CEU Making Project Management Work in the Real World The best way to manage projects is by properly using proper Project Cost Management Proprietary Information Of Energy 2013 Earned Value Acronyms ACRONYM AC TERM / FORMULA MEANING Actual Cost What did it actually cost us to do the work/complete the work? BAC Budget at Completion How much did we budget to do the work for the entire/total project? CPI Cost Performance Index The amount of money we are getting back for each $ 1.00 we spent on the project. A measure of efficiency. ( Good = > $1.00; Bad = < $1.00) EV/AC CV Cost Variance EV-AC= When we check the costs, are we under budget or over budget? [Positive = under budget; negative = over budget] ( Good = + Bad = -– ) EAC Estimate at Completion Today, what do we anticipate/expect/estimate it will have cost us to have completed the total or entire project? ETC Estimate to Complete BAC/CPI = or AC+ETC= or AC + (BAC-EV)= or AC + [(BAC-EV)/CPI]= From today, what do we think it will cost us to complete the total or entire project? [We know how much we spent already up to today, so how much more will we need to spend to complete all the rest of the work to complete the entire/total project?] EV Earned Value What is the expected or estimated cost of the work we have actually completed? PV Planned Value What is the expected or estimated cost of the work we planned to complete or get done? SPI Schedule Performance Index EV/PV= When we check the schedule, we are only progressing at ____% of the rate we planned to progress at. This is a measure of efficiency. ( Good = > 100%; Bad = < 100%) SV Schedule Variance EV-PV= When we check the schedule are we ahead of schedule or behind schedule. [Positive = ahead of schedule; negative = behind schedule] ( Good = + Bad = -– ) Variance at Completion BAC – EAC = At the end of the project, how much under or over budget do we expect to be? VAC Proprietary Information Of Energy 2013 4 Earned Value Analysis Planned Value = Budgeted Cost of Work Scheduled PV = BCWS Earned Value = Budgeted Cost of Work Performed EV = BCWP Actual Cost = Actual Cost of Work Performed AC = ACWP Proprietary Information Of Energy 2013 Spending Plans Point in Time e.g. Today BAC Original Spending Plan PV Actual Spending Plan VAC AC EAC Future Spending Plan ETC Proprietary Information Of Energy 2013 Earned Value Formulas Earned Value EV = BAC * % Comp Cost Variance CV = EV - AC Schedule Variance SV = EV - PV Cost Perf Index CPI = EV / AC Schedule Perf Index SPI = EV / PV Est at Completion EAC = AC / % Comp Est to Complete ETC = EAC - AC Variance at Completion VAC = BAC - EAC = BAC-EV / BAC-AC New with 4th Edition TCPI Proprietary Information Of Energy 2013 Net Present Value (NPV) • NPV is the present value of cash inflow minus the initial capital investment. Always take the greater NPV choice. • Present Value = (Future Value) / (1 + r)n – r = interest rate – n = number of interest rate time periods • NPV = sum of [ FV / (1+r)n ] - II - II represents the Initial Investment Proprietary Information Of Energy 2013 Types of Cost Cost estimates can be comprised of multiple types of cost Cost Type Description Example Fixed Costs that stay the same throughout the life of a project Piece of equipment Variable Costs that vary on the project Hourly labor Fuel for equipment Direct Costs that are billed directly to the project Software licenses Team’s salary Indirect Overhead costs that are shared and allocated among several/all projects Manager’s salary Sunk Costs that have been invested or expended Unrecoverable past expenditures Proprietary Information Of Energy 2013 13 Budget Estimating Budget Estimates Top-Down Estimating (Rough Estimate) Rough Order of Magnitude (ROM) - 50 % to + 100 % Completed during initiation (not very accurate) Budget - 10 % to + 25 % Completed during early planning (better accuracy) Definitive - 5 % to + 10 % Completed during late planning Bottom-Up Estimating “Most Accurate” Proprietary Information Of Energy 2013 EARNED VALUE MANAGEMENT 15 Proprietary Information Of Energy 2013 Earned Value Analysis What Is It ? Why Do I Need It ? How Do I Do It? 16 Proprietary Information Of Energy 2013 Today’s Situation • Need for accurate and consistent status information • Numerous complex (and interrelated) projects – Projects with many WBS activities – Virtual offices – Diverse technology platforms 17 Proprietary Information Of Energy 2013 There’s Room For Improvement 70% of projects are: •Over budget •Behind schedule 52% of all projects finish at 189% of their initial budget And some, after huge investments of time and money, are simply never complete Source: The Standish Group 18 Proprietary Information Of Energy 2013 How to answer the question: “Have we done what we said we’d do?” • • • • % complete estimating % of Budget spent % of work done % of time elapsed – subjective, incomplete – draws false conclusions 19 Proprietary Information Of Energy 2013 Enter Earned Value Analysis “Earned Value Analysis” is: • an industry standard way to: • measure a project’s progress, • forecast its completion date and final cost, and • provide schedule and budget variances along the way. By integrating three measurements, it provides consistent, numerical indicators with which you can evaluate and compare projects. 20 Proprietary Information Of Energy 2013 What’s more Important? • Knowing where you are on schedule? • Knowing where you are on budget? • Knowing where you are on work accomplished? 21 Proprietary Information Of Energy 2013 EVA Integrates All Three • It compares the PLANNED amount of work with what has actually been COMPLETED, to determine if COST , SCHEDULE, and WORK ACCOMPLISHED are progressing as planned. • Work is “Earned” or credited as it is completed. 22 Proprietary Information Of Energy 2013 Earned Value needed because... • Different measures of progress for different types of tasks • Need to “roll up” progress of many tasks into an overall project status • Need for a uniform unit of measure (dollars or work-hours). 23 Proprietary Information Of Energy 2013 Earned Value needed because... • Provides an “Early Warning” signal for prompt corrective action. – Bad news does not age well. – Still time to recover – Timely request for additional funds 24 Proprietary Information Of Energy 2013 And One More Reason Why You Need EVA ? Proprietary Information Of Energy 2013 25 Because It’s the law ! These Set the Stage: GPRA; 1993 FASA, Title V; 1994 Clinger-Cohen Act; 1996 And Then Along Came OMB! (Circular A-11, Part 7) "Agencies must use a performance based acquisition management system, based on ANSI/EIA Standard 748, to measure achievement of the cost, schedule, and performance goals." 26 Proprietary Information Of Energy 2013 How’s this project doing? 120000 100000 80000 Projected 60000 Actual 40000 20000 0 Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03 Dec-03 Proprietary Information Of Energy 2013 27 Let’s Take A Look Under The Hood Proprietary Information Of Energy 2013 28 But First! - We gotta get organized EVA works best when work is ‘compartmentalized’. Compartmentalization is best achieved with a well-planned Work Breakdown Structure. So, how do I create a WBS for a really complex project? Proprietary Information Of Energy 2013 29 Proper WBS Design One WBS per program • Deliverable-oriented • Work not in the WBS is out-of-scope • Each descending level represents more detail Full (and accurate) definition is key • Defined deliverable(s) • Timeframe for delivery of product • Total cost (direct and indirect) to deliver product Let’s Look at an example: Proprietary Information Of Energy 2013 30 WBS & Decomposition… A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Fifth Edition, Figure 5-13 31 Proprietary Information Of Energy 2013 WBS Units are “Work Packages” Lowest level WBS elements Have an accompanying narrative Have three measurable components • Scope of work to be accomplished • Total (direct and indirect) cost • Timeframe for completion Proprietary Information Of Energy 2013 32 Some New(er) Terms BCWS - Budgeted Cost of Work Scheduled ACWP - Actual Cost of Work Performed BCWP - Budgeted Cost of Work Performed Proprietary Information Of Energy 2013 33 Earned Value Definitions BCWS: “Budgeted Cost of Work Scheduled” Planned cost of the total amount of work scheduled to be performed by the milestone date. Proprietary Information Of Energy 2013 34 BCWS - Budgeted Cost of Work Scheduled 120000 100000 80000 60000 BCWS 40000 20000 Dec-03 Nov-03 Oct-03 Sep-03 Aug-03 Jul-03 Jun-03 May-03 Apr-03 Mar-03 Feb-03 Jan-03 0 Proprietary Information Of Energy 2013 35 Earned Value Definitions (cont.) ACWP: “Actual Cost of Work Performed” Cost incurred to accomplish the work that has been done to date. Proprietary Information Of Energy 2013 36 ACWP - Actual Cost of Work Performed 120000 100000 80000 56000 60000 BCWP ACWP 49000 40000 20000 Dec-03 Nov-03 Oct-03 Sep-03 Aug-03 Jul-03 Jun-03 May-03 Apr-03 Mar-03 Feb-03 Jan-03 0 Proprietary Information Of Energy 2013 37 Earned Value Definitions (cont.) •BCWP: Budgeted Cost of Work Performed The planned (not actual) cost to complete the work that has been done. Proprietary Information Of Energy 2013 38 BCWP - Budgeted Cost of Work Performed 120000 100000 80000 BCWP 55000 60000 BCWS 49000 40000 20000 Dec-03 Nov-03 Oct-03 Sep-03 Aug-03 Jul-03 Jun-03 May-03 Apr-03 Mar-03 Feb-03 Jan-03 0 Proprietary Information Of Energy 2013 39 The Whole Story 120000 100000 80000 BCWS 56000 60000 BCWP 55000 49000 40000 ACWP 20000 Dec-03 Nov-03 Oct-03 Sep-03 Aug-03 Jul-03 Jun-03 May-03 Apr-03 Mar-03 Feb-03 Jan-03 0 Proprietary Information Of Energy 2013 40 Some Derived Metrics FYI •SV: Schedule Variance (BCWP-BCWS) –A comparison of amount of work performed during a given period of time to what was scheduled to be performed. –A negative variance means the project is behind schedule •CV: Cost Variance (BCWP-ACWP) –A comparison of the budgeted cost of work performed with actual cost. –A negative variance means the project is over budget. Proprietary Information Of Energy 2013 41 Schedule Variance & Cost Variance FYI Schedule Variance = BCWP-BCWS SV = Cost Variance $49,000 - 55,000 - $6,000 = BCWP-ACWP CV = $49,000 - 56,000 - $7,000 Proprietary Information Of Energy 2013 42 Some More Derived Metrics •SPI: Schedule Performance Index FYI SPI=BCWP/BCWS SPI<1 means project is behind schedule •CPI: Cost Performance Index CPI= BCWP/ACWP CPI<1 means project is over budget •CSI: Cost Schedule Index (CSI=CPI x SPI) The further CSI is from 1.0, the less likely project recovery becomes. Proprietary Information Of Energy 2013 43 Performance Metrics SPI: BCWP/BCWS 49,000/55,000 = 0.891 CPI: BCWP/ACWP 49,000/56000 = 0.875 CSI*: SPI x CPI .891 x .875 = 0.780 Cost Schedule Index (combined) Proprietary Information Of Energy 2013 44 Making Projections Once a project is 10% complete, the overrun at completion will not be less than the current overrun. Once a project is 20% complete, the CPI does not vary from its current value by more than 10%. The CPI and SPI are statistically accurate indicators of final cost results. Source: Defense Acquisition University Proprietary Information Of Energy 2013 45 Making Projections 120000 103865 102000 90882 100000 80000 BCWS 60000 BCWP Today ACWP 40000 20000 Dec-03 Nov-03 Oct-03 Sep-03 Aug-03 Jul-03 Jun-03 May-03 Apr-03 Mar-03 Feb-03 Jan-03 0 Proprietary Information Of Energy 2013 46 Estimate to Complete 140000 120000 116,571 100000 102000 BCWS 80000 BCWP 60000 ACWP Today 40000 20000 Ja n04 M ar -0 4 Ja n03 M ar -0 3 M ay -0 3 Ju l-0 3 Se p03 No v03 0 Proprietary Information Of Energy 2013 47 A New Criteria Activities “earn value” as they are completed. The value earned is the WBS budgeted cost of the activity completed to date. Proprietary Information Of Energy 2013 48 Value of Earned Value • Schedule Status Reporting • Cost Status Reporting • Forecasting 49 Proprietary Information Of Energy 2013 A-11, Part 7 Requires an EVMS FYI “ . . . based on ANSI/EIA Standard 748” And what does that mean? ANSI/EIA 748 provides a list of guidelines •Organization •Planning, Scheduling, and Budgeting •Accounting Considerations •Analysis and Management Reports •Revisions and Data Maintenance But, ANSI/EIA 748 doesn’t identify ‘approved systems’ Proprietary Information Of Energy 2013 50 A-11, Part 7 Requires an EVMS FYI So where do I get one? Buy a prepackaged one. (Lot of ‘em around) Make your own. •Microsoft Project •Microsoft Excel Or it could be as simple as this: Proprietary Information Of Energy 2013 51 Requirements of Earned Value • • • • Proper WBS Design Baseline Budget Control Accounts Baseline Schedule Work measurement by Control Account – work-hours, dollars, units, etc. • Good Project Management Practices Proprietary Information Of Energy 2013 52 Shortcomings of Earned Value • Quantifying/measuring work progress can be difficult. • Time required for data measurement, input, and manipulation can be considerable. Proprietary Information Of Energy 2013 53 Summary • EVA & EVMS will help reduce guesswork in: – Measuring performance – forecasting • Need to get beyond misleading measures of progress. • Reasons to use EVA and EVMS: – Good project management practice – OMB requirement • Incorporate into contracts Proprietary Information Of Energy 2013 54 Summary In order to manage a real-world project, a complete understanding and accounting of all time, costs and work must be part of your regular routine. Proprietary Information Of Energy 2013 55 Proprietary Information Of Energy 2013