ASM Autoliv Supplier Manual Training Chapter Production Trial Runs (PTR): Process and Templates PRIVATE/PROPRIETARY AUTOLIV-0000/INITIALS/DATE/FILENAME - 2 PRIVATE/PROPRIETARY Production Trial Runs (PTR) Training Background Why does Autoliv require Production Trial Runs ? • Verify & confirm information on actual part / process • • • • evaluate performance as early as possible by First Trial Runs check against specifications (PPAP Trial Runs) ensure PPAP samples are run under serial conditions (PPAP Trial Runs) measure actual cycle times / capacities by Run@Rate What may happen if PTRs are not performed ? • late PPAP approval • endanger SOP • increase amount of waste / scrap AUTOLIV-0000/INITIALS/DATE/FILENAME - 3 PRIVATE/PROPRIETARY Production Trial Runs (PTR) Production Trial Run Participation & Documentation CLD PTR Requirements 1 documentation to be retained at supplier 2 documentation to be submitted to Autoliv 3&4 Autoliv participation at supplier, documents to be submitted to Autoliv AUTOLIV-0000/INITIALS/DATE/FILENAME - 4 PRIVATE/PROPRIETARY Production Trial Runs (PTR) 1. Supplier First Production-Trial-Run Project Time Line „FirstOff-Tool“ Serial order and drawing FirstProductionTrial-Run Potential supplier internal Production-Trial-Runs to verify corrective actions. Trial-Run-Modules Forms / Templates 1. Dimensional, Material, Test Result Report AIAG-Manual PPAP X - X Production-TrialRun-Checklist X Production-TrialCapacity Report X 3. Process-Quality-Audit 4. Capacity / Efficiency Audit PPAPSubmi ssion Run @ Rate Corrective actions resulting from (First-) Production-Trials Production-Trial-RunRequirement-Matrix: 2. Capability Study PPAPProductionTrial-Run First-ProductionTrial-Run X : Analysis and evaluation; “out of specification” results allowed Reviewing the PTR-modules and -templates through examples on the following pages ! PRIVATE/PROPRIETARY SOP Production Trial Runs (PTR) 1. Supplier First Production-Trial-Run Example: • Specifications (e.g. Drawings, DRDs, Standards) • Tooling & Machine • Raw Material • Special Processes (e.g. Heat Treatment, Coating) • Inspection & Testing • Operators AUTOLIV-0000/INITIALS/DATE/FILENAME - 6 PRIVATE/PROPRIETARY Cold Forming of Bolts Production Trial Runs (PTR) 1. Supplier First Production-Trial-Run Module 1. Dimensional, Material, Test Result Report Example: Measure all dimensions and verify all drawing requirements ! AUTOLIV-0000/INITIALS/DATE/FILENAME - 7 PRIVATE/PROPRIETARY Production Trial Runs (PTR) 1. Supplier First Production-Trial-Run Module 2. Capability Study- Example: The quality capability of a process is the comparison between the specified performance and the actual performance. Process capability is a powerful tool for predicting performance. Lower Spec Limit Upper Spec Limit Lower Spec Limit Upper Spec Limit Specified performance (voice of the customer) Actual performance (voice of the process) For further explanations see AS 52 ! AUTOLIV-0000/INITIALS/DATE/FILENAME - 8 PRIVATE/PROPRIETARY Production Trial Runs (PTR) 1. Supplier First Production-Trial-Run Module 3. Production Trial Run Checklist (1) Example: Questionnaire AUTOLIV-0000/INITIALS/DATE/FILENAME - 9 PRIVATE/PROPRIETARY Production Trial Runs (PTR) 1. Supplier First Production-Trial-Run Module 3. Production Trial Run Checklist (2) Example: Actions AUTOLIV-0000/INITIALS/DATE/FILENAME - 10 PRIVATE/PROPRIETARY Production Trial Runs (PTR) 1. Supplier First Production-Trial-Run Module 4. Production Trial Run Capacity Report Example: AUTOLIV-0000/INITIALS/DATE/FILENAME - 11 PRIVATE/PROPRIETARY Production Trial Runs (PTR) 2. Supplier PPAP Production-Trial-Run Project Time Line „FirstOff-Tool“ Serial order and drawing FirstProductionTrial-Run Potential supplier internal Production-Trial-Runs to verify corrective actions. PPAPProductionTrial-Run Corrective actions resulting from (First-) Production-Trials Production-Trial-RunRequirement-Matrix: Trial-Run-Modules Forms / Templates 1. Dimensional, Material, Test Result Report AIAG-Manual PPAP X X - X X Production-TrialRun-Checklist X 2. Capability Study 3. Process-Quality-Audit 4. Capacity / Efficiency Audit Production-TrialCapacity Report First-Production- PPAP-ProductionTrial-Run Trial-Run X X : Analysis and evaluation; “out of specification” results allowed X : Final verification; “out of specification” results NOT allowed PRIVATE/PROPRIETARY PPAPSubmi ssion Run @ Rate SOP Production Trial Runs (PTR) 3. Supplier Run@Rate Project Time Line „FirstOff-Tool“ Serial order and drawing FirstProductionTrial-Run Potential supplier internal Production-Trial-Runs to verify corrective actions. PPAPProductionTrial-Run PPAPSubmi ssion Run @ Rate Corrective actions resulting from (First-) Production-Trials Production-Trial-RunRequirement-Matrix: Trial-Run-Modules Forms / Templates 1. Dimensional, Material, Test Result Report AIAG-Manual PPAP X X - X X Production-TrialRun-Checklist X X Production-TrialCapacity Report X X 2. Capability Study 3. Process-Quality-Audit 4. Capacity / Efficiency Audit First-Production- PPAP-ProductionTrial-Run Trial-Run X : Analysis and evaluation; “out of specification” results allowed X : Final verification; “out of specification” results NOT allowed PRIVATE/PROPRIETARY Run @ Rate SOP Production Trial Runs (PTR) Supplier Production-Trial-Run Conditions Project Time Line Serial order and drawing „FirstOff-Tool“ FirstProductionTrial-Run Potential supplier internal Production-Trial-Runs to verify corrective actions. PPAPProductionTrial-Run PPAPSubmi ssion Run @ Rate SOP Corrective actions resulting from (First-) Production-Trials Trial-Run-Conditions First-Production- PPAP-ProductionTrial-Run Trial-Run Run @ Rate Full ProductionSpeed Serial Production Equipment / Site Trial-Run Minimum Durance Not specified 1 hour 4 -8 ** Minimum Number of parts produced Not specified 300 Tbd ** All Shifts considered in Trial-Run(s) Change-Over Procedures considered Trained Operators PPAP-ed Sub-Components Control Plan Pre-Launch Serial Production *** ** The trials durance and the number of parts produced must be representative of serial conditions. *** Serial Production Control Plan may be intensified (according to AS 412) upon Autoliv demand. PRIVATE/PROPRIETARY Serial Production *** Demanded Trial-Run Condition ASM: Supplier Production-Trial-Run Standard Project Time Line „FirstOff-Tool“ Serial order and drawing FirstProductionTrial-Run Production-Trial-RunRequirement-Matrix: Potential supplier internal Production-Trial-Runs to verify corrective actions. PPAPProductionTrial-Run PPAPSubmi ssion Run @ Rate Corrective actions resulting from (First-) Production-Trials Trial-Run-Modules Forms / Templates 1. Dimensional, Material, Test Result Report AIAG-Manual PPAP X X - X X Production-TrialRun-Checklist X X X X 2. Capability Study 3. Process-Quality-Audit* 4. Capacity / Efficiency Audit* SOP Production-TrialCapacity Report First-Production- PPAP-ProductionTrial-Run Trial-Run Run @ Rate X : Analysis and evaluation; “out of specification” results allowed X : Final verification; “out of specification” results NOT allowed Full ProductionSpeed Trial-RunConditions Serial Production Equipment / Site Trial-Run Minimum Durance Not specified 1 hour 4 -8 ** Minimum No. of parts produced Not specified 300 Tbd ** Demanded Trial-Run Condition; All Shifts considered in Trial-Run(s) Change-Over Procedures considered Trained Operators PPAP-ed Sub-Components Control Plan Pre-Launch Serial Production *** Serial Production *** * : The whole, inhouse process chain must be considered for the audits. For capacity audit all potential bottle-neck processes must be investigated. ** : The trial‘s durance and the amount of parts produced must be representative of the process‘s serial conditions. ***: Serial Production Control Plan might be intensified (according to GP 12) upon Autoliv demand. PRIVATE/PROPRIETARY