Presentation - Granite-PR

advertisement

Aberdeen-Stavanger Gateway

DOF Subsea

Welcome

Giovanni Corbetta, Managing Director

DOF Subsea, part of the DOF Group

DOF Subsea 2

DOF Subsea 3

“To be a world class integrated offshore company, delivering marine services and subsea solutions responsibly, without risk, together, every day

DOF Subsea 4

DOF Subsea business model

Steady business

Time charter/ROV contracts

Long-term contracts

DOF Subsea 5

Company Capabilities

Integrated Subsea Construction

Engineering

Flexible & Umbilical Installation

Subsea Structure Installation

Mooring & Riser Installation

Inspection Maintenance & Repair

Tie-in & Diverless Intervention

Capabilities

Field Abandonment & Decommissioning

Seabed Mapping

Positioning Services

DOF Subsea

DOF Subsea Atlantic fleet

Normand Reach

Skandi Skolten Skandi Skansen

Geoholm

DOF Subsea

Geosund Skandi Inspector

7

DOF Subsea in Aberdeen

Moved into Aberdeen in 2006

Opportunities in subsea / marine construction

Success to date

Followed by a trend of vessel owners moving towards a more projects-based approach

DOF Subsea 8

Aberdeen

– Norway

Working together as a region

350 staff working in Atlantic operations

People synergies

Skills transfer and maximising knowledge

Lessons learned

DOF Subsea 9

Challenges

Cultural differences

office culture

business relationships

Communication

language barriers

physical distance

DOF Subsea 10

Global Locations

Focus regions

DOF Subsea

DOF Subsea

Current projects

Gina Krog FSO Field Development

Scope:

Installation of TM Buoy

Installation of Riser and Riser

Base

Design, Fabrication and

Installation of Spool and Covers

Offshore installation May and

June 2016

Vessels:

Skandi Skolten

Normand Reach

DOF Subsea 13

Maersk Riser Replacement, North Sea

Scope:

Removal of existing flexible riser system on the Dunbarton field

Installation of new riser system

Associated surveys

Offshore installation will commence

July 2014

Vessel:

Normand Reach

DOF Subsea 14

Shell

– Corrib Natural Gass Field, Ireland

Scope:

Disconnecting of the redundant flexible flowlines

Install two flexible flowlines

Tie-ins of the new flowlines to the wellhead and subsea manifold using the GE Icarus tiein tool

Offshore Installation August 2014

Vessel:

Normand Reach

DOF Subsea 15