GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 GLAST LAT Tracker Tower7/9 Pre-Ship Review Luca.latronico@pi.infn.it INFN-Pisa Tracker Subsystem 1 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 Tower 7 - Assembly and test highlights tray17 replacement • June 14 - July 4, 2005 (INFN-Pisa) : – – – • assembly of complete tray stack incomplete cable set (C0,C1,C2,C3,C4,C7) Sidewalls, alignment July 7-15, 2005 (Alenia-Roma) : – VIB, TVAC test RUN I • • July 25-26, 2005 (INFN-Pisa) : – – tray to be replaced • Aluminum service sidewall C6 installation Solithane, EMI taping Alignment verification, final CPT Full EIDP details (soon) at: – Tracker Subsystem TVAC (7/28-8/4) RUN II VIB (8/31) RUN II (Z axis only) September 1-5, 2005 (INFN-Pisa) : – – – • Tray 17 replacement C5 installation July 28 – August 31, 2005 (Alenia-Roma) – – • NCR 544 layerX17 noise anomaly http://glast.pi.infn.it 2 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 Tower 7 – Environmental test runs configurations Tracker Subsystem 3 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 Tower 7 Delivery configuration Tower PN: LAT-DS-00722 (rev3) Tower SN: 7 Details on NCR 530 Tracker Subsystem 4 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 Tower 7 – Configuration and mechanical verifications Configuration: • Kapton tape and foam applied on the flex cables as per LAT-DS-00722 • 4 layers of Poron foam 0.037 THK used on Bottom and Top Tray (–X) side (in place of 5 layers) • Base Plate assembly: •Torque of nuts 5.3 Nm, spec is (5.08 +0.56/-0 Nm) Alignment, Mass, COG: Tracker Subsystem • Tower 7 well aligned and inside stayclear • Mass (32.705Kg) and CG near estimated values (when used real masses) • Full data available from EIDP and INFN-PISA web site 5 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 Tower 7 – Open NCRs • INFN/PI-530: environmental test in non-flight configuration – – – • INFN/PI-543: layer X7 not read out (TVAC RUN I) – – – – • As per MRB decision, tray 17 (MID010) was replaced with a new tray, and tower7 retested the NCR can be closed INFN/PI-570: cold/hot power off/on not performed (TVAC RUN II) – – • X7 could not be readout at power up after vib test. X7 was properly read at the following and first switch on during TVAC The problem is due to a known and documented issue with resetting MCM (NCR 417) with missing cables To avoid the many and unknown number of power cycle needed to re-establish a good configuration with as many readable layers as possible, hot/cold switch on and off were not performed the NCR can be closed INFN/PI-544: layer X17 noisy at hot soak (TVAC RUN I) – – • both environmental test runs were performed with missing cables, as agreed by an MRB As a consequence of the missing solithane, 4 screws loss nominal torque and 1 was halfway unscrewed on one sidewall after Z-axis vibrations: the screws were re-torqued to spec and the following X and Y axis vibrations did not show any torque loss the NCR can be closed Same as NCR 543 the NCR can be closed INFN/PI-547: Vacuum level out of specification (TVAC RUN I) – The situation is similar to earlier TVAC tests and the proposal is to accept the test as for previous MRBs. Tower 6 was tested with tower 7 RUN I and the same NCR was closed Tracker Subsystem 6 Y17 20 Y2 15 X17 10 T W R 7 R e -T e s t L P T a t 0 fro m 4 th c o ld to R T T W R 7 R e -T e s t L P T a t 0 C 4 th h o t --> 4 th c o ld s o a k T W R 7 R e -T e s t L P T a t 3 0 C 4 th h o t --> 4 th c o ld s o a k T W R 7 R e -T e s t L P T a t 3 0 C 3 rd c o ld --> 4 th h o t s o a k T W R 7 R e -T e s t L P T a t 0 C 3 rd c o ld --> 4 th h o t s o a k T W R 7 R e -T e s t L P T a t 0 C fro m 3 rd h o t to 3 rd c o ld s o a k T W R 7 R e -T e s t L P T a t 3 0 C fro m 3 rd h o t to 3 rd c o ld s o a k T W R 7 R e -T e s t L P T a t 3 0 C fro m 2 n d c o ld to 3 rd h o t T W R 7 R e -T e s t L P T a t 0 C fro m 2 n d c o ld to 3 rd h o t T W R 7 R e -T e s t L P T a t 0 C fro m 2 n d h o t to 2 n d c o ld T W R 7 R e -T e s t L P T a t 3 0 C fro m 2 n d h o t to 2 n d c o ld T W R 7 R e -T e s t L P T a t 3 0 C fro m 1 s t c o ld to 2 n d h o t T W R 7 R e -T e s t L P T a t 0 C fro m 1 s t c o ld to 2 n d h o t T W R 7 R e -T e s t L P T a t 0 C fro m 1 s t h o t to 1 s t c o ld T W R 7 R e -T e s t L P T a t 3 0 C T W R 7 R e -T e s t: C P T 1 s t H o t S o a k T W R 7 R e -T e s t: C P T a t R T in v a c u u m T W R 7 C P T R T in v a c u u m T W R 7 L P T @ 0 C fro m 4 th h o t to 4 th c o ld T W R 7 L P T @ ~ 0 C fro m 3 rd c o ld to 4 th h o t 7 Tracker Subsystem L P T @ 0 C fro m 3 rd h o t to 3 rd c o ld C P T @ 3 rd H o t S o a k C P T at 2nd hot soak L P T a t 0 fro m 1 s t h o t to 1 s t c o ld L P T a t 2 5 fro m 1 s t h o t to 1 s t c o ld CPT RT C P T N o C a b le 5 6 • • R U N II RUN I T W R 7 R e -T e s t C P T a t R T in v a c u u m NCR 534: 2 layers (Y2, X5) sometimes out of spec due to fluctuations in noisy channels; the NCR can be closed X17 fixed after tray M010 replacement X5 showed 1 noisy ladder when ramping from 3rd cold to 4th hot soak: similar isolated anomalies, appearing randomly and only once were observed in other towers and are very likely caused by noise pickup dependent on the setup and/or the readout system (remember NCR 461 on the interference between the 2 towers DAQ causing test failures) • FM7/9 PSR, Sept. 9, 2005 GLAST LAT Project Tower 7 – Bad channels 25 T K R T o w e r 7 B a d c h a n n e ls (n o is y + d e a d + d is c o n n e c te d ) X5 1 6 c h L e ve l Y1 5 0 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 Tower 7 - Efficiency taken in Alenia after 2nd TVAC •All layers well within spec (eff > 98%) •Differences correlated to bad channels •No change after z-axis vib retest Tracker Subsystem 8 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 Tower 7 TVAC – vacuum out of spec RUN I Same behaviour as previous tests – TWR4 - TWR5 - Cold Plate Same behaviour as tower6 proposal is to accept the test: 90 •Vacuum slightly higher than spec TVAC, accepted during 80 (~> 10-4 vs 5x10-5 Torr) during hot preship review 70 soaks •Vacuum level improving with time (corresponding NCR 546 60 •same pressure behaviour in dry was closed) 50 run with MGSE 1.00E-02 1.00E-03 40 Temperature (°C) 30 20 1.00E-04 10 0 101 Cold Plate 102 Cold Plate +X 103 Cold Plate +Y 105 Cold Plate -Y 01 TWR7 center top 02 TWR7 top C-O -X 04 TWR7 swall -X n.1 10 TWR7 center bot 12 TWR7 bot C-O +X 32 TWR6 center top Tray 33 TWR6 top c-o -X 37 TWR6 swall -X n.1 40 TWR6 swall +X n.9 43 TWR6 bot c-o +X -10 -20 -30 -40 1.00E-05 -50 -60 Pressurre 1.00E-06 -70 08/07/2005 08/07/2005 09/07/2005 09/07/2005 10/07/2005 10/07/2005 11/07/2005 11/07/2005 12/07/2005 12/07/2005 13/07/2005 13/07/2005 14/07/2005 14/07/2005 15/07/2005 15/07/2005 16/07/2005 00.00.00 12.00.00 00.00.00 12.00.00 00.00.00 12.00.00 00.00.00 12.00.00 00.00.00 12.00.00 00.00.00 12.00.00 00.00.00 12.00.00 00.00.00 12.00.00 00.00.00 Tracker Subsystem 9 Date GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 Tower 9 - Assembly and test highlights • July 8-15, 2005 (INFN-Pisa) : – – – • July 25 – august 4, 2005 (Alenia-Roma) : – tray to be replaced • C0, C7 replacement with flight cables C3 installation Solithane, EMI taping Alignment verification, final CPT Full EIDP details (soon) at: – Tracker Subsystem VIB, TVAC September 5-7, 2005 (INFN-Pisa) : – – – – • assembly of complete tray stack incomplete cable set (C0-non-flight,C3 missing,C7-non-flight) Sidewalls, alignment http://glast.pi.infn.it 10 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 Tower 9 – Configuration and mechanical verifications Configuration: • Kapton tape and foam applied on the flex cables as per LAT-DS-00722 • 4 layers of Poron foam 0.037 THK used on Bottom and Top Tray (–X) side (in place of 5 layers) • Base Plate assembly: •Torque of nuts 5.4 Nm, spec is (5.08 +0.56/-0 Nm) Alignment, Mass, COG: Tracker Subsystem • Tower 9 well aligned and inside stayclear • Mass (32.840Kg) and CG near estimated values (when used real masses) • Full data available from EIDP and INFN-PISA web site 11 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 Tower 9 – Open NCRs • INFN/PI-541: environmental test in non-flight configuration – – – • INFN/PI-560: cold/hot power off/on not performed – – • environmental test were performed with missing cables, as agreed by an MRB Missing cables are the consequence of the following NCRs the NCR can be closed To avoid the many and unknown number of power cycle needed to re-establish a good configuration with as many readable layers as possible, hot/cold switch on and off were not performed after a satisfactory running condition was found the NCR can be closed INFN/PI-559: layers X2 and X12 not read out – – – Despite the many power cycles it was never possible to reset the tower as to read these layers; when a practical configuration was found with all layers readable but these 2, TVAC was run with such two layers disabled Post environmental test show no problem in the performance of these two layers (see next slide) the NCR can be closed Tracker Subsystem 12 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 Tower 9 - Efficiency 100 T o w e r 9 - ru n 3 0 6 0 0 1 3 0 3 E ffic ie n c y 99 98 E ffic ie n c y (% ) 1 0 0 % e ffic ie n c y 9 8 % re q u ire m e n t 0 1 1 2 2 3 3 4 4 5 5 6 6 7 7 8 8 0 Y X X Y Y X X Y Y X X Y Y X X Y Y 9 X 9 Y X 10 10 Y X 11 11 X 12 Y 12 Y 13 X 13 X 14 Y 14 Y 15 X 15 X 16 Y 16 Y X X Y 17 17 97 L a ye r •All layers well within spec (eff > 98%) •X2 @99.8%, X12@99.9% •Total bad channels in tower ~50 Tracker Subsystem 13