1 SNCF Infra | juin 2010
Bernard SCHAER
Director of Contracts & Customers Services
SNCF Infrastructure Branch
EFRTC
June 11th, 2010
MAINTENANCE & TRAVAUX
CIRCULATION FERROVIAIRE
INGENIERIES
33 , 000 people
60 local entities
€ 3,500 m
2009
14,000 people
21 local entities
€ 950 m
2009
5 , 100 people
€ 650 m
2009
IG , INEXIA, SYSTRA
Maintenance of the railway network
Management of investments for RFF and SNCF
Troubleshooting 24/7
Timetable management
Traffic Control
Safety and punctuality of the railway system
Rail projects in France and throughout the world
Expertise and project management
Management of investments for RFF and SNCF
3 SNCF Infra | juin 2010
SNCF INFRA
P. IZARD
C.E.O
WORK &
MAINTENANCE
X. OUIN
Director
HUMAN
RESSOURCES
FINANCE
COMMUNICATION
STRATEGY
CONTRACTS &
CUSTOMER SERVICES
B. SCHAER
Director
INFORMATION
SECURITY
TRAFFIC SAFETY
ENGINEERING
F.DELORME
Director
4 SNCF Infra | juin 2010
TRAFFIC CONTROL
DCF
A.H. BERTRAND
Director
Operators
Regional
Authorities
(fund local trains)
Stations management
Infrastructure
Other operating Companies
Payments for paths
Maintenance contract
Operation contract
Infrastructure Manager
State
Safety body
Regulatory body
ARAF
6 SNCF Infra | juin 2010
ARAF
R.F.F.
Réseau Ferré de France
E.P.S.F.
Etablissement Public de
Sécurité Ferroviaire
ARAF
Autorité de Régulation des Activités Ferroviaires
D.C.F
Direction de la Circulation
Ferroviaire
SNCF Infrastructure
Created in 1997
Owns the network
Took over €20.4b of historical SNCF debt (SNCF retained €7b)
A performance contract was signed with the
State in November
2008
7 SNCF Infra | juin 2010
Created in march 2006
Created by law in
December 2009
European directive
2004/49
Regulatory body for the railway sector
Monitors safety issues on the national railway network
Should be in place before the end of 2010
DCF still belongs to
SNCF, however has some kind of an independent status
Its director is named directly by the government.
DCF works for RFF and is responsible for
Traffic Control
Maintains the network
Manages investment works on behalf of RFF
A maintenance contract is signed between SNCF and
RFF since 2007
Total track length
•
UIC 1 à 4 : 19885 km ( included 3839 km HSL )
9969 S & C ( included 754 HSL )
•
UIC 5 et 6 13803 km - 7621 S & C
Regional lines
•
• with passengers : 11723 km - 4113 S & C without passengers: 4417 km - 2171 S & C
Side tracks 14949 km - 46177 S & C
Level-crossings 18843
Bridges 40914
Tunnels 1 588 (631 km)
Signal boxes 2256
9 SNCF Infra | juin 2010
Power supply
Sub-stations: 535
Overhead lines
1500 V: 12 547 Km (40%)
25 000 V :19 098 Km (60%)
The study made by EPFL in 2005 showed
Bad conditions of the network
No optimization of M/R: The share M/R was 2/3;1/3 when it was from 1/2;1/2 up to 1/3;2/3 in other europeen countries
No optimization of track possession : According to the EPFL, track possession duration was too short
(1h50) and no technically and economically efficient
No optimization of traffic control : There were too much signalling boxes
10 SNCF Infra | juin 2010
At the end of 2005, RFF,SNCF and the French Government came to an agreement of an increasing of funding for renewal
1780 1800 1800 1800
1550
1343
1048
899
700
Track
Bridges
Sign
OHL
11 SNCF Infra | juin 2010
A 2005 A 2007 A 2008 A 2009 A 2010 A 2012 A 2013 A 2014 A 2015
2005
450
120
80
40
2007
602
130
75
50
2008
740
123
105
47
2009
965
132
144
51
2010
997
140
176
55
2012
1183
197
307
61
2013
1269
2014
1237
2015
1231
60
55
50
60
55
50
45
40
35
30
2008 2009 2010 2011 2012 2013 2014 2015 2016
Courbes d'évolution de la substance UIC 1-4
45
40
35
30
2008 2009 2010 2011 2012 2013 2014 2015 2016
Courbes d'évolution de la substance UIC 5-6
12 SNCF Infra | juin 2010
A model of the network’s evolution has be done
These figures show that the track renewal program do not allow to modernize the network
Courbes d'évolution de la substance UIC 1-6
60
55
50
45
40
35
30
2008 2009 2010 2011 2012 2013 2014 2015 2016
Without renewal
With Perfomance Contract
RFF has defined his strategic vision of the network
Definition of freight corridors with high level of availability
More accurate definition of the performance of the network according to the different routes, eg:
Axel load
Speed
Gauge
Availability
Increasing of the slots for TOCs and FOCs
Decreasing of maintenance and renewal costs
So SNCF has to improve the maintenance policies, in order to have more trains, more availability, as all Infra Managers do.
13 SNCF Infra | juin 2010
These huge requirements lead to
An optimization of maintenance and renewal, that means an assessment of the policies on each route based on LCC
More efficiency of the renewal
Longer zones
Uniformization
Planning
The necessity of planning and reducing maintenance costs; the best way is to move from an « on condition » based maintenance to a predictive maintenance
14 SNCF Infra | juin 2010
To do that,it is necessary:
To have a good knowledge of the conditions of the network
To know the parameters which have an impact on the behaviour of the components of the infrastructure
To know the degradation’s laws of these components according to the sollicitations they have to support
In order to plan the interventions
15 SNCF Infra | juin 2010
The knowledge of the degradation’s laws,eg:
Track circuits components
16 SNCF Infra | juin 2010
Development and implementation of measurement cars
IRIS 320 already in operation
Purchase of new measurement cars for conventional lines
Development and implementation of tools in order to modelize the degradation’s laws and so to define
« what to do » and « when to do » eg:
Contact wire wear measurement and planning of replacement (with « Catalyse »)
Track geometry quality measurement and planning of tamping (with « TIMON »)
17 SNCF Infra | juin 2010
18 SNCF Infra | juin 2010
Tableaux de synthèse classés par ligne
Tableau de prévision de remplacement
Tableau de suivi baguettes
Tableau de suivi des périodicités de mesures préconisées dans les référentiels
Résultats des différents calculs (% inexploitable, section moyenne des FC, point le plus bas, homogénéité,….) des différentes années de mesures
Affichage N° support
Affichage des courbes sur différentes années de mesures avec les couleurs correspondantes.
Bleu= année 2005
Orange= année 2007
Vert= année 2009
Seuil d’alarme
19 SNCF Infra | juin 2010
20 SNCF Infra | juin 2010
Sélection des fichiers de mesures de référence et choix de la date de projection
Différents traits de couleur suivant les années de mesures.
Bleu=2007
Orange=2009
Vert= Projection 2013
21 SNCF Infra | juin 2010
22 SNCF Infra | juin 2010
Development and implementation of remote control for level crossings Signalling and S & C in 3
Supervision Centers (Paris, Lyon,Pagny/Moselle)
Curve of translation of a switch
23 SNCF Infra | juin 2010
Implementation of new methods of maintenance for a higher durability of the interventions eg:
Tamping in BAS
Grinding
Tamping and grinding
24 SNCF Infra | juin 2010
X/T Y max
(T)/T
Y min
(T)/T
Niveau de saturation de
«jour»
Niveau de saturation de
«nuit»
T (âge de renouvellement)
To To
X = Coûts de régénération à la date 0
Y(T) = Coûts cumulés d’entretien de 0 à la date T
25 SNCF Infra | juin 2010
Maintenance costs are modelized according to track possession and distances between stations
D = 25km
14
12
10
Nombre de périodes
8
6
4
2
0
Nbr e P
/ 2h e P
Nbr
/ 3h
Nbr e P
/ 4h e P
/ 5h
Nbr
Nbr e P
/ 6h
19
17
15
13
11
5
7
9
Age Voie
26 SNCF Infra | juin 2010
12-14
10-12
8-10
6-8
4-6
2-4
0-2
D = 50km
25
20
Nombre de périodes
15
10
5
0
N br e P
/ 2h e P
N br
/ 3h
N br e P
/ 4h
N br e P
/ 5h
N br e P
/ 6h
19
17
15
13
11
5
7
9
Age Voie
27 SNCF Infra | juin 2010
20-25
15-20
10-15
5-10
0-5
28 SNCF Infra | juin 2010
Q&A