R-APDRP Programme

advertisement
Power Finance Corporation Ltd.
Restructured APDRP
23rd December 2011
Noida, UP
We create possibilities of a better tomorrow
By V K Shah
Executive Director, PFC
Power Finance Corporation Ltd.
The presentation cover:
i)
RAPDRP Structure
ii) Part A – IT, Part A – SCADA and Part B Projects
iii) RAPDRP implementation in UP
ii) Progress of Implementation of RAPDRP
iii) Issues / Areas of concerned / lessons learned
iv) Intervention required
v) Way forward
We create possibilities of a better tomorrow
Power Finance Corporation Ltd.
 Major , technology focused, initiative launched by GOI in 2008
 Objective is demonstrable performance in terms of sustained AT&
C loss reduction to below 15% at town level
 Loss reduction targets at utility level : 3 % per annum , if AT&C
loss > 30% and 1.5 % for utilities having AT&C loss < 30%
 Total Outlay of the Scheme is over Rs. 51577 cr.
 PFC has been designated, by MOP, as the Nodal Agency.
 RAPDRP steering committee constituted under the Chairmanship
of Sect(P).
 Part-A to focus on establishment of IT enabled system for
achieving reliable & sustainable baseline data system and
automisation of business process for distribution utilities.
We create possibilities of a better tomorrow
Power Finance Corporation Ltd.
 Part A also include establishment of SCADA and DMS systems in big
towns (population > 4 lacs and input energy > 350 MU).
 Part-B focuses on implementation of Sub Transmission & Distribution
system strengthening & up-gradation projects
 Part-C of the scheme aims at Capacity Building of Utility personnel,
development of franchisees, incentive scheme for loss reduction, pilot
projects in areas of innovative technologies and smart grid etc.
 Funding Part A -IT and SCADA projects : Initially 100% as loan. To be
converted into grant on successful completion and verification by Third
Party Independent Evaluation Agency (TPIEA) as per RAPDRP
guidelines.
 Funding Part B Projects: Initially 100 % as loan (from GoI and Fis / own
source ). Convertible into grant up to 50% (90% in special category states)
on AT&C loss reduction to below 15 on sustained basis for five years.
 Funding Part C is entirely through grant .
We create possibilities of a better tomorrow
Power Finance Corporation Ltd.
 Part A projects envisaged technological intervention, at such
massive scale, first time in the country for tackling the
inefficiency and AT &C losses in the Power Distribution
Sector. The Project covers establishment of one Data Centre
(DC) and Disaster Recovery Centre (DRC) in each for the
state/ UT. Common DC and DR envisaged for NE states and
UT with neighboring states. The data at HT consumers, 11 kV
feeders and DTs. The GIS (consumer indexing and assets
mapping ) are
also established.
The project include
establishment of one consumer care centre (CCC) in each of
the state power utilities for addressing consumer issues.
 The project include automisation of business process / Dev.
of software solution for 17 modules such as MBC, Energy
Audit, Connection / Disconnection , Network Analysis etc.
We create possibilities of a better tomorrow
Power Finance Corporation Ltd.
The part B project is for distribution system improvement &
strengthening works. The activities to be covered in DPR are :
 HVDS (11 kV), Aerial Bunched Conductoring in dense areas
 Replacement of electromagnetic energy meters with tamper proof
electronic meters.
 Installation of capacitor banks
 Renovation, modernization and strengthening of 11 kV S/S,
Transformers
 Reconductoring of lines at 11 kV level & below
 Load bifurcation, feeder separation, load balancing
 Mobile service centers
 Strengthening of 33 kV or 66 kV levels (in exceptional cases).
 Any other work which would lead to Loss Reduction in project area.
 Enabling works for Implementing SCADA projects in the eligible
towns.
We create possibilities of a better tomorrow
Power Finance Corporation Ltd.
PFC, as Nodal Agency, under the guidance of MoP :
 Empanelled 21 IT Consultants, 139 IT Implementation
Agencies to take up different roles
 Empanelled
14 SCADA Consultants , 15 SCADA
Implementation Agencies
 Appointed Third Party Independent Evaluation AgenciesEnergy Accounting (TPIEA-EA) for all states across India
 Process of appointment of TPIEA-IT in progress
 DPR Formats / template and Model Bidding Documents
finalised for use by the Utilities for all kind of projects
under RAPDRP.
 A dedicated web portal (www.apdro.gov.in) has been
established for dissemination
of
information and
monitoring.
We create possibilities of a better tomorrow
•
Power Finance Corporation Ltd.







All states across the country have appointed IT Consultants
28 states across the country have appointed IT
Implementation agencies
16 states have appointed SCADA Consultants
Appointment of SCADA Implementing Agency (SIA) in
progress Two utilities have appointed SIA.
All the states have signed the Quadripartite Agreement.
Capacity Building of Power Utility personnel at various
levels has been identified as an essential part of R-APDRP.
PFC is acting as National Repository for Capacity Building
Database
Model Incentive scheme drafted by PFC for the perusal of
the Utilities
We create possibilities of a better tomorrow
Power Finance Corporation Ltd.
•
•
•
•
•
•
•
•
Sanctioned :
Part A IT- all eligible 1402 towns, INR 5196 cr.
Part A SCADA – 60 towns, INR 1386 cr
Part B (Distribution Strengthening PROJECTS) – 1039
towns, INR 23658 cr.
Disbursement : Total INR 4561 cr
10,000+ personnel of the various Power Distribution Utilities
have been imparted training under Capacity Building (Part
C) of R-APDRP
Verification of AT&C losses
1113 towns ring fenced across India and baseline data
(AT&C losses) verified for 348 towns.
Integration of towns IT with Data Centre have commenced
under Part A. DC have been established in 7 states.
We create possibilities of a better tomorrow
Power Finance Corporation Ltd.





Part A IT implementation
States of Gujarat, West Bengal, Uttarakhand, MP and Punjab,
Sikkim, are progressing relatively better and expected to
complete the project within 36 – 42 months from sanction.
States and ITIA of UP, Maharashtra , AP, Tamilnadu,
Rajasthan,
Karnataka, HP have to put more efforts to
complete the project in 36-42 months from sanction.
Other states are lagging in implementation (Bihar, Jharkhand,
J&K, Goa and NE states).
Haryana and Kerala yet to start. Chhattisgarh
has
retendered.
Part B implementation
MP, Gujarat, Rajasthan, WB and Karnataka have started
implementation of Part B, other states are in the process.
We create possibilities of a better tomorrow
Power Finance Corporation Ltd.
Longer than envisaged time taken in appointment of IT
implementing agency (in many cases more than 12 months).
 Longer than envisaged time taken in mobilisation and tying
up of other agencies i.e. GSP, NBSP, MDAS etc and
commencement of work.
 Deployment of dedicated and skilled manpower by utilities and
ITIA , specifically for MDAS, GIS and Software Development
 Proper planning and Administrative restructuring in the
Utilities for migration to new IT based business environment –
preparing for change management
The activities lacking are:
•
Readiness of DC, DR and CCC building with infra in many
states.
•
Development of software modules ( 17 as per SRS of RAPDRP) /
Customization and legacy system.

We create possibilities of a better tomorrow
Power Finance Corporation Ltd.




Real Challenge is implementation of Geographical Information
System. Consumer indexing and Assets Mapping Achieved to the
extent of 15% to 40% only in most of the states in last more than one
and half year (except in West Bengal and Gujarat) and yet to
commence in many states. Large gaps in survey carried out /
information complied and validated by utilities. The main reason is
deployment of skilled man power by implementing agency.
Meter Data Acquisition System (MDAS) -- installation of meters and
modems ( almost in all states the progress is lacking, except in West
Bengal).
Tying up of Network Band Width Service Provider and Connectivity
of towns with DC is lacking.
The real Challenge is that the utilities run the risk of loans not
getting converted into grant, if project is not completed in
successfully time as per guidelines.
We create possibilities of a better tomorrow
Power Finance Corporation Ltd.








Other issues
Common Data Centre and DR Centre (within states –
amongst utilities, with state and neighboring UT / state and
common for all NE states).
Meters specifications and testing .
Readiness of Business process
Integration with legacy system
Mind set and cahange management
Procurement of imageries for towns
Court / litigation cases ( Kerala and Assam)
IT implementing Agency backing out.
We create possibilities of a better tomorrow
Power Finance Corporation Ltd.
•
•
•
•
•
•
Augmentation of skilled manpower by ITIA and Utilities
(ITIA to augment man power with domain knowledge in
power sector, Utility to augment core team dedicated for the
project).
Coordination amongst stake holders ( also co-ordination
between various implementing agencies and utilities in the
states).
Better Project Management and Monitoring of the project at
ITIA , Utility and state govt. level
Parallel action need to be plan for accelerating implementation.
Hired DC building, development of software, adoption of
best practices for GIS and MDAS activities.
Identifying critical areas and focusing on the same.
We create possibilities of a better tomorrow
Power Finance Corporation Ltd.
RAPDRP is creating IT enabling base line data system and TPIEA
have verified the towns AT&C losses in about 300 towns. Utilities
can draw the administrative measures for reducing the AT&C
losses in these towns by curbing the theft, without awaiting for
implementation of Part B.
•
RAPDRP may be considered for extending to towns having
population up to 15,000 ( up to 5000 in special category states)
from present 30,000 ( 10000 in spl cat states).
•
RAPDRP funding may be considered for extending to private
utilities, beginning with DISCOMs in Orissa.
•
RAPDRP funding may be considered for extending for Part B for
towns having AT&C losses < 15%.
•
RAPDRP funding may be considered for Part A SCADA projects
for towns having population of > 2 lacs and input energy of > 150
MU
We create possibilities of a better tomorrow
•
Power Finance Corporation Ltd.
•
RAPDRP projects are expected to establish base line IT systems
for about 1400 towns and SCADA / DMS in 60 large towns. It is
opportune time to start from here and initiate developing smart
grid suitable for implementation for Indian conditions.
Govt,. Of India have already taken the initiative of forming India
Smart Grid task force and India Smart Grid Forum. Pilot projects
for Smart grid can be considered for funding under Part C of
RAPDRP.
Conclusion
Huge
benefits are
involved for all stake holders in
implementation of RAPDRP and a concerted effort by all the
stakeholders can make the program a grand success; thereby
helping the power sector to grow.
•
We create possibilities of a better tomorrow
Power Finance Corporation Ltd.
Thank You
We create possibilities of a better tomorrow
Download