OG TEMPLATE - Gurgaon First

advertisement
MV NETWORK
MANAGEMENT
Amit Sharma
Anil Kadam
MV Public Distribution Network
20MVA
33/11kV
Public Distribution
Primary Substation
Primary
Distribution
20MVA
33/11kV
Process
Industry
Farm (rural
distribution)
kWh
kWh
Urban Distribution
kWh
Medium Industrial
Schneider Electric
Large Commercial
2
Radial network
33kV
Load
Centre 11
Primary
1
20MVA
11kV
Load
Centre 2
Load
Centre 3
Load
Centre 11
Load
Centre 1
Schneider Electric
3
Open ring network
33kV
Primary
1
20MVA
Load
Centre 11
11kV
Load
Centre 3
Schneider Electric
4
Open ring network
33kV
Primary
1
20MVA
Load
Centre 11
11kV
Load
Centre 3
NOP
Schneider Electric
5
- Why improve MV distribution?
●
To obtain the best possible power
quality
The main issue is to reduce
outage time and cost to the utility
and its customers
Schneider Electric
6
- How can outage time be reduced?
● By improving
MV networks:
● By improving the MV
networks management:
 Large number of short
sections
 With Fault Passage
Indicators (FPI’s)
 Redundant networks
 Or with remote controlled
load break switches
 Reliable components…
 Or with fully automated
reclosers and sectionalizers
 Or Ring Main Units with
FPI’s
Schneider Electric
7
- Different types of devices
R
Schneider Electric
R2
8
- overhead networks: types of faults
● Temporary
faults
80%
Schneider Electric
● Permanent
faults
20%
9
- temporary faults
● Temporary faults can be cleared by the
use of Automatic Circuit Reclosers
(ACRs)
Schneider Electric
10
- temporary fault: one recloser
R
Schneider Electric
11
- temporary fault: one recloser
O
15
s
C
R
100%
Time
Schneider Electric
12
- temporary fault: one recloser
O
15
s
15
s
C
R
100%
Time
Schneider Electric
13
- temporary fault: one recloser
O
15
s
15
s
C
R
100%
Time
Schneider Electric
14
- temporary fault: one recloser
O
15
s
15
s
15
s
C
R
100%
Time
Schneider Electric
15
- temporary fault: one recloser
O
15
s
15
s
15
s
C
R
100%
Time
2
mn
Schneider Electric
16
- temporary fault: TWO reclosers
R1
Schneider Electric
R2
17
- temporary fault: TWO reclosers
R1
Network A50%
R2
Network B50%
Network
B
Time
Schneider Electric
18
- permanent faults
Permanent faults cannot be cleared by
automatic reclosing
To manage “permanent faults”, the
best solution is to add some
“sectionalizers”
Schneider Electric
19
- case 1: no network automation
Permanent fault
R
100%
5H – 6H
Schneider Electric
20
- case 1: no network automation
Permanent fault
R
100%
95%
5H – 6H
Schneider Electric
21
- case 2: addition of non-communicating fault
passage indicators (FPI)
An FPI for each branch of the network
R
Add an FPI around
each major
«obstacle»…
Schneider Electric
22
- case 3: addition of communicating FPIs
R
Put several
communicating
FPIs in strategic
locations
Schneider Electric
23
- case 4: addition of communicating FPIs and remote
controlled load break switches
T
T
R
T
T
Schneider Electric
T
remote controlled load break
switches
Communicating FPI
24
- case 5: recloser and sectionalizer load break
switches
R
Schneider Electric
25
- case 5: recloser and
sectionalizer load break switches Permanent fault
S3
R
S4
S3
1
1
1
S2
S2
S1
Schneider Electric
27
- case 5: recloser and
sectionalizer load break switches
Permanent fault
S3
R
S4
S3
2
2
2
S2
S2
S1
Schneider Electric
28
- case 5: recloser and
sectionalizer load break switches
Permanent fault
S3
R
S4
S3
2
2
2
S2
S2
S1
2’
Schneider Electric
29
- case 5: recloser and
sectionalizer load break switches
Permanent fault
S3
S4
R
S3
S2
S2
S1
95
%
75
%
2’
Schneider Electric
60’
30
- summary of overhead networks 1/2
Permanent fault
95%
Case 1
A recloser
6h
95%
Case 2
A recloser
+ FPIs
3h
95%
Case 3
A recloser
+ FPI with Com
1h30
Schneider Electric
31
- summary of overhead networks 2/2
Permanent fault
95%
Case 4: A recloser,
70 %
remote controlled
switches
and FPI with Com
10
’
1
h
95%
Case 5
75 %
A recloser
and sectionalizers
2’
Schneider Electric
1
h
32
SAIDI/SAIFI variations – Quality Power
● SAIDI (System Average Interruption Duration Index) can vary from a
few minutes to several hours,
● SAIFI (System Average Interruption Frequency Index) can vary from
1 to 10 and more, depending on :
● population density (rural or urban area)
● proportion between underground and overhead distribution
● maximum accepted costs for non distributed energy
Urban area
Rural area
Excellent
Average
< 10 mn
30 mn
< 30 mn
2 hrs
Poor
>2 hrs
>10 hrs
Permanent Interruptions (>1 mn)
Schneider Electric
33
OPEN RING SYSTEM
MAIN SUBSTATION
51/51N
51/51N
What would happen to this network
if a fault occurred here ??
OPEN POINT
Schneider Electric
34
OPEN RING SYSTEM
MAIN SUBSTATION
51/51N
What would you do to get the
customers back on supply ??
OPEN POINT
Schneider Electric
35
OPEN RING SYSTEM
MAIN SUBSTATION
NEW OPEN POINTS SHIFTED FROM
Schneider Electric
36
Thank You!!
Schneider Electric
37
Download