PT PLN (PERSERO) INDONESIA ELECTRICITY SUPPLY CHALLENGES: TEN-YEAR ELECTRICITY DEVELOPMENT PLAN 2010-2019 1 ELECTRICITY DEMAND FORECAST 2010-2019 1. The electricity demand growth estimated average 9.3% per year (Jawa-Bali 8.97%, West Indonesia 10.2% and East Indonesia 10.6%) 2. The electricity sales from year 2010 onwards is forecasted by assuming an average economic growth of 6.2% and an average population growth of 1.17%. It is anticipated that the sales for those years would not be constrained, as all of the power plants of the fast track program would have been already in operation. 3. Electrification ratio increase from 65% in 2009 to 91% by the end of 2019. 4. DSM program to shave and shift peak load has not been taken into account. 2 DEMAND FORECAST 2010-2019 54 TWh 21 TWh IB : 10.2% JAVA-BALI SYSTEM 11 TWh 28 TWh IT : 10,6% 252 TWh 115 TWh JB : 8,97% Electricity Demand growth average 9.3%/year 3 INDONESIA ELECTRICITY RATIO 2009 sekita63% NAD 72,7% Category : > 60 % Sumut 75,5% Riau + Kepri 44,7% Kalselteng 56,3% Kaltim 53,9% Lampung 47,1% Jabar+Banten 64,95% 20 - 40 % Suluteng go 51,2% Kalbar 49,5% Sumbar 67,6% Sumsel+Jambi+Bengkulu 50,3% 41 - 60 % Babel 48,4% Sulselrabar 55,8% Sulten g 47,64 % Maluku 53,5% Bali 76,2% Jateng+Yog ya 70,2% Jatim 61,6% NTB 29,9% NTT 21,7% Papua + Irjabar 27,8% POLICY IN GENERATION EXPANSION PLANNING 1. Some ageing and inefficient oil-fired power plants are retired as soon as more effcient plants are available. 2. Generation expansion planning is made on least-cost principle, by looking for generation configuration that have minimum system costs. 3. However, development of renewables (especially geothermal and some hydro) is encouraged, by treating these as fixed plants prior to optimisation process. 4. Loss of Load Probability (LOLP) of <1 day/year is used as reliability criteria during planning process. The reserve margin is restricted within 35-50% range based on net dependable capacity. Rental power plants and excess power are not taken into account. 5 POLICY IN GENERATION EXPANSION PLANNING 5. Gas supply is assumed to be available for Java Bali system, yet for outside Java – Bali system gas-fired power plants are considered only if there is a definite gas supply. LNG receiving terminal is also considered as one option of gas supply. 6. Development of small scale coal-fired powerplants is used to substitute oil-fired powerplants for smaller systems, if there is no local primary energy resource available. 7. Coal-fired power plants with unit size of 1,000 MW supercritical would be introduced into the Java-Bali system. 8. PLN expects a bigger role from private sector in IPP development. 6 GENERATION CAPACITY EXPANSION PLAN Additional Capacity 53,219MW up to 2019 PLN Generation 32,636MW and IPP 20,583MW, Average 4800MW/year 7,000 6,000 1,258 890 936 5,000 2,763 4,000 2,238 413 IPP 3,461 3,000 3,329 2,896 PLN 2,282 5,248 5,141 2,000 1,000 4,699 3,553 3,425 3,178 117 1,479 1,054 1,440 1,738 1,681 2015 2016 2009 2010 2011 2012 2013 2014 2017 2018 2019 7 Fast Track Program Phase 1 (Jawa) 1. PLTU 1 Jateng-Rembang, 2x315MW, Cons. Zelan+Tronoh+Priamanaya, Contract Signed 21March2007 2. PLTU 2 Banten-Labuan, 2x300MW, Cons. Chengda+Truba Jurong, Contract Signed 21March2007 3. PLTU 1 Jabar-Indramayu, 3x330MW, Cons. Sinomach+CNEEC+PT Penta Adi Samudra, Contract Signed 21March2007 4. PLTU 2 Jatim-Paiton, 1x660MW, Cons. Harbin PE+Mitra Selaras+Hutama Energi, Contract Signed 7August2007 5. PLTU 1 Banten-Suralaya, 1x625MW, Cons. CNTIC+Rekayasa Industri, Contract Signed 12March2007 6. PLTU 1 Jatim-Pacitan 2x315MW, Cons. Dongfang Electric+Dalle Energy, Contract Signed 7Augus2007 7. PLTU 2 Jabar-Pelabuhan Ratu, 3x350MW, Cons. Shanghai Electric+Maxima Infrastructure, Contract Signed 7August2007 8. PLTU 3 Banten-Teluk Naga, 3x315MW, Cons. Dongfang Electric+Dalle Energy, Contract Signed 7August2007 9. PLTU 3 Jatim-Tg. Awar Awar, 2x350MW, Sinomach+CNEEC+Penta Adi Samudra, Contract Signed 25April2008 10. PLTU 2 Jateng-Adipala Cilacap, 1x660MW, Contract 22December2008, COD 2012 8 Fast Track Program Phase 1 (Outside Jawa) 1. 2. 3. 4. PLTU 2 Sumut-Pangkalan Susu, 2x220MW, Cons. Guangdong+Nintec+Bagus Karya PLTU Kepri-Tg. Balai Karimun, 2x7MW, Cons. Shangdong+Rekadaya Elektrika PLTU NAD-Meulaboh, 2x110MW, Synohydro PLTU 1 Riau-Bengkalis, 2x10MW, Cons. Guandong Machinery+Modaco+Kelsri+Angkasa Buana 5. PLTU 2 Riau-Selat Panjang, 2x7MW, Bouwstead Maxitherm 6. PLTU Sumbar-Teluk Sirih, 2x212MW, Cons. CNTIC+Rekayasa Industri 7. PLTU Lampung-Tarahan Baru, 2x100MW, Jiangxi Electric Power Design Institute+Adhi Karya 8. 9. 10. 11. 12. PLTU 3 Babel-Bangka Baru, 2x30MW, Cons. Truba,+China Shanghai Group PLTU 4 Babel-Belitung 2x16,5MW, Cons. Shandong Machinery+Poeser Indonesia PLTU 1 Kalbar-Parit Baru, 2x50MW, Cons. Bumi Rama Nusantara+Altons PLTU 2 Kalbar-Bengkayang, 2x27,5MW, Cons. Guangdong Machinery+Wijaya Karya PLTU Kalsel-Asam Asam, 2x65MW, Cons. Chengda+Wijaya Karya 13. 14. 15. 16. 17. PLTU 1 Kalteng, Pulang Pisau, 2x60MW PLTU 1 NTB-Bima, 2x10MW, Guandong+Modaco Enersys+Angkasa Buana Cipta PLTU 2 NTB-Lombok,2x25MW, Barata Indonesia PLTU 1 NTT-Ende 2x7MW, Cons. Shandong Machinery+Rekadaya Elektrika PLTU 2 NTT-Kupang, 2x16,5MW, Shandong Mavhinery+Poeser Indonesia 9 Fast Track Program Phase 1 (Outside Jawa) 18. PLTU Gorontalo, 2x25MW, Meta Epsi 19. PLTU 2 Sulut-Amurang, 2x25MW, Wijaya Karya 20. PLTU Sultra-Kendari, 2x10MW, Cons. Shangdong Machinery+Rekadaya Elektrika 21. PLTU Sulsel-Barru, 2x50MW, Cons. Hubei Hongyuan Engineering+Bagus Karya 22. PLTU Maluku Utara-Tidore, 2x7MW, Cons. Shandong Machinery+Rekadaya Elektrika 23. PLTU 3 Papua-Jayapura, 2x10MW, Cons. Modern Widya Technical+Boustead Maxitherm 10 Fast Track Program Phase 2 • More geothermal projects will be developed, and large coal fired power plant in Java to be excluded from Fast Track Program Phase 2. In addition to that, Upper Cisokan Pumped Storage Project will be included in the program. The composition of project will consist of: geothermal 48%, hydro 12%, gas combined cycle 14% and coal fired outside Java-Bali 26%. The capacity of the projects will be as follows: Java-Bali: geothermal 2,137 MW, hydro 1,000 MW and gas combined cycle 1,200 MW. Outside Java-Bali: coal plant 2,616 MW, hydro 174 MW, geothermal 2,596 MW, and gas combined cycle 240 MW. Total Indonesia: coal plant 2,616 MW, hydro 1,174 MW, geothermal 4,733 MW and gas combined cycle 1,440 MW, totalling 9,963 MW. Fast Track Program Phase 2 The second phase of fast track program will consist of 3,649 MW of PLN’s project and 6,314 MW of IPP project. The 1,200 MW gas combined cycle in Java-Bali is Muara Tawar Add-On 2,3,4 project. This project is very strategic in that it will meet the future demand by the year 2011-2012, however the feasibility of the project will subject to gas supply availability. The 1,000 MW hydro project in Java-Bali is Upper Cisokan Pumped Storage. This project is very strategic as it will serve as peaking unit to replace the role of oil fired plants. Most geothermal projects will be IPP. To ensure the success of the projects within the time frame of the program (up to 2014), geothermal developers must take immediate project preparation and PLN must make immediate geothermal IPP procurement. Summary of Fast Track Program Phase 2 REGION Steam Coal PP Combined Cycle PP (MW) (MW) Geo PP Hydro PP Total (MW) (MW) (MW) JAVA-BALI - 1.200 2.137 1.000 4.337 OUTSIDE JAVA-BALI 2.616 240 2.596 174 5.626 TOTAL 2.616 (26%) 1.440 (14%) 4.733 (48%) 1.174 (12%) 9.963 (100%) Map of Fast Track Program Phase 2 SUMATERA • • • • PLTA : 174 MW PLTP : 2285 MW PLTU : 1100 MW PLTGU : 120 MW KALIMANTAN • PLTU : 840 MW • PLTGU : 120 MW SULAWESI • PLTP : 195 MW • PLTU : 418 MW MALUKU PAPUA • PLTP : 40 MW • PLTU : 44 MW • PLTU : 114 MW NTT • PLTP : 46 MW • PLTU : 30 MW JAMALI • • • • PLTP : 2.137 MW PLTU : 0 MW PLTGU : 1.200 MW PLTA : 1.000 MW NTB • PLTP :30 MW • PLTU :70 MW TOTAL • • • • PLTA PLTP PLTU PLTGU TOTAL : : : : : 1174 4733 2616 1440 9963 MW MW MW MW MW Investment of Fast Track Program Phase 2 PLN Plant Steam Coal PP Combined Cycle PP Geothermal PP Hydro PP Total IPP Capacity (MW) Investment 380 549 2,236 3,231 1,440 1,210 - - 655 917 4,078 10,195 1,174 1,148 - - 3,649 3,824 6,314 13,426 (Million USD) Capacity (MW) Investment (Million USD) TRANSMISSION EXPANSION PLANNING JAVA-BALI 2008-2018 KEBUTUHAN TRANSMISI JAWA-BALI 2008-2018 Satuan kms TRANSMISI 2008 500 kV AC 2009 159 2010 2011 127 4 2012 329 2013 920 2014 606 2015 444 500 kV DC 100 2017 60 2018 340 350 150 kV 564 3,497 1,403 1,120 70 kV 14 80 10 22 578 3,735 1,541 1,146 TOTAL 2016 727 482 560 282 644 Total 3,089 350 276 12 9,567 126 1,056 1,402 1,166 726 1,094 336 352 13,132 KEBUTUHAN TRAFO JAWA-BALI 2008-2018 Satuan MVA TRAFO 2009 2010 2011 2012 2013 2014 2015 2016 1,666 4,666 3,000 2,000 1,000 4,000 3,500 3,000 6,000 150/70 kV 160 490 160 150/20 kV 1,820 4,800 7,920 4,036 3,570 3,480 3,330 3,690 5,370 60 460 190 90 90 80 80 150 3,706 10,416 11,270 6,126 4,660 7,560 6,910 6,840 500/150 kV 70/20 kV TOTAL 2008 2017 2018 Total 1,000 29,832 100 910 5,160 1,980 45,156 190 130 100 1,620 11,560 5,290 3,180 77,518 16 Project Name COD Financing Plan Transmisi 275 kV Sumatera (Payakumbuh – Padangsidempuan) 2012 Loan JICA Transmisi 275 kV Rengat – Garuda Sakti (220 km) 2014 unallocated Transmisi Sumatera-Jawa ± 500 kV HVDC 2016 USD 2,3 milyar, Loan JICA Jawa-Bali Crossing 500 kV HVAC 2015 USD 328 juta, akan diusulkan ke ADB Interkoneksi Kalbar-Serawak 275 kV HVAC 2012 USD 101 juta, akan diusulkan ke ADB Interkoneksi Sumatera-Malaysia ± 250 kV HVDC 2015 USD 353 juta, akan diusulkan ke ADB/JICA Perkuatan Transmisi Sistem Jakarta dan Bali 2011 USD 420 juta, KE 2012 Perkuatan Transmisi Kota-Kota Besar di Jawa 2012 USD 250 juta, IBRD Transmisi 500 kV AC Tj Jati - Ungaran – Pemalang – Mandirancan – Indramayu (±500 km) 2015 USD 300 juta, unallocated 17 DISTRIBUTION EXPANSION PLAN ADDIONAL DISTRIBUTION FACILITY •MV •LV •DISTRIBUTION TRANSFORMER •ADDITIONAL COSTUMER UP TO 2019: : 181,000KMS 16,500 KMS/YEAR : 249,500KMS 22,700 KMS/YEAR : 35,000 MVA 3,200 MVA/YEAR : 27,4 MILION 2,5 MIO/YEAR 18 PLN INVESTMENT INVESTMENT PROJECTION UP TO 2019 : USD 64,7 BILLION, INCLUDING INVESTMENT FOR LIFE EXTENSION/REFURBI SHMENT EXISTING GENERATION, SPARE IBT Juta USD 8,000.0 7,000.0 6,000.0 5,000.0 4,000.0 3,000.0 2,000.0 1,000.0 2009 Column1 Pembangkit Transmisi Distribusi Total Investasi 2010 2009 3,777.0 1,065.8 598.2 5,441.0 2011 2010 3,495.3 1,985.9 774.4 6,255.6 2012 2013 2011 3,188.3 1,939.7 1,080.4 6,208.4 2014 2012 2,851.1 1,297.4 1,006.8 5,155.3 2015 2013 3,143.0 1,145.7 947.5 5,236.1 2016 2017 2014 2,427.4 1,521.7 987.1 4,936.1 2018 2015 2,854.7 2,072.9 1,165.6 6,093.3 2019 2016 3,548.0 1,227.4 1,185.9 5,961.3 2017 4,270.4 592.2 1,300.2 6,162.8 2018 4,304.7 719.7 1,337.7 6,362.1 2019 4,721.4 851.6 1,304.4 6,877.4 Jumlah 38,581.2 14,419.9 11,688.3 64,689.4 19 PLN + IPP INVESTMENT Juta USD INVESTMENT PROJECTION UP TO 2019 : USD 83,0 BILLION OR USD 7,6 BILLION PER YEAR, INCLUDING INVESTMENT FOR LIFE EXTENSION/REFURBIS MENT EXISTING GENERATION, SPARE IBT 9,000.0 8,000.0 7,000.0 6,000.0 5,000.0 4,000.0 3,000.0 2,000.0 1,000.0 2009 Column1 Pembangkit Transmisi Distribusi Total Investasi 2010 2009 4,858.0 1,065.8 598.2 6,522.0 2011 2010 5,100.2 1,985.9 774.4 7,860.5 2012 2011 5,099.0 1,939.7 1,080.4 8,119.1 2013 2014 2012 5,369.2 1,297.4 1,006.8 7,673.4 2015 2013 5,810.6 1,145.7 947.5 7,903.8 2016 2014 5,061.4 1,521.7 987.1 7,570.2 2017 2018 2015 4,901.0 2,072.9 1,165.6 8,139.6 2019 2016 5,194.7 1,227.4 1,185.9 7,608.0 2017 5,483.1 592.2 1,300.2 7,375.5 2018 5,026.0 719.7 1,337.7 7,083.4 2019 4,987.8 851.6 1,304.4 7,143.8 Jumlah 56,891.0 14,419.9 11,688.3 82,999.2 20 PLN PROJECT JAWA-BALI SYSTEM PROYEK 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 PLN On-going dan Committed Project Muara Karang PLTGU Muara Tawar Blok #5 PLTGU Priok Extension PLTGU 500 194 234 500 Suralaya #8 PLTU Labuan PLTU Teluk Naga/Lontar PLTU 945 Pelabuhan Ratu PLTU 1,050 Indramayu PLTU 990 Rembang PLTU 630 Pacitan PLTU Paiton Baru PLTU Tj. Awar-awar Cilacap Baru / Adipala PLTU PLTU Sub Total On-going & Committed Rencana Upper Cisokan PS 300 300 630 660 700 660 800 3,399 3,359 243 - PLTA Muara Tawar Add-On 2,3,4 PLTGU Jawa Barat (LNG Terminal) PLTGU PLTGU Baru PLTGU PLTG Baru PLTG PLTU Baru PLTU Tangkuban Perahu 1 PLTP Kamojang PLTP Kesamben PLTA Kalikonto-2 PLTA Matenggeng PS PLTA Grindulu PS PLTA Sub Total Rencana Total PLN 243 625 150 1,360 - 500 500 700 - - - - 350 1,500 750 1,500 400 1,000 600 1,000 800 3,000 110 60 40 37 62 800 3,399 150 3,509 243 760 760 650 2,010 1,500 1,500 1,412 1,412 443 443 500 500 2,380 2,380 3,793 3,793 4,300 4,300 21 IPP PROJECT JAWA-BALI SYSTEM PROYEK 2009 2010 2011 2012 2013 2014 2015 2016 IPP On-going dan Committed Project Kamojang #4 PLTP Darajat #3 PLTP Wayang Windu PLTP 110 Bekasi Power PLTGU 130 Cikarang Listrindo PLTGU 100 50 Cirebon PLTU Paiton #3-4 Exp PLTU 815 Tanjung Jati B Exp PLTU 1,320 Celukan Bawang PLTU Sub Total On-going & Committed Rencana 110 Banten PLTU Madura (1x400 MW) PLTU Bali Timur PLTU Sumatera Mulut Tambang PLTU PLTU Jawa Tengah (Infrastruktur) PLTU PLTP Percepatan Tahap 2 IPP PLTP Rajamandala PLTA Jatigede PLTA Sub Total Rencana Total IPP RESERVE MARGIN MW % 230 710 130 250 2,265 250 - - 660 400 200 1,200 - - - 175 365 1,000 1,000 785 445 250 47 110 - Total Tambahan TOTAL KAPASITAS SISTEM 660 - - 175 565 1,942 1,845 2,110 110 230 710 2,440 815 1,942 1,845 2,110 910 3,629 4,219 2,683 1,575 3,952 3,345 3,522 22,796 26,030 30,209 32,816 34,391 38,343 41,688 45,210 29 34 41 39 33 36 35 35 22 SUMMARY For the next 10 years • The average electricity demand would grow at 9.3%/year (Jawa-Bali 8.97%, West Indonesia 10.2% and East Indonesia 10.6%) • Total additional generation capacity for Indonesia is 53,219 MW, consists of 32,636 MW of PLN projects and 20,583 MW of IPP projects • Development of renewable energy, especially geothermal, is encouraged, by additional 5,006 MW by 2018 • Total additional transmission network would reach 44,257 kms for all voltage levels, and total additional of transformers would be 103,000 MVA for all voltage levels. • Total additional distribution network is 175,013 kms for MV, 222,018 kms for LV, 30,877 MVA for distribution transformers and 25 million new customer connections. 23 SUMMARY • Total investment needed for Gen + Trans + Dis is US$ 64,69 billion (PLN only) or US$ 82,99 billion (PLN+IPP). • Investment needed for PLN power plant projects alone is US$ 38,581 billion, and for IPP projects is US$ 18,31 billion. 24 SUMMARY Some strategic generation projects: • CCGT Muara Tawar Add-on 2, 3, 4, 1,200 MW, commissioned in 2011-2012. • Fast Track Generation Project 10,000 MW Phase 2 with total capacity of 11,355 MW year 2011-2014 (this figure might change due to recent government’s will to promote more geothernal). • Upper Cisokan Pumped Storage of 4x250 MW in 2014 (WB) • CFPP Jawa Tengah Infrastruktur (IFC) 2x1,000 MW in 2014-2015. • CFPP mine mouth in Sumatera 6x600 MW in 2016-2017 (transferred to Java Bali system) • CCGT LNG Bojanegara 3x750 MW in 2015-2017. 25 SUMMARY Some strategic transmission projects: • HVDC transmission between Sumatera and Java in 2016. • Sub-sea 150 kV Java-Bali circuit 3,4, 2010 • Batam – Bintan interconnected system using sub-sea 150 kV, 2010 • 275 kV transmission connecting West Kalimantan – Serawak in 2011 • 500 kV Java-Bali Crossing from Paiton to Kapal/near Denpasar in 2015 26 PT PLN (PERSERO) 27