INFRASTRUCTURE DIVISION SUITE OF CONTRACTS AN INTRODUCTION [LAST AMENDED: 9 MARCH 2007] Legal\101242374.12 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Table of contents 1. GENERAL .................................................................................................................................... 1 1.1 1.2 1.3 1.4 1.5 Purpose ...................................................................................................................................................... 1 Types of contract ....................................................................................................................................... 1 Why have a Suite of contracts? .................................................................................................................. 1 History ....................................................................................................................................................... 2 Generally the Suite is "non-negotiable" ..................................................................................................... 3 2. PRINCIPLES OF CONTRACT LAW ........................................................................................... 3 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 Introduction ................................................................................................................................................ 3 What is a contract? ..................................................................................................................................... 3 Offer ........................................................................................................................................................... 3 Acceptance ................................................................................................................................................. 4 Consideration ............................................................................................................................................. 4 Intention to create legal relations ............................................................................................................... 4 Certainty .................................................................................................................................................... 5 Capacity to contract ................................................................................................................................... 5 Statutory Requirements .............................................................................................................................. 5 3. TENDER DOCUMENTS .............................................................................................................. 5 3.1 3.2 3.3 3.4 3.5 3.6 General ....................................................................................................................................................... 5 Invitation to Register Interest ("ITR") ....................................................................................................... 6 Tender Documents - Request for Tender ("RFT") ..................................................................................... 6 Tender Documents ..................................................................................................................................... 6 What should be obtained from Tenderers at time of tender? ..................................................................... 6 Tender acceptance .................................................................................................................................... 12 4. COMMONWEALTH PROCUREMENT GUIDELINES ("CPGS") ............................................. 12 4.1 4.2 4.3 4.4 4.5 4.6 General ..................................................................................................................................................... 12 Minimum time limits ............................................................................................................................... 12 Conforming tender submissions............................................................................................................... 12 Restrictions on terminating a tender process ........................................................................................... 12 Advising outcomes .................................................................................................................................. 12 Managing contractors............................................................................................................................... 12 5. PROJECT DELIVERY METHODS - WHICH DELIVERY METHOD DO I USE?...................... 13 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 5.10 5.11 5.12 5.13 5.14 5.15 General ..................................................................................................................................................... 13 HC-1 2003 ............................................................................................................................................... 13 When to use the construct only delivery method (HC-1 2003) ................................................................ 13 Risk allocation under the construct only delivery method ....................................................................... 14 Disadvantages of the construct only delivery method ............................................................................. 14 When to use the design and construct delivery method (HC-1 2003) ...................................................... 15 Advantages of the design and construct delivery method ........................................................................ 15 Disadvantages of the design and construct delivery method ................................................................... 16 When to use the document and construct deliver method (HC-1 2003) .................................................. 16 Advantages of the document and construct delivery method ................................................................... 16 Disadvantages of the document and construct delivery method .............................................................. 16 Managing Contractor - MCC-1 2003 ....................................................................................................... 17 Advantages of the Managing Contractor delivery method ...................................................................... 19 Disadvantages of the Managing Contractor delivery method .................................................................. 19 What is the difference between the Managing Contractor and Construction/Project Management? ....... 20 6. HEAD CONTRACT ("HC-1 2003") ........................................................................................... 20 6.1 6.2 General ..................................................................................................................................................... 20 Specific features of HC-1 2003 ................................................................................................................ 21 7. MANAGING CONTRACTOR CONTRACT ("MCC-1 2003") .................................................... 27 7.1 7.2 General ..................................................................................................................................................... 27 Planning Phase ......................................................................................................................................... 28 Legal\101242374.12 i Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction 7.3 7.4 7.5 7.6 7.7 7.8 7.9 Planning Phase Agreement and Planning Phase Approval ...................................................................... 28 Flexibility of MCC-1 2003 ...................................................................................................................... 28 Delivery Phase ......................................................................................................................................... 29 Contractor's Remuneration....................................................................................................................... 29 Incentive .................................................................................................................................................. 29 Whole of Life/Ecologically Sustainable Development ............................................................................ 30 Subcontractors (including consultants and subcontractors) ..................................................................... 30 8. DESIGN SERVICES CONTRACT ("DSC-1 2003") .................................................................. 31 8.1 8.2 General ..................................................................................................................................................... 31 Key features of DSC-1 2003 .................................................................................................................... 31 9. NATIONAL CODE ..................................................................................................................... 32 10. PANEL CONTRACTS ............................................................................................................... 33 10.1 10.2 Defence Infrastructure Panel ("DIP") Subpanel for Contract Administrators.......................................... 33 Other Panels ............................................................................................................................................. 33 11. DETAILED CONTRACTOR'S OR CONSULTANT'S ACTIVITIES PROPOSAL ("DCAP") ................................................................................................................................... 34 12. OTHER FORMS OF CONTRACT ............................................................................................. 34 12.1 12.2 MW-2 2004 .............................................................................................................................................. 34 Minor Works Contract ............................................................................................................................. 34 13. COLLATERAL DOCUMENTS .................................................................................................. 35 13.1 13.2 13.3 13.4 13.5 13.6 13.7 13.8 General ..................................................................................................................................................... 35 Unconditional Undertaking ...................................................................................................................... 35 Collateral Warranty.................................................................................................................................. 35 Moral Rights Consent .............................................................................................................................. 35 Payment Claim ......................................................................................................................................... 36 Payment Statement .................................................................................................................................. 36 Expert Determination Agreement ............................................................................................................ 36 Subcontractor and Consultant Deeds of Covenant ................................................................................... 36 14. CONTRACT MANUALS ............................................................................................................ 37 14.1 14.2 14.3 14.4 14.5 14.6 14.7 General ..................................................................................................................................................... 37 Volume 1 - Introduction........................................................................................................................... 37 Volume 2 - Completing the Tender and Contract Documents ................................................................. 37 Volume 3 - Clause-by-clause Guidance ................................................................................................... 38 Volume 4 - Flowcharts............................................................................................................................. 39 Volume 5 - Proforma Notices .................................................................................................................. 39 Volume 6 - Clause-by-Clause Commentary on Special Conditions ........................................................ 39 15. RISK ALLOCATION .................................................................................................................. 39 ANNEXURE A - RISK MATRIX .................................................................................................................. 40 Legal\101242374.12 ii Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction 1. GENERAL 1.1 Purpose The purpose of this document is to provide a brief introduction to the Department of Defence's Infrastructure Division ("ID") suite of contracts ("Suite"). It should be read in conjunction with the contracts themselves and the accompanying manuals. The following should always be kept in mind in using the Suite: (a) personnel should always obtain the most recent version of a contract and manual from the Infrastructure Management website which can be found at www.defence.gov.au/im/; (b) the Director Construction Contracts ("DCC") should always be consulted on any proposed changes to the Suite or any other contentious issues regarding any of the contracts and manuals within the Suite. This is critical to ensure the integrity of the Suite and that Defence's required risk allocation is not gradually eroded over time by project-specific changes; (c) the Defence Legal Services Panel ("LSP") (through DCC) should always be used for finalising tender and contract documents and the drafting of any amendments to these documents; and (d) the Department of Employment and Workplace Relations ("DEWR") (through DCC) should be consulted on any issues concerning compliance with the National Code of Practice for the Construction Industry ("National Code") and the Office of the Federal Safety Commissioner ("FSC") in respect of the OHS Accreditation Scheme ("OHS Accreditation Scheme") established under the Building and Construction Industry Improvement Act 2005 (Cth). These are particularly sensitive policy and legislative areas and, therefore, personnel must ensure that they raise all compliance issues immediately with DCC. 1.2 Types of contract DSG-ID personnel need to be familiar with the types of contracts commonly used by Defence for the construction and maintenance of Defence facilities. As there is no one contract which suits all projects, Defence has developed the Suite to give it the flexibility to select the most appropriate contract for a specific project. The Suite comprises the following contracts: (a) Head Contract ("HC-1 2003"); (b) Managing Contractor Contract ("MCC-1 2003"); (c) Design Services Contract ("DSC-1 2003"); (d) Medium Works Contract ("MW-2 2004"); (e) Short form minor works contract; (f) companion documents including subcontracts, collateral documents (eg approved forms of security, novation deeds, warranties) and consolidated lists of special conditions; and (g) a series of panel arrangements under which panels of specialist consultants (including project management, environment, UXO and various other disciplines) are created on terms of standing offers (providing the general terms upon which consultants are engaged by Defence), under which they are then engaged from time to time on specific projects (by means of a project-specific contract). The Suite also includes a number of maintenance contracts, for both building and fixed plant and equipment maintenance. Most recently, this includes the Garrison Support Services and Comprehensive Maintenance Services Contracts ("GSS/CMS"). 1.3 Why have a Suite of contracts? There are several benefits in having a "suite" of contracts. Legal\101242374.12 1 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (a) Time and cost efficiencies Firstly, as opposed to drafting "fresh" contracts for each and every project, the standard form contracts reflect Defence's agreed contracting position. For example, they set out the risk allocation Defence is prepared to accept for each contract delivery method. This has at least two implications: (b) (i) tender evaluation is easier, as all tenders are evaluated on the same terms with no departures; and (ii) rather than two parties negotiating the terms of a contract from start to finish, the terms are known from the outset as Defence selects the most suitable contract for a project and goes to tender with these terms. The less time spent in negotiating the terms of a contract, the more cost effective it is for Defence, especially given the size of its annual spend on construction and related services. Range of contracting options Secondly, the "suite" approach means that there is a range of contracts available to Defence, depending on the size, nature and complexity of the project and the risk allocation required. (c) Ease of use A third benefit in having a suite is ease of use. The Suite comprises a set of standard documents, so that users (both within ID and industry) eventually develop a certain level of familiarity with the documents. This makes preparation of tender and contract documents more efficient and facilitates greater consistency in contract administration. (d) Compliance with legislation and policy The Suite has been drafted (and is continuously updated) to ensure compliance with all legal and policy requirements for Commonwealth contracting. Other standard form contracts, such as the Standards Australia contracts, do not address Commonwealth-specific contracting requirements. They are also updated and amended on a less frequent basis. 1.4 History The Suite was first introduced in 1992 and represented a significant departure from the widely-accepted practice amongst public sector agencies of using the National Public Works Council Edition 3 standard form contract ("NPWC3"). Rather than developing a set of modifications to an existing standard form, Defence took the significant step of creating its own suite of owner-focused standard forms (albeit broadly based on NPWC3). Given its substantial annual expenditure on construction, Defence wanted to ensure that construction services were managed by it on the basis of a suite of contracts which provided the appropriate project delivery method and risk allocation. In 2002, the Suite underwent a comprehensive review. This resulted in the consolidation of the Suite into primarily four new forms of contract, namely HC-1 2003, MCC-1 2003, DSC-1 2003 and MW-2 2004. The contracts are unique to Defence and differ from most other common standard form contracts, such as contracts published by Standards Australia. The aim of developing standard form contracts is to maximise, to the extent practicable, the structure and terms used by Defence when contracting for construction and related services. This has the benefit of reducing administrative costs for both Defence and contractors or consultants. The contracts have also been developed to comply with Commonwealth policy and legal requirements. Although the contracts are unique to Defence, HC-1 2003 is derived from PC-1 (the standard form project contract promulgated by the Property Council of Australia), but has been significantly adapted by Defence to address specific Defence concerns. In particular, it contains specific provisions dealing with compliance with Commonwealth policy and legislative requirements relating to the National Code, the OHS Accreditation Scheme, the Commonwealth Procurement Guidelines ("CPGs"), Equal Opportunity for Women in the Workplace, indigenous employment opportunities, privacy legislation, security of payment legislation, SAFEBASE, classified information and long service leave obligations. Legal\101242374.12 2 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction As the Defence contracts have been developed for different types of project delivery methods, ID personnel should not assume that the risk allocations under each contract within the Suite are identical. ID personnel must familiarise themselves with the relevant contract and corresponding manuals before using any of the contracts. 1.5 Generally the Suite is "non-negotiable" The contracts within the Suite represent Defence's way of doing business within the construction industry. Those terms have been developed over a significant period of time and have been carefully tailored to Defence's procurement processes and objectives. They are not generally subject to amendment by project teams (except as approved by the DCC) or negotiation with tenderers and tenders should be submitted on the basis that the terms are accepted without contractual qualification or departure. An alternative tender should be submitted if departures or qualifications are proposed (see 3.5(j) below). On some projects, Defence may hold a tender briefing to better inform tenderers about the requirements of a tender process. Tender briefings are not a platform to provide potential tenderers with information additional to that contained in the tender documentation. Therefore, it should be made clear to potential tenderers that they cannot rely on a statement made at a tender briefing as amending or adding to the tender documentation unless the amendment or addition is confirmed in writing. The Suite's Tender Documents for MCC-1, HC-1, MW-2 and DSC1 contain a clause to this effect. 2. PRINCIPLES OF CONTRACT LAW 2.1 Introduction The construction and maintenance of Defence facilities is achieved through the formation of contracts. Defence ID personnel should therefore have a basic understanding of the principles of contract law and the necessary procurement competencies. In this regard, please refer to Section 2, Chapter 2.1 and Section 1, Chapter 1.5 of the Defence Procurement Policy Manual which is available at http://www.defence.gov.au/dmo. 2.2 What is a contract? A contract is a legally binding or agreement made between two or more parties. The essential requirements for contract formation are: (a) an agreement consisting of: (i) an offer by one party to the other; and (ii) an acceptance of the offer by that other party; (b) an intention to create legal relations; (c) certainty as to the obligations contained in the agreement; and (d) "consideration" for the offer (i.e. the offeree must provide something of value in exchange for the offer received from the offeror; this could be something tangible, like the payment of money, or something intangible, like a promise). 2.3 Offer An offer is an expression of willingness to contract on certain terms by a person with the intention that it becomes binding when accepted by the person to whom the offer is addressed. An offer is often confused with an invitation to treat. An invitation to treat is merely an invitation to make an offer that is, the preliminary step before an offer is made. Traditionally, a request for tender was regarded as an "invitation to treat" and a response from a tenderer in the form of a tender was an offer. However, recent cases suggest the possibility of "process contracts" in government tender processes. That is, the issue of a request for tender and a response from a tenderer may give rise to legal obligations, which bind the relevant government agency to conduct its tender process in a particular way. Defence's Tender Documents have been drafted to minimise the possibility that the request for tender by Defence gives rise to such a "process contract". Legal\101242374.12 3 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Handy Hint Ensure that any request for tender avoids a "process contract", by adopting the standard form documentation. This increases Defence's flexibility during the tender process and reduces the risk of legal exposure to tenderers. 2.4 Acceptance A final, clear and unequivocal acceptance of an offer terminates the negotiations. After acceptance, the offer cannot be revoked and, provided all other pre-conditions are met, the contract will have come into existence. It is possible to prescribe the method of acceptance in an offer or an invitation to make offers. Indeed, this is precisely the way in which the Tender Documents (see 3.3 below) are drafted. They state that Defence has not accepted a tender unless it either signs a contract or issues a "letter of acceptance" in a particular form. The intention of this is to avoid a contract being created unintentionally, by the exchange of correspondence or a course of dealings during contract negotiations. "Letters of acceptance" must be distinguished from "letters of intent". Please refer to item 3.6 for commentary on the distinction between the two types of letters. Handy Hint Only issue a letter of acceptance at the conclusion of negotiations, when every negotiation point has been agreed with certainty. Before this, ensure all correspondence makes it clear that there is no intention to accept an offer and thereby create a contract at that point in time. In particular, ensure that no oral or other informal contract is created by discussions or correspondence which were intended to be no more than a request for information or negotiation. All letters of acceptance and letters of interest should be the subject of review by DCC or a member of the LSP to ensure that Defence's legal position is clearly stated. 2.5 Consideration Each party to the contract must provide "consideration". Consideration is the "value" given by the promisee in exchange for the promise given by the promisor. "Value" does not necessarily have to be financial value - it can be anything (tangible or intangible), provided it has some value. For example, mutual promises can (and usually do) provide the basis of consideration in commercial contracts. Example A promises to B to carry out works for $100,000 A's consideration is the promise to carry out the works for B B's consideration is the promise to pay the amount of $100,000 2.6 Intention to create legal relations There must be an intention by both parties that their agreement give rise to legal rights and obligations. This intention may be express (explicitly written or said) or implied (derived from the conduct of the parties or the terms of the written agreement). In commercial (as opposed to social) dealings, there is a strong presumption that there is an intention between the parties to create legal relations, unless the situation or the circumstances can show otherwise. Thus, in a commercial arrangement, there is a heavy onus of proof on the party alleging a contract does not exist on the grounds that the parties did not intend to be bound. Handy hint If parties have acted in a way which is ambiguous, then there may be a question as to whether the parties intended to create a contract. To avoid ambiguity, Defence personnel should be clear in all correspondence between Defence and the Contractor, as to whether or not there is an intention to be legally bound. Legal\101242374.12 4 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction 2.7 Certainty The essential terms of an agreement should be expressed with certainty or be capable of being calculated on objective criteria without requiring further agreement between the parties. The courts will not make a contract for the parties. If the agreement on its face is ambiguous the court may rule that the agreement, or part of the agreement if it can be severed, is void. In determining whether an uncertain clause can be severed, or whether the whole agreement is void, the court will consider the importance of the term in question: (a) if the clause considered void for uncertainty was so central that the parties would not have entered into the contract without it, then the entire contract is void; (b) if, however, the clause is only of minimal importance, the court may simply strike out the offending clause leaving the rest of the contract intact. Handy hint The failure to fill in, or incorrect filling in of, one of the Contract Particulars in a standard Defence contract may cause uncertainty and could cause the contract to ultimately fail. Therefore, when dealing with Defence contracts, it is essential that all of the Contract Particulars are filled out properly. Avoid inserting "TBA", "to be agreed" or similar expressions. 2.8 Capacity to contract The parties to a contract must have capacity to contract. "Capacity" can be described as the legal ability or competence of a person or body to enter into a contract. Lack of capacity may affect the enforceability of a contract. To avoid any issue of capacity, Defence should not enter into contracts with: (a) persons under 18 years of age; (b) persons suffering a mental disability (eg brain damage, mental disorder or senility); (c) persons under the influence of drugs or alcohol; or (d) unincorporated associations or bodies, unless incorporated under State/Territory legislation. Although undischarged bankrupts do have legal capacity to enter into contracts, Defence should also avoid entering into contracts with undischarged bankrupts. This is largely due to the fact that there may be limited resources available to satisfy a judgment obtained against a bankrupt for breach of contract. The common law presumption is that a party who enters into a contract has capacity and it is up to the person alleging lack of contractual capacity to prove their incapacity. 2.9 Statutory Requirements The parties to a contract must also generally (subject to certain constitutional exceptions in favour of Defence) comply with all statutes applicable in the jurisdiction governing the contract or in which the works or services are being carried out. It is therefore important to understand the statutory context in which a contract is being performed. Different terms may be required, depending on the jurisdiction. To some extent, this has already been addressed in the contracts and the special conditions prepared as part of the Suite. However, as legislation is subject to change, legal advice should be considered where there is any concern that there could be statutory provisions which have not been addressed. 3. TENDER DOCUMENTS 3.1 General HC-1 2003, MCC-1 2003, DSC-1 2003 and MW-2 2004 have each been structured so that they can be used for a one or two stage tender process. The one stage tender process involves the issuing of "Tender Documents" to a Legal\101242374.12 5 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction select group of tenderers, whereas, the two stage tender process involves the issuing of an "Invitation to Register Interest" followed by "Tender Documents". Two proforma documents are available for use with each contract to deal with a one or two stage tender process, namely: (a) Invitation to Register Interest; and (b) Tender Documents. The one-stage tender process is used when Defence has a preselected group of tenderers and, therefore, does not need to seek registrations of interest from the market place. This should only be done in the limited circumstances permitted under the CPGs, (see Division 2 of the CPGs for further information). 3.2 Invitation to Register Interest ("ITR") The purpose of the ITR stage is to seek an indication from industry for the purposes of: (a) identifying potential contractors or consultants who are interested in bidding; (b) enabling applicants to pre-qualify for the tender process; (c) determining which applicants are not going to be able to provide a conforming and/or a compliant tender; and (d) enabling Defence to compile a shortlist of applicants from whom it wishes to request a tender. 3.3 Tender Documents - Request for Tender ("RFT") Once Defence has received ITR responses, it evaluates them and then compiles a shortlist of applicants from whom it will request a tender. Defence will then seek tenders from the shortlisted applicants by issuing an RFT (including the Tender Documents). The Tender Documents provide details of the contract in Part 5. Traditionally, a request for tender is not an offer. Rather, it is an "invitation to treat". A response from a tenderer in the form of a tender is an offer (for example, to provide services for a price) and a contract is not completed until Defence unequivocally accepts a tender (by issuing a letter of acceptance or entering into a formal contract). The traditional model has been modified by recent case law which suggests that an RFT can create a binding collateral contract at the time a tender is submitted (a "process contract"). The terms of the contract are those provided in the RFT. This has significant implications for Defence procurement practices and ID personnel are referred to paragraphs 122-132, Section 2, Chapter 2.1 of the Department Procurement Policy Manual for more detailed information. Defence's standard form Tender Documents contain a provision which attempts to minimise the possibility that a "process contract" will arise during the tender process. 3.4 Tender Documents The Tender Documents are in five parts, comprising: (a) Part 1 - Tender Conditions; (b) Part 2 - Tender Particulars; (c) Part 3 - Tender Form; (d) Part 4 - Tender Schedules; and (e) Part 5 - Conditions of Contract. 3.5 What should be obtained from Tenderers at time of tender? A tenderer is responsible for completing the Tender Schedules and returning them as part of its tender submission. There are a number of Tender Schedules under HC-1 2003, MCC-1 2003 and DSC-1 2003 which are discussed Legal\101242374.12 6 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction below. Some of the Tender Schedules are common to each of the contracts while others are specific to a particular contract. (a) Detailed Contractor's Activity Proposal ("DCAP") (MCC-1 2003 and DSC-1 2003 only) The tenderer is requested to complete each item in the DCAP to demonstrate the tenderer's understanding of what the contract requires and all material aspects of the way in which the tenderer proposes to perform the Contractor's Activities or the Services which could distinguish its approach from other tenderers. Under MCC-1 2003, the tenderer is requested to (as a minimum): (i) include an outline approach on how it proposes to prepare Project Plans; (ii) demonstrate its compliance with any Commissioning and Handover Guidelines; (iii) include a plan that indicates how it proposes to take all steps necessary to ensure the timely, efficient and comprehensive commissioning of the Works, the smooth handover of the Works and that all required planned and unplanned maintenance is provided during the Defects Liability Period for the Works; (iv) demonstrate its compliance with the Ecologically Sustainable Development ("ESD") Principles; and (v) prepare a plan to indicate how it proposes to design and construct the Works to achieve the Whole of Life ("WOL") Objectives. Under DSC-1 2003, the tenderer is requested to identify its approach to: (vi) designing the works and preparation of the Design Documentation; (vii) preparing the Design Documentation and carrying out the Services in a manner which achieves the WOL Objectives and ESD Principles; (viii) ensuring the Design Documentation complies with the Commissioning and Handover Guidelines; (ix) programming; (x) quality assurance for the Services; and (xi) preliminary design solutions, to the level specified. Although a tenderer under HC-1 2003 is not requested to submit a DCAP, it is requested to prepare Project Plans (including the Site Management Plan and an Environmental Management Plan) and to submit an outline Commissioning and Handover Plan and WOL Plan. Under MW-2 2004, a tenderer is required to submit a Task Appreciation and Methodology. (b) Current capacity and capability The tenderer is requested to provide detailed information as to its current workload, resources (including subconsultants (DSC-1 2003 only) and a list of consultants from whom the tenderer recommends that tenders be obtained to form a design team (the tenderer should also provide reasons for its recommendation) (MCC-1 2003 only). (c) Previous performance The tenderer is requested to provide details of its past performance in respect of projects of different values and all projects completed in the last 12 months. The purpose of this tender schedule is to assess the credibility and capability of the tenderer by reference to its previous performance. In MCC-1 2003 only, the tenderer is also requested to provide details of any specific collaborative contracting experience, in response to a detailed questionnaire. Legal\101242374.12 7 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction If the tenderer submitted a Registration of Interest, it is only requested to identify in its tender any amendments to the matters submitted in the Registration of Interest. This is to minimise tendering costs. (d) Tenderer's financial details The tenderer is requested to provide details of its financial standing to enable Defence to assess the tenderer's financial viability and capability to undertake the project. Depending on the type and size of the company (or partnership or other legal entity), the tenderer is requested to provide copies of its financial reports and such other information as identified in the Tender Particulars. If the tenderer submitted a Registration of Interest, it is only required to identify any amendments to the matters submitted in the Registration of Interest. This is to minimise tendering costs. Defence may direct a tenderer to provide a solvency statement. If such a direction is made before the relevant tender closing date and time, submission of the solvency statement becomes one of the "conforming bid" requirements. If the tenderer does not submit the solvency statement as directed, the tender will be non-conforming and must not be admitted to evaluation. A solvency statement can also be requested after close of tenders. (e) Remuneration For HC-1 2003, the tender schedule needs to be tailored depending on whether tenders are sought on a lump sum basis, or on a schedule of rates basis, or a combination of the two. If a lump sum is sought, then a contract price breakdown will need to be included to enable Defence to assess the lump sum offered. If tenders are sought on a schedule of rates (or remeasurement) basis, then the outline schedule of rates needs to be included to allow the tenderer to identify the rates it needs to submit for the relevant components of the work. Defence may also request that the tenderer provide a cost schedule as part of its tender. Such a cost schedule would ultimately form part of the contract if the tenderer's tender is successful, and is to be used for the purposes of assisting the valuation of variations. Note that Defence contracts do not generally incorporate bills of quantities (either guaranteed or not guaranteed). If the project contains civil works or a bill of quantities is proposed, advice should be sought from DCC. Under MCC-1 2003, tenderers are requested to provide relevant details for the Planning Phase, Delivery Phase, Outline Cost Plan (if specified in the Contract Particulars) and Incentive. In the Planning Phase, the amounts include: (i) lump sum Contractor's Work Fee (Planning); (ii) the Milestone Fee Payment Schedule (should be significant milestones representing completion of discrete activity during the Planning Phase and should not be monthly instalments); and (iii) Schedule of Rates (the schedule set out or referred to in the Contract Particulars containing rates and prices to be used for the purpose of valuing adjustments to the lump sum Contractor's Work Fee (Planning)). In the Delivery Phase, the amounts include: (iv) lump sum Management Fee; (v) lump sum Contractor's Work Fee (Delivery); (vi) a detailed break-up of the calculation of the Management Fee and Contractor's Work Fee (Delivery); (vii) the Milestone Fee Payment Schedule; (viii) a detailed basis for any adjustment to the Management Fee or Contractor's Work Fee (Delivery); and Legal\101242374.12 8 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (ix) Schedule of Rates (the schedule to be set out or referred to in the Contract Particulars containing rates and prices to be used for the purpose of agreeing an adjustment to the Contractor's Work Fee (Delivery) and Management Fee prior to the Delivery Phase and valuing adjustments to the Contractor's Work Fee (Delivery)). The tenderer should include in its Outline Cost Plan for the Works an outline target cost for Reimbursable Costs (i.e. those payable to subconsultants and subcontractors) during the Planning Phase and Delivery Phase and the Contractor's Work Fee (Planning and Delivery) and Management Fee. The Outline Cost Plan must not exceed the Initial Target Cost (set by Defence). Tenderers are given the opportunity to nominate an incentive mechanism which is contingent upon exceptional performance (measured against agreed key performance indicators). The Incentive is usually paid after the expiration of the last Defects Liability Period. Under DSC-1 2003, tenderers are requested to provide details of amounts including a breakdown of the lump sum Fee, a schedule of rates and an outline of proposed progress payments for the Fee, including any Milestones. The proposed progress payments should be based on the milestones described on in IM website (www.defence.gov.au/im). (f) Programming Tenderers are requested to submit a program showing its order of work, periods for carrying out all design, documentation and construction activities, including off-site activities, key dates including milestones, and the percentage of time against activities each of the tenderer's proposed key people would be dedicated to the Contractor's Activities or the Services. Under MCC-1 2003, the tenderer is requested to submit programs for both the Planning Phase and Delivery Phase. The program for the Planning Phase must be based on a proposed date for Planning Phase Agreement to be tendered by the tenderer and is for carrying out design, cost planning, programming and negotiation. The proposed date for Planning Phase Agreement cannot be later than the date stated in the Tender Particulars. The proposed program for the Delivery Phase must be for the completion of design (to the extent not prepared during the Planning Phase), commencement, construction, completion, commissioning and handover of the Works. (g) Tenderer's insurance details Tenderers are requested to provide details of the insurances which they have or will put in place for the purposes of their insurance obligations under the contract. The types of insurances are: (i) workers' compensation insurance and employees liability insurance; (ii) construction risks insurance (not DSC 1-2003); (iii) public liability insurance; and (iv) professional indemnity or errors and omissions insurance (except if the HC-1 2003 or MW2 2004 is being used for contract only). tenderers should also provide details of any additional types of insurance that are required for a particular project or specified by Defence. Advice regarding appropriate levels should be sought from DCC. (h) Statutory declaration (HC-1 2003, MCC-1 2003 and MW-2 2004 only) Under HC-1 2003, MCC-1 2003 and MW-2 2004, tenderers are requested to submit a statutory declaration. The purpose of this statutory declaration is to obtain an acknowledgement by the tenderer that it: (i) Legal\101242374.12 has carried out the tender process in a proper and fair manner, including by acknowledging that it has not engaged in any collusive tendering or cover bidding; 9 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (i) (ii) will not provide any benefit or financial advantage to an industry association in respect of the tender; and (iii) has not entered into any arrangement with other tenderers that the successful tenderer would pay any money or provide any other benefit or financial advantage to unsuccessful tenderers for the tender. Miscellaneous Contract Particulars There are a number of miscellaneous items which tenderers are requested to tender and which will ultimately form part of the contract (by being included in the Contract Particulars). The purpose of this schedule is therefore to enable the tenderer to provide details of such miscellaneous matters to be inserted into the Contract Particulars when the contract is signed by the parties. Items which are requested to be tendered include details of the Executive Negotiator and address and fax number for the giving or service of notices. Additional information is requested under HC-1 2003 including agreed damages (if any), percentage of extra costs due to acceleration, percentage of adjustments for valuing of variations and percentage of wages paid or payable by the contractor (used in determining the value of daywork). (j) Alternative Proposal If a tenderer wishes to provide an alternative proposal in respect of any aspect of the Contractor's Activities or Services, it must insert details of that alternative proposal in the relevant tender schedule. However, in order for that alternative to be considered, the tenderer must also provide a fully conforming tender. If a tenderer wishes to propose any departures from or qualifications to the standard form conditions of contract, the tenderer should do it by way of alternative proposal. If it does not do so, and seeks to incorporate such departures/qualifications in its original bid, then its tender will be non-conforming and will not be admitted to evaluation. ID personnel should be aware of and recognise attempts by tenderers to qualify or depart from the standard form conditions with "limiting" type language used throughout a bid, for example "This bid excludes XYZ" or "This bid does not include XYZ", particularly in circumstances where "XYZ" forms part of the standard conditions of contract, the special conditions or the brief. The purpose of an "alternative proposal" schedule is to emphasise the fact that the documents in the Suite are true standard forms which are not to be generally subject to change or negotiation. This is only to occur if required by Defence at the time it is preparing the Tender Documents for issue to tenderers, or if Defence considers that any changes offered by a tenderer in the alternative will enhance value for money. In either case, all standard form changes have to be approved by the DCC. This approval process ensures that Defence sends consistent terms and risk allocation into industry, thereby reducing potential bid costs for both Defence and its tenderers. The "alternative bid process" is a minimum form and content requirement in the Tender Documents for the purposes of the CPGs. It is a mandatory requirement. If qualifications or departures are not contained in the relevant Tender Schedule, the tender will be non-conforming and must not be admitted to evaluation. ID personnel are required to review tenders to identify if tenders contain "hidden" departures or qualifications, such as in the schedule addressing "price" or "fee". Handy Hint If any alternative proposal is accepted, then it needs to be carefully documented. This applies to any technical alternatives and to any contractual amendments. The latter should only be proposed through the DCC and the LSP. Legal\101242374.12 10 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (k) National Code Tenderers must submit signed undertakings of compliance under which the tenderers (amongst other things) warrant to Defence that they have acted consistently with the National Code and the Guidelines and will continue to do so. If an Invitation to Register Interest was used for the project, tenderers are also required to clarify their response to the relevant National Code Schedule in their Registration of Interest. If a tenderer was not required to submit a Registration of Interest, it is required to complete a questionnaire. This is a minimum form and content requirement for the purposes of the CPGs. It is a mandatory requirement. If not completed and attached to the tender, the tender will be non-conforming and must not be admitted to evaluation. (l) Equal Opportunity for Women Tenderers are requested to submit either a statutory declaration that the Equal Opportunity for Women in the Workplace Act 1999 (Cth) does not apply or, if it does apply, a letter or other evidence confirming that the tenderer is compliant with (or has been waived from the reporting requirements of) the Act and that its equal opportunity for women in the workplace program has been submitted to and approved by the Equal Opportunity for Women in the Workplace Agency. (m) Commercial-in-Confidence This tender schedule provides an opportunity to identify and justify any "commercial-in-confidence" information that is required to be kept confidential by the Commonwealth, subject to certain permitted disclosures. The Tender Documents contain guidance as to the type of information which will be "commercial-in-confidence". It should be noted that tenderers are required to provide justifications, so that Defence is in a position to make an assessment. If insufficient justification is provided, clarification should be sought. (n) Adjustment for imported items (HC-1 2003 and MW-2 2004 only) The tender schedule under HC-1 2003 and MW-2 2004 may provide a contractor with an opportunity to identify any imported items that it may require to perform its Contractor's Activities in order to be able to claim an adjustment to the contract price for any exchange rate fluctuation that might impact on the imported item(s). This only applies if Defence has determined that it applies for the project in question. (o) OHS Accreditation Scheme The OHS Accreditation Scheme is part of the Australian Government's response to the Cole Royal Commission into the building and construction industry, which recommended that the Australian Government use its purchasing power to help improve occupational health and safety outcomes on building sites. This is consistent with the National OHS Strategy 2002-2012 to which the AttorneyGeneral is a signatory. The OHS Accreditation Scheme will only apply if the tender is for a "Commonwealth building contract" valued in excess of $6 million (GST inclusive). This expression is defined in the Building and Construction Industry Improvement Act 2005 (Cth) ("BCII Act") and needs to be reviewed for each project. To be assessed for accreditation, tenderers need to apply for the Office of the Federal Safety Commissioner and will need to provide evidence against specific occupational health and safety criteria. At the relevant award date for the contract, the tenderer must be provisionally or fully accredited in accordance with the Australian Government Building and Construction OHS Accreditation Scheme, as provided for in the BCII Act. Essentially, tenderers are requested to demonstrate that they are provisionally or fully accredited in accordance with the Australian Government Building and Construction OHS Accreditation Scheme, as provided for in the BCII Act, or to describe the steps taken to ensure the tenderers will be so accredited before the award date for the contract. Legal\101242374.12 11 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction More information on the OHS Accreditation Scheme is available at www.fsc.gov.au or by contacting the Federal Safety Commissioner on 1800 652 500. 3.6 Tender acceptance A tender will be deemed to be accepted when either a formal agreement is signed by Defence and the selected tenderer or Defence issues a "letter of acceptance" notifying the selected tenderer that its tender has been accepted. A "letter of acceptance" must be distinguished from a "letter of intent". A letter of intent is usually issued where Defence is not in a position to enter into a formal contract but wants the tenderer to commence all or part of the Works or Services on an "early" basis. For example, Defence may want the preferred tenderer to commence the design of the Works so it will issue a letter of intent in respect of that design, but it does not oblige Defence to enter into a contract for the whole of the Works or the Services. The DCC must approve all letters of intent. 4. COMMONWEALTH PROCUREMENT GUIDELINES ("CPGs") 4.1 General The purpose of the CPGs is to: (a) establish a core procurement policy framework; and (b) articulate the Government's expectations of departments and agencies subject to the Financial Management and Accountability Act 1997 (Cth) and their officials when performing duties in relation to procurement. 4.2 Minimum time limits The minimum time limits are: (a) if a request is published electronically, 25 days from the date and time the request is published; and (b) if a request is not published electronically, 30 days from the date and time the request is published. The above time limits can be reduced to a period of not less than 10 days from the date and time of publication but only in certain, specific circumstances. 4.3 Conforming tender submissions Defence can only consider tenders which are received before the prescribed closing date and which satisfy the minimum form and content (or mandatory) requirements. If a tender fails to satisfy these requirements, it must be excluded from consideration. A tenderer can also be excluded on the grounds of bankruptcy, insolvency, false declarations, and significant deficiency in performance. 4.4 Restrictions on terminating a tender process There are some restrictions on Defence terminating the procurement process. Advice from DCC and the LSP should always be obtained before terminating (or significantly altering) a tender process. 4.5 Advising outcomes Defence must advise all tenderers of its decision and, if requested, provide reasons as to why a tenderer was not successful. Comparisons with other tenders should be avoided. Debriefs should be conducted against the evaluation criteria specified in the request documentation. 4.6 Managing contractors As the CPGs apply to Commonwealth departments and agencies, they have no direct application to the procurement processes of managing contractors for reimbursable work. However, such contractors are subject to a contractual obligation to comply with the CPGs. More specifically, MCC-1 2003 imposes an obligation on contractors to ensure that all subcontract tender documentation is prepared and all tender processes are conducted in accordance with the CPGs (refer to clause 8.1(c)(i) of MCC-1 2003). Legal\101242374.12 12 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction 5. PROJECT DELIVERY METHODS - WHICH DELIVERY METHOD DO I USE? 5.1 General The choice of delivery system is determined by an assessment of a number of factors, including: (a) the nature of the construction activity and size and complexity of the overall project; (b) budgetary constraints and the degree of control and hands-on management necessary to contain out-turn costs; (c) anticipated changes in political and/or Defence priorities; (d) anticipated degree of overlapping of design and construction phases, either because of a need to fasttrack the project or a requirement for ongoing review and refinement of design necessitated for some reason such as the project's magnitude, complexity or heritage and/or environmental considerations; (e) whether the construction work to be undertaken is civil engineering or building or both within the one project; (f) expertise in Defence personnel that may be committed to the project or, alternatively, the necessity to engage the private sector (whether contractor or consultant) to plan, manage, administer, supervise and co-ordinate the project; (g) allocation of risk for the major risk areas of design, cost and time; and (h) duration, staging of the project and packaging of elements. 5.2 HC-1 2003 As stated above, HC-1 2003 can be used in the following delivery methods: (a) construct only delivery; (b) document and construct delivery; (c) full design and construct delivery; (d) lump sum or schedule of rates delivery; and (e) major or medium works. 5.3 When to use the construct only delivery method (HC-1 2003) A construct only contract is predicated on the contractor being provided with a fully documented design at time of tendering, with no further design documentation necessary except shop drawings by the contractor, the documentation of variations (if any) and design documentation for Provisional Sum Work. When using this delivery method, Defence engages consultants to design the project under DSC-1 2003. Once the design is complete (apart from Provisional Sum Work), Defence calls for tenders from contractors to undertake construction in accordance with the design as documented. This traditional contract structure is the suitable delivery system for a project where: (a) Defence requires maximum control over design and thus wishes to engage and manage design consultants directly; (b) the detailed design documentation, apart from Provisional Sum Work, is complete well in advance of calling tenders and quality control mechanisms are in place to ensure that the detailed design documentation is without deficiencies and that the design is buildable; (c) experienced personnel are available to manage and co-ordinate the interface between preparation of detailed design for Provisional Sum Work and the letting of Provisional Sum Work; Legal\101242374.12 13 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (d) Defence has internal personnel or can engage outside consultants with the expertise to administer the construction phase and the construction contract; (e) there is no requirement to overlap the design and construction phases, other than for Provisional Sum Work included in the contractor's scope of work; (f) no changes in scope of the project work are predicted other than those additions or omissions dictated by cost management of the project; and (g) few variations to the design because of deficiencies in design documentation or changing end-user requirements are anticipated during construction. Provisional sums HC-1 2003 provides for the inclusion of "provisional sums". Provisional sums are included for work within the scope of the contract but which is not sufficiently defined in the tender documents. It is subsequently defined by further design prepared by either Defence or the Contractor. Provisional sums are typically included in contracts for building work to allow some overlap between the design and construction phases (ie fast-tracking) or because Defence is uncertain whether it will ultimately include the work within the project. Provisional sums are included in the contract price and are subject to certain adjustments. 5.4 Risk allocation under the construct only delivery method The contractor assumes no risk for design or deficiencies in design documentation. The risk assumed by the contractor is construction in accordance with the design for the lump sum (or at the schedule of rates as tendered) and on time. Defence has to manage the risk of design under this delivery system. Design deficiencies, poor documentation of design and buildability problems provide the greatest potential for cost blow-out in this traditional contract structure (because they are Defence's and not the contractor's responsibility). The other significant area of cost increase is variations, particularly a number of minor variations, arising from changes in end-user requirements. To avoid or at least minimise the major areas for additional payment, design consultants engaged by Defence must have buildability knowledge, be fully briefed on end-user needs (and those needs should be firmed up during design stage and have the support of Defence to freeze those needs to avoid variations during construction), and produce a fully documented design subject to quality assurance procedures prior to calling tenders for the construction work. When using HC-1 2003 for construct only, always include the special condition dealing with "buildability problems". This essentially attempts to reduce the contractor's ability to claim variations for minor or obvious design errors, omissions and discrepancies, where the contractor should have identified the problem at the time of tender and allowed for it in its tender. There is a corresponding special tender condition which needs to be inserted. 5.5 Disadvantages of the construct only delivery method Disadvantages of construct only delivery include: (a) no single line of responsibility for design and construction of the project, thus Defence has the task of sorting out whether a defect is attributable to design or construction; (b) the capacity to pass on the risk of design and deficiencies in design documentation is limited to the design consultant's failure to exercise reasonable care and skill, whereas the risk of design assumed by a contractor undertaking design in other standard forms is the higher and more onerous warranty of fitness of the design for its purpose; Legal\101242374.12 14 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (c) commitment of resources by Defence to manage and co-ordinate the interface between design and construction; (d) arm's length relationship of designers and constructors, so that there is no input from constructors into buildability of the design, which may increase time and cost significantly; (e) the chance of dispute between Defence and the contractor is high, with opposing interests in the final cost. Defence must rely heavily on its contract administrator to prevent the contractor exploiting defects in design documentation, from overpricing variations and also to administer the extension of time provision in a manner so as to keep alive Defence's right to liquidated damages for delay in completion; and (f) if the contractor fails to perform, the remedies open to Defence are drastic and may lead to serious financial repercussions if not exercised strictly in accordance with the contract provisions. 5.6 When to use the design and construct delivery method (HC-1 2003) The optimum delivery system for projects involving simple building work (ie. barrack blocks, recreational facilities and the like) is design and construct. Design and construct is appropriate where: (a) the priority is best design for a price; (b) Defence has developed the concept design, performance specification and quality requirements for the design brief to a level of particularity sufficient to ensure the delivery of the required product prior to calling tenders; (c) Defence requires tenderers to develop the design concept to satisfy the performance and quality criteria in the design brief, prepare the detailed design and documentation in accordance with the design brief and carry out the construction and commissioning of the project in accordance with the design brief; (d) the design brief is expressed in clear objective terms as to performance and quality criteria, to measure whether the project satisfies those requirements when completed; (e) sufficient experienced resources are available in Defence or outside personnel can be engaged to be committed to documenting negotiation details of the successful contractor's design proposal to avoid subsequent dispute over the contractor's interpretation of the design brief; (f) the control required over design and construction is limited to minimum interference to ensure design and construction achieve the performance and quality criteria set out in the design brief; (g) Defence opts to hand over control of the detailed design to the contractor in exchange for itself assuming no design risk; (h) because of the simplicity of the project, Defence requires only a project of a specified performance and quality delivered for an agreed cost and on time; and (i) limited variations necessitated by user requirements are anticipated during construction. 5.7 Advantages of the design and construct delivery method The advantages of this delivery system are: (a) the contractor is responsible for co-ordinating the interface between design documentation and construction, so there is no risk to Defence of claims for design documentation deficiencies or late supply of design clarification or other information (traditionally a major source of claims in lump sum contracts); (b) cost and time may be reduced by the contractor's capacity to achieve significant efficiencies by its control over design consultants, and by buildability studies and value management carried out by the contractor to ensure the product can be delivered for the lump sum price within the time for completion; Legal\101242374.12 15 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (c) there is a single line of responsibility for the design and construction phases, rendering it unnecessary for Defence to distinguish between defects in design and construction (in pursuing rectification from the contractor); (d) the contractor assumes a more onerous responsibility than design professionals, by warranting design and construction are fit for purpose; and (e) the contractor has a higher degree of control over the project and is better placed to predict, manage and absorb the risk of neutral events impacting on time and cost, such as latent conditions, adverse weather and industrial disputation. 5.8 Disadvantages of the design and construct delivery method The disadvantages of this form of delivery system are: (a) the potential for contractors to effect savings and increase profit within the lump sum, by underdesigning aspects of the project where there is inadequate definition of performance criteria and quality requirements in the design brief; (b) the advantage of shifting design responsibility and risk of design to the contractor is lost where Defence or the contract administrator undertakes an active and dominant role in finalising the detailed design, beyond the limits of monitoring the design and construction phases to ensure the work is being executed in accordance with the design brief; (c) the clarity of the objective performance and quality criteria in the design brief is crucial to control of the end product, and failure to achieve clarity may lead to disputation as to whether the contractor has in fact achieved the product described in the design brief; (d) variations to the design brief during design and construction phases will generate claims, forfeiting the benefit of the lump sum and impacting adversely on the final cost and timing of the project; and (e) from a practical and legal point of view, Defence has significantly less control than in other delivery systems during the course of the project or (if seeks to assume control) runs the risk of design responsibility being transferred back to Defence. 5.9 When to use the document and construct deliver method (HC-1 2003) Document and construct, as opposed to design and construct, allows greater control over the end product and a better capacity to comparatively assess tenders, whilst retaining Defence's flexibility to consider alternative value management proposals from tenderers. The significant difference is that the design phase is significantly advanced beyond concept stage, and may in fact have been substantially completed by Defence's design consultants. To retain the design and construct advantage of a single line of responsibility, the contractor is required to take over and be responsible for all design completed prior to entry into the contract, and assume responsibility for the design consultants who have prepared the design upon which the contract has been let. To achieve this, Defence's design consultants' terms of engagement are novated to the contractor, a legal mechanism by which the contractor steps into Defence's contracts with the design consultants on the same terms of engagement. 5.10 Advantages of the document and construct delivery method The advantages of document and construct, additional to those in design and construct, are: (a) Defence has a significantly greater control over the design of the end product as design may be substantially completed prior to contracting; and (b) Defence selects and engages design consultants who are subsequently novated to the contractor. 5.11 Disadvantages of the document and construct delivery method In addition to the disadvantages noted for the design and construct delivery system, disadvantages of document and construct include: Legal\101242374.12 16 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (a) an extended tendering period must be allowed to permit prospective contractors to assess prior design and Defence's design consultants, to be able to price the risk of design; (b) the extended tendering period results in a later commencement of construction and, unlike design and construct, does not allow an overlap between design and construction; (c) the efficiencies possible under design and construct, which can be achieved by the contractor fine-tuning design by buildability and value management studies to reduce time and cost, are not present to the same degree and may require redesign to allow the contractor to increase buildability and utilise its preferred construction methodology; (d) contractors with the expertise to undertake design and construct project delivery may be reluctant to price the risk of accepting responsibility for prior design; and (e) increasingly, design consultants are showing resistance to novation, which can result in delays unless the novation process is carefully managed from the outset (i.e. time of tender for the design consultant). STEPS IN USE OF DESIGN AND CONSTRUCT OR DOCUMENT AND CONSTRUCT Choice of design and construct or document construct delivery system Design consultants engaged to prepare Design Brief Design concept only performance specification and quality criteria OR Design and Construct 5.12 Design Brief with details providing solutions to performance specification and quality criteria Document and Construct Managing Contractor - MCC-1 2003 MCC-1 2003 combines design and construct responsibility and features of a project management concept. Procurement under MCC-1 2003 has three distinct stages: (a) tender stage; (b) Planning Phase; and (c) Delivery Phase. It is the optimum contract strategy where the criteria set out for a project management structure are satisfied, but where Defence opts to share some of the risks associated with a major construction project with a contractor. Large Legal\101242374.12 17 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction contractors have a capacity to carry risks associated with design and construction to an extent not normally assumed by a project manager. Tenders for the managing contractor are called not on the basis of fee for service (as in project management) but on a lump sum bid for preliminaries and management services ("Contractor's Work Fee (Planning)" and "Contractor's Work Fee (Delivery)" and a lump sum profit ("Management Fee")). The basis for the lump sums bid is a project of a broadly defined scope and ceiling cost, with adjustments to the lump sum bid for preliminaries if the scope of the project is varied or delayed by conduct of Defence or its agents or employees, particularly during the Planning Phase. This strategy provides Defence with maximum flexibility in determining the elements to be included in a project and the design of those elements. It does this by utilising the management expertise of a contractor organisation to develop the design, co-ordinate the interface between design and construction, undertake the construction and generally plan the project so as to remain within a target cost and target time for delivery of the project. This contract strategy seeks to do this through a collaborative arrangement, which generally involves less adversarial tension between the contractor and Defence than would be the case where HC-1 2003 is used. Defence has, however, retained some elements of competing interest between it and the contractor, as these are necessary for effective and accountable project delivery. The essential elements of this contract strategy are: (a) the contractor is responsible for design, in that it engages the design consultants, and then warrants fitness for purpose of the design and the works (when completed); (b) the contractor is the head contractor, fully responsible for the quality of the works and responsible for subcontract claims arising from its own inadequate performance; (c) the contractor is paid (in summary): (i) actual design costs (less claims for which it is responsible, etc); (ii) actual subcontract costs (less claims for which it is responsible, etc); (iii) a fixed fee for preliminaries; (iv) an agreed fee for profit and off-site overheads; and (v) possibly, an incentive (if it achieves against agreed key performance indicators); (d) the actual design and subcontract costs that are properly payable to design consultants and other subcontractors are paid through a trust account. The purpose of this is to promote prompt and secure payment at the subcontract level (for example, if the contractor is wound up the money in trust will still be applied to pay design consultants and other subcontractors); and (e) the contractor is required to manage the project to achieve timely completion within a defined cost limit, but does not have fixed price, fixed time obligations (ie. the target cost does not function as a lump sum cap and the contractor is not exposed to liquidated damages for late completion). Defence has adopted a compromise between no adversarial element and an arrangement which would provide it with guaranteed cost and time. The line drawn between these extremes can be identified on a continuum of risk allocation as follows: Legal\101242374.12 18 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Fixed time guaranteed maximum price share of savings / overrun Due care design risk Fixed Preliminaries Fixed fee Head Contract obligations Consultants reimbursed on cost plus agreed margin. Sub-contractors reimbursed on actual cost with no recovery for additional cost caused by Contractor conduct or default. Due care time / cost obligations. Due care design risk Cost Plus No design adequacy risk Direct trade contracts No time or cost obligations Max Competing Interests Max Co-operation Fixed lump sum Head Contract Fitness for purpose Fixed Time 5.13 Cost plus Fit for the purpose design risk Head Contract Cost plus Due care design risk Head Contract Advantages of the Managing Contractor delivery method The major advantages of this form of contracting are: (a) Defence gets the benefit of early contractor involvement in the detailed business case and before the PWC hearing; (b) because the design costs payable to design consultants are reimbursable, the contractor has greater flexibility to consider all options in design development; (c) because of the split between the Planning and Delivery Phases, the contractor has a clear incentive to use the Planning Phase to come up with the best possible project solutions, to maximise its chances of being awarded the delivery phase; (d) if the KPI and incentive regime is carefully negotiated, it could provide incentive for exceptional performance; (e) no fixed time/fixed price tension makes for greater flexibility in ordering variations, particularly in the design of, and the number of elements to be ultimately included in, a project after the contractor has been retained; (f) the contractor assumes the responsibility for design and design documentation prepared by consultants as a design and construct contractor (ie. fitness for purpose); (g) the contractor undertakes the risk of construction in the same manner as a contractor under HC-1 2003, with the essential difference that the managing contractor does not itself undertake construction; and (h) construction work is generally let to subcontractors on a competitive basis, to maximise value for money for Defence. 5.14 Disadvantages of the Managing Contractor delivery method The major disadvantages of this form of contracting are: (a) less cost/time certainty than under more traditional fixed time/fixed price delivery; (b) risk of reduction in scope where budget cannot be met; (c) significant investment in managing the contract; Legal\101242374.12 19 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (d) only applicable to larger more complex multi-element projects. 5.15 What is the difference between the Managing Contractor and Construction/Project Management? The managing contractor delivery method should be distinguished from "construction management" or "project management" contracts. The original managing contractor contract deliver method was expressly developed to overcome the legal and commercial deficiencies inherent in the construction management delivery method. With construction management contracts, the "manager" merely manages trade contracts as the agent of the owner. The "manager" does not assume any real responsibility for the time, cost or quality outcomes of the project. In particular, the "manager" is not responsible for defective works. This is assumed by the various trade contractors. The problem with this is that there is no single line of responsibility to the principal for the quality or completion of the project. Further, the "fee" paid to the "manager" may be linked to the out-turn cost of the project. This provides little incentive for the manager to manage variations and other claims for additional costs. This is in contrast to the managing contractor method where the contractor is responsible for the quality of design and construction. This means that if any work is defective, Defence only has to look directly to the managing contractor. 6. HEAD CONTRACT ("HC-1 2003") 6.1 General HC-1 2003 represents a flexible standard form which can be used for: (a) construct only delivery; (b) document and construct delivery; (c) full design and construct delivery; (d) lump sum or schedule of rates delivery; and (e) major or medium works. There is nothing that needs to be done to HC-1 2003 to determine which delivery method is being used, other than the selection of the document and construct clauses. The choice of delivery method will be implicit in the Works Description, which sets out the requirements of the Works (for example, drawings, specifications). Additionally, HC-1 2003 has a number of optional clauses which can be employed to alter the risk allocation, including: (f) an optional entitlement to time and cost for latent conditions; (g) the ability to widen or narrow the entitlement to extensions of time; (h) an option for agreed damages payable to the contractor for Defence caused delay (limited to breach of contract); and (i) an optional provision for bonus for early completion. Legal\101242374.12 20 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction HC-1 2003 Delivery Methods Traditional/Construct Only This is where Defence provides the design and the contractor is engaged to construct the project in accordance with the design. Design and Construct This is where Defence engages the contractor to design and construct the project so as to meet the needs of Defence. Defence's brief may include some basic or incomplete designs which the contractor will be required to complete. Document and Construct This is where Defence has commenced the design of the project, usually by engaging design consultants. The contractor takes over that preliminary design (and, usually, has Defence's design consultants novated to it) and so bears single line responsibility to Defence for design in a similar manner to a design and construct contract. 6.2 Specific features of HC-1 2003 The key features of HC-1 2003 are set out as follows: (a) Cooperation The parties are obliged to co-operate in carrying out their respective obligations under the contract. (b) Contract Administrator HC-1 2003 is administered by a contract administrator which is expressed to be the agent of Defence. The contract administrator may be an internal employee or an external consultant. For further details on the functions of the contract administrator, refer to 10 below. (c) Key People The contractor has to ensure that it employs certain key people, as represented in its tender, on the project. It can only replace them in certain circumstances. (d) Security Under HC-1 2003, the contractor must provide security by way of an unconditional bank undertaking (often loosely called a "bank guarantee"). Generally, there are considered to be as good as cash because they can readily be converted to cash upon presentation to the issuing bank. Upon presentation of a bank guarantee, a bank must make payment even if the contractor considers the call is unjustified. However, a contractor may be able to obtain an injunction preventing Defence from making a demand under a bank guarantee based on a negative covenant in a contract that a bank guarantee will not be called on unless and until the principal has an entitlement to do so. If a contractor obtains an injunction preventing Defence from calling on the bank guarantee, then the obligation of the bank to make payment pursuant to the bank guarantee never arises because Defence does not have an entitlement. HC-1 2003 does not contain any negative covenants in relation to Defence's right to call on the security which means that Defence's right to make a call on the security is unconditional. The effect of this is that the contractor is less likely to obtain an injunction to prevent the release of the security. Legal\101242374.12 21 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Handy Hint Although a bank undertaking may be unconditional, you should still do all your homework and have fully prepared the case in support of your encashment of it, before doing so. Encashment is likely to provoke a hostile reaction from the contractor, and will ultimately need to be defensible (sometimes immediately, in response to proceedings for an interim injunction). Further, the practical problem with encashment is the requirement to return the money into Consolidated Revenue. Encashment should not be considered without first seeking advice from DCC and the LSP. (e) Design As stated above, HC-1 2003 may be used for full design and construct delivery - from partial design to full design and construct. For design and construct delivery, the contract will need to specify the design obligations of the contractor, which is typically done in a design brief, which forms part of the Works Description. The contractor must warrant that its design will be fit for its intended purpose and the Works or a Stage of the Works which have been completed in accordance with the contractor's design are fit for their intended purpose. The contract does not impose any obligation on the contract administrator to review and approve any design documentation. Rather, the contract provides that the contract administrator "may review" the design, but there is no obligation to review. This seeks to avoid any implication that the contract administrator participated in the design process which could affect the contractor's warranty that the design is fit for its intended purpose. The contract administrator does have the right to reject all or any part of the contractor's design, but the contract administrator should endeavour not to unduly interfere with the contractor's design, and should only do so where there is a failure to comply with the design brief or the other requirements of the contract. Defence is granted a perpetual licence over any design documentation of the contractor. Summary of Design Provisions The design provisions under HC-1 2003 include: (f) fitness for purpose obligations on the part of the contractor; review of design and documentation by the contract administrator (but preserving the responsibility of the contractor); and a licence to Defence of all intellectual property. Non-reliance upon information HC-1 2003 provides a warranty from the contractor that it has relied upon its own enquiries and not upon information (such as site information) provided by Defence. Handy Hint If this information is being provided to tenderers, it should be reviewed by the LSP, to minimise the risk associated with the provision of the information. Although the Tender Documents contain a disclaimer of liability which is intended to address this issue (and which is to be provided to and signed by Tenderers before they receive the tender documentation), a review of the information can also assist to identify any information of particular concern and suggest ways to mitigate that concern. Legal\101242374.12 22 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (g) Latent Site Conditions There is an option for the risk of site conditions to be placed upon the contractor or, alternatively, for the contractor to be entitled to relief under certain circumstances where unforeseen latent site conditions are encountered. Generally, it is more appropriate to include the clauses entitling relief from latent conditions under a construct only or document and construct delivery, where the contractor may have less control over design and, therefore, less ability to manage this risk. Under HC-1 2003, latent conditions are defined as any ground conditions at the Site which differ materially from those which should have been anticipated by a prudent, competent and experienced contractor if it has assessed the risks which it is assuming under the contract and ensured that the contract price contains sufficient allowances to protect it against the eventuation of the risks it is assuming under the contract. Summary of Latent Conditions (h) (a) HC-1 2003 includes the option of transferring the risk of latent conditions to the contractor. (b) If Defence bears the risk, and a latent condition is encountered or found, the contractor is entitled to an extension of time and to be paid any extra costs reasonably incurred by the contractor (after the date of the contractor notifying Defence of the latent condition) arising from the latent condition. Site Access The contractor is not given exclusive possessory rights over the site. Instead, the contractor is given sufficient access to enable construction to be carried out. Defence may engage other contractors to carry out work on the site concurrently with the contractor's activities. The contractor is obliged to provide access to the site to Defence, the contract administrator and other authorised persons. (i) Other Contractors Defence may need to engage other contractors on certain projects. The contractor is obliged to cooperate, and not to interfere, with other contractors engaged by Defence and to co-ordinate and integrate its work with the work of other contractors. Handy Hint Although it may be necessary to engage numerous contractors on a site, this may increase the risk of delay and disruption to each of the contractors and, therefore, creates exposure for Defence. To minimise this risk, Defence could make other contractors of Defence subcontractors to a single head contractor. (j) Subcontractors The outdated concept of nominated subcontractors has been avoided. For defined work only, the contractor is obliged to select from a list of subcontractors that are approved to carry out specific work or otherwise gain approval for alternative subcontractors to those listed. (k) Provisional Sums Defence may carry out Provisional Sum Work either using the contractor, itself or by engaging other contractors. There are optional provisions for design of Provisional Sum Work to be carried out either by Defence or the contractor. For Provisional Sum Work to be carried out by the contractor, the Legal\101242374.12 23 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction contractor must select the subcontractor from a pre-approved list or use a subcontractor approved by the contract administrator. What is Provisional Sum Work? Provisional Sum Work is typically an element of work for which it is not possible to obtain a firm price at the time of tender or in respect of which Defence is uncertain whether it will be required. This could be because Defence has not finalised its requirements for the work. (l) Professional Indemnity Insurance There is provision for the contractor to effect professional indemnity insurance or errors and omissions insurance. This is only required where the contractor is responsible for design to any extent. (m) Environment The contractor is obliged to comply with environmental laws and contractual conditions for the protection of the environment. It must not pollute, contaminate or otherwise damage the environment and must rectify any pollution, contamination or other damage it does cause. (n) Industrial Relations The contractor is responsible for industrial relations. There are also specific provisions dealing with the National Code. (o) Project Plans Rather than simply dealing with quality assurance, HC-1 2003 contains provisions requiring the contractor to develop and implement a series of project plans. The matters for which project plans will be required may vary on a project-by-project basis. Typically, they will address quality, occupational health and safety, environmental management and other similar issues. The implementation of project plans will not limit the contractor's responsibility for work and materials. There are additional requirements if the works are near an airfield. (p) Defects There is provision for flexible solutions to deal with defective work or materials, including power to order rectification, acceptance of the defect subject to adjustment of the contract price and variation subject to adjustment of the contract price. There is also no final certificate which would adversely affect Defence's capacity to recover for defects during the statutory limitation periods (which continue after the expiry of the contractual defects liability period). (q) Construction Program There is a clear provision for construction programs as management tools to assist the parties and contract administrators. Because of their importance in monitoring progress and assessing extension of time claims, the contract administrator must ensure that the contractor complies with its ongoing programming obligations, including to provide updates of the program. Handy Hint The initial program should never be attached to the contract or stated to form part of the contract The risk with this is that it could be argued to have precedence over the other time provisions of the contract or give the contractor a right to extensions of time where it would otherwise not be so entitled. Legal\101242374.12 24 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (r) Staging HC-1 2003 makes provision for the Works to be completed in stages. The concept of "stages" in Defence contracts is akin in some ways to "separable portions" under Australian Standards contracts. Each stage has a separate date for completion, separate liquidated damages for late completion and a separate defects liability period. (s) Extensions of Time The contractor may claim an extension of the relevant Date for Completion of the Works or a Stage. The contractor's entitlement to an extension will be subject to the satisfaction of certain requirements. The most significant of these are: (i) complying with the notice provisions; (ii) the delay being covered by an "Act of Prevention" (as defined in the contract) or an event of delay (if any) inserted in the Contract Particulars; and (iii) demonstrating the required delay effect (ie a delay in achieving completion by the date for completion); The contractor's claim can be reduced to the extent that it contributed to the delay or failed to preclude, avoid or minimise the delay. HC-1 2003 also contains flexible provisions enabling partial or complete acceleration as an alternative to extensions of time. In that event, if the contractor would otherwise have been entitled to an extension, it will be entitled to its direct costs plus an agreed margin. Handy Hint There is provision for additional events of delay to be inserted in the Contract Particulars. This should only be done if, in the context of the specific project, this will offer value for money. The form of words should be settled by DCC or the LSP. (t) Delay Damages There is an optional provision for pre-agreed damages in the event of delay due to a breach of the contract by Defence. This provision functions in the same way as liquidated damages (except in reverse), by liquidating the liability of Defence in the event of delay to the contractor. However, there is no relationship or correlation between the amount of pre-agreed damages for "agreed damages" (payable by Defence) and the pre-agreed damages as "liquidated damages" (payable by the contractor). They need to be separately calculated so that they constitute a genuine pre-estimate. Handy Hint If agreed damages are to be provided, the rate(s) must be agreed before signing the contract and inserted in the contract particulars. Never insert "to be agreed" or "to be negotiated", as this will not be enforceable, and will leave Defence exposed to the contractor's entitlement to general law damages, which is uncapped. If the agreed damages clause is not to be used, then any alternative should be settled by DCC or the LSP. (u) Liquidated Damages The contractor must pay Defence liquidated damages at a set rate (as specified in the contract particulars) if the date of completion of the Works or a Stage has not occurred by the date for completion. Liquidated damages, to be enforceable, must be a genuine pre-estimate of the loss which Defence will suffer if the contractor fails to achieve completion by the date for completion. Although this does not require a precise mathematical calculation, every effort should be made to ensure that the rate stated in Legal\101242374.12 25 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction the contract particulars reflects Defence's best assessment of the loss it will suffer if completion is late. Conversely, Defence should avoid inserting an arbitrarily low figure, as this will cap the contractor's liability and prevent Defence from recovering more if its actual loss is greater. Handy Hint Agreed or delay damages: if the contractor is delayed due to a breach by Defence, and receives an extension of time, Defence pays the contractor delay damages (Defence contracts call these "Agreed Damages"). Liquidated damages: if the contractor does not complete the Works or a Stage by the date for completion, the contractor pays Defence liquidated damages. Typically, this should be stated as a daily rate. Increasingly, contractors are seeking an aggregate cap on liquidated damages (often in the order of 10%). This should not be agreed without approval of DCC. Also, always ensure a positive rate is inserted in the contract particulars. Never insert "nil" or "not applicable", as this could leave Defence without any entitlement to delay damages for late completion. Where there is more than one Stage, ensure that an appropriate rate is inserted for each Stage. (v) Variations Defence can require the contractor to submit a price for a proposed variation and give notice of the effect of the proposed variation on the construction program. Defence can unilaterally direct variations, subject to the contractor's entitlement to payment for them, in accordance with an agreed valuation mechanism. The contractor may propose variations for the convenience of the contractor or for project efficiency. Such proposals can be rejected, or accepted unconditionally or on conditions (such as provision for a share of savings). The contract contains the capacity to delete work by variation, and for Defence to have this work subsequently carried out by another contractor. However, this power is suspiciously regarded by contractors, and should only generally be used where it is not feasible to have this current contractor carry out the work. Handy Hint All variation requests and other directions under the contract should be instructed through the contract administrator, and not given directly by Defence personnel. The risk with the latter is that, although a Defence person may not be intending its direction/request for information to have any time or cost consequences, if it varies work scope or delays progress, it may do so. (w) Payment The contract contains provision for payment on the basis of either a lump sum or schedule of rates. Payment is made on completion of certain defined stages or on a monthly basis (depending on the option chosen). There is provision for the contractor to provide additional security as a condition precedent to payment of unfixed goods and materials. Defence should never pay for unfixed goods and materials unless it first receives additional security to the same or similar value. Otherwise, it could make a payment (which it forfeits in whole or in part on the Financial default of the contractor) without ever receiving title to or possession of the goods. The contractor releases Defence from further claims which have not been made in accordance with the contract after both the completion and final payment claims. Legal\101242374.12 26 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction HC-1 2003 contains payment provisions drafted specifically to remain consistent with the various security of payment legislative regimes around Australia. Handy Hint Ensure the contract administrator meticulously administers payment in accordance with the contract. If not, Defence could be exposed to a security of payment claim by the contractor. Defence has already been exposed to such claims. They can be difficult, costly and timeconsuming to defend. (x) Bonus There is an optional bonus provision for early completion. This should not be used unless there is a clear commercial benefit to Defence in early completion. (y) Termination The termination provisions for default or insolvency only apply in favour of Defence and not the contractor. In addition, there is provision for termination for convenience. This is subject to payment of certain costs. Handy Hint These provisions must not be executed or used without full involvement of DCC and the LSP. If used incorrectly, they could expose Defence to liability in damages (including for lost profit) to the contractor. (z) Notices To ensure timely and efficient contract administration, HC-1 2003 contains notification of claim requirements, and time bars for non-compliance. (aa) Dispute Resolution The dispute resolution provisions include expert determination (of certain matters directed by the contract administrator), executive negotiation and commercial arbitration. There is also potential for the parties to agree on other alternative dispute resolution methods, such as mediation. 7. MANAGING CONTRACTOR CONTRACT ("MCC-1 2003") 7.1 General Defence Procurement involves a two phase process for determining the viability of projects: (a) the strategic business case ("SBC"); and (b) the detailed business case ("DBC"). It is against this backdrop that MCC-1 2003 has been developed. MCC-1 2003 involves a two phase delivery method comprising an initial preliminary contract in the Planning Phase and a subsequent consolidated contract in the Delivery Phase. More specifically, under this contract, Defence engages a contractor to: (c) plan and design the works in the Planning Phase; and (d) complete the design of, commence, construct, commission, complete and handover the works in the Delivery Phase. Tenders are sought well before PWC approval. The intention is to capitalise on the contractor's expertise by obtaining "early contractor involvement". This includes having the contractor provide input into the detailed Legal\101242374.12 27 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction business case (at the second pass stage above). The earlier strategic business case is usually prepared by Defence's consultants (for example, the contract administrator). At the time of tender, Defence provides tenderers with an outline scope and target cost. Tenderers are required to tender their remuneration proposal for both the Planning Phase and Delivery Phase upon the basis that they may not proceed to the Delivery Phase. The remuneration proposed for the Delivery Phase will also require tenderers to propose the basis on which that remuneration would be subject to adjustment to take into account the outcomes of the Planning Phase. 7.2 Planning Phase The Planning Phase is an initial preliminary contract and involves two sub-phases, namely: (a) Planning Phase Agreement; and (b) Planning Phase Approval. 7.3 Planning Phase Agreement and Planning Phase Approval From the date the parties enter into a formal agreement, the contractor must achieve Planning Phase Agreement and Planning Phase Approval by specified dates. If the contractor fails to satisfy the Planning Phase requirements, Defence may: (a) re-tender for the Delivery Phase in respect of the delivery of the works; or (b) waive satisfaction of the Planning Phase requirements in relation to certain parts of the Planning Phase works (provided they are below the relevant PWC threshold) and enter into a new contract. Under the new contract, the contractor will complete the design of the works (to the extent not completed in the Planning Phase), and commence, commission, complete and handover the works. If Defence elects to re-tender for the works, the contractor has no entitlement to complete the works but is entitled to payment for fees due and payable for the works completed up to the date of issue of the relevant notice by Defence. In achieving Planning Phase Agreement, the contractor must finalise "Planning Phase Design Documentation" and prepare a cost plan, program and project plans. The contractor must also assist Defence in achieving specified "Planning Phase Milestones" and agree on the contractor's remuneration for the Delivery Phase. In achieving Planning Phase Approval, the contractor must do all things or tasks as may be required to provide Defence with assistance to obtain approvals including Government and Parliamentary approvals and approvals in accordance with the Financial Management and Accountability Act 1997 (Cth). 7.4 Flexibility of MCC-1 2003 MCC-1 2003 gives Defence benefits of early contractor involvement and flexibility, with the right to elect not to proceed with the contractor to the Delivery Phase, but only if: (a) Defence is not satisfied (in its absolute discretion) with the design development, programming, cost planning or project plans prepared by the contractor; (b) Planning Phase Milestones have not been achieved by the specified dates; (c) the parties are unable to agree on the remuneration structure for the Delivery Phase; (d) the requisite approvals have not been obtained; (e) the contract particulars for the Delivery Phase have not been agreed and executed; or (f) the contractor fails to perform all the planning work in accordance with the contract. If Planning Phase Agreement is achieved, Defence must issue a written notice to the contractor stating the date upon which it was achieved. The primary aspect of this will be the fee negotiation referred to in (c) above, and discussed in 7.6 below. Legal\101242374.12 28 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction When Planning Phase Approval is also achieved, a second written notice must be issued to the contractor stating the date upon which Planning Phase Approval was achieved. Defence must then proceed with the contractor to the Delivery Phase on the terms of a subsequent consolidated contract under which the contractor will complete the design of the works (to the extent not completed in the Planning Phase) and commence, construct, commission, complete and handover the works. 7.5 Delivery Phase The Delivery Phase has the following features: (a) the contractor completes design (through its design consultants) based on the design prepared in the Planning Phase; (b) underlying construction work will generally be let to subcontractors on a competitive basis (to ensure value for money), subject to any innovative proposal in the contractor's DCAP which provides Defence with greater value for money; and (c) if Defence elects not to proceed with the contractor (per paragraph 7.4 above), it can proceed with another tenderer and use all project documents prepared by the contractor and obtain a novation of its subcontractors. 7.6 Contractor's Remuneration Under MCC-1 2003, Defence pays the contractor in progressive payments as follows: (a) the Contractor's Work Fee (Planning Phase and Delivery Phase) for the work that the contractor does (as opposed to the underlying design and construction work delivered by design consultants and subcontractors); (b) the Management Fee, for overhead and profit (in the Delivery Phase only); and (c) "Reimbursable Costs" (Planning Phase and Delivery Phase), for actual design and construction costs properly incurred and payable to subcontractors (including consultants and subcontractors). Payment of (a) and (b) will usually be in agreed instalments based on the achievement of agreed milestones (to avoid overpayment of fees as against project progress). The Management Fee and Contractor's Work Fee (Delivery), as tendered, are both negotiated prior to the completion of the Planning Phase, based on the tendered adjustment mechanisms, in light of changes to the scope of the project during the Planning Phase. This is likely to be a robust commercial negotiation and therefore needs to be undertaken on behalf of Defence by an experienced negotiation team, which both understands MCC-1 2003 in detail and has carefully prepared its position in response to the contractor's fee proposal. Defence needs to remember that there is no compulsion on it to accept any fee proposal put to it by the contractor, and it can continue to negotiate until it achieves fees that it is satisfied with. The Reimbursable Costs payable to subcontractors are paid into a trust account. This promotes prompt payment and security of payment. The contractor sets up the trust account on the terms of the trust deed in the schedule of collateral documents which accompanies MCC-1 2003. 7.7 Incentive As part of the "remuneration deal" negotiated before the conclusion of the Planning Phase, an incentive may be made available to the contractor. The purpose of the incentive is to align the interests of Defence with those of the contractor in delivering the work. Again, the negotiation of the incentive should be undertaken by an experienced negotiation team. Generally, the intention of providing the incentive is to: (a) provide the contractor with an opportunity to earn an incentive contingent upon exceptional performance (measured against agreed key performance indicators), following completion; but (b) allow tenderers to nominate (within general guidelines) the incentive mechanism which would most closely provide an alignment of interest for them. Legal\101242374.12 29 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction As a guide, the incentive mechanism should have regard to the following principles: (c) Defence will, at the end of the preliminary planning stage, make available an incentive pool to the contractor; (d) the extent of the incentive pool, to be made available, will be determined having regard to the performance of the contractor during the Planning Phase; (e) whether or not (and the extent to which) the contractor is entitled to any payment out of the incentive pool will depend on the contractor: (i) either achieving completion of the initially agreed workscope for a total cost less than the target cost, or achieving completion of the initially agreed workscope, together with additional scope, for no more than the target cost; (ii) achieving completion by the target date; and (iii) achieving the key performance indicators agreed by the parties. Quite apart from incentives, proposals will also be sought from tenderers as to the extent to which they are prepared to put at risk any part of their fees, depending upon their performance. 7.8 Whole of Life/Ecologically Sustainable Development Defence has developed general "Whole of Life Objectives" and "ESD Principles". They are able to be added to on a project by project basis. Tenderers are requested to submit a "WOL Plan" at the time of tender indicating how they propose to further the objectives and principles set by Defence. There will be scope for the tendered plan to be negotiated with the preferred tenderer. Once a contract is entered into, the contractor will be required to comply with its tendered plan (as negotiated and as later amended with the consent of the contract administrator) and to use best endeavours to achieve the stated Defence objectives and principles. The contractor will have an obligation to identify proposals for maximising the stated Defence objectives and principles during the course of design and construction. There will also be a regime of periodic reviews of, and reports on, progress against the tendered plan and the stated objectives and principles. At present, there will be no express incentives or penalties for the achievement (or otherwise) of WOL Objectives and ESD Principles. However, the results of any post occupancy evaluation carried out may be used in the evaluation of any future tenders submitted by the contractor to Defence. 7.9 Subcontractors (including consultants and subcontractors) The subcontract tender documentation must be approved by the contract administrator before the contractor invites tenders from subcontractors. The contractor must examine and analyse tenders and recommend to the contract administrator which tender it considers should be accepted. The contract administrator has the right to reject the contractor's recommendation and direct the contractor to accept the tender of another tenderer. The contractor must enter into a subcontract agreement with the approved tenderer in the form of agreement contained in the subcontract tender documentation. The contractor is responsible for administering, supervising, inspecting, coordinating and controlling the work of all subcontractors which it has engaged. The contractor is also responsible for all subcontractors and their work as if the contractor was itself executing the work. When making a payment claim, the contractor must provide the contract administrator with a statutory declaration declaring that all subcontractors have been paid all moneys due and payable to them. All moneys payable to subcontractors are paid through a trust account to facilitate security of payment to subcontractors. That is, the money held in trust must be used to pay subcontractors and cannot be used for any other purpose (eg the payment of the contractor's creditors). Legal\101242374.12 30 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Standard form subcontracts for use with MCC-1 2003 have been prepared and are in the Schedule of Collateral Documents. Their purpose is to ensure that, given Defence is paying the amounts payable to subcontractors as part of the Reimbursable Costs, the risk allocation reflects one which provides value for money. Accordingly, Defence should always ensure that, if a contractor suggests different forms of subcontract, they are not either passing through risks to the subcontractor which the contractor should be bearing (and adding to the Reimbursable Costs payable by Defence) or providing a risk allocation which reduces cost certainty for Defence by providing undue opportunities for further remuneration. 8. DESIGN SERVICES CONTRACT ("DSC-1 2003") 8.1 General DSC-1 2003 is used by Defence for the procurement of design services. There is no Defence "panel" for the provision of design services. The DIP and DEHP Panel arrangements should generally not be used except to the extent described in the relevant Statements of Work, as they may not specifically address the relevant "design issues" or Defence's required risk allocation for designs. 8.2 Key features of DSC-1 2003 The key features of DSC-1 2003 are set out as follows: (a) Standard of care Although the consultant's basic obligation is to carry out the services in accordance with the contract, the contract imposes a standard of care which it must exercise. In particular, the consultant must exercise the standard of skill, care and diligence of an expert professional provider of the services. This is a high standard which Defence expects of all its design consultants (ie that they be "experts" in designing the relevant facilities), and it should therefore not be subject to change at the request of a consultant. The consultant must also warrant that each of its subconsultants will exercise the same standard of skill, care and diligence. The consultant must also: (b) (i) use its "best endeavours" to ensure that its design documentation is fit for its intended purpose; (ii) ensure that the services are provided economically and in accordance with any budgetary requirements; and (iii) exercise the utmost good faith in the best interests of Defence and keep Defence fully and regularly informed of all matters affecting or relating to the services. Payment Payment under the contract is on the basis of a lump sum and is made on the completion of certain milestones or on a monthly basis (depending on the option chosen). Apart from the lump sum fee, the contract makes provision for additional costs in respect of: (c) (i) a change in statutory requirements after the award date resulting in extra costs being incurred by the consultant; (ii) variations at the direction of the contract administrator; (iii) suspension of the contract by the contract administrator; and (iv) acceleration. Time The consultant must regularly and diligently progress the services and achieve completion of each milestone by the date specified for completion in the contract particulars. Although there is no liability Legal\101242374.12 31 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction on the consultant for liquidated damages for delayed completion, the consultant could be liable for general damages if it fails to meet a milestone and Defence suffers loss. (d) Programming The consultant is required to prepare a program of the services, within 14 days of the award date, which must be approved by the contract administrator. The consultant must update the program periodically at specific intervals to take account of any changes to the program or delays which may have occurred or extensions of time which may have been granted. (e) Extension of time The consultant may only claim an extension of time if it has been delayed in completion of a milestone by a breach by Defence, any act or omission of Defence, the contract administrator or other contractor engaged by Defence or a variation at the direction of the contract administrator. (f) Acceleration The contract administrator has the power to require the acceleration of the consultant's performance of its services. However, the power to require acceleration under DSC-1 2003 differs from the power under HC-1 2003 in the following key aspects: (i) it is not predicated on the consultant first having submitted a claim for an extension of time; (ii) the contract administrator can unilaterally seek to bring the original date for completion forward; and (iii) the consultant only has a "best endeavours" obligation to achieve the accelerated date for completion. The intention of the acceleration provision is that Defence be able to require the consultant to deliver design earlier than originally agreed due to changes in the project program. In exchange, the consultant is entitled to extra costs properly and reasonably incurred in complying with the direction to accelerate. (g) Review of design documentation The consultant must submit the design documentation it prepares to the contract administrator, but there is no obligation on the contract administrator to review the design documentation. The contract administrator is absolved from liability for errors in design and omissions if it does exercise its right to review the consultant's design documentation. Specifically, the contract provides that the contract administrator does not assume or owe any duty of care to the consultant for errors, omissions or compliance with the contract. If the contract administrator does review the consultant's design documentation, it has the right to reject it and the consultant must then resubmit amended design documentation. Despite the contract administrator's ability to reject design documentation, it should endeavour not to unduly interfere with the consultant's design, as this may lead to the consultant being relieved of sole responsibility for design problems. (h) Licence over design documentation The consultant grants Defence a perpetual, royalty-free, irrevocable, non-exclusive, worldwide licence to exercise all rights of the owner of the intellectual property rights in the design documentation. This clause does not give Defence ownership of the intellectual property. Rather, the clause is designed to ensure that Defence is able to exercise any of the rights held by the actual owner of the intellectual property in the design documentation which includes any other material brought or required to be brought into existence by the consultant as part of carrying out the services. 9. NATIONAL CODE Defence's contractors and consultants must comply with the National Code, and the relevant Implementation Guidelines for the National Code of Practice for the Construction Industry ("Guidelines"). The Guidelines and National Code are available at www.workplace.gov.au. Legal\101242374.12 32 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction This is an absolute requirement, which cannot be avoided. If there are any concerns, (either during a tender process or during project delivery) the matter must be immediately referred to DCC. The National Code requires that contractors and consultants performing construction activities for or on behalf of Defence: (a) comply with awards and/or certified agreements; (b) comply with laws relating to freedom of association, right of entry and strike pay; (c) act responsibly and fairly in the resolution of any disputes which may occur; (d) take a positive approach toward improving productivity through flexible workplace practices and working arrangements; and (e) take a responsible approach to industrial relations, leading to economically-sustainable arrangements. The Guidelines identify how the National Code should be applied on Australian Government projects. Defence's contractors and consultants must ensure that all subcontracts impose equivalent obligations in respect of the Guidelines and National Code on subcontractors and subconsultants. 10. PANEL CONTRACTS 10.1 Defence Infrastructure Panel ("DIP") Subpanel for Contract Administrators HC-1 2003, MCC-1 2003, DSC-1 2003 and MW-2 2004 require Defence to appoint a contract administrator to administer the contracts. The contract administrator acts as Defence's agent and is primarily responsible for giving all directions to the contractor or consultant. The contract administrator may be an internal employee of Defence or a private sector consultant (but is usually the latter). The requirement that the contract administrator act as the agent of Defence and not as a certifier when exercising the contract administrator's functions under a contract ensures that the contract administrator can act on Defence's instructions and does not have to exercise its functions independently of these instructions. This is appropriate given that the contract administrator will usually be a consultant engaged and paid for by Defence. Defence has established the DIP for the purposes of providing Defence with access to a variety of expert consultants, including contract administrators. The terms of appointment of the consultants to the DIP are governed by the Panel Agreement. Specific projects are governed by Terms of Engagement. Defence will normally select a consultant from the DIP (as opposed to an internal employee) to act as the contract administrator for a project. Regardless of the terms of the agreement between Defence and the contract administrator, the relevant contractor or consultant will be entitled to rely on the actions of the contract administrator under the contract. Defence will be bound by those actions of the contract administrator, as against the contractor or consultant, because the contract administrator is the agent of Defence. The contract administrator has obligations to consult with and inform Defence with respect to matters impacting on the project, and should not make any material determinations or give any material directions without such prior consultation. The contract administrator has broad functions under each of the contracts, some of which are compulsory (eg granting an extension of time, certifying payment or issuing a completion certificate) whilst others are discretionary (eg ordering a variation). As the contract administrator's functions are broad, it will often be necessary for the contract administrator to delegate certain functions to others. A comprehensive list of the contract administrator's functions can be found in Volume 3 of the manuals for HC-1 2003, MCC-1 2003, DSC-1 2003 and MW-2 2004. Because the contract administrator has the primary responsibility for giving directions to the contractor, Defence personnel should ensure they provide all of their instructions through the contract administrator, who can then direct the contractor in a co-ordinated way. If Defence personnel instruct the contractor directly and individually, then it is likely that this will expose Defence to claims for times and cost. This should therefore be avoided. 10.2 Other Panels The other Defence panels relate to: Legal\101242374.12 33 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (a) environment and heritage services; (b) UXO; (c) legal services; and (d) other sub-panels of the DIP, such as planning. The purpose of those panels is to provide Defence with access to "pre-qualified" groups of specialists, through stream-lined processes which reduce the time and cost involved in procurement. Also, over time, it is anticipated that the panellists increase their understanding of Defence business and their expertise in providing services to Defence. Details of these panel arrangements are located on the Defence Infrastructure Management website. 11. DETAILED CONTRACTOR'S OR CONSULTANT'S ACTIVITIES PROPOSAL ("DCAP") The tender documents for MCC-1 2003 and DSC-1 2003 request the submission of a DCAP, which focuses on the tenderer's approach to key processes such as design development, cost planning, relationship contracting, team building and subcontractor procurement processes. The DCAP serves at least 3 distinct functions: (a) it provides tenderers with a basis for distinguishing the innovations which they can provide to the management aspects of the form of delivery. At the same time, the DCAP will provide Defence with the ability to evaluate a tenderer's approach; (b) it will be subject to negotiation with the preferred tenderer after which it will become a contract document. This means that the contractor or consultant will then be bound by the representations made by it at the time of tender and Defence will be able to enforce those representations; and (c) it provides tenderers with an opportunity for obtaining a full understanding of Defence's expectations (i.e. through the process of preparing the DCAP). Essentially, the DCAP is a "reverse brief" explaining how the contractor or consultant will approach the delivery of its activities or services, is used in tender evaluation and subsequently becomes a contractually binding document. Before being attached to the contract, it should be the subject of a collaborative workshop, in which it is negotiated and finalised to the satisfaction of Defence. Amongst other matters, this process should ensure that the DCAP does not contain assumptions, words of limitation or exclusion, any legal or commercial terms or any provision which is inconsistent with the other provisions of the contract. Under the conditions of contract, the contractor or consultant warrants that the DCAP and design documentation comply with the requirements of the contract and, in the case of MCC-1 2003, that construction in accordance with the DCAP will ensure that the works achieve completion in accordance with contract. The DCAP is intended to be dynamic and therefore subject to change, as and when required, to ensure it reflects what is required to deliver the relevant works or services. It does not represent a limitation on the scope of the obligations of the contractor or consultant. 12. OTHER FORMS OF CONTRACT 12.1 MW-2 2004 This contract has been developed by Defence for the procurement of construct only or design and construct lump sum delivery for medium works. MW-2 2004 generally allocates risk in a way which is more weighted towards the contractor. It is not merely a "short" version of HC-1 2003. Although generally following the format of HC-1 2003 (albeit with less detail), the "softer" risk allocation is because the sorts of works which are likely to be the subject of this contract (being smaller, simpler and lower risk) will involve contractors less likely to accept the risk allocation under HC-1 2003. See the comparative risk matrix in Annexure A. 12.2 Minor Works Contract This can also be used for construct only or design and construct lump sum delivery. It is to be used for simple works (eg involving a single trade) that are not especially risky. Legal\101242374.12 34 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction The risk allocation is generally like MW-2 2004. However, there are some differences. This form is now primarily used under the CMC. It would generally be more appropriate to use MW-2 2004 for Defence infrastructure projects, given their value. 13. COLLATERAL DOCUMENTS 13.1 General Each contract in the Suite refers to a "Schedule of Collateral Documents" which the contractor or consultant must either produce, enter into with Defence or agree to comply with. Some of the collateral documents include: (a) Unconditional Undertaking; (b) Collateral Warranty; (c) Deeds of Novation: (d) Moral Rights Consent; (e) Subcontractor Deed of Covenant; (f) Consultant Deed of Covenant; (g) Payment Claim; (h) Payment Statement; and (i) Expert Determination Agreement. There are also collateral documents dealing with the National Code and certain certifications. 13.2 Unconditional Undertaking Under HC-1 2003, MCC-1 2003 and MW-2 2004, the contractor is required to provide security to Defence in the form of "Approved Security" in the amount set out in the contract particulars. The approved security is an unconditional undertaking, that is, a "bank guarantee". The financial institution undertakes to pay Defence the amount set out in the undertaking, being the equivalent amount to that set out in the contract particulars, on receipt of a demand from Defence. There is a prescribed form of unconditional undertaking. However, if a financial institution wishes to use its own form of unconditional undertaking rather than the prescribed form, this may be acceptable to Defence provided all the requirements in the Defence proforma appear in substance in the form of undertaking provided by the financial institution. Advice from the LSP should be sought if the contractor asserts that its bank wishes to use its own form of undertaking. 13.3 Collateral Warranty Under HC-1 2003, MCC-1 2003 and MW-2 2004, the contractor must obtain from subcontractors those warranties as are specified for minimum warranty periods for goods supplied under the contract in a prescribed form. The prescribed form of warranty is the "Collateral Warranty". This creates a direct legal relationship between Defence and the "warrantors" which Defence can later enforce. 13.4 Moral Rights Consent Certain works which attract copyright protection are also protected by moral rights. These are rights under the Copyright Act 1968 (Cth) and are additional to traditional copyright. Unlike copyright, moral rights cannot be assigned, licensed or waived. Moral rights attach to individual authors and not organisations such as companies. An author's moral rights in respect of work are: (a) the right to be identified as author of that work; (b) the right to prevent authorship of the work being falsely attributed to someone else; and Legal\101242374.12 35 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (c) the right not to have the work subjected to derogatory treatment. In an extreme case, an author may exercise the third right in the list above to limit how Defence could use material created by that author. As an example, an architect who prepared a design for a building may claim that changes to the design subsequently required by Defence amount to a derogatory treatment of the original design. This risk exists despite the broad licence which the contractor grants to Defence under the contract (as the contractor or consultant cannot licence use of the author's moral rights). The contracts contain provisions which are aimed at protecting Defence and other parties engaged on a project against any liability to the contractor or consultant (or to individuals who are authors of work under the agreement) for breach of a person's moral rights in respect of any project documents by releasing Defence and other parties engaged on a project from liability for certain acts which may otherwise be in breach of an individual's moral rights. The contractor or consultant must obtain the consent of any person who is or may be an author of any material which may be used in connection with the works or services in the form of the "Moral Rights Consent". There are two forms of moral rights consent - one for an individual author and one where there are multiple authors. 13.5 Payment Claim A "Payment Claim" is the prescribed form which must be completed and submitted by a contractor or consultant when it makes a claim for payment. 13.6 Payment Statement A "Payment Statement" is the prescribed form which the contract administrator must give the contractor or consultant on behalf of Defence within 10 business days of receiving a payment claim from the contractor or consultant. The Payment Statement must provide details of the payment claim to which it relates, the value of work completed, the amount already paid to the contractor or consultant, and the amount which the contract administrator believes to be payable to the contractor or consultant under the contract. If this amount is less than the amount claimed by the contractor or consultant, the contract administrator must provide reasons for the lesser amount. These reasons are critical. Both this payment statement (and the payment claim, above) are in standard form because of the security of payment legislation around Australia. To ensure that Defence and its contract administrators are in the best position to comply with the requirements of the legislation in certifying payment claims, these forms have been provided and must be used. 13.7 Expert Determination Agreement The "Expert Determination Agreement" sets out the terms of appointment of an expert if a dispute is submitted to an expert for determination. 13.8 Subcontractor and Consultant Deeds of Covenant The subcontractor and consultant deeds of covenant bring Defence into direct contractual relationship with the relevant subconsultants and subcontractors engaged by contractors or consultants. Subcontractors and subconsultants employed by contractors or consultants warrant to Defence that in designing the project or elements within the project they will exercise due care and skill. Subcontractors warrant to Defence that they will carry out the subcontract works in a thorough and tradesmanlike manner using good quality materials which are fit for their purpose. Defence, by virtue of the contractual relationships created by the deeds, is in a position to commence an action directly against subconsultants or subcontractors for defects in a project resulting from breach of the warranties contained in the deeds. In this manner, Defence has a remedy directly against the party at fault which is a significant protection to Defence where, for example, the contractor employing the consultants or subcontractors is wound up. A further protection of Defence's interest is the option in the deeds to take over the terms of engagement subcontract (either itself or by a substituted contractor) to ensure subconsultants and subcontractors are bound to continue on a project despite the contractor or consultant dropping out. Legal\101242374.12 36 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction 14. CONTRACT MANUALS 14.1 General Contract manuals have been prepared to give guidance to Defence personnel on HC-1 2003, MCC-1 2003, DSC-1 2003 and MW-2 2004. The contract manuals for HC-1 2003, MCC-1 2003, DSC-1 2003 and MW-2 2004 comprise six separate volumes which are discussed below. The manuals are not a substitute for reading each contract. You should read the manuals in conjunction with each contract, as this will assist your understanding of the contracts. 14.2 Volume 1 - Introduction This volume provides background information about the format, structure and purpose of each of the contract manuals. This volume also describes how the manual is divided into six separate volumes, being: (a) Volume 1: Introduction; (b) Volume 2: Completing the Tender and Contract Documents; (c) Volume 3: Clause- by-Clause Guidance for the Conditions of Contract; (d) Volume 4: Flowcharts; (e) Volume 5: Proforma Notices; and (f) Volume 6: Clause-by-Clause guidance for Special Conditions. The key features of Volume 1 are set out below: (g) general background information including key principles; (h) details of optional clauses contained in the contract which can affect risk allocation; (i) details of the contract structure including pre-contractual tender stages; (j) a summary of the protection of Defence's rights (HC-1 2003 only: this contract contains provisions which protect Defence against a number of matters including problems arising through nominating subcontractors, the effect of approval on behalf of Defence of contractor design, environmental pollution or damage, occupational health and safety problems); (k) description of the two phase delivery, being Planning Phase and Delivery Phase (MCC-1 2003 only); and (l) notable features of the contract including contractor's remuneration, incentives, DCAP, and whole of life/ecologically sustainable development (MCC-1 2003 only). 14.3 Volume 2 - Completing the Tender and Contract Documents This volume provides detailed guidance on the tender process, from the issuing of the initial Invitation to Register Interest document (two-stage tender process), the Tender Documents and the completion of the final contract documents once the tender process is complete and the successful tender is selected. The volume is separated into a number of sections, which reflect the different stages and procedures that must be completed by Defence during the procurement process. (a) Section 1 - Outline of Manual Section 1 contains general commentary on the manual and the tender process. (b) Section 2 - Invitation to Register Interest Section 2 is broken down into the following sub-sections: Legal\101242374.12 37 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (c) (i) general information; (ii) completing the ITR clauses by Defence. This sub-section sets out a table containing information on the clauses which must be completed by Defence (or its ITR Administrator) prior to issue to Applicants. The table also contains guidance notes; (iii) completing ITR Schedules by Defence. This sub-section lists all the ITR Schedules that require the insertion of additional information by Defence (or its ITR Administrator) prior to issue to Applicants; and (iv) clause-by-clause commentary. This sub-section sets out a clause-by-clause commentary on specific clauses of the ITR. Section 3 - Tender Documents This section gives guidance on completion of the Tender Documents by Defence before being issued to tenderers, details of the manner in which, and the conditions under which, a tenderer is to submit its tender and the prerequisites to, and basis for consideration and acceptance of, tenders by Defence. This section includes: (d) (i) a table to assist Defence personnel in preparing the Tender Documents. The table lists all the details that need to be filled out and amendments that need to be made by Defence to the Tender Documents; (ii) clause-by-clause commentary on the specific clauses of the Tender Conditions; (iii) a summary of the table of Tender Particulars in Part 2 of the Tender Conditions with an explanation as to what information needs to be inserted by Defence (or its Tender Administrator); and (iv) commentary on the preparation and analysis of the Tender Schedules. Guidance notes are also included as well as details of the information that is to be inserted by Defence (or its Tender Administrator). Section 4 - The Contract This section provides commentary and guidance on completing the Conditions of Contract and the Contract Particulars to enable them to be included in the Tender Documents. (e) Section 5 - Finalising the Contract This section provides guidance on finalising the Conditions of Contract and Contract Particulars once the successful tenderer is chosen and the parties wish to formally execute the contract, including: 14.4 (i) what must and must not be included in the contract; (ii) the parts that comprise the contract, namely the letter of acceptance or formal agreement, Conditions of Contract, Contract Particulars, annexures to the Conditions of Contract, Special Conditions and other documents referenced in the Contract Particulars; (iii) guidelines to the information and details to be included in Contract Particulars; and (iv) formalities for the execution of contracts. Volume 3 - Clause-by-clause Guidance This Volume provides a commentary on each clause of the Conditions of Contract, explaining the purpose of the clause within the contract and matters of which personnel should be aware in relation to it. Interspersed throughout the clause-by-clause commentary is general advice about issues likely to be encountered in the administration of the contract, such as: (a) communication and meetings with various contractor or consultant personnel; and Legal\101242374.12 38 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction (b) dealing with claims made by the contractor, including those in respect of the primary risk areas of time, cost (including variations) and quality. The Volume also provides a general discussion of the major themes within the contract, including quality and defects, time and progress, variations and payment procedures. 14.5 Volume 4 - Flowcharts This volume contains a number of flowcharts, which provide diagrammatical explanations for various processes under HC-1 2003, MCC-1 2003, DSC-1 2003 and MW-2 2004. The flowcharts may be used by Defence to evaluate the stages and steps within those processes and to understand what options Defence has and what actions should be taken upon notification or occurrence of certain events. For example, the flowcharts set out procedures to follow in relation to matters such as variations, payment, termination, disputes and extensions of time. It is important to note that the flowcharts are intended to be used for preliminary guidance only, and Defence personnel must carefully assess their rights and obligations under the contract, where action is required. 14.6 Volume 5 - Proforma Notices This volume contains proforma notices to assist both parties in complying with the formal notification requirements of the Conditions of Contract. The proforma notices: (a) indicate from and to whom particular notices or instructions must be sent; (b) set out information which must be contained in the notice; (c) contain instructions to the persons preparing the notice indicating what additional information should be provided or completed; and (d) set out options where more than one option is provided. 14.7 Volume 6 - Clause-by-Clause Commentary on Special Conditions This volume provides commentary on each clause of the menu of special conditions available for inclusion in Defence contracts. The special conditions deal with specific issues including the discovery of hazardous substances on site, the use of hazardous substances, and the Heritage Act 1995 (Vic) requirements (amongst others). Importantly, the Special Conditions contain the occupational health and safety provisions applicable to each jurisdiction. The special conditions have not been included in the general Conditions of Contract, because they deal with subject matter which is likely to be project specific. Therefore, their inclusion in Defence contracts needs to be considered on a case-by-case basis. The words "ALL CONTRACTS" etc in the special conditions do not indicate that the special condition should be used for all contracts, rather that the special condition can be used, if it is necessary for the project, with amendments as indicated. This process needs to be discriminating for two reasons. Firstly, an existing special condition should only be used where an assessment has been made that it is generally required. Secondly, a consideration should be made of all other project risks, and new special conditions developed to deal with any of those risks not covered by the existing menu. Such "non-standard" special conditions should always be reviewed by a member of the LSP and the DCC. 15. RISK ALLOCATION As the Defence contracts have been developed for different types of projects and project delivery methods, the risk allocation under each contract is not identical. Please refer to the table set out in Attachment A for a comparison of the risk allocation under HC-1 2003, MW-2 2004, MCC-1 2003 and DSC-1 2003. Legal\101242374.12 39 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Annexure A - Risk Matrix Legal\101242374.12 40 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Risk HC-1 2003 MW-2 2004 MCC-1 2003 DSC-1 2003 Risk of Works Except to the extent that loss or damage arises from a "Commonwealth Risk", the contractor bears the risk of, and must indemnify Defence against, loss or damage to the Works and unfixed goods and materials (whether on or off-Site) until a Notice of Completion issues for the Works. As per HC-1 2003. As per HC-1 2003. No equivalent provision (given no construction obligations) but refer to indemnity below. After the issue of a Notice of Completion, the contractor's risk is limited to any loss or damage to the Works which results from something that the contractor does (or does not do) while it is rectifying defects or from something which occurred before the issue of the Notice of Completion. The contractor's risk does not include a Commonwealth Risk. Commonwealth Risks include such things as: Legal\101242374.12 war, invasion, revolution, hostilities, act of foreign enemies, civil war, rebellion, insurrection or military or usurped powers, martial law or confiscation by order 41 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Risk HC-1 2003 MW-2 2004 MCC-1 2003 DSC-1 2003 No equivalent provision, but this would effectively be the position in any event to the extent of the contractor's assumption of the risk of the Works. As per HC-1 2003. No equivalent provision. As per HC-1 2003 except that there is no carve out for loss, damage, injury or death contributed to by Defence, the contract administrator or another contractor. As per HC-1 2003. No equivalent provision but refer to indemnity below. Generally as per HC-1 2003. As per HC-1 2003. No equivalent provision. of government; Reinstatement terrorism; and ionising radiations or radioactive contamination. Contractor must reinstate at its own cost, except where due to a Commonwealth Risk. Note: reinstate means to replace or otherwise make good any loss of, or repair the damage to, the Works or any unfixed goods and materials. Public Liability Except where it arises from a Commonwealth Risk, the contractor indemnifies Defence for loss or damage to Defence property and third party claims arising out of property damage or personal injury or death arising out of the Contractor's Activities. The contractor's responsibility is reduced to the extent an act or omission of Defence, the contract administrator or another contractor contributed to loss, damage, injury or death. Site Information Legal\101242374.12 Defence warrants that it has made available to the contractor certain site information obtained by Defence for purpose of the Works. 42 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Risk HC-1 2003 MW-2 2004 MCC-1 2003 DSC-1 2003 Generally as per HC-1 2003, except the provisions dealing with Latent Conditions are not optional. Defence bears the risk of Latent Conditions. No equivalent provision, as this is dealt with in the subcontracts for construction work. No equivalent provision. As per HC-1 2003. MCC-1 2003 is design and construct only. Contractor is required to design the Works in accordance with the Brief and other requirements of the Contract. Fitness for purpose warranty as per HC-1 2003. DSC-1 2003 is a design only contract. The site information does not form part of the contract and to the extent that the law permits, Defence is not liable upon any claim by the contractor arising out of the site information. Defence does not warrant, guarantee or make any representation about the accuracy or adequacy of the site information. Latent Conditions HC-1 2003 includes the option of transferring the risk of Latent Conditions to the contractor (usually where HC-1 2003 is being used for design and construct delivery). If Defence bears the risk and a Latent Condition is encountered or found, then the contractor will be entitled to an extension of time and the payment of extra costs. Contractor's design HC-1 2003 can be used as a design and construct contract. If the contract is to be used for design and construct, then the contract will include a design brief, which effectively sets out the design obligations of the contractor. Where the contractor is obliged to design any part of the Works, it must warrant that the Design Documentation it prepares is fit for its intended purpose and, upon Completion, the Works will be fit Legal\101242374.12 The contractor must also undertake site investigations and other risk reductions studies. The contractor must advise the contract administrator of every The consultant is engaged to carry out the Services described in the Brief, using the standard of care of an expert professional provider. The consultant's Design Documentation must comply with the requirements of the Contract. The consultant must also use its best endeavours to 43 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Risk HC-1 2003 MW-2 2004 for their intended purpose. Review of Design Documentation by contract administrator The contractor must submit Design Documentation to the contractor Administrator but there is no obligation on the contract administrator to review any Design Documentation. The contract administrator may only reject Design Documentation if it is not in accordance with the Contract. The contract administrator does not owe or assume any duty of care to review any Design Documentation. If it does review, then it does not owe or assume any duty of care in reviewing the Design Documentation for errors, omissions or compliance with the contract. Adopting Defence's design Legal\101242374.12 HC-1 2003 includes the option of passing on the design risk arising out of Defence's design consultants by requiring the contractor to take a novation of agreements between Defence and its design consultants. This is where document and Unlike HC-1 2003, the contract administrator must reject or give their permission for the contractor to use the contractor's design. The contract administrator owes no duty to the contractor to review the contractor's design for errors, omissions or compliance with the contract. No equivalent provision. MCC-1 2003 DSC-1 2003 reasonable available method of design and construction for the Works and the possible alternative materials which are suitable for use with each particular method. ensure that the Design Documentation is fit for its intended purpose (but it does not have a strict fitness for purpose obligation, as it is not usual for consultants to do so, as it is not usually capable of being covered by professional indemnity insurance). The contractor must submit its Design Documentation to the contract Administrator for review. This is both during design development in the Planning Phase and detailed design during the Delivery Phase. As per HC-1 2003. Given the greater flexibility under this from of delivery, the contract administrator is not limited to rejecting design if it is not in accordance with the contract (as under HC-1 2003). Otherwise as for HC-1 2003. As per HC-1 2003, although it would be less likely that document and contract be used here. This contains the mirror provision, enabling Defence to novate the consultant to the contractor, where document and contract delivery is being used. 44 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Risk HC-1 2003 MW-2 2004 MCC-1 2003 DSC-1 2003 contract delivery is being used. In these circumstances, contractor bears full responsibility for past and future design work prepared by Defence's design consultants. Liability for subcontractors Contractor responsible for subcontractors and for all work which is subcontracted. As per HC-1 2003. As per HC-1 2003. The consultant remains liable to Defence for all of the Services regardless of whether they are ultimately subcontracted to a third party. Similarly, the consultant will be liable to Defence for all acts, omissions and defaults of subconsultants. Defects Contractor must correct all defects at its own cost unless the defect is something for which the contractor is not responsible (in which event corrective work will be treated as a variation). Generally as per HC-1 2003. Contract makes a distinction between non-conforming works and defects or omissions. As per HC-1 2003. As the contract is for design services, it addresses defective design in the form of noncomplying services rather than defects. Defence may accept work despite a defect or order a variation to work around the defect. The Contractor has primary responsibility for correcting all parts of the Works that are: non-conforming (before the date of Completion; or defective or omission (after the date of Completion), unless otherwise directed. Defence can direct the contractor to respond to a non-conformance / defect or omission in one of Legal\101242374.12 The contract administrator may instruct the contractor to respond to the non-complying services in one of the following ways: to reperform the non-conforming services by a specified time; take all reasonable steps to mitigate the effect of the noncompliance to 45 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Risk HC-1 2003 MW-2 2004 MCC-1 2003 DSC-1 2003 Defence; and three ways: Maintenance during Defects Liability Period ("DLP") Legal\101242374.12 If provided for in the Contract Particulars, the contractor must ensure that during the DLP, such planned and unplanned maintenance is carried out: as required by the Commissioning and Handover Plan; and as is otherwise necessary to ensure Works are, at end of DLP, in a condition fit for their intended purpose. to correct the nonconformance / defect or omission; to carry out a Variation; or to ignore the nonconformance / defect or omission, in which case, Defence accepts the Works as is and recovers the cost of rectifying the defect from the contractor. No equivalent provision. to take all reasonable steps to put Defence in (as closely as possible) the position it would have been if the consultant had carried out the Services in accordance with the contract. Defence may also accept the non-complying Services despite the non-compliance and then recover its costs and losses from the consultant. As per HC-1 2003. No equivalent provision. 46 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Risk HC-1 2003 MW-2 2004 MCC-1 2003 DSC-1 2003 DLP DLP commences on the Date of Completion of the Works or a Stage and continues for the period specified in the Contract Particulars, unless extended. AS per HC-1 2003. As per HC-1 2003. No Defects Liability Period. Extension of DLP If Defence gives the contractor an instruction during the DLP, the DLP will be extended for the work required by the instruction by the period set out in the Contract Particulars. No equivalent provision. As per HC-1 2003. No equivalent provision. Time Obligations The contractor has to achieve Completion by the Date for Completion, whether of the Works or (if applicable) each Stage. As per HC-1 2003. The contractor must use its best endeavours to achieve Completion of the Works or each Stage by the relevant Target Date. The consultant has an obligation to achieve the state milestones by the stated milestone dates (but see liquidated damages below) Extension of Time The contractor may only claim an extension of time if the cause of delay was beyond its reasonable control and there has been: Acts of delay entitling the contractor to claim an extension of time are broader than under HC-1 2003 and include: MCC-1 2003 provides for a Target Date rather than a fixed date for completion. As per HC-1 2003, except there is no provision for extension for additional events to be set out in the Contract Particulars. an Act of Prevention (breach by Defence, other acts or omissions of Defence, contract administrator or other contractor, or a variation); or an act or omission of Defence, the contract administrator or an employee of Defence; a Variation; there are other events of delay entitling, an extension of time set out in the Contract Particulars (i.e. neutral Latent Conditions; proceedings being taken by adjacent or neighbouring owners Legal\101242374.12 Unlike the extension of time mechanism in HC-1 2003 where there is a fixed date for completion with liquidated damages for delay, as there is only a best endeavours obligation upon the contractor to reach Completion by the Target Date, MCC-1 2003 does not provide for any mechanism to adjust the Target Date. 47 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Risk HC-1 2003 MW-2 2004 events, such as latent conditions, weather or industrial disputes). Insurance Legal\101242374.12 Contractor must effect the following insurance policies: construction risks insurance public liability insurance; workers compensation insurance; errors and omissions insurance or professional indemnity insurance (if required by the Contract Particulars); and any other insurances as MCC-1 2003 DSC-1 2003 As per HC-1 2003. Additionally, the contractor must ensure that subcontractors who perform design work maintain professional indemnity insurance or errors an omissions insurance. As per HC-1 2003 but excluding construction risks insurance and option for errors and omissions insurance. or occupiers; civil commotion or industrial dispute which is not confined to the contractor or any subcontractor; inclement weather; delay of any governmental authority in giving any Approval; or compliance with the requirements of local or other authorities. As per HC-1 2003 but excluding option for errors and omissions insurance. 48 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Risk HC-1 2003 MW-2 2004 MCC-1 2003 DSC-1 2003 As per HC-1 2003, except that it is not an optional clause. The contractor is entitled to have its fixed preliminaries ("Contractor's Work Fee") increased by the amount of extra costs incurred in respect of delays caused by Defence acts or omissions. No equivalent provision. As per HC-1 2003. As per HC-1 2003. As per HC-1 2003. No equivalent provisions. No equivalent provisions. Defence can direct the consultant to accelerate, but it only has a best endeavours obligation to do so. required by the Contract Particulars. Contractor must ensure that subcontractors have workers compensation insurance. Delay costs/agreed damages HC-1 2003 includes an option for the payment of delay damages payable by Defence for delays caused by breach of contract to take the form of "agreed damages". The contractor is entitled to be paid the amount specified in the Contract Particulars for each day by which the Date for Completion is extended due to a breach by Defence. The agreed damages operate as a limitation on Defence's liability for damages (just like liquidated damages in reverse). Suspension The contractor has no right to suspend work under the Contract unless ordered to do so by the contract administrator. However, if Security of Payment legislation applies, contractor may have a right to suspend work. Acceleration Legal\101242374.12 Instead of granting an extension of time, Defence can require the contractor to accelerate through all or part of the delay, in exchange for paying the relevant direct costs 49 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Risk HC-1 2003 MW-2 2004 MCC-1 2003 DSC-1 2003 As per HC-1 2003. As per HC-1 2003. No equivalent provision. As per HC-1 2003. MCC-1 2003 has the option of including an incentive mechanism which rewards early completion (as well as other exceptional performance). No equivalent provision. of doing so plus an agreed margin. Unfixed goods and materials Unfixed goods or materials will not be included in the value of the work unless certain conditions have been satisfied including the provision of additional security for the amount claimed by the contractor and evidence that title to the goods will pass to Defence on payment. Additional security will be released once the goods and materials are incorporated into the works. Bonus incentive A bonus may be stipulated in the Contract Particulars. Defence must pay the contractor the bonus amount for each day Completion of the Works or a Stage is early (i.e. occurs before the fixed bonus date, which is not subject to extensions). The incentive mechanism uses key performance indicators to calculate the incentive. The contractor must provide a monthly report with each payment claim which includes an analysis of its performance against the key performance indicators. Indemnity Legal\101242374.12 Contractor must indemnify Defence against any liability, claim, cost, loss or damage arising out of a breach by the contractor. As per HC-1 2003. As per HC-1 2003. As per HC-1 2003. 50 Department of Defence - Infrastructure Division - Suite of Contracts - An Introduction Risk HC-1 2003 MW-2 2004 MCC-1 2003 DSC-1 2003 Liquidated damages If the Works or a Stage do not reach Completion by the relevant Date for Completion, the contractor must pay liquidated damages at the rate specified in the Contract Particulars for every day after the Date for Completion until the Date of Completion or until the contract is terminated (whichever occurs first). As per HC-1 2003. No equivalent provision. No equivalent provision. Delayed access A failure by Defence to grant access to the Site by the contractual date is not a breach of Contract. As per HC-1 2003. No equivalent provision as there is no extension of time or agreed damages mechanism. No equivalent provision. Contractor's only entitlement is to the actual costs incurred for delayed access and to an extension of time to any relevant Date for Completion. Security The contractor must provide security to Defence by way of an unconditional undertaking (bank guarantee) within 14 days of the Award Date. As per HC-1 2003. As per HC-1 2003 except that contractor must provide security as a condition precedent to Planning Phase Approval. No equivalent provision. Release of Security Defence must release 50% of the security upon Completion of the Works or for each and every Stage and the remaining 50% at the end of the last DLP. Defence may vary these amounts where it considers that more money is required to be withheld in order to ensure that the interests of Defence are protected. As per HC-1 2003, except that Defence has no right to vary the amounts. As per HC-1 2003. No equivalent provision. Legal\101242374.12 51