AGREED SUM AND SPECIFIC PERFORMANCE

advertisement
CONTRACT LECTURE 14
REMEDIES PART 2
C STRICKLAND
Track/slide 1
In a previous lecture we considered the main remedy for breach of contract, that is, damages.
In this lecture, we consider other remedies for breach of contract, namely:
i.
ii.
iii.
iv.
an agreed sum
specific performance
injunctions, and,
quantum meruit.
We shall start then with an agreed sum.
Track/slide 2
The claim for an agreed sum is a common law remedy so is available as or right. It usually
means that the claimant is suing for the PRICE of the contract. It differs from a claim in
damages in that:
i.
ii.
iii.
there is no need to prove loss, and so
there is no need to worry about remoteness of damage nor to
mitigate loss
This is because when suing for the price the claimant is basically just enforcing a DEBT.
Although, should the claimant want to, they can ask for the agreed sum and also any loss over
and above the price.
We might ask, why would anyone sue for the price only?
Well, as we have mentioned, there is no need to prove loss or worry about mitigation and
remoteness. In addition, the amount being claimed is known – it is a ‘liquidated sum’ (whereas the amount of damages is for the court to decide) and the case can get through court
quite quickly.
Track/slide 3
These rules can however sometimes result in what appears to be an abuse of the innocent
party’s ‘rights’ following breach of contract. This can be seen in the case of White and
Carter (Councils) Ltd v McGregor 1962, a House of Lords case.
In this case the appellants who were advertising contractors had made a contract with the
respondent, who owned a garage, to display adverts for the garage on council litter-bins for a
period of 3 years. On the same day that the deal was made for renewal for a further 3 years of
the advertising contract, the defendant said he had changed his mind and didn’t want to go
ahead. This amounted to an anticipatory breach of contract. Despite this, the advertisers
decided to go ahead with the contract and displayed the adverts for the 3 years and then
brought an action for the ‘agreed sum’ for breach of contract.
In the House of Lords it was held that the advertisers had been entitled to carry out the
contract and could recover the full contract price.
Lord Reid stated that in the case of an anticipatory breach the innocent party may
either accept the repudiation and sue for damages
or
he may affirm the contract and then sue for an agreed sum, as the plaintiffs did here.
Lord Reid stated that:
i.
since this was an action for an agreed sum, the contract price, the
advertisers had no duty to try to mitigate their loss, by for example
accepting the end of the contract and then trying to get another one.
He also said that,
ii.
continued performance of the contract despite the anticipatory
attempt at breach was permitted so long as the plaintiffs had a
‘legitimate’ interest in continuing with the contract, be this
a financial interest or other interest. If there is no legitimate
interest in continuing with the contract the plaintiff should accept
the breach and sue for damages. His Lordship stated:
‘Here the respondent did not set out to prove that the appellants had no
legitimate interest in completing the contract and claiming the contract
price rather than claiming damages; there is nothing in the findings of fact
to support such a case, and it seems improbable that any such case could have
been proved. It is, in my judgment, impossible to say that the appellants should
be deprived of their right to claim the contract price merely because the benefit
to them, as against claiming damages and re-letting their advertising space, might
be small in comparison with the loss to the respondent: that is the most that could
be said in favour of the respondent. Parliament has on many occasions relieved
parties from certain kinds of improvident or oppressive contracts, but the
common law can only do that in very limited circumstances.’
His Lordship further said that
iii.
continued performance is only possible if this can be achieved
without the co-operation of the other side – and clearly in this
case this was possible.
The actions of the advertisers do seem a little bizarre in this case and the case has been
criticised – for instance, it has been said that even in an action for an agreed sum the plaintiffs
should be required to mitigate.
Track/slide 4
We can now consider the question of whether interest can be charged for late payment of the
agreed sum.
At common law the position would appear to be that the debtor only has to pay the actual
price of the contract without interest. However, this common law position is usually avoided
by either:
i.
an express term in the contract stating that interest will be charged
for late payment or
ii.
application of the Late Payment of Commercial Debts
(Interests) Act 1998 though this only applies to sale and supply
contracts where both sides are acting ‘in the course of a business’.
Track/slide 5
We can now move on to consider specific performance.
First, we should remember that ‘damages’ for breach of contract are the main remedy for
breach of contract. Specific performance is rare, other than in contracts for the sale of land.
An order of specific performance is an equitable, and therefore discretionary remedy, that
compels the actual performance of the contract. If the performance does not take place this
amounts to contempt of court for which the person may be sent to prison or fined. The court
may also sequester property.
That the order of specific performance is only available as a ‘secondary’ remedy to damages
is seen by Anson as a good thing because:
i.
when specific performance is ordered it relieves
the claimant of any duty to try to mitigate loss, and,
ii.
it is less necessary these days since the courts are now better
at assessing the amount of damages that can be awarded to
compensate the innocent party
Track/slide 6
Generally then, specific performance is only available where:
i.
ii.
iii.
iv.
v.
damages are not an adequate remedy,
he who comes to equity comes with clean hands,
the contract is not one for personal services,
the contract would not take a lot of supervision to enforce, and
where the performance to be enforced is clearly ascertainable.
Track/slide 7
First then we shall consider the point that specific performance is only available where
damages are not an adequate remedy. However, these days the
scope of when it may be ordered is wider in that it may be
ordered where it will ‘do more perfect and complete justice than
an award of damages’. The key case here is Beswick v Beswick 1968.
It was Lord Reid in the House of Lords that awarded specific performance
to achieve a ‘just result’ in the circumstances of the case. Lord Pearce
granted specific performance because he said it was a more ‘appropriate’
remedy. The extent to which this case means that specific performance
is ‘generally available’ in unclear. Professor Treitel has suggested that
whether or not it is granted depends on the ‘appropriateness’ of it in the
circumstances of the case in hand.
Let us consider what happened in this case.
Peter Beswick operated a coal round and made a contract with his nephew that
he would transfer the business to the nephew. One of the stipulations in the
contract was that when Peter died, the nephew would pay Peter’s widow
£5 a week for the rest of her life. When Peter died, the nephew only made one
payment of £5 and then stopped.
The widow sought to enforce the payments of the weekly £5 in her capacity
as administratix of Peter’s estate and in her personal capacity. She was successful
in gaining an order of specific performance from the House of Lords rather than
damages. We can see why below.
Track/slide 8
Lord Reid stated:
‘Applying what I have said to the circumstances of the present case, the respondent in her
personal capacity has not right to sue, but she has a right as administratix of her late
husband’s estate to require the appellant to perform his obligation under the agreement. He
has refused to do so and he maintains that the respondent’s only right is to sue him for
damages for breach of his contract.
If that were so, I shall assume that he is right in maintaining that the administratix could then
only recover nominal damages because his breach of contract has caused no loss to the estate
of her deceased husband.
If that were the only remedy available the result would be grossly unjust. It would mean that
the appellant keeps the business which he bought and for which he has only paid a small part
of the price which he agreed to pay. He would avoid paying the rest of the price, the annuity
to the respondent, by paying a mere 40 shillings damages...
The respondent ‘s second argument is that she is entitled in her capacity of administratix of
her deceased husband’s estate to enforce the provision of the agreement for the benefit of
herself in her personal capacity, and that a proper way of enforcing that provision is to order
specific performance. That would produce a just result, and, unless there is some technical
objection, I am of opinion that specific performance ought to be ordered. For the reasons
given by your Lordships, I would reject the arguments submitted for the appellant that
specific performance is not a possible remedy in this case.’
Track/slide 9
Lord Pearce disagreed with Lord Reid on the amount of damages that would be available for
breach of contract but agreed on the availability of specific performance when he stated:
‘In the present case I think that the damages, if assessed, must be substantial. It is not
necessary, however, to consider the amount of damages more closely since this is a case in
which, as the Court of Appeal rightly decided, the more appropriate remedy is that of specific
performance.
the adminstratix is entitled, if she so preferes, to enforce the agreement rather than accept its
repudiation, and specific performance is more convenient than an action for arrears of
payment followed by separate actions as each sum falls due. Moreover, damages for breach
would be a less appropriate remedy since the parties to the agreement were intending an
annuity for a widow; and a lump sum of damages does not accord with this. And if (contrary
to my view) the argument that a derisory sum of damages is all that can be obtained be right,
the remedy of damages in this case is manifestly useless.
The present case presents all the features which led the equity courts to apply their remedy of
specific performance. The contract was for the sale of a business. The defendant could on his
part clearly have obtained specific performance of it if Beswick senior or his adminstratix had
defaulted. Mutuality is a ground in favour of specific performance.’
However, the court will refuse the order is they consider that the award of damages
will put the plaintiff in as beneficial a position as if the contract had been specifically
performed.
Track/slide 10
Specific performance is also only available on the basis that
‘he who comes to equity comes with clean hands’ – one has to
remember that specific performance is an equitable remedy and so equitable maxims apply.
So, the court may refuse specific performance if it thinks the claimant’s behaviour has been
‘tricky’ or ‘unfair’.
This equitable point was explored in Quadrant Visual Communications Ltd v Hutchinson
Telephone (UK) Ltd 1993. The plaintiff’s appeal was against an order refusing specific
performance of a contract and payment of £1.2263 million with interest. In the contract it
specified that the sum was to be payable ‘free from any equity, cross claim, set off or other
deduction whatsoever’. It was held that the words ‘any equity’ covered the concept of
coming to equity with clean hands. However, it was also held that whilst this part of the
contract might bind the parties to the contract, once the issue was before the court, then when
specific performance has been requested, the court’s discretion to award it or not could not be
fettered by reference to the contents of the contract. Otherwise, the court would simply be
rubber stamping the contract. The appeal was dismissed.
Track/slide 11
Specific performance is also only available if the contract is not one for personal services – if
it is a contract for personal services then the courts are reluctant to order specific
performance as it would be an infringement of personal liberty.
The case of Page One Records Ltd v Britton 1968 shows the relationship between specific
performance and injunctions [that usually order someone not to do something]. In this case
the plaintiffs, Page one records, were the managers of the pop group ‘the Troggs’. In the
contract between them and the Troggs it stated that the pop group would not employ anyone
else as their manager for the 5 years of the life of the contract. When things turned sour
between the two, the group sought to employ a new manager, Harvey Block Associates Ltd.
Page one records therefore sought an injunction preventing them from doing this. The
injunction was not granted because if it had it would have forced the group to keep page one
as their manager and they had lost faith in them. Thus, the granting of the injunction would
have had the same effect as if the court had ordered specific performance of the 5 year
contract and it would not do so for such a personal service.
Track/slide 12
Specific performance will also only be awarded when the performance of the contract does
not require a lot of supervision – here we can look at 3 cases:
Ryan v Mutual Tontine Westminster Chambers Assoc 1893
Posner v Scott-Lewis 1986
Co-operative Insurance Society Ltd v Argyll Stores (Holdings)
Ltd 1997
In the Ryan case an order of specific performance was not granted
- it would require too much supervision to ensure that a resident
porter would be in attendance at all times at a block of flats as
stated in the leases.
In the Posner case however with similar facts an order of
specific performance was granted.
However, the Argyll case puts the Posner case in doubt and
seems to support the approach in the Ryan case. In the Argyll
case the defendant was a supermarket chain with a lease for a
unit in the plaintiff’s shopping centre. The lease was for 35
years and they were to be open during the usual hours of
business. The presence of this supermarket was very important to
the success of the shopping centre as it would attract customers and
help to support the smaller units. However, after less than 6 years,
due to poor profits, the defendants closed the shop and moved out
of the unit. The plaintiff sought specific performance of the
contract requiring the shop to come back and keep trading. The
House of Lords realised that damages were not an adequate remedy
as it would be difficult to quantify the expectation losses over the
remaining 19 years left to run on the lease. Despite this they refused the order of
specific performance because:
-
it would be difficult to draft the order
it would be difficult to supervise it
it would in effect compel the defendants to carry on an
uneconomic business.
Track/slide 13
Finally, specific performance is only available where the performance expected is clearly
ascertainable.
If the contents of the contract are not clearly specified then it may be impossible for the court
to order specific performance as they would not know exactly what to order. Thus in Wilson
v Northampton and Banbury Railway Company 1874 the court did not order specific
performance where the contract was to ‘construct a railway station’ with no reference to the
nature, materials, style, dimensions or anything else.
Track/slide 14
We can now move on to consider Injunctions.
Injunctions are either PROHIBITORY or MANDATORY. Prohibitory ones are used to stop
one side acting positively when the contract is designed to prevent positive action.
Mandatory ones are used to compel some action. Both are equitable and discretionary.
First then, we shall consider Prohibitory injunctions
A prohibitory injunction may be granted when there is the breach of a negative contract or
contract term. For example if the contract is NOT to carry on a certain trade or not to drive
vehicles after a certain time at night, then if the person who promised not to do these things in
the contract does in fact do them (acts positively) then a prohibitory injunction will normally
be granted to prevent them from doing these things.
In a contract for personal services, a prohibitory injunction may serve the purpose of
encouraging the party in breach to actually perform the contract, though remember that it is
rare for an order of specific performance for a personal contract.
Track/slide 15
An interesting case is:
Lumley v Wagner 1852
In this case the defendant agreed to sing at the plaintiff’s theatre and during a certain time
frame she agreed not to sing anywhere else. Despite this, she then made a contract with
someone else to sing at another theatre and refused to fulfil her original contract. The court
refused to order specific performance of her positive contractual duty to sing at the plaintiff’s
theatre, BUT, the court granted a prohibitory injunction to prevent her from breaching her
promise not to sing anywhere else. Thus, in a subtle way, she was being encouraged to sing
at the plaintiff’s theatre.
Track/slide 16
The courts only apply the Lumley and Wagner use of injunctions where:
i.
the contract had the negative provision included as an express term, and,
ii.
the defendant is able to get some work to live off. If the effect
of the injunction would be to give the defendant the choice of
working for the plaintiff or not being able to work at all – then
the courts won’t grant the injunction as it would in effect be
achieving the same result as an order of specific performance.
An interesting case is Warner Bros Pictures Inc v Nelson 1937. In this case the actress
Bette Davis (Mrs Nelson) had a contract with Warner Bros to the effect that for a certain
period she would ‘not render any similar services to any other person or engage in any other
occupation’.
Despite this she made a contract with another film company and Warner Bros sought an
injunction to stop her working for them. At first instance it was held that although it would
not be possible to grant an injunction to stop her from working for someone else in ‘any’
occupation [otherwise she could starve to death] it was possible to grant an injunction to stop
her working ‘as an actress’ for someone else for the specified time.
Track/slide 17
We can now make a few comments on Mandatory injunctions
An example of when a mandatory injunction might be used is to make a landlord let tenants
back if he evicted them in breach of their contract. They are thus used to restore the status
quo that existed before the defendant’s breach of contract.
Note, that under the Supreme Court Act 1981, ss 49and 50, the court has the power to award
damages in addition to or in place of specific performance or an injunction. Such damages
are assessed just like the common law damages are assessed.
Track/slide 18
We can now make a few comments on Quantum meruit
This is the principle dating from Planche v Colburn 1831 that where one party confers a
benefit on another with the intention on both sides that the benefit will be paid for, then, in the
absence of a contract, the party conferring the benefit on the other will be able to recover
reasonable remuneration for what they have done. Thus, in British Steel Corporation v
Cleveland Bridge and Engineering Co ltd 1984 the plaintiffs started work on a major
construction project before the final contract was drawn up. Both sides had expected the
contract to go ahead without any problems. However, the contract never materialised. The
plaintiffs were allowed to succeed on a claim in quantum meruit for the work they had done.
Quantum meruit does not normally operate where there is a contract because the parties will
be bound by the actual terms of the contract. However, we have already noted that for an
‘entire’ contract, where the consumer pays for a job done, such as home improvements, once
the work is complete, quantum meruit may apply. We looked first at Cutter v Powell when
the widow could not get the wages of her deceased sailor husband for his work at sea before
he died because the contract was an entire one and he did not complete the contract.
We then noted how this harsh rule could be avoided when the claiminat had conferred a
benefit on the defendant and the defendant had a real choice as to whether to accept the
benefit or not. Thus, if a builder half completed a house and then abandoned the project in
breach of contract, this would be the breach of an entire obligation and so no money would be
due – in this case nothing would be due on a quantum meruit basis either because the
defendant has no choice but to accept the work done. But, in the Sumpter v Hedges case we
noted that the builder could recover in quantum meruit for the value of building materials he
left when he abandoned his building project because the owner had had a choice of using the
materials or returning them to the builder.
Download