not fulfill their contractual obligation to clean the site. Accepting the Finished Project Issuing the Certificate of Warranty Commencement A Certificate of Warranty Commencement (Figure 2) is required for all materials and equipment that are subject to warranty. The Associate initiates a Certificate of Warranty Commencement to establish the date warranty coverage begins for a system or piece of equipment. The Contractor and the Associate sign the certificate, and the Associate presents it to the University for approval. Issuing the Certificate of Completion When all work items noted on the Associate’s punch list have been completed and all project record deliverables have been approved, the Associate initiates the Certificate of Contract Completion (Figure 3). The Contractor and the Associate sign the certificate, and the Associate presents it to the University for approval. By signing this document, the Project Administrator certifies the University’s acceptance of the project. Page 14 February 2003 Project Turnover and Closeout Division of the University Architect Department of Construction Management PO Box 210181 Cincinnati, Ohio 45221-0181 Project No.: 02999 Project Name: Contractor: Smart Residence Hall Addition VBC, Inc. CERTIFICATION OF WARRANTY COMMENCEMENT Describe the Equipment or Materials to be accepted: HVAC system List of incomplete/deficient items associated with Equipment or Materials Date to be Completed O&M Manual Contact information for manufacturer 19 August 2002 Statement of the terms associated with acceptance, i.e., testing, maintenance, cleaning, etc.: Limited occupancy begins 9 August 2002. Warranty begins 9 August 2002. Seasonal testing to be performed over next 12 months. Record of Inspection (Associate and/or University notes): Functional tests OK, 8 August 2002. The undersigned certifies that the warranty complies with the requirements of the Contract Documents. James D. Knox Contractor Approval 9 Aug 2002 Date Brian L. King Associate 9 Aug 2002 Date Owner acknowledgement of receipt of warranty, operating manual, etc., associated with acceptance of Equipment or Material. Annmarie P. Thurnquist 9 Aug 2002 University Date Certification of Warranty Commencement.doc Rev. 2/02 Figure 2: Certificate of Warranty Commencement Project Turnover and Closeout February 2003 Page 15 Division of the University Architect Department of Construction Management PO Box 210181 Cincinnati, Ohio 45221-0181 Project No.: 02999 Project Name: Contractor: Smart Residence Hall Addition VBC, Inc. CERTIFICATION OF CONTRACT COMPLETION The undersigned certifies that all the Contractor's Work is 100 percent complete, with exception of the below noted deficiencies, and the Contractor has complied with all conditions precedent to final payment and release of retainage. When upon Final Inspection, items of Work cannot be completed because of seasonal conditions approved by the Associate and the University, such as bituminous paving, landscaping, etc., and if the University agrees that a particular item need not be completed until a subsequent date, the University may release payment to the Contractor less two (2) times the cost of completing the remaining Work. Date to be Completed No deficiencies remain; work is 100% complete. James D. Knox 21 August 2002 Contractor Date We, the undersigned, together with a representative of the Contractor employed for the execution of the work, have inspected the work included in the captioned contract, prior to the date of this certificate, and hereby certify that all work on the contract has been completed in accordance with the requirements of the Drawings, Specifications, and other Contract Documents, and accordingly recommend that the work included on said contract be accepted. Brian L. King 21 August 2002 Associate Date Final Acceptance of Project Annmarie P. Thurnquist 21 August 2002 University Date Figure 3: Certificate of Contract Completion Page 16 February 2003 Project Turnover and Closeout Notifying Stakeholders In accepting the project, the University assumes the responsibilities of ownership, including maintenance, security, and liability protection. The UC departments responsible for these functions must be notified of the acceptance. A copy of the Certificate of Contract Completion should be sent to the building’s future occupants and to the University’s Facilities Management, Public Safety, and Risk Management departments, at a minimum. Notification of other UC departments should proceed according to the turnover plan that was established at the beginning of the project. Conducting Walk-Throughs The Project Administrator should schedule an informational walk-through of the completed project with Facilities Management personnel. In addition, the occupants should have an opportunity to walk through the new facility before moving in. Walk-throughs may also be scheduled for other UC departments as warranted. Providing Training and Documentation The Contract Documents may call for Contractors to provide orientation and training on specific systems (e.g., electrical, mechanical, and plumbing) for the responsible Facilities Management personnel and end users. Training by Contractors is often negotiated into contracts on projects that will undergo commissioning. The Project Administrator should work with Contractors and Facilities Management as required to schedule this training before occupancy begins, if possible. Facilities Management also requires copies of much of the project record documentation. The Project Administrator should ensure that Facilities Management receives, at a minimum, copies of the following documents: State Certificate of Occupancy. All state inspection certificates. Any records of early acceptance for parts of the facility, as applicable. Warranties and guarantees (Facilities Management in turn will provide this information to its Work Control Department [http://www.uc.edu/facmgmt/maint.asp], which will assume responsibility for managing the warranties after turnover). Associate’s final punch list (Record of Final Inspection), which serves to document the turnover from Construction Management to Facilities Management. One set each of Project Record Drawings, specifications, and shop drawings. (These documents should be provided to Facilities Project Turnover and Closeout February 2003 Page 17 Management at the time the Contractor submits them to the Associate. The Associate may require a significant amount of time to prepare the Project Record Documents, and Facilities Management may need a preliminary copy during that period.) Page 18 One complete set of Operation and Maintenance Manuals. A list of names, addresses, and telephone numbers for all contractors, subcontractors, and suppliers, including after-hours contact information. Commissioning documentation and reports, as applicable. February 2003 Project Turnover and Closeout Project Closeout Outcome The project’s design and construction contracts have been closed, and project records have been forwarded for archiving and financial closeout. Once the University has accepted the project and a Certificate of Contract Completion has been signed, the Associate, Project Administrator, and Accountant work together to move the project out of “active” status. Project closeout includes the following activities: 1. Closing construction contracts, 2. Closing design contracts, and 3. Forwarding project records for financial closeout and archiving. Chart 2 on the following page shows the process flow for project closeout. Note: The information in this chapter describes Construction Management’s activities in closing projects. A future chapter will present the steps involved in financial closeout. Project Turnover and Closeout February 2003 Page 19 Associate or Project Administrator processes reconciliation Change Order to close contract Contractor requests f inal payment, release of retainage 2. Close design contracts Associate submits contract deliverables Project Administrator, Associate reconcile Change Order f ees, reimbursable expenses University amends Prof essional Design Services Agreement, if necessary 3. Provide project records to Accountant Project Administrator f orw ards f inal pay applications to Accountant (f or contractors, Associate) Project Administrator notif ies Accountant that Purchase Orders can be closed Project Administrator provides project f iles to Accountant f or storage (hard copy or electronic) 1. Close construction contracts Project Administrator authorizes release of contractor's retainage, if applicable Project Administrator approves request and authorizes payment Associate submits f inal payment request Project Administrator approves request and authorizes payment Project Administrator provides copies of project documents to Document Control Chart 2: Process Flow for Project Closeout Page 20 February 2003 Project Turnover and Closeout Closing Construction Contracts All construction contracts must be closed at the end of a project. The Associate or Project Administrator starts the closeout process by completing a reconciliation Change Order Form. Processing a Reconciliation Change Order Form An example of a completed Change Order Form for contract closeout appears on the next page as Figure 4. The purpose of the reconciliation Change Order is usually to deduct unused funds from the contract. (See the Supplemental Topic “Following the Change Order Process” for additional information on processing change orders.) Approving Final Pay Applications, Affidavits, and Releases of Retainage Contracts cannot be closed until all Contractors’ final pay applications (and Contractor affidavits attesting to ORC 4115 compliance) have been approved. (Contractors submit their affidavits with the project record deliverables in connection with project acceptance. See the sections “Processing Punch Lists and Conducting Inspections” and “Approving Project Record Deliverables” in this chapter.) Companies that had escrow agreements will also request release of their retainage. Project Administrators should evaluate and approve all outstanding pay requests as quickly as possible and forward them to the Project Accountant for payment and release. (See “Forwarding Project Records” later in this chapter for further information.) The chapter “Managing the Construction Phase” presents complete instructions for evaluating and approving Contractor pay applications. Project Turnover and Closeout February 2003 Page 21 Division of the University Architect Department of Construction Management PO Box 210181 Cincinnati, Ohio 45221-0181 CHANGE ORDER X ADD (White paper only) UC Purchase Order No. Change Order No. PC02C-00800 102 General Type of Contract: O2999 Project No.: DEDUCT (Goldenrod or Yellow paper only) Project Name: Smart Residence Hall Addition Check Reason for Change Order Error/Omission Field Condition Field Dispute Settlement Owner Request Value Engineering Other: Close contract Contractor's Proposal Dated: N/A Contract Days Changed N/A Revised Completion Date: N/A Original Contract Sum Net Change by Previous C.O.s Contract Sum Prior to this C.O. Total Cost of this C.O. NEW CONTRACT SUM Total Cost $ 800,000.00 $ $ $ $ $ 800,000.00 (1,450.00) 798,550.00 (1,450.00) Description / Justification (Add more pages if necessary) Reconciliation The terms and conditions of this Change Order, including the cost and time contained herein, constitute a full accord and complete satisfaction for all costs and time of performance related to the work described or referenced herein, including but not limited to, all delay and impact costs for the entire Project resulting from this Change Order. Except as amended herein, all provisions of the Contract remain in full force and effect. CONTRACTOR'S ACCEPTANCE Name & Address: VBC, Inc 1420 Chestnut Street Cincinnati, OH 45202 James D. Knox Contractor Signature ASSOCIATE'S RECOMMENDATION Name & Address: C.P. Jones & Associates 9999 Mason-Montgomery Rd., Suite 20A Cincinnati, OH 45242 30-Aug-02 Date Brian L. King Associate Signature 30-Aug-02 Date CHANGE ORDER APPROVED (Vendor cannot invoice until receipt of University approved form A-600 "Cancellation or Change Order".) Dewey Enderle Sr. Staff Engineer Signature 30-Aug-02 Date Annmarie P. Thurnquist Project Manager Figure 4: Change Order Form for Reconciliation Page 22 February 2003 Project Turnover and Closeout 30-Aug-02 Date Closing Design Contracts After working with the Associate to close out construction contracts, the Project Administrator begins the process of closing the Associate’s contract as well as any design consultant agreements. Before a design contract can be closed, the Project Administrator must verify that the Associate or consultant has submitted all contract deliverables; meet with the Associate to reconcile fees and reimbursable expenses; and approve the final pay application. Checking Associate Deliverables The Associate will have presented many of its deliverables during acceptance. At project closeout, the Project Administrator must confirm that Associate has provided the following: Note: Project Record Drawings (as updated from the Contractor’s “as-built” drawing submittals) Associate-approved O&M Manuals Associate-approved guarantees and warranties Commissioning documentation as applicable On projects that do not use an Associate A/E, the deliverables listed above must be approved by the project’s internal design professional or external design consultant, as applicable. Reconciling Fees and Expenses Before closing out the contract, the Project Administrator meets with the Associate (or design consultant) to reconcile the Change Order fees and reimbursable expenses associated with the project. If outstanding fees or expenses cause the contract total to increase, the Project Administrator must complete and process a contract Amendment (Figure 5) to adjust the contract before closing it. Amendments to design contracts also require completion of both the A-600 Form (to report the change to University Purchasing) and the A-910 Form. See the Supplemental Topic “Following the Change Order Process” for complete instructions on processing Amendments and Change Orders. Project Turnover and Closeout February 2003 Page 23 Amendment Number: 02999-004 March 29, 2002 The original Architect’s Agreement executed on C.P. Jones & Associates, Inc. , between the University of Cincinnati, the Owner, and the Architect, is hereby amended as a result of additional services on the following project: Project No. Project Name 02999 Smart Residence Hall Addition Article 1, Architect’s Services, shall be amended to include the following scope of work as part of the Architect’s professional services: N/A; amendment is for Associate’s reimbursable expenses incurred in August Article 5, Basis of Compensation, shall be amended as follows: $ Total add to contract amount for this Amendment Dollars and (Three hundred seventy-eight 378.00 zero /100 Cents) Compensation Summary: $ 56,000.00 $ 1,850.00 378.00 $ $ 58,228.00 Original Contract Previous Amendments This Amendment Total Current Contract Amount All other terms of the Agreement shall remain as written. IN WITNESS WHEREOF, the parties hereto have agreed and hereunto set their hands on this date , the University of Cincinnati signing and sealing these 30 August 2002 presents through its authorized signature: UNIVERSITY OF CINCINNATI ARCHITECT Name of Firm: C.P Jones and Associates By: Brian L. King By: Title: Architect Title: Date: 30 August 2002 Date: UC Contracting Officer Figure 5: Amendment for Contract Closeout Page 24 February 2003 Project Turnover and Closeout Approving the Associate’s Final Pay Application The Project Administrator must check and approve the Associate’s final pay request as soon as possible and forward it to the Project Accountant for payment and release. Forwarding Project Records The Project Accountant needs the following information from the Project Administrator to complete the project’s financial closeout: Final, approved pay applications for all construction Contractors Final, approved pay application for the Associate, if applicable Notification to close out Purchase Orders from any term contractors or vendors (the Accountant will notify Purchasing). At closeout the Accountant also archives the project files. The Project Administrator provides all project records to the Accountant in either hardcopy or electronic (OnBase document imaging system) format. The University Architect Division’s goal is to have all projects archived in the OnBase system. The Project Administrator also provides the following documents to the Construction Management Document Control Center: O&M Manuals Project Record Drawings Specifications Shop drawings Project Turnover and Closeout February 2003 Page 25