Janet6 Update Neil Shewry Project Manager Agenda • • • • • • Background Procurement What we’re building How we’re getting on Strategic Research Facilities Plans for the future Background SuperJanet5: 2006 to 2013 • Janet6: Project to replace the UK wide Janet backbone, SuperJanet5 Requirements gathering & analysis 2010 to 2011 Procurement • Fibre infrastructure • Optical transmission equipment Oct 2011 to Sept 2012 Rollout Sept 2012 to April 2013 Transition SJ5 to J6 May 2013 to July 2013 SJ5 ‘turned-off’ Oct 2013 Procurement • Fibre infrastructure contract signed: 31st July 2012 • • • • Scottish & Southern Energy Telecoms (SSET) 4 year framework 10 (+5) year contract £30M • Optical transmission contract signed: 6th September 2012 • • • • Ciena Inc. 7 year framework Order for supply and 5 years support £12.8M What we’re building 5 delivery phases Core 4 Regional RNs connect at multiples of 10G Most are getting an upgrade What we’re building I could go into more detail… …but how good is your eyesight? What we’re building - Points of Presence • Vacating the Verizon Business PoPs – Except for small presence in Glasgow and Reading • Existing Provider-Neutral PoPs – Telehouse North, Telecity Harbour Exchange – Telecity Manchester, Scolocate • New Provider-Neutral PoPs – Telecity Powergate, Telehouse West, Leeds (aql) • SSET Core PoPs – Bradley Stoke, Erdington, Lowdham, Glasgow • SSET Transmission PoPs – Multiplex circuits from regional fibres onto the backbone • SSET In-Line Amplifier PoPs – Single rack, small amplifier shelf • RNEPs What we’re building - Lightpath • Increase bandwidth between backbone nodes to 100GE • Topology reflects what is currently required How we’re getting on – fibre • Acceptance of core infrastructure February 2013 • Acceptance of regional infrastructure March 2013 How we’re getting on – DWDM equipment • Ciena 6500 platform • All kit is in the country 40% on site 60% in staging • Deployment began in January Staging Delivery Installation Commissioning • Completion end April 2013 How we’re getting on – IP routing equipment • Upgrade: Juniper T1600 • Professional Services Juniper T4000 How we’re getting on – other stuff • Regional Network Readiness Space & power RNEP router capability • Transition Planning • Operational Readiness PoP Control Fault Management Network Management • Service Management SSET Ciena • Decommissioning Strategic Research Facilities • Government e-Infrastructure initiative – £26m funding to Janet • £10m for Janet6 backbone • £12m for phase 1 (below) • £4m for ‘industrial connectivity’ • Phase 1 – – – – Met Office, Exeter Norwich Research Park Hinxton Campus, Cambridge (Francis Crick Institute, St Pancras) Plans for the future • LOTS of bandwidth – 100Gbit/s x 88 channels = 8.8Tbit/s – 400Gbit/s? • Strategic Research Facilities – possible phase 2 • Thames Valley Network • South Region (formerly LeNSE) • Other regional networks? • Individual customers? Questions? Janet, Lumen House Library Avenue, Harwell Oxford Didcot, Oxfordshire t: +44 (0) 1235 822200 f: +44 (0) 1235 822399 e: Service@ja.net