College of Engineering Wind-Related Transmission/Distribution Technologies & Needs James McCalley (jdm@iastate.edu) REU Short Course on Wind Energy Science, Engineering and Policy June 17, 2011 Discovery with Purpose www.engineering.iastate.edu Windfarm Electrical System: 2 Three transmission/distribution related issues: Windfar m Windfar m Windfar m Windfar m LEVEL 2 LEVEL 3 MULTI-FARM COLLECTION NETWORK LEVEL 2 MULTI-FARM COLLECTION NETWORK BACKBONE TRANSMISSION LEVEL 1 LEVEL 1 Windfar m Windfar m Windfar m Windfar m Level 1, Multi-turbine collection network: Interconnect turbines to transmission sub. Level 2, Multi-farm collection network: Interconnect windfarms to backbone trans. Level 3, Backbone transmission: Transport energy from resources to load centers. 3 Multi-turbine collector network • Common voltage levels are 13.8, 25, 34.5 kV • Three-phase, always underground, cable POI or connection to the grid Collector System Station Interconnection Transmission Line Individual WTGs Feeders and Laterals (overhead and/or underground) 4 Multi-turbine collector network Multi-turbine collector network In the midwest, cutting drain tiles is a common problem that windfarm developers must contend with. Level 2: Multifarm collection networks Wind farms site where the wind resources are good, close to existing transmission that has residual capacity. If capacity is insufficient, one of the below happens: • Wind farm is not built; • Special protection schemes are used; • Incremental transmission upgrades are made; • Extensive transmission upgrades are implemented. OK when considering 3.7 GW wind out of 10GW total. Not OK when considering 20 GW wind out of 30GW total. There has not been much intentionality at level 2…. yet. But we need to consider Level 2 Designs, before wind grows much more. 7 Level 2: Multifarm collection networks - Examples • Depends on backbone transmission (may very well change….) 8 The backbone transmission issue: Where are the people? …But where are the resources? 9 Long-term National Planning & Resource Integration SOLAR CLEAN-FOSSIL GEOTHERMAL Where, when, & how to interconnect? BIOMASS NUCLEAR Wind 10 Questions on backbone transmission • Is transmission expensive? • Who pays for transmission? Who permits it? • Are there choices for transmission technologies? • Have we ever had a national transmission plan? • Why do many people feel “NIMBY” for transmission? • Why not just put it underground? • Transmission raises cost of energy at sending end and reduces it at receiving end why does sending end generally like it & receiving end often does not? • If a national transmission superhighway lowers average cost of energy for the nation, why not build it? 11 Transmission Technologies HVAC: 69kV, 115kV, 138kV, 161kV and 230kV EHVAC: 345kV, 500kV, 765kV Long distance must be overhead due to high line charging. HVDC: 500kV, 600kV, 800kV, Today, all high-capacity HVDC is thyristor-based Overhead DC lines less expensive than AC lines but higher termination investment cost. 400 miles is approximate breakover distance. Intermediate terminals (on-off ramps) are expensive. Use of IGBT-based voltage-source converters (lite) alleviates this but only at lower capacities. Long-distance HVDC underground bulk transmission is possible. Underground Superconducting Pipe Regional Transmission: HSIL, GIL, HVDC-lite 12 Transmission Technologies Fig. 4: Cost comparisons between HVDC and EHVAC for 6000 MW of capacity 13 Superconducting pipe 14 Tres Amigas 15 American Superconductor 16 AEP Conceptual 765--kV overlay for wind integration 17 18 20% Strong West 20% Strong Offshore 20% Distributed 30% 19 20 20% Strong 20% 20% Strong Distributed Offshore Most Economical West + RPS 30% 21 22 Criteria for a national overlay design • Facilitate low-carbon resource development • Move generation to load centers • Low total costs (investment + production) • Reduce overall national energy costs • Avoid “pockets” of high energy costs • Minimal environmental impact • Resilient to large-scale disruptions • Flexible for adaptation to future infrastructure 23 Green Power Express Cost: $10 billion Voltage: 765 kV Mileage: 3000 miles Who: ITC Proposed date: 2020 Capacity: 12000 MW 24 SPP EHV Overlay - Ultimate 25 ERCOT - CREZ 26 PacifiCorp Gateway Project 27 NREL’s Eastern Wind Integration and Transmission 28 Background A Brief Introduction of Our Proposed Study Process: 1. Determine 40 years’ generation and load portfolio using NETPLAN. Transmission capacities = inf. 2. Identify source/sink nodes under certain criteria 3. Obtain an initial transmission candidate topology (graph theory) Get a min cost spanning tree connect all nodes; Apply “reliability” constraints like N-1 security and rule of 3 4. Optimization. Determine capacities. Discard those arcs with no investment. Can coordinate with the first step 5. Transmission technology selection. 6. Production cost simulation 7. Power flow, stability studies, etc. Identifying Futures Key drivers Examples 30 References J. McCalley, W. Jewell, T. Mount and D. Osborn, “Technologies, Tools, and Procedures for Energy Systems Planning at the National Level,” to appear in Power and Energy Magazine. Slides from Midwest ISO Engineering Presentations in EE 552 (2008 and 2010). McCalley lecture notes from EE 552. N. Reddy, “Superconductor Electricity Pipelines: A compelling solution to today’s longhaul transmission challenges,” Right of Way, May/June, 2010, pp. 26-33, available at www.irwaonline.org/EWEB/upload/may_web_SuperConductor.pdf. R. Dunlop, R. Gutman, and P. Marchenko, “Analytical Development of Loadability Characteristics for EHV and UHV Transmission Lines,” IEEE Transactions on Power Apparatus and Systems, Vol. PAS-98, No. 2, March/April 1979. R. Gutman, E. Wilcox, 21st Century Transmission Planning: The Intersection of Engineering, Economics, and Environment,” CIGRE, 2009, Calgary. J. Fleeman, R. Gutman, M. Heyeck, M. Bahrman, and B. Normark, “EHV AC and HVDC Transmission Working Together to Integrate Renewable Power,” CIGRE Paper 978-285873-080-3, 2009. 31