Aberdeen-Stavanger Gateway
DOF Subsea
• Welcome
• Giovanni Corbetta, Managing Director
• DOF Subsea, part of the DOF Group
DOF Subsea 2
DOF Subsea 3
“To be a world class integrated offshore company, delivering marine services and subsea solutions responsibly, without risk, together, every day ”
DOF Subsea 4
DOF Subsea business model
• Steady business
• Time charter/ROV contracts
• Long-term contracts
DOF Subsea 5
Company Capabilities
• Integrated Subsea Construction
• Engineering
• Flexible & Umbilical Installation
• Subsea Structure Installation
• Mooring & Riser Installation
• Inspection Maintenance & Repair
• Tie-in & Diverless Intervention
Capabilities
• Field Abandonment & Decommissioning
• Seabed Mapping
• Positioning Services
DOF Subsea
DOF Subsea Atlantic fleet
Normand Reach Skandi Skolten Skandi Skansen
Geoholm
DOF Subsea
Geosund Skandi Inspector
7
DOF Subsea in Aberdeen
• Moved into Aberdeen in 2006
• Opportunities in subsea / marine construction
• Success to date
• Followed by a trend of vessel owners moving towards a more projects-based approach
DOF Subsea 8
Aberdeen – Norway
• Working together as a region
• 350 staff working in Atlantic operations
• People synergies
• Skills transfer and maximising knowledge
• Lessons learned
DOF Subsea 9
Challenges
• Cultural differences
office culture
business relationships
• Communication
language barriers
physical distance
DOF Subsea 10
Global Locations Focus regions
DOF Subsea
DOF Subsea
Gina Krog FSO Field Development
Scope:
• Installation of TM Buoy
• Installation of Riser and Riser
Base
• Design, Fabrication and
Installation of Spool and Covers
• Offshore installation May and
June 2016
Vessels:
• Skandi Skolten
• Normand Reach
DOF Subsea 13
Maersk Riser Replacement, North Sea
Scope:
• Removal of existing flexible riser system on the Dunbarton field
• Installation of new riser system
• Associated surveys
Offshore installation will commence
July 2014
Vessel:
• Normand Reach
DOF Subsea 14
Shell – Corrib Natural Gass Field, Ireland
Scope:
• Disconnecting of the redundant flexible flowlines
• Install two flexible flowlines
• Tie-ins of the new flowlines to the wellhead and subsea manifold using the GE Icarus tiein tool
Offshore Installation August 2014
Vessel:
• Normand Reach
DOF Subsea 15
Thank you!