Risk Log for <<project name>> PROJECT DETAILS Project/Programme Name Project Sponsor Project/Programme Manager Start Date Completion Date DOCUMENT DETAILS Version Status Date Author/Editor Details of Change Risk Log <<project name>> [RL v4] Page 1 RISK LOG A full risk log will be maintained throughout the project. Key to colour coding: Low risk Risk Scores (see end of document for full descriptions) Critical Success Factors (CSF) Medium risk Impact a Student experience High risk Likelihood Insignificant 1 1 Very Low b Securing and diversifying income Risk not live 2 Minor 2 Low c Employee engagement Risk closed 3 Moderate 3 Medium d Capital programmes Positive risk 4 Serious 4 High e Brand, image and reputation 5 Very serious 5 Very High Likelihood Movement Ref Description Impact Mitigation R01 R02 R03 R04 R05 CSF Owner Status Risk Log <<project name>> [RL v4] Action taken Page 2 INITIAL RISK MATRIX: Only negative risk is shown 5 Impact 4 3 2 1 1 2 3 4 5 Likelihood Risks in the red zone need frequent monitoring and should be actively managed and reported to the Project Board Risk Log <<project name>> [RL v4] Page 3 RISK CATEGORIES ARE: IMPACT Severity Possible consequences Description 1 - Insignificant Negative outcomes from risks or lost opportunities that might have some effect on a small part of the project Won’t affect the outcome of the project 2 - Minor Negative outcomes from risks or lost opportunities that are unlikely to have a significant effect on the project 3 – Moderate Negative outcomes from risks or lost opportunities that will have a significant impact on the project but can be managed 4 - Serious Negative outcomes from risks or lost opportunities with a significant effect that will require major effort to manage and resolve but do not actually threaten the project’s overall viability 5 – Very serious Negative outcomes from risks or lost opportunities which if not resolved will result in the failure of the project Less than 1% overspend No regulatory consequence Minor adverse publicity Less than 5% over schedule Between 1 and 5% overspend Limited regulatory consequence Local adverse publicity Between 5% and 15% over schedule Between 6% and 25% overspend Significant regulatory consequence Negative headlines in the national press Between 16% and 50% over schedule 26% or more overspend Substantial regulatory consequence Sustained negative headlines in the national press Failure of major part of business More than 50% over schedule Risk Log <<project name>> [RL v4] Page 4 LIKELIHOOD Descriptor Likelihood 1 – Very low It probably won’t happen during the life of the project 2 – Low it might just happen during the life of the project 3 – Medium it could well happen during the life of the project 4 – High it’s fairly likely to happen during the life of the project 5 – Very high it’s almost certain to happen during the life of the project CSF (CRITICAL SUCCESS FACTORS) Code CSF a Student experience b Securing and diversifying income c Employee engagement d Capital programmes e Brand, image and reputation MOVEMENT This is the difference between the initial risk weighting and the current risk weighting. For example if a risk is initially scored at Minor/Medium, its weighting is 2x3 =6. If the current risk scores have changed to Minor/Low, then the new weighting is 2x2 = 4, so the movement is 6-4 = 2. (Thus a negative number shows an increased level of risk). The movement weighting should be recalculated each time the risk log is updated. Risk Log <<project name>> [RL v4] Page 5