Chapter 6: Investment decision rules

Chapter 6

Investment

Decision Rules

Chapter Outline

6.1 NPV and Stand-Alone Projects

6.2 Alternative Decision Rules

6.3 Mutually Exclusive Investment Opportunities

6.4 Project Selection with Resource Constraints

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-2

Learning Objectives

1.

Define net present value, payback period, internal rate of return, profitability index, and incremental IRR.

2.

Describe decision rules for each of the tools in objective

1, for both stand-alone and mutually exclusive projects.

3.

Given cash flows, compute the NPV, payback period, internal rate of return, profitability index, and incremental

IRR for a given project.

4.

Compare each of the capital budgeting tools above, and tell why NPV always gives the correct decision.

5.

Define Economic Value Added, and describe how it can be used in capital budgeting.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-3

6.1 NPV and Stand-Alone Projects

• Consider a take-it-or-leave-it investment decision involving a single, stand-alone project for Fredrick

Feed and Farm (FFF).

 The project costs $250 million and is expected to generate cash flows of $35 million per year, starting at the end of the first year and lasting forever.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-4

NPV Rule

• The NPV of the project is calculated as:

NPV

 

250

35 r

• The NPV is dependent on the discount rate.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-5

Figure 6.1 NPV of FFF’s New Project

• If FFF’s cost of capital is 10%, the NPV is $100 million and they should undertake the investment.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-6

Measuring Sensitivity with IRR

• At 14%, the NPV is equal to 0, thus the project’s

IRR is 14%. For FFF, if their cost of capital estimate is more than 14%, the NPV will be negative, as illustrated on the previous slide.

 In general, the difference between the cost of capital and the IRR is the maximum amount of estimation error in the cost of capital estimate that can exist without altering the original decision.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-7

Alternative Rules Versus the NPV Rule

• Sometimes alternative investment rules may give the same answer as the NPV rule, but at other times they may disagree.

 When the rules conflict, the NPV decision rule should be followed.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-8

6.2 Alternative Decision Rules

• The Payback Rule

 The payback period is amount of time it takes to recover or pay back the initial investment. If the payback period is less than a pre-specified length of time, you accept the project. Otherwise, you reject the project.

• The payback rule is used by many companies because of its simplicity.

• However, the payback rule does not always give a reliable decision since it ignores the time value of money.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-9

Example 6.1

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-10

Example 6.1 (cont'd)

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-11

Alternative Example 6.1

• Problem

 Projects A, B, and C each have an expected life of 5 years.

 Given the initial cost and annual cash flow information below, what is the payback period for each project?

Cost

Cash Flow

A

$80

$25

B

$120

$30

C

$150

$35

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-12

Alternative Example 6.1

• Solution

 Payback A

• $80 ÷ $25 = 3.2 years

 Project B

• $120 ÷ $30 = 4.0 years

 Project C

• $150 ÷ $35 = 4.29 years

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-13

The Internal Rate of Return

• Internal Rate of Return (IRR) Investment Rule

 Take any investment where the IRR exceeds the cost of capital. Turn down any investment whose IRR is less than the cost of capital.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-14

The Internal Rate of Return (cont'd)

• The IRR Investment Rule will give the same answer as the NPV rule in many, but not all, situations.

• In general, the IRR rule works for a stand-alone project if all of the project’s negative cash flows precede its positive cash flows.

 In Figure 6.1, whenever the cost of capital is below the

IRR of 14%, the project has a positive NPV and you should undertake the investment.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-15

The Internal Rate of Return (cont'd)

• In other cases, the IRR rule may disagree with the

NPV rule and thus be incorrect.

 Situations where the IRR rule and NPV rule may be in conflict:

• Delayed Investments

• Nonexistent IRR

• Multiple IRRs

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-16

The Internal Rate of Return (cont'd)

• Delayed Investments

 Assume you have just retired as the CEO of a successful company. A major publisher has offered you a book deal. The publisher will pay you $1 million upfront if you agree to write a book about your experiences. You estimate that it will take three years to write the book. The time you spend writing will cause you to give up speaking engagements amounting to

$500,000 per year. You estimate your opportunity cost to be 10%.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-17

The Internal Rate of Return (cont'd)

• Delayed Investments

 Should you accept the deal?

• Calculate the IRR.

 The IRR is greater than the cost capital. Thus, the IRR rule indicates you should accept the deal.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-18

Financial Calculator Solution

1000000 CFj

-500000 CFj

3 Gold Nj

Gold IRR 23.38

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-19

The Internal Rate of Return (cont'd)

• Delayed Investments

 Should you accept the deal?

NPV

1,000,000

500, 000

1.1

500, 000

1.1

2

500, 000

1.1

3

 

$243,426

 Since the NPV is negative, the NPV rule indicates you should reject the deal.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-20

Figure 6.2

NPV of Star’s $1 million Book Deal

• When the benefits of an investment occur before the costs, the NPV is an increasing function of the discount rate.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-21

The Internal Rate of Return (cont'd)

• Nonexistent IRR

 Assume now that you are offered $1 million per year if you agree to go on a speaking tour for the next three years. If you lecture, you will not be able to write the book. Thus your net cash flows would look like:

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-22

The Internal Rate of Return (cont'd)

• Nonexistent IRR

NPV

500, 000

1

 r

500, 000

(1

 r

2

500, 000

(1

 r

3

 By setting the NPV equal to zero and solving for r , we find the IRR. In this case, however, there is no discount rate that will set the NPV equal to zero.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-23

Figure 6.3 NPV of Lecture Contract

• No IRR exists because the NPV is positive for all values of the discount rate.

Thus the IRR rule cannot be used.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-24

The Internal Rate of Return (cont'd)

• Multiple IRRs

 Now assume the lecture deal fell through. You inform the publisher that it needs to increase its offer before you will accept it. The publisher then agrees to make royalty payments of $20,000 per year forever, starting once the book is published in three years.

 Should you accept or reject the new offer?

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-25

The Internal Rate of Return (cont'd)

• Multiple IRRs

 The cash flows would now look like:

 The NPV is calculated as:

NPV

1,000, 000

500, 000

1

 r

500, 000

(1

 r

2

1,000, 000

500, 000 r

1

1

(1

 r

3

20, 000

(1

 r

3

(1

1 r

20, 000

(1

 r

4

3 

20, 000 r

20, 000

(1

 r

5

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-26

The Internal Rate of Return (cont'd)

• Multiple IRRs

 By setting the NPV equal to zero and solving for r , we find the IRR. In this case, there are two IRRs: 4.723% and 19.619%. Because there is more than one IRR, the

IRR rule cannot be applied.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-27

Figure 6.4 NPV of Star’s

Book Deal with Royalties

• If the opportunity cost of capital is either below 4.723% or above

19.619%, you should accept the deal.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-28

The Internal Rate of Return (cont'd)

• Multiple IRRs

 Between 4.723% and 19.619%, the book deal has a negative NPV. Since your opportunity cost of capital is

10%, you should reject the deal.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-29

The Internal Rate of Return (cont'd)

• IRR Versus the IRR Rule

 While the IRR rule has shortcomings for making investment decisions, the IRR itself remains useful. IRR measures the average return of the investment and the sensitivity of the NPV to any estimation error in the cost of capital.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-30

Economic Profit or EVA

• EVA and Economic Profit

 Economic Profit

• The difference between revenue and the opportunity cost of all resources consumed in producing that revenue, including the opportunity cost of capital

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-31

Economic Profit or EVA (cont'd)

• EVA and Economic Profit

 Economic Value Added (EVA)

• The cash flows of a project minus a charge for the opportunity cost of capital

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-32

Economic Profit or EVA (cont'd)

• EVA When Invested Capital is Constant

 EVA in Period n (When Capital Lasts Forever)

EVA

C rI n n

• where I is the project’s capital, C n is the project’s cash flow in time period n , and r is the cost of capital. r × I is known as the capital charge

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-33

Economic Profit or EVA (cont'd)

• EVA When Invested Capital is Constant

 EVA Investment Rule

• Accept any investment in which the present value (at the project’s cost of capital) of all future EVAs is positive.

• When invested capital is constant, the EVA rule and the

NPV rule will coincide.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-34

Example 6.2

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-35

Example 6.2 (cont'd)

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-36

Alternative Example 6.2

• Problem

 Ranger has an investment opportunity which requires an upfront investment of $150 million.

 The annual end-of-year cash flows of $14 million dollars are expected to last forever.

 The firm’s cost of capital is 8%.

 Compute the annual EVA and the present value of the project.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-37

Alternative Example 6.2

• Solution

 Using Eq. 6.1, the EVA each year is:

EVA n

C n

 rI

EVA n

$14 million

8% $150 million

$2 million

 The present value of the EVA perpetuity is:

PV

$2 million

8%

$25 million

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-38

Economic Profit or EVA (cont'd)

• EVA When Invested Capital Changes

 EVA in Period n (When Capital Depreciates)

EVA

C

 rI n n n

 n

• Where C n is a project’s cash flow in time period n , I n – 1 is the project’s capital at time period n – 1, and r is the cost of capital

• When invested capital changes, the EVA rule and the NPV rule coincide.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-39

Example 6.3

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-40

Example 6.3

(cont'd)

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-41

6.3 Mutually Exclusive

Investment Opportunities

• Mutually Exclusive Projects

 When you must choose only one project among several possible projects, the choice is mutually exclusive.

 NPV Rule

• Select the project with the highest NPV.

 IRR Rule

• Selecting the project with the highest IRR may lead to mistakes.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-42

Differences in Scale

• If a project’s size is doubled, its NPV will double.

This is not the case with IRR. Thus, the IRR rule cannot be used to compare projects of different scales.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-43

Differences in Scale (cont'd)

• Identical Scale

 Consider two projects:

Initial Investment

Cash Flow

Year 1

Annual Growth Rate

Cost of Capital

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

Girlfriend’s

Business

$1,000

$1,100

-10%

12%

Laundromat

$1,000

$400

-20%

12%

6-44

Differences in Scale (cont'd)

• Identical Scale

 Girlfriend’s Business

NPV

 

1000

1100 r

0.1

 

1000

1100

0.12

0.1

$4000

1000

1100 r

0.1

r

100%

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-45

Differences in Scale (cont'd)

• Identical Scale

 Laundromat

NPV

 

1000

400 r

0.2

 

1000

400

0.12

0.2

$250

• IRR = 20%

 Both the NPV rule and the IRR rule indicate the girlfriend’s business is the better alternative.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-46

Figure 6.5

NPV of Investment Opportunities

• The NPV of the girlfriend’s business is always larger than the NPV of the single machine laundromat. The IRR of the girlfriend’s business is 100%, while the IRR for the laundromat is 20%.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-47

Differences in Scale (cont'd)

• Changes in Scale

 What if the laundromat project was 20 times larger?

NPV

20

1000

400

0.12

0.2

$5000

• The NPV would be 20 times larger, but the IRR remains the same at 20%.

 Give an discount rate of 12%, the NPV rule indicates you should choose the 20-machine laundromat (NPV = $5,000) over the girlfriend’s business (NPV = $4,000).

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-48

Figure 6.6 NPV of Investment Opportunities with the 20-Machine Laundromat

• The NPV of the 20-machine laundromat is larger than the NPV of the girlfriend’s business only for discount rates less than 13.9%.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-49

Differences in Scale (cont'd)

• Percentage Return Versus Impact on Value

 The girlfriend’s business has an IRR of 100%, while the

20-machine laundromat has an IRR of 20%, so why not choose the girlfriend’s business?

• Because the 20-machine laundromat makes more money

 It has a higher NPV.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-50

Differences in Scale (cont'd)

• Percentage Return Versus Impact on Value

 Would you prefer a 200% return on $1 dollar or a 10% return on $1 million?

• The former investment makes only $2, while the latter opportunity makes $100,000.

• The IRR is a measure of the average return , but NPV is a measure of the total dollar impact on value .

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-51

Timing of Cash Flows

• Another problem with the IRR is that it can be affected by changing the timing of the cash flows, even when that change in timing does not affect the NPV.

 It is possible to alter the ranking of projects’ IRRs without changing their ranking in terms of NPV.

 Hence you cannot use the IRR to choose between mutually exclusive investments.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-52

Timing of Cash Flows (cont'd)

• Assume you are offered a maintenance contract on the laundromat machines which would cost

$250 per year per machine. With this contract, you would not have to pay for maintenance and so the cash flows from the machines would not decline.

 The expected cash flows would then be:

$400 – $250 = $150 per year per machine

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-53

Timing of Cash Flows (cont'd)

• The time line would now be:

NPV

20

1000

150 r

$5000

 The NPV of the project remains $5,000 but the IRR falls to 15%.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-54

Figure 6.7 NPV With and Without the Maintenance Contract

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-55

Timing of Cash Flows (cont'd)

• The NPV without the maintenance contract exceeds the NPV with the contract for discount rates that are greater than 12%.

 The IRR without the maintenance contract (20%) is larger than the IRR with the maintenance contract (15%).

• The correct decision is to agree to the contract if the cost of capital is less than 12% and to decline the contract if the cost of capital exceeds 12%.

With a 12% cost of capital, you are indifferent.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-56

The Incremental IRR Rule

• Incremental IRR Investment Rule

 Apply the IRR rule to the difference between the cash flows of the two mutually exclusive alternatives

(the increment to the cash flows of one investment over the other).

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-57

The Incremental IRR Rule (cont'd)

• Incremental IRR Rule Application

 The following timeline illustrates the incremental cash flows of the maintenance contract laundromat over the laundromat without the contract.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-58

The Incremental IRR Rule (cont'd)

• Incremental IRR Rule Application

NPV

150

 r

400 r

0.2

 Setting this equation equal to zero and solving for r gives an IRR of 12%.

• Applying the incremental IRR rule, you should take the contract when the cost of capital is less than 12%. Because your cost of capital is 12%, you are indifferent. This finding concurs with the NPV rule.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-59

The Incremental IRR Rule (cont'd)

• Shortcomings of the Incremental IRR Rule

 The fact that the IRR exceeds the cost of capital for both projects does not imply that both projects have a positive NPV.

 The incremental IRR may not exist.

 Multiple incremental IRRs could exist.

 You must ensure that the incremental cash flows are initially negative and then become positive.

 The incremental IRR rule assumes that the riskiness of the two projects is the same.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-60

6.4 Project Selection with Resource Constraints

• Evaluation of Projects with Different Resource

Constraints

 Consider three possible projects that require warehouse space.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-61

Profitability Index

• The profitability index can be used to identify the optimal combination of projects to undertake.

Profitability Index

Value Created

Resource Consumed

NPV

Resource Consumed

 From Table 6.1, we can see it is better to take projects

B & C together and forego project A.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-62

Example 6.4

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-63

Example 6.4 (cont'd)

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-64

Shortcomings of the Profitability Index

• In some situations the profitability Index does not give an accurate answer.

 Suppose in Example 6.4 that NetIt has an additional small project with a NPV of only $100,000 that requires

3 engineers. The profitability index in this case is

0.1 / 3 = 0.03, so this project would appear at the bottom of the ranking. However, 3 of the 190 employees are not being used after the first four projects are selected. As a result, it would make sense to take on this project even though it would be ranked last.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-65

Shortcomings of the Profitability

Index (cont'd)

• With multiple resource constraints, the profitability index can break down completely.

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-66

Questions?

Copyright © 2007 Pearson Addison-Wesley. All rights reserved.

6-67